RENCANA ANGGARAN BIAYA


Proyek : INTERIOR KAMAR TIDUR
Lokasi : -
Tahun : 2019
HARGA SATUAN JUMLAH
NO Description QTY SAT
( Rp ) ( Rp )
I. PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Site Awal 1.00 ls 1,950,000.00 1,950,000.00
2 Mobilisasi Alat - Alat 1.00 ls 1,560,000.00 1,560,000.00

Sub total Pek. I 3,510,000.00


II. PEKERJAAN AREA KAMAR TIDUR
1 Pekerjaan Pembongkaran
A. Pek. Pembongkaran Dinding Kamar Tidur 15.03 m2 58,500.00 878,991.75
B. Pek. Pembongkaran Plafond Kamar Tidur 33.92 m2 42,900.00 1,454,953.50
C. Pek. Buangan Puing 4.20 m3 169,000.00 709,800.00
2 Pek. Plafond Gypsum 33.92 m2 113,100.00 3,835,786.50
3 Pek. Pengecatan Plafond 33.92 m2 48,100.00 1,631,311.50
4 Pek. List Gypsum 25.63 m' 71,500.00 1,832,580.75

Sub total Pek. II 10,343,424.00


III. PEKERJAAN AREA KAMAR MANDI
1 Pekerjaan Pembongkaran
A. Pekerjaan Pembongkaran Lantai 11.13 m2 65,000.00 723,450.00
B. Pekerjaan Pembongkaran Plafond 11.13 m2 42,900.00 477,477.00
C. Pekerjaan Pembongkaran Dinding 38.64 m2 58,500.00 2,260,440.00
D. Pek. Buangan Puing 9.14 m3 169,000.00 1,543,815.00
2 Pek. Area Lantai Kamar Mandi
A.Pekerjaan Rabat Beton 1.11 m3 1,244,100.00 1,384,683.30
B. Pekerjaan Pasangan Lantai Keramik 40x40cm 11.13 m2 468,000.00 5,208,840.00
C. Pekerjaan Pasangan Lantai Keramik Batu Alam 40x40 Area Rain Shower 2.21 m2 468,000.00 1,031,940.00
D. Pekerjaan Pasangan Lantai Pembatas Area Rain Shower 0.90 m2 468,000.00 421,621.20
3 Pek. Area Dinding Kamar Mandi
A. Pekerjaan Penebalan Area Dinding Rain Shower 4.73 m2 59,800.00 282,555.00
B. Pekerjaan Pasangan Batu Alam Dinding Area Rain Shower 8.88 m2 494,000.00 4,388,202.00
C. Pekerjaan Coating Batu Alam 8.88 m2 494,000.00 4,388,202.00
D. Pekerjaan Pasangan Glass Block 28.00 unit 49,400.00 1,383,200.00
E. Pekerjaan Waterproofing Kamar Mandi 11.13 m2 50,700.00 564,291.00
F. Pekerjaan Dinding Keramik Kamar Mandi 32.29 m2 507,000.00 16,369,762.50
4 Pek. Plafond Gypsum Kamar Mandi 11.13 m2 113,100.00 1,258,803.00
5 Pek. Pengecatan Plafond Gypsum Kamar Mandi 11.13 m2 48,100.00 535,353.00

Sub total Pek. III 42,222,635.00


IV. PEKERJAAN KUSEN, DAUN PINTU
IV.A. Pekerjaan Kusen Stainless Aluminium
- Kamar Tidur
1 Kusen Pintu Geser dan Fix Glass ( 6/12, 1 Unit ) 11.31 m' 422,500.00 4,777,841.25
- Kamar Mandi
2 Kusen Pintu ( 3/3, 1 Unit ) 7.77 m' 422,500.00 3,282,825.00
3 Kusen Fix Glass ( 3/3, 1 Unit ) 17.14 m' 422,500.00 7,239,960.00
IV.B. Pekerjaan Daun Pintu
- kamar Tidur
1 Daun Pintu Pintu Geser dan Fix Glass ( 1 Unit ) 15.12 m2 1,560,000.00 23,587,200.00

Sub total Pek. IV 38,887,826.25


V. PEKERJAAN INTERIOR
V.A. Pekerjaan Interior Kamar Tidur
1 Pek. Lemari Pakaian Finish. HPL 1.00 unit 39,066,300.00 39,066,300.00
2 Pek. Rak Buku dan TV Finish HPL 1.00 unit 11,700,000.00 11,700,000.00
3 Pek. Meja Rias Finish HPL 1.00 unit 4,305,600.00 4,305,600.00
V.B. Pekerjaan Interior Kamar Mandi
1 Pek. Wall Storage Fin. HPL 1.00 unit 390,000.00 390,000.00
2 Pek. Rak Mesin Cuci 1.00 unit 5,323,500.00 5,323,500.00
3 Pek. Meja Wastafel
HARGA SATUAN JUMLAH
NO Description QTY SAT
( Rp ) ( Rp )
A. Pek. Semen Polish 3.40 m2 364,000.00 1,238,328.00
B. Pek. Toping Kayu 0.76 m2 575,250.00 434,889.00
4 Pek. Storage Toilet
A. Pek. Semen Polish 4.45 m2 364,000.00 1,620,528.00
B. Pek. Toping Kayu 2.54 m2 575,250.00 1,461,710.25
5 Pek. Cermin Wastafel 1.00 unit 1,040,000.00 1,040,000.00

Sub total Pek. V 66,580,855.25


VI. PEKERJAAN SANITAIR
1 Pek. Instalasi Rain Shower 1.00 unit 877,500.00 877,500.00
2 Pek. Dudukan Meja Wastafle 0.68 m3 1,131,000.00 769,532.40
3 Pek. Instalasi Wastafel 1.00 unit 1,430,000.00 1,430,000.00

Sub total Pek. VI 3,077,032.40


TOTAL 164,621,772.90
DIBULATKAN 164,600,000.00

Denpasar, Agustus 2019


Dibuat oleh :
PT. WISMAKARMA ALAM KARYA

A A Ngr. Arya Putra Damar, ST


Direktur