SNRP
PLN/Q1801/QC /01 Rev 00
Originated by : ______________________
(Mr. V Narsimhulu, WEL)
Approved by : ______________________
(Mr. Pramod Singh, WEL)
Approved by : ______________________
( ,IE / NHAI)
“This document is a property of Welspun Enterprises Ltd and is not to be reproduced, copied, handed
over to a third party or used for any purpose other than that for which it has been loaned”.
TABLE OF CONTENTS
Title Page No
1.0 PURPOSE.................................................................................................................4
2.0 PROJECT QUALITY POLICY:..................................................................................4
3.0 PROJECT QUALITY OBJECTIVES:.........................................................................4
4.0 SCOPE OF SERVICES:............................................................................................4
5.0 DEFINITIONS:...........................................................................................................6
6.0 DOCUMENT AND RECORD CONTROL SYSTEM:.................................................8
7.0 PROJECT MANAGEMENT:....................................................................................10
8.0 QMS ORGANIZATION............................................................................................11
9.0 PRODUCT REALIZATION PROCESS:...................................................................20
10.0 PROCESS CONTROL SYSTEM:..........................................................................27
11.0 HANDING OVER OF WORKS:.............................................................................32
12.0 CONTROL OF NON-CONFORMING PRODUCT(S):...........................................33
13.0 TRAINING:.............................................................................................................37
14.0 DISTRIBUTION LIST:............................................................................................37
15.0 LIST OF ATTACHMENTS:.....................................................................................37
History of Revisions
Chapter/clause
Revision Revision
No. & text Reason for revision
No. date
affected
0 15/12/20149 NA Initial Submission
1.0 PURPOSE:
This project specific quality plan defines the Quality Management System of project
management, engineering & design, procurement, construction and commissioning
functions to comply with the requirements of contract document of Four Laning of
Sattanathapuram to Nagapattinam (Design Chainage Km 123+800 to Km 179+555)
Section of NH-45A (New NH-332) in the State of Tamil Nadu under NHDP Phase – IV
on Hybrid Annuity Mode.
Flyover No. 01
5.0 DEFINITIONS:
In the context of this project quality plan the following abbreviations, words or
phrases will be assigned to them:
CROSS REFERENCES:
The following documents are referred while preparing the Project Quality Plan
(PQP). The latest revision of the referred document shall be applicable
Table - 1
S
Description of Document Reference No.
#
Quality Management System:
1 ISO 9000
Fundamentals and vocabulary
Quality Management Systems -
2 ISO 9001
Requirements
Guidelines for performance
3 ISO 9004
improvements
4 Contract documents CA
Manual for Quality Control in Road and
5 IRC SP 112
Bridge Works
6 Specifications for Road and Bridge Works MORT& H
A. Drawings and other project specific documents received from the client
/Consultant / Contractors and its associates:
Step-1 Head of function / PM will study the document and decide to whom it
should be distributed.
Step-2 The planning at site will first enter the details in document master list
and take the number of copies required and prepare a document distribution list
in a register.
Step-3 Planning will put the “Controlled Copy” stamp and also the copy no on
each copy and issue to the identified users. When a revised document is
issued, it will be ensured by the document controller that the superseded
documents are withdrawn from all points of use and destroyed. In cases where
superseded document has to be preserved for record, the same shall be kept
separately after putting ‘SUPERSEDED’ stamp on it.
Step-4 Planning will maintain issue control register including its distribution.
Relevant details regarding document title, document number, issue (Revision /
Edition), Date of receipt & issue of the document in the distribution register,
signature of the recipient shall be taken on the document issue register as an
evidence of receipt of the document.
In cases where hard copies are required for distribution, the control shall be
exercised as stated in Steps 2 to 4 in para A above.
All the records identified will be codified to ensure proper identification and
traceability of the record as per the guidelines on document codification.
Format of the record will be designed and approved by Project Manager for
capturing the information in structured fashion, with easy traceability.
After the retention period for a file / register is over the record will be disposed
and new file / register for the same purpose will be created.
Owner
Is s u e o f w o rk o rd e r
& c o n tr a c t te c h n ic a l
s p e c if ic a tio n
HCC
M a n a g e m e n t o f D e s ig n s M a n a g e m e n t o f C o n s tr u c tio n
D e s ig n Yes S e le c t D e s i g n C o n s tr u c tio n /
o u ts o u r c in g P ro c u re m e n t
C o n s u lt a n t P la n n i n g
r e q u ir e d
No
S u b - c o n tr a c t S u p p li e r
P r e p a r e D e s ig n s m anagem ent m anagem ent
D e s ig n r e v ie w e d
& v e r if ie d C o n s tr u c tio n
Is s u e D r a w in g s I n s p e c tio n &
te s tin g
H a n d in g o v e r
WEL
Project Quality Plan
SNRP
PLN/Q1801/QC /01 Rev 00
Implement the performance targets set for the project execution team and
ensure delivery
Review Daily Progress and implement corrective actions as needed &/or as
suggested by Project management & Controls.
Ensure coordination amongst agencies.
Be a part of the project leadership team and ensure performance by all project
functions.
Implement project programs to improve productivity and reduce costs.
Ensure that quality parameters and HSE norms are complied with during
project execution.
Interact with Client and all external stakeholders in the project as required and
resolve issues if any.
Develop WBS along with Project head, plan project milestones, determine
resource requirement, propose deviations in productivity norms as per site
conditions, and prepare supplier schedules and initial project plan.
Prepare project annual/ monthly/ daily work plan and budgets in consultation
with Project Head.
Ensure timely and accurate planning, scheduling and expediting of resources
and adherence to productivity norms
Resolve all issues and queries which are escalated by the project execution
team
Monitor & report actual project performance against budgets & raise an early
warning on non-achievement of targets.
Implement the contracts appreciation document and ensure adherence to
contractual conditions
Develop and maintain client relationship
Ensure timely & accurate work measurement, billing, certification and collection
Ensure identification, documentation and submission of claims & variations.
Ensure documentation for Dispute Review Boards & arbitration
Ensure effective claims and recovery management
Validate contractual letters to be sent to Client/ Contracts Head- HO
Finalize sub contractor engagement, scope of work, rates (including rates for
variations)
Ensure validation of subcontractor’s bills as per contract conditions, including
reconciliation of material/ quantities
Carry field testing of materials/ works as per approved ITPs, obtains approvals
from Client / Consultants and record the testing activities in approved formats,
maintain the same.
Coordination with Execution team during testing of Materials/works and
suggest necessary Corrective & Preventive actions to control the
Nonconforming products/process.
Preparation of Project Handing over documents related with quality .
8.3.4.1 Responsibilities of the ‘Quality Engineer’:
Assisting Quality Manager in setting up the field laboratories
Day to day supervision of works of lab technicians
Ensure proper calibration of all laboratory equipment
Preparation of JMF for flexible pavement & concrete mix Design
Conducting laboratory and field tests on random basis
Calculation of test results from test observations carried out by lab
technicians
Maintaining respective records
Selection of borrow areas
Periodical checking of calibration of WMM plant, Hot mix plant, Batching
plants
Preparation of summary test results for monthly progress report
8.3.4.2 Responsibilities of the ‘Lab Technician:
Sampling of construction materials and preparation for testing as per IS code
Conducting laboratory test of aggregate, cement, soil, bitumen and other
materials
Recording of test observations
Inspection of batching plant, hot mix plant and WMM plant at the time of
production
Conducting field tests at site and recording test observations
8.3.5 Responsibilities of the ‘HSE Manager’:
Implementation of Occupational Health & Safety and Environment
management System at project site.
Project Quality Management includes the processes required to ensure that the
project will satisfy the needs for which it was undertaken.
Compliance is required as per relevant standards like MoRTH, IRC, NHAI Circulars,
BIS, BS, ASTM and AASHTO. Any exceptions require prior approval.
The Project QA/QC Head / Engineer reports and takes action as per the
directions of Project Manager/functional head at HO. The Project QA/QC
Head / Engineer is primarily responsible for effective administration of entire
project quality assurance/control activities and plays a pivotal role in liaison with
Client/Consultants/Sub-contractors/Vendors and other project involved
agencies in all Quality Management related matters such as finalization of
relevant Method Statements/Procedures, Inspection & Test Plans,
Inspection/Testing procedures etc.
9.2.2 Process for determining and reviewing of the design and Engineering
Inputs.
The various inputs as mentioned below will be taken into account while
carrying out basic engineering at preliminary stage:
Construction / Erections
Performance Criteria.
These inputs will be determined and reviewed for adequacy, completeness, and
clarity without being ambiguous, and not in conflict with each other.
A schedule for Design Review will be prepared and accordingly the review will be
done by competent Authority. Whenever external design agencies are engaged,
the schedule for design and design review will be prepared by the external
agency. Wherever so stipulated final Detail Engineering, Design, Drawings and
specification will be issued to Client for review before approval and acceptance
for issuing them to site for construction. Records of the results of reviews and any
necessary actions will be maintained.
9.3.1Process of Procurement:
a. For Material:
Project Quality Department will evaluate the quality of samples and approve
them, as per approved Inspection and Test Plan / Technical Specifications.
Revision No.0 Revision date 15.12.20149 Page 23 of 37
Project Quality Plan
SNRP
PLN/Q1801/QC /01 Rev 00
All Sub-contractors will have to execute the works as per the Contract
Specifications, detailed Engineering specifications, drawings and conditions
provided to them by the Construction Function as per the direction of
Management of Construction Function.
S E L E C T IO N O F S U B -C O N T R A C T O R C O N T R O L & P E R F O R M A N C E E V A L U A T IO N
R e s p o n s ib ility
D e c is io n t o o u t s o u r c e / A
P r o je c t M a n a g e m e n t s u b -c o n tra c t th e p a rt o f th e
F u n c t io n Job
P e r io d ic e v a lu a t io n o f
s u b - c o n tr a c to r 's
C o n s t r u c t io n P r e - q u a l i f i c a t io n , p e r f o r m a n c e in t e r m s o f
M anagem ent S e le c tio n o f s u b - c o n t r a c t o r C r it e r ia a s p e r Q u a lit y , S a f e t y
F u n c t io n / H e a d - f r o m t h e lis t o f r e g is t e r e d T e c h n ic a l S p e c .
S u b -c o n tra c ts @ H O s u b -c o n tra c to rs
C o n s t r u c t io n M a n a g e m e n t P la c e t h e w o r k O r d e r
F u n c t io n / H e a d - w it h T e r m s / c o n d it io n s A r e t h e e v a lu a t io n
S u b -c o n tra c ts @ H O & T e c h .S p e c . r e s u lt s m e e t in g t h e s e t
c r it e r ia r e q u ir e m e n t s
Yes fo r r e n e w a l o f
W o r k e x e c u t io n a s p e r R e g is t r a t io n
S u b -c o n tra c to r (s ) Tech. S pec. and
C o n s t . s c h e d u le s
R e n e w a l o f th e
R e g is t r a t io n &
c o n t in u e t o e n g a g e No
In s p e c t io n & T e s t in g th e s u b - c o n tr a c to r
C o n s t r u c t io n M a n a g e m e n t o f w o rks a s p e r
F u n c t io n in c lu d in g Q A / Q C S p e c if ic a t io n / C o d e s
D e - r e g is t e r t h e
s u b -c o n tra c to r (s )
C o n s t r u c t io n M a n a g e m e n t A re th e w o r k s
F u n c t io n in c lu d in g m e e t in g t h e No R e je c t / R e p a ir / R e d o
Q A /Q C T e c h .S p e c ./ th e w o rk (s )
r e q u ir e m e n t s
Yes
C le a r a n c e t o p r o c e e d Yes A re th e w o rk s
C o n s t r u c t io n M a n a g e m e n t No
a fte r a p p r o v a l fr o m m e e t in g t h e
F u n c t io n in c lu d in g C o n s t r u c t io n , Q A / Q C T e c h .S p e c ./
Q A /Q C F u n c t io n r e q u ir e m e n t s
G o to A
N o t e : F o r a ll t h e a b o v e O p e r a t io n s d o c u m e n t e d e v id e n c e / R e c o r d s s h a ll b e m a in t a in e d
In addition to Site Quality team, all project engineers are required to ensure that
the defects or deviation in material or workmanship are not tolerated. If not
corrected / improved it shall be bought to the notice of Project Manager. Apart
from the criteria mentioned in the Construction Methodologies, the QC Head shall
also ensure the routine quality check up of other aspects such as:
Keep a track on resources engaged for other non major activities.
Asses the availability of resources and material for carrying out the activity as
per planned schedule.
Monitoring of Non Conformities and taking appropriate action to close the
same.
Time to time awareness training to site personnel.
Training on technical aspects related to any construction activity.
Co-ordination with Project Head for any inputs/suggestions for improvement.
Interaction with client’s QC representative to asses their views if any.
Before carrying out any construction activities at project, testing facilities for the
raw materials shall be established at site as a part of quality check. Materials
used in the construction activities shall be tested in accordance with the standard
procedures. Project QC Head shall also be responsible in setting up of the field
laboratory for testing of materials, apart from carrying out various quality checks
based on Construction Methodologies. Only calibrated lab instruments shall be
used to carry out various test as per the standards / procedures and the outputs
shall be recorded as per the WEL standard formats attached herewith in
Annexure.
Project Inspection & Test Plan has been established and required to be followed.
Refer to relevant ITP for various activities.
10.2 The type of inspection and QC checks to be carried out for different
areas of construction are as mentioned below:
The areas listed above and the Quality aspects are not limited and are broadly
mentioned to describe the general inspection and checks to be carried out.
Project Quality Head shall identify the areas/activities specific for any particular
project and shall generate the ITPs for the same. ITP will be prepared
describing product characteristics, controlling specification, verifying document,
frequency of inspection/test and inspection category.
During the execution of the Activity all the applicable inspection and test
requirements as per contract specifications / good engineering practice and
other relevant applicable codes / standards / specifications etc. is identified in
Inspection and Test Plans (ITP) for various sub-activities. Following parameters
shall be considered during the preparation of the ITP:
Where, when and how the WEL intends to engage qualified third parties (if
required) to perform inspections or testing.
The following steps will be followed for calibration of various measuring and
monitoring equipment at field testing laboratory.
a) Ensure that the adequate care is taken while selecting the measuring and
monitoring equipment with suitable specification, including range to be
measured for the full-scale range of the device, accuracy and robustness,
under specified environmental conditions.
b) Ensures that the initial calibration has been carried out prior to first use, in
order to validate the required accuracy (accuracy and precision). All
instruments shall be calibrated with traceability to National / International
Standard.
c) Test and verify periodically as specified, where appropriate, the software and
procedure controlling automatic test equipment.
d) The Quality function at site will be responsible for calibrations and will prepare
a calibration plan indicating therein the frequency of calibration, method of
calibration, accuracy required and other details as mentioned in the format.
e) Recall periodically for adjustment, repair and recalibration, keeping in
consideration the following:
i. The manufacturer’s specification
ii. Results of prior calibration
iii. The method and extent of use and
iv. Maintain their required accuracy in use
f) Evidence through a record be kept indicating the identification of the
instruments, frequency of recalibration, calibration status.
g) Document and maintain records or evidence to indicate the traceability
Prior to the completion of the project, when substantial completion has taken
place and adequate enough to make the project functionally useful, the project
management, construction management function will start collecting, storing,
updating and retrieving of relevant information of completed works / structures
of the project and ensuring that these information is checked for validity.
The facility will be handed over to the owner in accordance with the contract.
All project team members are responsible for identifying and reporting any non-
conformity found in process or activities within their area of responsibility. The
non-conformity so found shall be identified by suitable means so as to prevent
its unintended use or delivery.
Action to be initiated for all Internal / External NCR’s within 7 days from the date
of issue. Monthly summary statement to be provided with explanation of aging
NCR’s not closed. Repetition of same or similar non conformity shall be strongly
discouraged.
4) Non conformance report will consist of the following information about the
observed Product Non conformity:
12.3 Disposition:
Rework:
If a rework is needed to overcome the Non-Conformity then it will be done as
per the approved procedure. This rework will be re-inspected and tested so as
to confirm that Non-Conformity does not exist and the final product is as per the
customer’s specified requirement.
Reject:
If the Non-Conforming structure, equipment, material or activity cannot be
made fit for the process then it will be rejected. If a material, equipment or
activity is found Non-Conforming at receipt, it will be returned to the
manufacturer, supplier or originator. And the Non-Conformance report will be
submitted along with a claim statement for new equipment, material or
document.
Use as is:
In cases of Minor Non- conformities where the Non-Conforming product can be
used for the process, which will not deviate from the customer’s specified
requirement at final stage then no action will be taken and the process will
continue. This concession will be authorized.
The flow chart depicted in the subsequent page outline the established
Nonconformity control system.
R e s p o n s ib ilit y
P ro d u c t u s e r N o n - - C o n f o r m it y Id e n d i t i e d
Q M P e rs o n n e l
P ro d u c t u s e r P r e v e n t e d f r o m u n in t e n d e d
u s e / d e l iv e r y
P ro d u c t U s e r Is s u e o f N o n - - c o n f o r m it y N o n -C o n fo r m a n c e
Q M P e rs o n n e l R e p o rt R e p o rt
H O D /P ro d u c t u s e r T a k e r e m e d ia l a c t i o n
( C o r r e c t io n )
H O D /P ro d u c t u s e r/ R e v i e w o f N C f o r p r o p o s in g
Q M P e rs o n n e l C A /P A
Im p le m e n t a t io n o f C A / P A
H O D /P ro d u c t u s e r w it h in a g r e e d d a t e
Is t h e C A / P A No
Q M P e rs o n n e l v e r if ie d a n d In f o r m t o H O D
f o u n d e f f e c t iv e ?
Yes
Q M P e rs o n n e l C lo s e t h e N C
13.0 TRAINING:
Training and Evaluation of all Project involved personnel including workmen in a
continuing process to determine the necessary work competence of people to
perform the work effectively and efficiently, Identification of necessary Training
needs and imparting training.