Código Recurso Unida Cantidad Precio S/.Parcial S/. JULIO AGOSTO SETIEMBREOCTUBRE TOTAL DIFERENCIA
d
MANO DE OBRA
1 OPERARIO hh 3023.52 8.13 24,581.19 27332.32 35000 14503.16 76835.48 -52,254.29
2 OFICIAL hh 2732.09 6.75 18,441.60 0 18,441.60
3 PEON hh 5445.02 5.38 29,294.21 0 29,294.21
4 OPERARIO TOPOGRAFO hh 123.04 23.45 2,885.39 0 2,885.39
75,202.39 76,835.48 -1,633.09
MATERIALES
5 GASOLINA 90 OCTANOS gal 216.77 13.50 2,926.42 1788 1788 1,138.42
6 PETROLEO D-2 gal 355.46 14.00 4,976.42 3650 3650 1,326.42
7 ASFALTO RC-250 gal 17.43 15.00 261.38 0 261.38
8 FLETE TERRESTRE MATERIALES glb 1.00 1,000.00 1,000.00 0 1,000.00
9 TRANSPORTE DE EQUIPOS Y HERRAMIENTAS glb 1.00 800.00 800.00 0 800.00
10 ALAMBRE NEGRO RECOCIDO N° 8 kg 129.82 4.50 584.21 1750 1750 -1,165.79
11 ALAMBRE NEGRO RECOCIDO N° 16 kg 334.65 4.00 1,338.61 750 750 588.61
12 ALAMBRE GALVANIZADO N° 8 kg 14.00 4.50 63.00 0 63.00
13 ALAMBRE GALVANIZADO N°16 kg 14.00 4.50 63.00 0 63.00
14 ANGULO DE FIERRO NEGRO 1 1/2"X1 1/2X 3/16" m 372.44 8.00 2,979.50 0 2,979.50
15 ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 kg 5865.79 3.00 17,597.37 19609.5 19609.5 -2,012.13
16 ACERO CORRUGADO Ø 1/4" m 361.15 1.20 433.38 0 433.38
17 CLAVOS PARA MADERA CON CABEZA 1 1/2" kg 7.20 4.50 32.40 70 70 -37.60
18 CLAVOS PARA MADERA CON CABEZA DE 2 1/2" kg 14.00 4.50 63.00 0 63.00
19 CLAVOS PARA MADERA CON CABEZA DE 3" kg 138.00 4.50 621.02 450 450 171.02
20 CLAVOS PARA MADERA CON CABEZA DE 4" kg 103.71 4.50 466.68 450 450 16.68
21 MALLA GALVANIZADA COCADA N°10 DE 2"x2" h=2.0m m2 25.52 25.00 637.88 0 637.88
75 CASCO CON RACHET POSTERIOR und 30.00 20.00 600.00 445 445 155.00
76 LENTES DE PROTECCION und 30.00 6.00 180.00 210 210 -30.00
77 PROTECTOR DE OIDOS TIPO TAPON und 30.00 6.00 180.00 96 96 84.00
78 MASCARILLA RESPIRADOR CONTRA POLVO und 60.00 9.00 540.00 130 130 410.00
79 GUANTES DE CUERO par 60.00 12.00 720.00 240 240 480.00
80 GUANTES DE JEBE par 60.00 6.00 360.00 600 600 -240.00
81 ZAPATOS CON PUNTA DE ACERO par 30.00 50.00 1,500.00 2034 2034 -534.00
82 CHALECO REFLECTIVO PARA OBRA und 30.00 35.00 1,050.00 1494 1494 -444.00
83 BOTAS DE CAUCHO par 30.00 25.00 750.00 0 750.00
84 LINEAS DE VIDA VERTICAL und 30.00 50.00 1,500.00 0 1,500.00
85 ARNES DE CUERPO ENTERO CON LINEA DE und 15.00 120.00 1,800.00 0 1,800.00
ENGANCHE
86 CAMILLA RIGIDA DE MADERA und 1.00 250.00 250.00 0 250.00
Código Recurso Unida Cantidad Precio S/.Parcial S/. JULIO AGOSTO SETIEMBREOCTUBRE TOTAL DIFERENCIA
d
87 BOTIQUIN (equipado segun lista de materiales) und 1.00 150.00 150.00 230 230 -80.00
88 CONO DE SEÑALIZACION NARANJA DE 28" DE ALTURA und 6.00 25.00 150.00 0 150.00
98 TUBO RECTANGULAR ESTRUCTURAL LAC m 720.00 22.00 15,840.00 13416 13416 2,424.00
80mmX40mm E=3mm (ROLADO)
101 DISCO DE CORTE PARA ACERO und 24.51 15.00 367.72 760 760 -392.28
102 CALAMINA #30 DE 1.83x0.83x3mm pza 62.40 20.00 1,248.00 0 1,248.00
103 AGUA m3 111.88 2.00 223.75 0 223.75
104 EXTENSION 10 MTS. C/ADAPTADOR und 4.00 20.00 80.00 0 80.00
105 CALAMINON ALUZIN FORMATO TR4 E=0.30mm m2 957.85 27.50 26,340.93 27000 27000 -659.07
(ROLADO)
106 SOPORTE CANALETAS DE ETERNIT DE 6" und 132.40 12.00 1,588.80 0 1,588.80
### ### 94,486.98
EQUIPOS
107 ESTACION TOTAL hm 123.04 15.00 1,845.66 0 1,845.66
108 HERRAMIENTAS MANUALES %mo 2,120.13 1123 1123 997.13
109 MOTOBOMBA DE 2" (5HP) día 10.00 35.00 350.00 0 350.00
110 COMPACTADORA VIBRATORIA TIPO PLANCHA 7 HP hm 351.43 15.00 5,271.50 0 5,271.50
111 COMPACTADORA DE PLANCHA día 3.84 40.00 153.46 0 153.46
112 CARGADOR SOBRE LLANTAS DE 125-135 HP 3 yd3 hm 43.03 150.00 6,454.43 3000 3000 3,454.43
113 MOTONIVELADORA 130 - 135 HP hm 0.14 180.00 26.08 0 26.08
114 GRUA hm 16.00 100.00 1,600.00 0 1,600.00
115 CAMION VOLQUETE 6x4 340HP DE 12 m3 hm 17.31 130.00 2,250.22 3000 3000 -749.78
116 VIBRADOR DE CONCRETO 4 HP 1.25" hm 191.38 8.00 1,531.05 0 1,531.05
117 MEZCLADORA DE TROMPO 9 P3 (8 HP) hm 194.34 12.00 2,332.06 0 2,332.06
118 AMOLADORA hm 230.80 2.00 461.60 0 461.60
119 CIZALLA hm 923.18 2.00 1,846.36 0 1,846.36
120 ANDAMIO METALICO hm 2178.96 1.50 3,268.44 0 3,268.44
121 INSTALACION DE ENERGIA ELECTRICA PARA OBRA glb 1.00 200.00 200.00 0 200.00
29,710.99 7,123.00 22,587.99
SUBCONTRATOS
Código Recurso Unida Cantidad Precio S/.Parcial S/. JULIO AGOSTO SETIEMBREOCTUBRE TOTAL DIFERENCIA
d
122 SC M. O. ESTRUCTURA METALICA INC. APLICACION DE und 16.00 60.00 960.00 35000 35000 -34,040.00
BASE ZINCROMATO Y PINTURA
ELECTRICIDAD 8000
124 SC MANO DE OBRA ESPECIALIZADO PARA INTALACION m2 912.24 16.00 14,595.84 0 14,595.84
DE CALAMINON ALUZIN EN COBERTURAS INC EQUIPO
Y OTROS
125 SC MANO DE OBRA ESPECIALIZADO PARA MONTAJE DE glb 8.00 800.00 6,400.00 0 6,400.00
VIGA METALICA SERCHA Y CORREAS INC EQUIPO Y
OTROS
126 SC MANO DE OBRA ESPECIALIZADO PARA ARMADO DE und 8.00 800.00 6,400.00 0 6,400.00
VIGAS METALICA TIPO SERCHA INC EQUIPO Y OTROS
135 PROFESIONAL I. RESIDENTE DE OBRAS ING, CIVIL 5062.5 6177.58 5651.75 11829.33
136 ASISTENTE TECNICO DE OBRA, ING. CIVIL 2800.8 2674.02 2477.23 5151.25
137 ESPECIALISTA EN CONTRATACIONES - CONTADOR 2498.4 1801.1 2018.48 3819.58
138 ALMACENERO 0 1571.87 1571.87
139 GUARDIAN 715.96 715.96
140 MAESTRO DE OBRA 2510.96 2510.96
141 UTILES DE ESCRITORIO 613.4 613.4
26212.35
GASTOS DE SUPERVISION
Código Recurso Unida Cantidad Precio S/.Parcial S/. JULIO AGOSTO SETIEMBREOCTUBRE TOTAL DIFERENCIA
d
Código Recurso Unida Cantidad Precio S/.Parcial S/. JULIO AGOSTO SETIEMBREOCTUBRE TOTAL DIFERENCIA
d