Sei sulla pagina 1di 6

7/20/2018

Introduction
• Utilities 
CE‐323 Quantity and Cost  – Sewerage System 
– Water Supply Schemes 
Estimation – Electricity 
– Gas Pipelines
Dr. Farrukh Arif

CE‐323 Quantity and Cost Estimation  CE‐323 Quantity and Cost Estimation 
1 2
Dr. Farrukh Arif Dr. Farrukh Arif

Quantities for Utilities Types of Pipes
• Stages of Water supply Scheme • Asbestos Pipes. • Galvanized Iron Pipes (G.I.)
– Excavation (Cubical i.e. Cubic Units)
– Sand Cushions (Cubic Units)
– Pipe laying (Rft)
– Laying pipes in trenches over sand cushions 
complete with the joining arrangement 
– Backfill
• Cement Concrete (C/C) or 
– Valves 
Reinforced Concrete RCC 
– Chambers
Pipes.
– Control

CE‐323 Quantity and Cost Estimation  CE‐323 Quantity and Cost Estimation 
3 4
Dr. Farrukh Arif Dr. Farrukh Arif

1
7/20/2018

Important Specs. Pipe Joints
• In sewer lines we have to maintain a slope as  • Asbestos Pipe Joints
it travels under gravity.
• The emphasize in that case is therefore more 
on invert levels.
• Water lines usually we do not need slope. 
• Pipe must be placed 2’‐6” below from ground  Collar + Rubber Ring (made up of asbestos)

level (G.L.)

CE‐323 Quantity and Cost Estimation  CE‐323 Quantity and Cost Estimation 
5 6
Dr. Farrukh Arif Dr. Farrukh Arif

Pipe Joints Pipe Joints
• C/C Pipe or RCC (Typically Sewer Pipes)
• G.I. Pipes are gas welded.
• To avoid rust, “Safeeda’ is applied on G.I. 
Pipes. 

• Cocking arrangement  Cocking arrangement 
– Cement 
– Jute
– Concrete
– Duracrete is used as fillings if any gaps are formed. 

CE‐323 Quantity and Cost Estimation  CE‐323 Quantity and Cost Estimation 
7 8
Dr. Farrukh Arif Dr. Farrukh Arif

2
7/20/2018

Typical Cross‐Section
Backfilling
Water Pipeline
• If smaller diameter pipe (i.e. <18”) is being 
2’‐6”
laid, backfilling, compaction, removal of 
surplus is included in excavation
1’‐0”’ min

Sand Cushions • If diameter > 18”, counted as separate item. 
3’‐0”

Pipeline is provided 3’‐6” away from the property line.

CE‐323 Quantity and Cost Estimation  CE‐323 Quantity and Cost Estimation 
9 10
Dr. Farrukh Arif Dr. Farrukh Arif

Valves Example 1‐Excavation
• Gate Valve
• No Return Valve • A utility contractor is to install the sewer line 
whose plan and profile is shown in figure 1. 
The trench is to have the cross section shown 
in the figure 2. Using the average‐end method, 
determine the volume of excavation in cubic 
• Sluice Valve yards needed to install the sewer line. The 
• Bibcock Valve excavation of the manhole is set to be 6 feet 
by 6 feet and 2 feet deeper than the flow line 
at the manhole. 
CE‐323 Quantity and Cost Estimation  CE‐323 Quantity and Cost Estimation 
11 12
Dr. Farrukh Arif Dr. Farrukh Arif

3
7/20/2018

Figure 2‐Sewer Line Cross Section at 
Figure 1‐Sewer Line Profile
STA 14 + 30.2
Existing Manhole New Manhole 3.62’ 3.62’

Sewer Line 150’ @ 2%

4.82’
1

7.82’
1150 0.75
Finish Grade
STA 14 + 30.2
STA 15 + 80.2

3.00’
RIM 1148.20
RIM 1146.71

FL 1143.88 0.5’

2.00’
1140
FL 1140.88

CE‐323 Quantity and Cost Estimation  CE‐323 Quantity and Cost Estimation 
13 14
Dr. Farrukh Arif Dr. Farrukh Arif

Example 1‐Solution Bedding
• Kindly refer to the class lecture

DP DP
DB
Y
DB a

W W

CE‐323 Quantity and Cost Estimation  CE‐323 Quantity and Cost Estimation 
15 16
Dr. Farrukh Arif Dr. Farrukh Arif

4
7/20/2018

Bedding Example 2‐Bedding
a = Cos‐1 (1‐2Y) • The pipe in Example 1 is bedded in gravel. The 
DP depth of gravel is 1 foot, and the pipe is 
Where Y = Depth of the pipe in the Bedding bedded into the gravel 6 inches. The outside 
DP = Outside Diameter of Pipe diameter of the sewer pipe is 11 inches. 
Ignoring the manhole, determine the quantity 
Volume =  W(DB) – [a‐ (Sin a) (Cos a)] L of gravel needed for the sewer line. 
(DP)2
4
Where, 
W = Width of Trench at the Bottom • Solution discussed in class
DB = Depth of the bedding 
A = angle in radians
L = length of the trench CE‐323 Quantity and Cost Estimation  CE‐323 Quantity and Cost Estimation 
17 18
Dr. Farrukh Arif Dr. Farrukh Arif

Example 3‐Bedding  Example 4‐Utility Lines
• The pipe in example 1 is surrounded by gravel.  • Determine the utility components needed for the 
The depth of the gravel is 2 feet. The outside  sewer line in example 1. The pipe is available in 
20‐foot lengths and includes a bell with gasket at 
diameter of the sewer pipe is 11 inches.  one end. 
Twelve inches of bedding is also placed below 
• Solution 
the manhole. Determine the quantity of gravel  – gasket for sewer pipe
needed for the sewer line.  – Flat manhole top
– Metal ring
– Manhole Cover
• Solution discussed in class
– Eight number of 20 ft long pipes
CE‐323 Quantity and Cost Estimation  CE‐323 Quantity and Cost Estimation 
19 20
Dr. Farrukh Arif Dr. Farrukh Arif

5
7/20/2018

Example 5‐Backfill
• Using the excavation in example 1 and the 
bedding quantity from example 2, determine 
the volume of the backfill for the sewer line in 
example 1. 

• Solution discussed in class

CE‐323 Quantity and Cost Estimation 
21
Dr. Farrukh Arif

Potrebbero piacerti anche