1. Farhan Ajmal
2. Ikram Ul Haq
3. Rahim Ahmed
4. Shoaib Mehdi
Table of Contents
Project Overview
The information in this phase includes the basic information associated for the website business
Project Manager
Project Description
Project Purpose
The current business world is rapidly changing from physical business establishment to
effective digital prototypes. There are some sophisticated and understandable ways to digitalize
the business and get popularity in the market for the small businesses. Our organization aims to
help the small businesses and enterprises to grow with the help of digital marketing, website
making, and to provide opportunities to get benefit thorough digitalization of the business.
Website Optimization
Development of Template
The project will initially identify the opportunities available in the market and will work
on them. It will later on develop a plan, deadlines, and process details which would be later on
Background
Currently there are many ways to be identified for the small businesses to expand and
grow. The best and the most effective way to increase the number of customers is to engage the
business with digital marketing and E-commerce. The need of the digitalization of the business
or a component of the business is really important because the new generation is linked with the
world through digital mediums and it is essential for every business to have a website/portal and
RISK MANAGEMENT 5
highly optimized user interface. The project will include the defining the purpose, building the
Project Objectives
Project Scope
marketing.
Following are the team members that are working in the project.
Project Manager
Business Analyst
RISK MANAGEMENT 6
Website Developer
Graphic Designer
Content Writer
There are three departments which will provide an extensive staff members who will work on
this project.
Project Manager
Business Analyst
Develop a report of digital marketing and its benefits for the specific client.
Website Developer
Graphic Designer
Content Writer
Project Phases
Description
There are a large number of phases which include design, develop, market, and present to the
client but in a brief description, five are the main phases which are as following.
Analytical Report
Website template
Website Development
The back-end coding and the overall general development of the website.
The designing of the Logo & color scheme, the completion of the content of
website.
Digital Marketing
RISK MANAGEMENT 8
Project Cost
Completion
Project Timeframe
Point 7: Identification of Risks, Risk Owners, and Response planning / mitigation strategy
Underneath is a complete table explaining the identification of risks. Risk owners, and
1.5 Poor Usability Digital Marketing Executive Focus on the outcomes rather than the process.
Website 2.1 Security Digital Marketing Executive, Implement policies that indicate appropriate conduct
template Website Developer by employees.
2.2 Time wastage Entire team Process for accounting for time spent focus on
organization objective must be documented.
2.3 No updates Website Developer Appropriately ensure the developer’s work and
mention this concern in the very first instructions.
2.4 Client rejection Project Manager, Website Properly revise the work for reduction of the
Developer possibilities of the rejection.
2.5 Compatibility Website Developer Make sure the work would be done on the correct tools
issues and platform.
Website 3.1 Project team Project Manager Ensure personnel have clear directives and are fully
Development availability committed to the project before it gets underway.
3.2 Lack of Business Analyst, Website Ensure staff is equipped with adequate monitoring
relevance Developer tools and know how to use them.
3.3 Deadlines Website Developer, Project Empower social media representative to resolve
Manager customer issues with an adequate level of autonomy.
RISK MANAGEMENT 11
3.4 Poorly written Website Developer, Project Hiring should include the code factor as well.
code Manager
3.5 Unsecure logins Project Manager Develop process for issue escalation as required.
Website 4.1 Instable Website Developer, Project Ensure staff is equipped with adequate monitoring
Designing & application Manager tools and know how to use them.
Completion
4.2 Inaccurate Digital Marketing Executive, Develop process for issue escalation as required.
estimations Business Analyst
4.3 3rd Party Website Developer, Digital Empower social media representative to resolve
Systems Marketing Executive customer issues with an adequate level of autonomy.
4.4 Cross-platform Content Writer, Project Make sure that the hired staff knows cross platform
compatibility Manager, Website Developer issues.
4.5 Scope creep Website Developer, Project Prefer to reduce new features addition unless they are
Manager, Digital Marketing compulsory and adequately implement them.
Executive
Digital 5.1 Instable market Business Analyst Improve the review of the code.
Marketing Enhance the rapid quality checks on the tasks.
5.2 Fluctuations Business Analyst Enhance the understanding of the market
Increase the importance of the future events
predictability.
5.3 Unknown and Website Developer, Graphic This issue could not be resolved but only predicted.
sudden changes Designer
5.4 Staff turnover Digital Marketing Executive, Consider all the possibilities and be ready for it.
Project Manager
Risk is defined as the possibility of any negative occurrence that may happen due to
external or internal factors, and that may be mitigated through preventive actions. All projects
are subject to risks. In fact, there is an infinite number of things that might prevent you from
achieving your goals when working on a project. Risk management minimizes those threats that
could cause project failure, and allows you to stay in control of your project’s schedule, budget
According to the classic PMBoK guide, risk management can be divided into four
processes:
[1] Identification. Detect risks that might prevent you from achieving your project’s
goals.
[4] Monitoring and control. Maintain the project’s plan and continually identify
risks.
It is required to understand the risk associated with website development, and how to reduce the
As a rule, information about contractors and clients, and a project’s deliverables and
milestones is included in the Scope of Work (SOW). It’s challenging to define a relevant scope of
work, because every contract and all requirements are different, and it takes time to write
thorough documentation describing the scope of work. Here are common risks related to the
scope of work:
RISK MANAGEMENT 14
Scope of work is poorly specified. The risk here is in missing important details or simply
Scope creep. Scope creep refers to unexpected changes and uncontrolled growth to a project’s
scope. Scope creep can mean failure to meet time constraints, additional costs, and even project
failure.
Adding unnecessary features. According to PMBoK, the addition of features that were not
originally requested in the scope is called “gold plating.” Gold plating is a source of additional
risk (additional costs, human resources, time, testing, etc.) and is considered bad management
practice.
While project managers try to minimize or eliminate SOW changes, some changes might
be urgent and necessary for a project. In our workflow we stick to Agile methodologies that
advocate an iterative approach to implementing any changes. Such an approach is realized via
sprints, i.e. development cycles that typically last 2-4 weeks. During a sprint, the team decides
which features should be implemented next in the product, how they should be tested, how they
Agile methodologies resolve the problem of a scope creep by replanning the scope at the
start of each iteration, and continually estimating change during a project’s development. In this
way, the problem of scope creep becomes a moot point. This approach works effectively in a
continuous testing environment, when scope changes are driven by defects found in an
application. In this way, a project team immediately fixes issues at the initial stage and keeps
development team. Here are some common risks that can be posed by human resources:
In a nutshell, these are several common risks in website development, and some common
approaches to solving them. RubyGarage’s project management team relies on the classic
PMBoK guide during our work to foresee risks and mitigate them. We also reduce the risk of
failing to meet deadlines through efficient communication within our teams and through