Sei sulla pagina 1di 10

TUNNEL CONSTRUCTION SITE VENTILATION AND COOLING: AN INTEGRATED

FLOW AND HEAT LOAD SOLVER APPLIED TO THE LYON-TURIN HIGH-SPEED


RAILROAD TUNNEL PROJECT

Uwe Drost, Marco Bettelini, INELMEC SA, Switzerland

ABSTRACT
Ventilation is required during the construction of any tunnel. This is true whether the tunnel is con-
structed by blasting, boring or placing prefabricated tubes in a trench. Temporary ventilation is neces-
sary to provide a suitable, safe working environment for the construction workers. Since many flam-
mable or airborne toxic gases, dust mist and fumes are released during the construction process, these
contaminants can only be removed by ventilation. A dedicated, well-tailored ventilation system is
compulsory in the presence of natural gas in terms of flammability and asbestos in terms of toxicity.
Ventilation systems for construction sites must be flexible in order to grow and move with the con-
struction progress. They may therefore imply rather complex flow pattern including leakage flows,
booster stations, filtering and cooling devices, conjunctions and disjunctions etc.

Depending on the excavation length and method as well as the geothermal and ambient boundary con-
ditions, cooling of the working environment may also be required. Considerable heat may be trans-
ferred to the tunnel air from the rock mass, from the boring machine, other machinery and vehicles as
well as from cement setting. Especially heat transfer from the rock-mass is complex, because it is tran-
sient in time due to the gradual cool-down of the rock from the tunnel wall.

Three major construction ventilation schemes are typically applied:


- forced ventilation employing flexible ducts to introduce fresh air directly to the work sites.
- exhaust ventilation sucking consumed and loaded air out of the tunnel employing reinforced flexi-
ble ducts or spiral steel ducts.
- circulation ventilation schemes being mainly used in double bore projects, where fresh air is intro-
duced via one bore and consumed air is extracted via the second.
Obviously, combinations of these schemes are also often used in dependency of the local require-
ments.
The actual choice of the ventilation system for a specific site depends on one hand on the complexity
of the project (excavation length and diameter, single or double bore, cooling requirements, intermedi-
ate multifunction stations, etc) and on the other hand on the national or local legislation, directives,
codes and guidelines, which may differ largely from one country to another.

An integrated flow and heat transfer design tool capable to resolve all of the above described ventila-
tion schemes is presented in the present paper. Examples are outlined and results of the construction
site ventilation and cooling design for the Lyon-Turin high-speed railroad system are presented to il-
lustrate the tools capacity.

1 (10)

TMI International Conference:


Tunnel protection and security against fire and other hazards, 15-16. May 2006, Torino, Italy
NOMENCLATURE For important current railway tunnel projects in
2 Europe, namely
A m cross section
Bi - Biot number • Lötschberg base tunnel
Cp J/(kg K) thermal capacity • Gotthard base tunnel
D m diameter • Lyon-Turin base tunnel (LTF)
f* m2/m2 active leakage area
Fo - Fourrier number the depth of coverage reaches values beyond
g - usage factor 1’500-2’000 m, thus rendering the thermal as-
k W/(m K) thermal conductivity pect a most important one with rock tempera-
M kg/s mass flow tures on the tunnel trajectory level in excess of
Nu - Nusselt number 40-50°C. Exemplarily, the temperature evolu-
p Pa total pressure tion forecast for the LTF project is depicted in
P kW power Diesel engines Fig. 1.
Pr - Prandtl number
50

Val Clarea
Q W heat flux

Modane
La Praz
St. Martin
45
R m radius
40
Re - Reynolds number
t s time 35

t m thickness T rock [°C]


30

S m2 surface 25

T °C temperature 20

u m/s speed 15

U W/m2K total thermal resistance 10

V m3/s volume flow 5


Bussoleno
Base tunnel
x m distance 0
0 10000 20000 30000 40000 50000 60000 70000

α
Pm (Tunnel axis) [m]
W/(m2 K) convection coefficient
Λ m2/s thermal diffusivity Fig. 1: Exemplary temperature profile, LTF.
η - efficiency
λ - friction coefficient
ρ kg/m3 density REGULATIONS & RECOMMENDATIONS
ζ - pressure loss coefficient The present paper is somewhat focused on the
European LTF project. Consequently, mainly
the relative prescriptions shall be discussed.
INTRODUCTION
The main aspects, which need to be considered France
for an appropriate design of a tunnel construc- In France, two recommendations deal with un-
tion site ventilation and cooling system, are: derground construction site ventilation systems,
namely the Recommendation R352 of the
• Removal of the pollutants (exhaust gases of CNAM [1] and the more recent AFTES Rec-
the vehicles, blasting fume, dust). ommendation [2].
• Establishment and maintenance of a climatic
state (temperature, humidity) in accordance Italy
with the required physical activities of the The « Presidential decree » 320 from 1956 is the
work force in the underground construction Italian legal basis. However, this document is
sites. not very specific in regard to construction site
The main sources of heat release, which are ventilation and only regulates the fresh air need
typically encountered, are fourfold: of a worker, that the air shall remain breathable
and as far as possible exempt of pollutants.
• The rock mass and the tunnel walls. Regional public administrations, however, do
• The tunnel-boring machine. recommend more specific conditions, such as
• The vehicles and other motorized equip- the “Regione Emilia-Romagna” [4] and particu-
ment. larly in regard to the LTF project the “Regione
• The cement. Piemonte” [5].

2 (10)

TMI International Conference:


Tunnel protection and security against fire and other hazards, 15-16. May 2006, Torino, Italy
WORK SITE VENTILATION
Switzerland, CH:
Fresh air requirements, example LTF
Although Switzerland is not directly involved in
The vehicles typically in service within a con-
the LTF project, the experience collected during
struction site are listed in Tab. 2 both for con-
the ongoing AlpTransit projects is currently
ventional excavation by blasting as well as for
knowledge-transferred in rather large scale. In
boring-machine tunneling. Based on a fresh air
regard to tunnel construction site ventilation,
rate of 50 l/s per CV, 48.3 m3/s are required for
Switzerland disposes of a specific and detailed
blast heading whereas for the mechanized head-
regulation [6], which is quoted regularly also in
ing 26.6 m3/s are necessary. As the cross section
other countries.
of the main tubes of the LTF project is approx.
Value
85 m2, the fresh air requirement for the boring-
machine advances must be increased to 42.5

I: Piemonte
m3/s to fulfill also the AFTES minimum speed
I: Emilia-
Romagna
AFTES
CNAM
France

France

rule of 0.5 m/s.


CH

Fresh air 50 l/s 50 l/s work: 50 l/s 50 l/s WORK SITE COOLING
need per 50-74 l/s
CV Die- trans- Heat load from the rock mass
sel port:
25-37 l/s The temperature profile along the tunnel axis is
max. depicted in Fig. 1. The heat transfer calculation
without from the tunnel wall to the air is rather complex,
filter
Min. air 0.3 m/s 0.5 m/s 0.3 m/s 0.2 m/s 0.3 m/s because it depends at each axial location on the
speed (0.5 m/s excavation time history and the related wall
if CH4) temperature cool down. The influencing pa-
Max. air 1.5 m/s
speed rameters are:
Tem- 26°C 28°C 25°C
perature, humid dry wet bulb • Local convective heat transfer coefficient
work site (function of Reynolds number, wall rough-
Recom- exhaust exhaust circul., blowing exhaust
mended blowing
ness and tunnel diameter)
type • Initial wall temperature (temperature of the
Tab. 1: Comparison of prescriptions.
rock mass)
• Air temperature in the tunnel
• Tunnel age, function of excavation length
Tab. 1 compares the cited prescriptions. In terms and excavation speed.
of fresh air needs, only the Swiss values differ
somewhat in function of Diesel engine dust- For the present calculations, the following con-
filter presence and the type of the engine em- stant physical properties of the rock are consid-
ployment, either at the work front or down road ered:
in the tunnel. In terms of minimal air speed, the • Thermal capacity: 900 J/(kg K)
recent French AFTES recommendation is the • Conductivity: 2.3 W/(m K)
most restrictive requiring a least 0.5 m/s. It is
• Density: 2600 kg/m3
also the only document, which defines an upper
bound for air speed (1.5 m/s). Concerning tem- The radial heat transfer may be resolved nu-
peratures the Italian prescription for LTF from merically or analytically. In the former case,
Piemonte is the most stringent allowing a high- also variable properties in terms of space and
est worksite wet bulb temperature of only 25°C. temperature may be included.
In regard to the ventilation system type, both Additional heat input related to warm water
French recommendations emphasize the impor- seepage through the rock may be taken into ac-
tance of efficient dust and blasting fume capture count with an enhancement factor applied to the
at its origin and removal to the exterior, imply- thermal conductivity.
ing thus the employment of exhaust ventilation
systems.

3 (10)

TMI International Conference:


Tunnel protection and security against fire and other hazards, 15-16. May 2006, Torino, Italy
Tab. 2 : Exemplary fresh air requirements, based on 50 l/s and CV.

Heat dissipated by engine-driven equipment by the thermal inertia of the rock, which releases
In case of tunnel boring-machine (TBM) exca- the absorbed heat rather slowly.
vation works, the latter represents a major The heat dissipated by other equipment is less
source of heat release. About 60% of the ab- important. For Diesel engine driven vehicles, the
sorbed power (approx. 5 MW for an excavation mechanical power values listed in Tab. 2 must
diameter of 10 m) is used to detach rock chips, be corrected with the engine efficiency of about
which are hereby heated-up to a temperature 30% to obtain the total dissipated heat.
approx. 40°C above its initial value. The re- The heat dissipation of the ventilation fans is ob-
maining 40% are equipment-related losses, tained considering a global fan efficiency of
which are directly cooled away. These losses 70%.
develop within the electric and hydraulic drives
Heat of cement setting
or the frequency converters.
Cement setting is an exothermal chemical proc-
ess, during which the hydration heat is released.
Power for rock chip
It amounts to 380 kJ of heat per kg of cement. In
detachment, 60% the present calculations, 400 kg of cement are
Total power
boring machine, 100% taken into account for each m3 of concrete.
Heat released during mucking
The muck spoil cools down when transported
away by mucking trains or trucks. As a conser-
Friction heat Borer cooling Electric and hydraulic
vative approach, total cool down is assumed
(bearing), 5% 15% drive losses, 20% here.
Fig. 2: Typical boring-machine heat balance. Environmental conditions
The typical time usage factor of a boring- The external ambient conditions of the air fed
machine is 30%-50%. The remaining time is re- into the tunnel work site are usually taken as fol-
quired, among others, for its displacement, ma- lows:
terial supply and maintenance. Taking into ac-
• Temperature: 20°C
count these periods of inactivity, the necessary
• Initial humidity: 100%
tunnel air cooling power may be reduced pro-
portionally. The cooling system design basis is Evaporative cooling is therefore normally not
thus rather the average power consumed instead considered, as it depends heavily on the initial
of the installed power. This approach is justified humidity conditions and could yield an under

4 (10)

TMI International Conference:


Tunnel protection and security against fire and other hazards, 15-16. May 2006, Torino, Italy
dimensioned cooling system during hot and hu- The computation is then carried out sequentially
mid periods. for each segment resolving first the flow in the
tunnel itself (Eq. 1) and thereafter in the duct for
COOLING CONCEPT FOR LTF blowing ventilation (Eq. 2) or vice-versa for ex-
haust ventilation, respectively.
For the LTF project, a modular, flexible and eas-
ily extensible remote cooling system has been Mleakage
i−1
Miduct = Miduct
−1 −
adopted, which relies on combined chiller and Nduct
radiator units being distributed in the areas Viduct
uiduct =
where cooling is required (Fig. 3). This type of A iduct ρ iduct
equipment is available with cooling capacities of (
Q iduct = S iduct ⋅ Uiduct Tiduct − Ti )
approx. 150 to 400 kW and can be easily ac- Q iduct − Q ifan + Q iduct,cool
Tiduct = Tiduct
−1 −
commodated within the working areas to di- Miduct ⋅ Cp
rectly cool the tunnel air. The heat is removed ρ iduct duct duct ⎡ ⎤
∑ζ
dx i
p iduct = p iduct
−1 − ui ui ⎢λ duct duct +
duct

from these chillers to a water ring piping, which 2 ⎣⎢ Di
i
⎦⎥
in turn is re-cooled externally in a cooling tower. dp = p iduct − p i
dp
uleakage =
Cooling tower
ρ iduct
2
(
1 + ζ Leakage )
Mleakage
i = Nduct ⋅ uleakage ⋅ S iduct ⋅ S leakage ⋅ ρ iduct

Water pump
Eq. 2: Duct computation
Chiller/radiator unit
The transient heat transfer from the wall to the
air is either resolved numerically with a radial
25°C
heat conduction explicit scheme and a convec-
35°C Boring-mach.
tive boundary condition:
∂T Λ ∂ ⎛ ∂T ⎞
= ⎜r ⎟
Boring-mach.
∂t r ∂r ⎝ ∂r ⎠
∂T
−λ = α(Tair − T(0, t ))
Fig. 3: Cooling concept. ∂t r = 0
for j = 1 :

CALCULATION SCHEME
( )
Tjp +1 = 2 ⋅ Fo Tjp+1 + Bi ⋅ Tair + (1 − 2 ⋅ Fo − 2 ⋅ Bi ⋅ Fo) ⋅ Tjp
for j > 1 :
The tunnel ventilation and cooling calculation
code uses a one-dimensional model to solve the
⎛ 1
Tjp +1 = Λdt⎜ (
T p − Tjp−1 +
⎜ 2R j dR j + 1
1
dR 2
) (
Tjp+ 1 + Tjp−1 − 2Tjp )⎞⎟⎟ + T p
j
⎝ ⎠
equations in a discrete manner based on ele- Eq. 3: Radial transient heat conduction, numerical
ments of constant length dx. The tunnel is fur- solution.
thermore divided into functional segments ac-
cording to the local ventilation schemes applied or with a semi-infinte plane wall analytical solu-
(blowing, exhaust or circulation ventilation). tion:
Twall (t ) − Ti
Mi = Mi−1 + Min (
i − Mi
out
+ Mleakage ) = − exp(ω2 )erfc (ω)
i Tair − Ti
Mi
ui = α Λt
A iρi ω=
λ
NuDi (ReD , Pr, roughness ) ⋅ k
αi = i Eq. 4: Transient heat conduction, analytical solu-
D hyd
i tion.
(
Q iwall = S i ⋅ α i Tiwall − Ti ) The latter accelerates the calculation considera-
PiDiesel gi
Q iwall + Q iduct Nduct + + Q iTBM + Q iconcrete − Q icool bly, but is valid only for constant rock properties
ηDiesel
Ti = Ti−1 + and sufficiently large tunnel diameters to ap-
Mi ⋅ Cp
proximate the actually curved surface with a
Mi ⋅ c p ⋅ Ti + Mleakage c p ⋅ Tiduct
Ti = i
plane wall. Furthermore, a constant air tempera-
Mi ⋅ c p + Mleakage cp
i
ture must be also assumed, whereas the numeri-
ρi ⎡ ⎤
∑ ζ ⎥⎥
dx cal solution may account for time-dependent
p i = p i−1 + ui ui ⋅ ⎢λ (ReD ,roughess) hydi + i
2 ⎢⎣ i
Di ⎦ tunnel temperature profiles.
Eq. 1: Tunnel computation

5 (10)

TMI International Conference:


Tunnel protection and security against fire and other hazards, 15-16. May 2006, Torino, Italy
Fig. 4: Modane intermediate site with forced ventilation system.

Fig. 5: Modane intermediate site with exhaust ventilation system.

Fig. 6: Modane intermediate site with circulation ventilation system.

6 (10)

TMI International Conference:


Tunnel protection and security against fire and other hazards, 15-16. May 2006, Torino, Italy
Duct characteristics The results presents hereafter have been ob-
The ventilation duct leakages and friction losses tained for an S-class duct (new material, very
are calculated according to the values given in carefully mounted).
[2] and [6] for various duct types. As the maximum duct pressure considered is
limited to 2500 Pa, the duct must be split into
Duct type Friction co- Active leakage two segments with a booster ventilator station
efficient, λ surface, f*
Flexible forced, class S 0.015 5 mm2/m2
after about 6000 m (Fig. 7).
Flexible forced, class A 0.018 10 mm2/m2 To avoid the inflow of polluted air returning
Flexible forced, class B 0.024 20 mm2/m2 through the tunnel, the fresh air flowrate exiting
Flexible exhaust, reinforced 0.025 5-20 mm2/m2
with helical-wound spring
the first segment must exceed the flowrate of the
steel booster ventilator by 10-20% [2], [6], Fig. 8.
Sheet metal duct 0.010 2 mm2/m2 This flow interaction is fully taken into account
both aerodynamically as well as in terms of mix-
FORCED VENTILATION EXAMPLE ing temperature. The same is true for the con-
tinuous leakage flowrate of the duct. In addition
Forced ventilation schemes are generally not to this mixing temperature effect, the conduc-
considered for the LTF project because of the tive/convective heat transfer from the tunnel into
specific French guidelines [1] and [2], which the duct is also accounted for.
strongly recommend dust and blasting fume cap-
12.0
ture at its origin and removal to the exterior.
10.0
The following example of blowing ventilation is
8.0
nevertheless based on a LTF excavation geome-
Air speed [m/s]

6.0
try, namely the eastern advancements of the
4.0
Modane intermediate construction site (Fig. 4). u tunnel
2.0
The main characteristics are: u duct
0.0
o Max. excavation length 9.8 km -2.0
o Excavation type TBM -4.0
o Advancement 4500 m/a 0 2'000 4'000 6'000 8'000 10'000
Distance [m]
o Excavated diameter 10.4 m
o Excavated section 85 m2 Fig. 8: Modane eastern bores with blowing ventila-
o Diameter after shotcrete lining 9.8 m tion, air speed.
o Section after shotcrete lining 75 m2 The temperature evolution of the tunnel and duct
o Final diameter 8.4 m air and the tunnel wall for a rather continuous
o Final section 51 m2 rise of the rock temperature from the intermedi-
o Fresh air requirement (Tab. 2) 27 m2/s ate site is depicted in Fig. 9. The duct air taken
o Air required for 0.5 m/s 42.5 m3/s outside rises due to heat exchange along the first
o Duct diameters 2m duct segment. At the booster station the duct
o No. of ducts 2 temperature jumps by some degrees due to the
o Max. duct pressure 2500 Pa fan heat input and then decreases slightly further
inwards due to the cooler surrounding tunnel air,
3'000
before being released through a chiller unit at
p tunnel the excavation site.
2'500
p duct The back-flowing tunnel air is cooled in the
work areas at and downstream of the excavation
Pressure [Pa]

2'000

1'500 site and exhibits therefore a saw tooth profile


due to the discrete chiller locations. At the
1'000
booster station, a sudden temperature reduction
500 of the tunnel air takes place due to mixing with
0 the surplus fresh air from the first duct segment.
0 2'000 4'000 6'000 8'000 10'000 The wall temperature dips rapidly from its
Distance [m]
maximum value at the excavation site because
Fig. 7: Modane eastern bores with blowing ventila- of the transient cooling process of the rock mass
tion, pressure evolution. and thus the growing thermal boundary layer in
the solid.

7 (10)

TMI International Conference:


Tunnel protection and security against fire and other hazards, 15-16. May 2006, Torino, Italy
45 equipment requirements largely. In order to re-
40 spect the minimum air velocity of 0.5 m/s (Fig.
35
12), a 60% higher initial flowrate is required be-
Temperature [°C]

30
cause of the increased leakage rates and higher
25
20
friction, which in turn renders 3 instead of 2
15 T rock
booster stations necessary, Fig. 11.
10 T wall 20.0
T duct
5 T tunnel
0 15.0

Air speed [m/s]


0 2'000 4'000 6'000 8'000 10'000
Distance [m] 10.0

u tunnel
Fig. 9: Modane eastern bores with blowing ventila- 5.0
u duct
tion, temperatures.
0.0
140%
-5.0
120%
0 2'000 4'000 6'000 8'000 10'000
100% Distance [m]
Loading level

80% polluted air fraction


(T actual)/(T allowed)
Fig. 12: Modane eastern bores with blowing ventila-
60% tion, air speed with A-type ducts.
40%

20% EXHAUST VENTILATION EXAMPLE


0%
0 2'000 4'000 6'000 8'000 10'000
The schematic of an exhaust ventilation system
Distance [m]
for the excavation sites departing from the Mo-
dane intermediate construction site is depicted in
Fig. 10: Modane eastern bores with blowing ventila-
Fig. 5. This approach is fully compatible with
tion, pollution and thermal loading levels
with S-type ducts.
the French recommendations and does not re-
strict the infrastructure, as the crossway may
Fig. 10 depicts the pollution and thermal loading remain open.
levels within the tunnel, with the pollution level
referring to the ratio of fresh air in respect to the To ensure that the captured dust loaded air is
consumed air from Diesel exhaust gases. At the safely extracted without any leakage, the ex-
excavation site, fresh air arrives, which is haust dust must be operated at negative pressure.
quickly loaded by the local machinery and vehi- Typical ventilation spiral steel sheet ducts sup-
cles in the backward working areas. Down- port at the most about 750 Pa depression, requir-
stream of the working areas, only weak linear ing thus a certain number of booster stations.
pollution sources representing the transportation
trucks add additional loading, which is however The main characteristics of the ducts are now:
overbalanced by the continuous fresh air leakage o Duct diameter 2m
of the ducts. o No. of ducts 2
3'000
o Max. duct pressure -750 Pa
p tunnel
2'500 0
p duct
-100
Pressure [Pa]

2'000 -200
Pressure [Pa]

1'500 -300
-400
1'000 -500

500 -600
-700 p tunnel
0 -800 p duct
0 2'000 4'000 6'000 8'000 10'000
-900
Distance [m]
0 2'000 4'000 6'000 8'000 10'000
Distance [m]
Fig. 11: Modane eastern bores with blowing ventila-
tion, pressure evolution with A-type ducts. Fig. 13: Modane eastern bores with exhaust ventila-
tion, pressure evolution.
Employing standard quality A-type ducts instead
of the high quality S-type ones changes the The results for the present geometry show, that 4
booster stations are required, Fig. 13.
8 (10)

TMI International Conference:


Tunnel protection and security against fire and other hazards, 15-16. May 2006, Torino, Italy
4.0 CIRCULATION VENTILATION EXAMPLE
2.0
The layout of the Modane construction site with
0.0
a circulation ventilation system is depicted in
Air speed [m/s]

-2.0 u tunnel
Fig. 6. This system has a strong impact on the
-4.0 u duct
construction infrastructure and logistics, as it re-
-6.0
quires an aerodynamic separation of the two
-8.0
parallel tunnel bores and thus closed crossways.
-10.0
-12.0 700
0 2'000 4'000 6'000 8'000 10'000
600
Distance [m] p tunnel
500
p duct
Fig. 14: Modane eastern bores with exhaust ventila-

Pressure [Pa]
400
tion, air speed. 300
Inlet tube
As the fresh air is provided through the plain 200

tunnel section, the air temperature heats gradu- 100

ally up as the wall temperature rises. At the 0

work sites, suitably installed chillers reduce the -100


0 2'000 4'000 6'000 8'000 10'000
temperature to the required level. At the excava- Distance [m]
tion front, the air is sucked into the exhaust
1'500
ducts and carried away (Fig. 15).
1'300 p tunnel
45 1'100 p duct
Pressure [Pa]

40 900
35
700
Temperature [°C]

30 Exiting tube
500
25
300
20
15 100
T rock
10 T wall -100
T duct
5 T tunnel 0 2'000 4'000 6'000 8'000 10'000
Distance [m]
0
0 2'000 4'000 6'000 8'000 10'000 Fig. 17: Modane eastern bores with circulation venti-
Distance [m]
lation, pressure evolution.
Fig. 15: Modane eastern bores with exhaust ventila-
tion, temperatures.
In fact, the first tube provides fresh air for both
excavation sites. In some distance from the
The pollution level of the inflowing air increases front, fresh air is drawn into the second tube and
first gradually due to the transportation truck delivered to its extremity through a flexible ven-
line sources. A steeper rise occurs at the work tilation duct. For the first tube, a duct is equally
sites backward and at the excavation front. As employed to bring the fresh air to the front. The
the total air flowrate is dictated by the minimum consumed air from the first tube then flows back
air speed of 0.5 m/s and not the fresh air re- and is transferred into the second tube by means
quirements of the Diesel engines, the air loading of a ventilator installed in a crossway barrier.
does not exceed 60%. The combined loaded air streams are returned
140%
through the plain section of the exiting tube.
120%
The typical evolutions of the main quantities are
100%
illustrated in the following figures. The inlet
Loading level

80%
polluted air fraction
tube is operated with negative pressure, whereas
60% (T actual)/(T allowed) the exiting tube is slightly pressurized, Fig. 17.
40%

20% The pollution level increases gradually in the


0%
inlet tube due to the transportation truck line
0 2'000 4'000 6'000 8'000 10'000 sources (Fig. 18). Close the excavation site, the
Distance [m]
back-flowing air is loaded by the local Diesel
Fig. 16: Modane eastern bores with exhaust ventila- machinery. The excavation site of the second
tion, pollution and thermal loading levels. tube receives rather clean air, which has been

9 (10)

TMI International Conference:


Tunnel protection and security against fire and other hazards, 15-16. May 2006, Torino, Italy
extracted at a low pollution level from the first 2. Forced ventilation schemes are rather cheap,
tube. as standard flexible ducting can be used.
This equipment is on the other hand not par-
120%
ticularly tight, resulting thus in high power
100%
Inlet tube
requirements due to the rather important
leakage flows. As already pointed out, these
Loading level

80%

60% polluted air fraction


schemes are not recommended in France
(T actual)/(T allowed) without separate extraction ducting.
40%
3. Exhaust ventilation is expensive in terms of
20% capital costs, as several booster stations are
0%
required and spiral steel sheet pipes must be
0 2'000 4'000 6'000 8'000 10'000 installed. Power consumption on the other
Distance [m] hand is moderate and the scheme is com-
140%
Exiting tube
patible with French requirements, which are
120% applicable to all LTF construction sites, in-
100%
cluding the Italian ones. It is thus this
Loading level

polluted air fraction


(T actual)/(T allowed)
scheme, which has been generally adopted
80%
for the LTF construction site ventilation sys-
60%
tems.
40%

20% REFERENCES
0%
0 2'000 4'000 6'000 8'000 10'000
[1] Caisse nationale de l’assurance maladie des
Distance [m] travailleurs salaries, « Mise en œuvre de
Fig. 18: Modane eastern bores with circulation venti- dispositifs de ventilation mécanique lors
lation, pollution and thermal loading levels. des travaux de creusement en souterrains de
galeries, de puits, ou de grandes excava-
tions », Recommandation R352 adoptée le
CONCLUSIONS 27 juin 1990
The previously described 3 ventilation schemes [2] AFTES (France), « Recommandations Re-
are compared below in terms of air flow re- latives à la Ventilation des Ouvrages Sou-
quirements and power consumption for the two terrains en Cours de Construction », p. 76-
eastern tunnel bores excavated from the Modane 106, Tunnels et ouvrages souterrains – N°
construction site. The factor 2 in the table refers 176, mars/avril 2003
to the two bores. [3] Decreto del Presidente della Repubblica
Forced Forced Exhaust Circulation
(DPR) 20 marzo 1956, n. 320, « Norme per
S-type A-type la prevenzione degli infortuni e L’igiene
Initial air 2x70 m3/s 2x105 m3/s 2x70 m3/s del lavoro in sotterraneo »
flow =140 m3/s =210 m3/s =140 m3/s 90 m3/s
Ventilators/
[4] Dossier 28, Regione Emilia-Romagna
2 3 4 3 /CDS, Aziende USL Città di Bologna e Ra-
boosters
Ventilation 2x305 kW 2x780 kW 2x200 kW venna, «Gli scavi in sotterraneo – Analisi
power =610 kW =1560 kW =400 kW 115 kW
dei rischi e normativa in materia di sicurez-
za», Novembre 1996
1. Circulation ventilation is aerodynamically [5] Ministero del Lavoro e delle Politiche So-
the best choice, as flow leakage is no issue ciali, Direzione Regionale del Lavoro del
and friction is low because the plain sections Piemonte, « Indirizzi operativi comuni per
of the tubes are used. Also, the ventilation la costruzione in sicurezza del megatunnel
equipment costs are low. On the other hand, sulla linea ferroviaria Torino-Lione », Giu-
however, the logistics and infrastructure are nio 2005
handicapped, as the crossways must remain [6] SIA 196, « Ventilation des chantiers souter-
closed. Furthermore, the French require- rains», 1998
ments of dust and blasting fume capture at
its origin and removal to the exterior are not
fulfilled and would require separate extrac-
tion ducting.

10 (10)

TMI International Conference:


Tunnel protection and security against fire and other hazards, 15-16. May 2006, Torino, Italy

Potrebbero piacerti anche