COST ESTIMATES FOR CHURCH REFLECTED CEILING PLAN

MATERIALS LABOR
ITEM NO. DESCRIPTION UNITS QTY UNIT PRICE AMOUNT UNITS QTY UNIT PRICE AMOUNT
CEILING WORKS SQM 116.00 103.45 12,000.00
1.00 2" X 2" X 10' GOOD LUMBER BF 1,170.00 25.00 29,250.00
2.00 4"X8"X5mm FIBER CEMENT BOARD/HARDIFLEX PCS 61.00 350.00 21,350.00
3.00 # 2" CWNAIL KG 15.00 60.00 900.00
4.00 CEILING CORNICE 1"X1"X10' PCS 28 200.00 5,600.00
5.00 SCREWS pcs 2379 2.00 4,758.00
PAINTING WORKS SQM 116.00 40.00 4,640.00
1.00 PRIMER-PERMACOAT FLAT LATEX GAL 6.00 500.00 3,000.00
2.00 SPOT PUTTY 7311 GAL 6.00 300.00 1,800.00
3.00 TOP COAT-PERMACOAT FLAT LATEX 701/705/710 GAL 10.00 500.00 5,000.00
4.00 PAINT BRUSH & ROLLERS LOT 1.00 400.00 400.00

TOTAL 72,058.00 16,640.00


GRAND TOTAL 88,698.00

NOTE: RECESSED LIGHT BULBS & OTHER LIGHTINGS NOT INCLUDED IN THIS ESTIMATES