SASSCO Intermediate Check Instruction Sheet

SAUDI ARABIAN SENSING SOLUTIONS CO., LTD.

Title: Intermediate Check Instruction Sheet Prepared by:


Equipment: 87V Digital Multimeter Fluke Omer Nadeem
Approved
Asset no: SS-128 by:
Abdulwahab Almajed

Date of Intermediate Check: __________________

Instruction Checklist for Intermediate Check / Maintenance Check


(Mark the Figures for any Visible Defect)

Figure 01 : Front Panel Schematic

Page 1 of 2
SASSCO Intermediate Check Instruction Sheet
SAUDI ARABIAN SENSING SOLUTIONS CO., LTD.

Figure 02 : Rear Panel Schematic

Instruction Sheet for Intermediate Check / Maintenance Checklist


Instruction Detail(a) Check Box(b) Remarks
Ports Connection Grip Check
(Front Panel).

Battery Power Check

Fuse Check
Stabilization time of 30 Minutes
for the Equipment

Check zero value of the


equipment when fully stabilized

Functions check by selecting all


the menus

Buttons Functionality Test

Cleaning Terminals with Swab /


Removal of Partcles Check
Intermediate Readings Check(c)
(a) Instruction details to be followed as it is, for any further calcification refer to manual in the Server
(b) Mark Check Box with Alphabets A: Accepted , AC: Accepted with Comments, R: Rejected, RE: Repaired
(c) Reading Data Sheet attached for filling.

Date:_________________ Check Done By: ___________________

Page 2 of 2