Project Proposal

[Graduate Department Training]


Last Revised: [08/30/2019]

[Project Name] Project Proposal


Project Manager: Michael Vicent
Sponsor: CSU Monterey Bay
Prepared by:Michael Vicent

Revision History
Revision Revised by Approved by Description of change
date

Project Goal

Goal: Develop an asynchronous online training for the Graduate Departments at


California State University Monterey Bay that provides training and feedback on three-
business process: Graduate Reclassification Process, Course Substitution, and
Academic Requirements Report Training.

Problem/Opportunity Definition
The business processes above were overhauled from traditional paper forms to a
completely online process. These business processes require attention to detail,
knowledge of the software involved, and accuracy when processes as any mistakes can
be detrimental to a student’s records. While these new business processes have
streamlined much of the paperwork involved for both the Office of the Registrar and the
Graduate Departments, no training has been implemented to bridge the gap between
the old business processes and the new online processes.

Proposed Solution
During the duration of the Fall 2019 semester, I will be building an asynchronous online
training in Adobe Captivate which will provide necessary content and feedback through
software simulations.

Project Selection & Ranking Criteria


Project benefit category: TBD

Portfolio fit and interdependencies TBD

Project urgency: Routine

Cost/Benefit Analysis

1 of 4
Project Proposal
[Graduate Department Training]
Last Revised: [08/30/2019]

Tangible Benefits
Benefit
 Streamlined business processes lead to more efficient use of time
and university resources
 No cost to the university
Value & Probability
 TBD
Assumptions Driving Value
 TBD
Intangible Benefits
Benefit
 Improved accuracy of student records
 Decrease in frustration due to a lack of resources or training
Value & Probability
 TBD
Assumptions Driving Value
 TBD

Cost Categories Amount


Internal Labor hours
 None. Student-driven
project/internal university project
External costs:
 None anticipated
Labor (consultants, contract labor)
 None anticipated
Equipment, hardware or software
 Adobe Captivate and Microsoft
Office Suite. Provided at the cost of
the student.
List other costs such as travel & training
 None anticipated

Financial Return

2 of 4
Project Proposal
[Graduate Department Training]
Last Revised: [08/30/2019]

 TBD

Business Requirements
1. Adoption of the new business processes across departments with minimal or
no errors in student records.

Scope
Major project activities
1. Introduction of the subject matter to Graduation Department
2. Presentation to the Deans and Department Chairs
3. Presentation to the Faculty, Advisers and Coordinators
4. Appointment with SME
Out of scope activities that are critical to the success of the project
 TBD

Major Obstacles
1. Garnering widespread adoption of the training across departments could be
a challenge as it could be seen as time consuming when compared to on-
the-job training.
2. The sheer number of different departments involved (8 with more on the
way)
3. Potential resistance to change from some departments.

Risks
1.There are no significant risks

Schedule Overview
Estimated Project Completion Date: [11/12/2019]
Major Milestones
 Presentation to the Deans and Department chairs
completed prior to start of term.
 Presentation to the Faculty, Coordinators, and Advisers
completed prior to start of term.

3 of 4
Project Proposal
[Graduate Department Training]
Last Revised: [08/30/2019]

External Milestones Affecting the Project


None Anticipated

Impact of Late Delivery


Item Description Status Completion Timeline

Content Outline Completed Competed 08/30/19

Storyboard Media placeholders and 09/15/19

navigation

Resource retrieval Images, videos, narrative, 09/20/19

Project Development Master slide development in Have built one module 9/21/19 – 10/5/19

Phase 1 Adobe Captivate in Adobe Captivate for

IST 526

Project Development Development of website 10/6/19 – 10/20/19

Phase 2

Usability Testing and Upload and conduct usability 10/21/19 – 10/28/19

Evaluation testing an surveys

Final Report Final product developed with 10/29/19 – 11/12/19

evaluation results

 None