Sei sulla pagina 1di 4

BILL OF QUANTITY

Date :
Project : CAR GARAGE
Location : TARLAC STATE UNIVERSITY
Company : SAPON, DANIEL JOHN M.

ITEM DESCRIPTION QUANTITY MATERIAL COST LABOR COST


UNIT PRICE AMOUNT UNIT PRICE AMOUNT
1 GENERAL REQUIREMENTS
a. Mobilization/ Demobilization 1.00 lot 20,000 20,000
b. Temporary Facilities / Fences 1.00 lot 25,000 25000
c. Building Permits / Occupancy Permit (Leg Work Only) 1.00 lot 300 300
d. As Built Plans 1.00 lot 1,000 1000
e. Safety, Health and Security 1.00 lot 10,000 10,000 3,000 3,000
Sub-total 10000 49300
2 EARTHWORKS
a. General Cleaning / Demolition Works 1.00 lot 400 2000
b. Stacking Out 1.00 lot 400 2000
c. Excavation 512.76 cum 400 1025520
d. Backfill and Compaction 813.00 cum 400 1626000
e. Gravel Bedding 43.68 cum 1000 43680 400 87360
f. Soil Poisoning 436.00 sqm 400 872000
g. Hauling and Disposal 1.00 lot 400 2000
Sub-total 43680 3616880
3 CONCRETE WORKS
a. Retaining Walls
a.1 Concrete 44.70 cum 500 10000 350 156450
a.2 Rebars 4,487.62 kls 65 1300 350 3500
a.3 GI Tie Wire Ga. 16 74.54 kls 50 3727
b. Footings
b.1 Concrete 5.15 cum 500 2500 350 9012.5
b.2 Rebars 111.65 kls 65 325 350 350
b.3 GI Tie Wire Ga. 16 4.10 kls 50 205
c. Columns
c.1 Concrete 6.85 cum 500 3000 350 11987.5
c.2 Rebars 1,006.56 kls 65 650 350 1050
c.3 GI Tie Wire Ga. 16 24.60 kls 50 1230
d. Beams
d.1 Concrete 12.59 cum 500 5000 350 22032.5
d.2 Rebars 2,233.63 kls 65 750 350 1750
d.3 GI Tie Wire Ga. 16 31.40 kls 50 250
e. Slab on Fill
e.1 Concrete 67.76 cum 500 12000 350 237160
e.2 Rebars 3,583.01 kls 65 3250 350 3500
e.3 GI Tie Wire Ga. 16 617.00 kls 50 30850
Sub-total 75037 446792.5
4 Masonry Works with Plastering
a. CHB 6" x 4' x 8' 240.00 sqm 120 28800
b. Rebars at 10mm x 6m 200.00 pcs 115 23000
d. GI Tie Wire Ga. 16 27.30 kgs 50 1365
e. Cement 350.00 bags 275 1285
f. Washed Sand 21.40 cum 1200 25680
g. Natural Stone Cladding 149.80 sqm 1000 149800
Sub-total 229930
5 Roof Framing and Sun Baffles Framing
a. 50 x 50 x 2.0mm Tubular 95.00 pcs 600 57000 350 350
b. 100 x 50 x 2.0mm Tubular 9.00 pcs 500 4500 350 350
c. 100 x 50 x 4.5mm Tubular 9.00 pcs 1170 10530 350 350
d. 100 x 100 x 2.0mm Tubular 8.00 pcs 800 6400 350 350
e. 175 x 50 x 2.0mm Tubular 16.00 pcs 750 12000 350 350
f. 200 x 200 x 4.5mm Tubular 2.00 pcs 1850 3700 350 350
g. W 12x14 12.00 lm 20500 24600 350 350
h. W 12x16 12.00 lm 20500 24600 350 350
i. C-Purllins 100 x 50 x 15 x 2mm 65.00 pcs 800 52000 350 350
j.16mm ɸ Plain Rod 8.00 pcs 200 1600 350 350
k. 10mm ɸ Plain Rod 8.00 pcs 140 1120 350 350
l. Turn Buckle 4.00 pcs 90 360 350 350
m. L 50 x 50 x 4.5mm 13.00 pcs 1200 15600 350 350
n. Base Plates and Anchor Bolts 1.00 lot 900 900 350 350
n. Consumables 1.00 lot 5000
Sub-total 219910 4900
6 Roofing
a. Pre Painted G.I Roof Long Span Rib Type Ga. 26 154.56 sqm 500 77280 350 350
b. Cement Board Senepa 78.00 lm 400 31200 350 350
c. Drip Edge Flashing 11.58 lm 300 3474 350 350
d. Wall Flashing 11.58 lm 600 6948 350 350
e. Polycarbonate Roofing 11.20 sqm 200 2240 350 350
f. Consumables 1.00 lot 1000
Sub-total 122142 1750
7 Metal Works
a. Stair Railings 24.00 lm 300 7200 350 700
b. Balcony Railings 34.00 lm 150 5100 350 700
c. Gate Frame 50 x 200 x 2.3mm Tubular 12.00 pcs 300 3600 350 700
d. Consumbles 1.00 lot 2000
Sub-total 17900 2100
8 ROOFING WORKS
a. Random size solid wood w/ Varnish Finish 39.00 sqm 500 19500 350 2050
b. Consumables 1.00 lot 1500
Sub-total 21000 2050
9 Painting Works
a. Plastered Painted finish 452.50 sqm 140 350 1750
b. Metals 223.20 sqm 3000 350 700
c. Consumables 1.00 lot 2200
Sub-total 5340 2450
10 Specialty Finishes
a. Vertical Garden 12.00 sets 10000 350 1050
b. Vegetable Plot 1.00 lot 1000 350 700
Sub-total 11000 1750
TOTAL AMOUNT
Direct Amount
Contractor's Profit (10%)
VAT (12%)
Total Project Cost
Says
TOTAL AMOUNT

59300

3660560

521829.5

229930
224810

123892

20000

23050

7790

12750
4883911.5
4883911.5
488391.15
58606.938
₱ 5,430,909.59
₱ 5,430,909

Potrebbero piacerti anche