Sei sulla pagina 1di 42

CHAPTER III

ON-JOB-TRAINING ACTIVITIES AND OUTPUTS

WEEK 1

Day 1 (January 22, 2019)

Figure 1. Orientation

Before our on the job training started in the site proper, Engr. De Guzman

properly explain the do’s and don’ts when in the actual site. He also gave us pointers in

the actual work done in the site ( Figure 1).

Day 2 (January 22, 2019)

Figure 2. Site Visitation Figure 3. Construction of Roof Beams

CIVIL ENGINEERING APPRENTICESHIP Page 1


This day our OJT adviser or head of the institute we applied for OJT tour us in

our designated site areas to worked or observed (Figure 2). The construction already

started and we immediately saw workers working on different areas like construction of

roof beams forms (Figure 3).

On this day, as our adviser touring us to the site and asking some question

regarding about minimum sizes for plumbing pipes for example. Also question us about

rebars to be used in beam construction.

Giving us some information is Engr. De Guzman, our OJT adviser. He gave us

tips and knowledge about site construction and how to handle things in site. He also

explains some critical things to know about site construction. He also makes sure the site

engineer is following the plans strictly for safety purposes.

Figure 4. Painting of Angle Figure 5. Construction of Septic Tank


Bars

On the same day, we witness other work in the site like painting of angle bar and

construction of septic tank (Figure 4 and 5). This is our first day in site but immediately

learned and saw different works in construction that will help us in the future.

CIVIL ENGINEERING APPRENTICESHIP Page 2


Day 3 (January 23, 2019)

Figure 6. Wall Plastering Figure 7. Laying of CHB in Septic Tank.

On the second day of the training, the activities scheduled are wall plastering and

laying of CHB in the septic tank (Figure 6 & 7).

The workers started plastering in some walls of the structure. The mason laborer

is the mason laborer continued to plaster the column on some parts of the structure.

Day 4 (January 25, 2019)

Figure 8. Construction of Rebar Figure 9. Welding of Truss

CIVIL ENGINEERING APPRENTICESHIP Page 3


In our third day, we saw workers constructing a rebar and assembling the rebar.

The laborer is assembling the rebars for some beams. Bending of required bars is being

conducted by steel man in the site (See Figure 8).

At the same time welding of truss is conducted. The laborer is welding the angle

bars to form trusses for the roof works. He has no PPE so there is a large hazard in the

situation (Figure 9).

WEEK 2

Day 5 (January 28, 2019)

Figure 10. Orientation Figure 11. Orientation

In the 6th day of the training, we go on a site visitation around CLSU. We visited

the famous CLSU Auditorium that is under renovation. As we go around the area, some

work we saw is the fixing of metal piping into PVC pipes. The plumbing pipelines of the

old auditorium approve to change. They use PVC pipes instead (Figure 10).

Another activity is the renovation of auditorium roofing. In construction of the

ceiling the laborers are working at heights so they put extra safety for themselves and a

lot of scaffoldings are necessary (Figure 11).

CIVIL ENGINEERING APPRENTICESHIP Page 4


Day 6 (January 29, 2019)

Figure 12. Site Visitation Figure 13. Construction of Roof Beams

To continue our training on site, we moved to another site since it has just started.

Excavation is done by the laborer for foundation construction. The workers make sure

that the excavated earth must store away from the edge of the trench (Figure 12). The

laborer used steel cutting machine to cut the steel bars according to its required length

(Figure 13).

On this day, we began our training in our new site which is the Construction of

College of Engineering Workshop and Micro-hydro Laboratory. The project is also being

handled by the CLSU Inspectorate Team, the team that also handled us.

Day 7 (January 30, 2019)

Figure 14. Placing of gravel Figure 15. Forming of reinforcing steel bars
bed
CIVIL ENGINEERING APPRENTICESHIP Page 5
In Figure 14 and 15, we can see the workers starting to work for the footing

works. The laborers are laying the gravel as bedding and leveling it to make sure the

footing is stable (Figure 14). Also in the same day, the laborer assembles the steel bars

and the stirrups using the G.I. wires to form the reinforcement for the columns and

footings (Figure 15).

Figure 16. Erection of footing and column


reinforcement
bed

In erection of reinforcement, the laborers are working and coordinating together

in order to erect it perfectly because this is a very sensitive work in the site that requires

no failure (Figure 16).

WEEK 3
Day 8 (February 6, 2019)

Figure 19. Inspection of plumbing pipes Figure 20. Plastering of Walls


bed

CIVIL ENGINEERING APPRENTICESHIP Page 6


We got a chance to train again in our first site on this day. The Site Foreman

inspected that VTR (Vent thru Roof) has been constructed on all comfort rooms (Figure

19). We notice in our first day that the VTR was not installed.

Another work is the plastering of walls. The mason laborer is plastering the outer

wall. They used plumb bob to level the plaster (Figure 20).

Figure 21. Coating of trusses Figure 22. Completion of septic tank


Figure 22. Completion of septic tank
bed
bed
Since the trusses have already been installed, the laborer used scaffolding to reach

and coat the said trusses (Figure 21). And we also noticed that the construction of septic

tank is almost finished (Figure 22)

Day 9 (February 7, 2019)

Figure 23. Slump Test Figure 24. Concrete Pouring for Column
Footings

bed
CIVIL ENGINEERING APPRENTICESHIP Page 7
For every construction there is always a slump test where the mixture for

concrete in being tests. On this site, they prepared multiple samples for the slump test

(Figure 23). Concrete mix samples were poured into the column footing in a thoroughly

and organized fashion. The workers are working with coordination (Figure 24).

Figure 25. Continuation of bending and


cutting of rebar works for wall footing

In bending of reinforcement it requires a lot of time and stamina because

you will bend tons of rebars for the whole footing, columns, beams and stirrups manually

(Figure 25).

Day 10 (February 8, 2019)

Figure 26. Concrete Pouring for Figure 27. Forming of reinforcing steel
Column Footings bars for wall footing

bed

CIVIL ENGINEERING APPRENTICESHIP Page 8


The next day they’ve continued to pour concrete mix samples on the remaining

column footing efficiently (Figure 26). As the construction progresses the bending of

rebars continues because this activity requires a lot of time (Figure 27).

Figure 28. Laying of wall footing

After the pouring and hardening of the concrete in footing they began to lay

rebars for the wall footing since they finished working on the column footing (Figure

28).

WEEK 4

Day 11 (February 13, 2019)

Figure 29. Excavation for wall footing Figure 30. Laying of reinforcement for
wall footing

bed

CIVIL ENGINEERING APPRENTICESHIP Page 9


Excavation is done by the laborer for wall footing construction. They make sure

that the excavated earth must store away from the edge of the trench (Figure 29). After

finishing the column footing, the laborers proceed to lay the reinforcement for wall

footing in some parts of the structure after the excavation (Figure 30).

Figure 31. Erection of formworks for column.

The laborers are working and coordinating together in order to erect it perfectly

because this is a very sensitive work in the site that requires no failure. It must follow

required size in plans for quality work and to make sure it will not failed (Figure 31).

Day 12 (February 14, 2019)

Figure 32. Excavation for wall footing Figure 33. Laying of reinforcement for
wall footing

bed

CIVIL ENGINEERING APPRENTICESHIP Page 10


The next day they’ve continued to excavate trenches for wall footing construction.

Make sure that the excavated earth must store away from the edge of the trench (Figure

32). Also the laborers continued to lay the reinforcement for wall footing on some parts

of the structure (Figure 33).

Figure 34. Erection of formworks for column.

They’ve continued to erect some formworks for columns efficiently. The plan

requires a lot of column since it is a two project being constructed (Figure 34).

Figure 35. Concrete Pouring for Figure 36. Excavation for wall footing
Column
As the training progresses, the next activity is concrete mixing. Concrete mix

samples were poured into the column in a thoroughly and organized fashion. The workers
bed

CIVIL ENGINEERING APPRENTICESHIP Page 11


are working with coordination (Figure 35). Again, they’ve continued to excavate

trenches for wall footing construction. Make sure that the excavated earth must store

away from the edge of the trench (Figure 36).

Figure 37. Laying of reinforcement for Figure 38. Erection of formworks for
wall footing column.

The laborers continued to lay the reinforcement for wall footing on some parts of

the structure. Workers worked with unity to provide efficient work in the site (Figure 37).

Also, they’ve continued to erect some formworks for columns efficiently (Figure 38).
bed

WEEK 5

Day 14 (February 19, 2019)

Figure 39. Excavation for wall footing Figure 40. Laying of reinforcement for
tie beam

CIVIL ENGINEERING APPRENTICESHIP Page 12

bed
On our fifth week in training, the laborers continued to excavate trenches for wall

footing construction. Make sure that the excavated earth must store away from the edge

of the trench (Figure 39). After laying of CHB under the tie beam, the laborers proceeded

to lay the reinforcement for tie beam on other parts of the structure (Figure 40). The

progresses in site are now visible because of the continuous activity going in the

construction site.

Figure 41. Installation of formworks for tie beam

One of the progresses in site is the installation of wooden formworks for tie beam

was done by the laborer after laying of CHB and reinforcement of the tie beams. They’ve

started working on bed


the formworks for tie beam in one the project (Figure 41).

Day 15 (February 20, 2019)

Figure 42. Laying of CHB Figure 43. Excavation for wall footing

CIVIL ENGINEERING APPRENTICESHIP Page 13


The next day, for the walls, CHB 4” was laid on some parts of the structure by the

laborers and binding them with cements mortar and rebars (Figure 42). They’ve

continued to excavate trenches for wall footing construction. Make sure that the

excavated earth must store away from the edge of the trench (Figure 43).

Figure 44. Installation of formworks Figure 45. Erection of Scaffoldings.


for tie beam

The installation of wooden formworks for tie beam continues until all the

formworks are installed in the tie beam that will be molded (Figure 44). The wooden

scaffolds started to erect for the continuation of concrete mix pouring in the column

(Figure 45). As we all know that scaffolds helps workers to climb in some parts of the

sitebed
that is not reachable enough by the height.

CIVIL ENGINEERING APPRENTICESHIP Page 14


Day 16 (February 21, 2019)

Figure 46. Laying of CHB Figure 47. Excavation for wall footing

The next day, CHB was continued to lie on some parts of the structure by the

laborers and binding them with cements mortar and rebars (Figure 42). They’ve

continued to excavate trenches for wall footing construction. Make sure that the
bed earth must store away from the edge of the trench (Figure 43).
excavated

Figure 48. Installation of formworks Figure 49. Erection of Scaffoldings.


for tie beam

The installation of wooden formworks for tie beam continues until all the

formworks are installed in the tie beam that will be molded (Figure 44). The wooden

scaffolds started to erect for the continuation of concrete mix pouring in the column

bed CIVIL ENGINEERING APPRENTICESHIP Page 15


(Figure 45). As we all know that scaffolds helps workers to climb in some parts of the

site that is not reachable enough by the height.

Day 17 (February 27, 2019)

Figure 50. Laying of CHB Figure 51. Excavation for wall footing

The laborers continued to lay CHB 4” on some parts of the structure and binding

them with cement mortar and rebar (Figure 50). After laying of CHB 4”, the laborers

proceeded to lay the reinforcement for the beam that will be molded on some parts of the
bed (Figure 51).
structure

Figure 52. Inspection Figure 53. Delivery of cement

CIVIL ENGINEERING APPRENTICESHIP Page 16


Three of the inspectors visited the ongoing construction for some reports. They’ve

notice some errors in plans like the walls beside the tanks should be a pure concrete

mixture and not made of CHB (Figure 52). As the construction progresses, the delivery

of materials will be continued until the construction is finished (Figure 53). It is

important that the delivery of materials is continuous so that the project will have no

problems regarding in material shortage and causing the delay of the project.

WEEK 6

Day 18 (March 5, 2019)

Figure 54. Fabrication of formworks Figure 55. Installation of formworks for


beams
In our sixth week in our on-the-job training in the same site, some of the activities

we encounter are presented above. The laborers fabricated the formworks for the beams

that will be installed before concrete pouring (Figure 54). And the other activity is the

installation
bed of wooden formworks for beams was done by the laborer after laying of CHB

and reinforcement of the tie beams (Figure 55).

CIVIL ENGINEERING APPRENTICESHIP Page 17


Figure 56. Installation of electrical pipes

Some workers are doing their respective assignments and areas at work as we

observed. The laborers started to chisel the wall for the installation of electrical pipes
bed
(Figure 56).

Day 19 (March 6, 2019)

Figure 57. Fabrication of formworks Figure 58. Installation of formworks for


column

The next day, the workers just continued the task assigned to them. The laborers

continued to fabricate the formworks for the beams that will be installed before concrete

pouring (Figure 57). Also as we can see, the installation of wooden formworks for

bed continues until all the formworks is installed and can be used for concrete
column

pouring of column (Figure 58).

CIVIL ENGINEERING APPRENTICESHIP Page 18


Figure 59. Concrete pouring of roof Figure 60. Erection of Scaffoldings.
beams
Concrete mix samples were poured into the beam in a thoroughly and organized

fashion and the workers are working with coordination for better outcome of the task

given (Figure 59). The steel scaffolds started to erect for the continuation of concrete mix

pouring in the column (Figure 60).

bed
Day 20 (March 7, 2019)

Figure 61. Removal of formworks Figure 62. Concrete pouring for wall
footing
After the curing of column, the laborers remove the formworks so that it may also

be used for other parts of the structure (Figure 61). And pouring of concrete gradually

bed
CIVIL ENGINEERING APPRENTICESHIP Page 19
starts. Concrete mix samples were poured into the wall footing in a thoroughly and

organized fashion. The workers are working with coordination (Figure 62).

Figure 63. Installation of formworks Figure 64. Erection of Scaffoldings


for column
Same day, the installation of wooden formworks for column continues until all

the formworks are installed in the column that will be molded (Figure 63). And as we all

know scaffoldings is important for any construction site. The wooden scaffolds continued

to erect by the laborers for the continuation of concrete pouring (Figure 64).

Daybed
21 (March 9, 2019)

Figure 65. Plastering of walls Figure 66. Concrete pouring for wall footing

CIVIL ENGINEERING APPRENTICESHIP Page 20

bed
` Last day for this week of training some activity were just continued and new task

were assigned. The mason laborer proceeds on plastering the wall. Using plump bob, they

level the plaster. It is unsafe for the workers to work without appropriate PPE. Always

protect yourself within the site to avoid accidents (Figure 65). They’ve continued to

poured concrete mix samples into the wall footing in a thoroughly and organized fashion

(Figure 66).

Figure 67. Installation of formworks Figure 68. Erection of Scaffoldings.


for column

The installation of wooden formworks for column continues until all the

formworks are installed in the column that will be molded as continue by the laborers

(Figure 67). And also with the wooden scaffolds were continued to erect by the laborers

for the continuation of concrete pouring (Figure 68).

bed

CIVIL ENGINEERING APPRENTICESHIP Page 21


WEEK 7

Day 22 (March 11, 2019)

Figure 69. Fabrication of formworks Figure 70. Plastering of walls

To continue our training, we can now tell that just being on the site will gave you

learning that can’t be taught in four corners of the room. Observed work on this day, the

laborers fabricated the formworks for the column that will be installed before concrete

bed (Figure 69). Also, the mason laborer proceeds on plastering the inner wall. First,
pouring

they used plumb bob to level the plaster (Figure 70).

Figure 71. Reinforcement for CHB Figure 72. Laying out of panel box

CIVIL ENGINEERING APPRENTICESHIP Page 22

bed
The reinforcement for walls has been erected on some parts of the structure. With

the time allotted for every activity, the workers were productive with the time given

(Figure 71). They’ve started working on the panel board holder, the electrician finishing

the chiseled wall for later placement of the panel box (Figure 72).

Day 23 (March 12, 2019)

Figure 73. Installation of scaffoldings Figure 74. Plastering of walls

Erection of steel scaffolds continued to erect by the laborers for the continuation

of concrete pouring. They needed to erect scaffolds for the column is too high for

workers to reach (Figure 73). The mason laborer proceeds on plastering the wall. They

used plump bob to level the plaster. It is unsafe for the workers to work without
bed
appropriate PPE. Roughly to finish the project by plastering walls is done by the workers

(Figure 74).

CIVIL ENGINEERING APPRENTICESHIP Page 23


Figure 75. Reinforcement for CHB Figure 76. Cutting and fabricating truss

The reinforcement for walls continued to erect on some parts of the structure. It is

important so that structure or project can stand on its own (Figure 75). The Steel man use

acetylene kit to cut the angle bars that later used in fabricating the truss. It is nearly

finished (Figure 76).

bed
Day 24 (March 13, 2019)

Figure 77. Cutting of reinforcing steel Figure 78. Fabrication of trusses


bars and angle bars
The fabrication is continued the next day. The Steel man continued to cut the

angle bars using acetylene kit that later used in fabricating the truss (Figure 77). Now the

workers nearly finish in the fabrication of trusses. In fabrication of trusses, the welder

used welding machine to connect every member of the truss (Figure 78).

bed
CIVIL ENGINEERING APPRENTICESHIP Page 24
Figure 79. Plastering of walls Figure 80. Installation of forms.

They are now plastering the one side of the one project. The mason laborer

proceeds on plastering the wall. They used scaffolding since the wall is high. It is unsafe

for the workers to work without appropriate PPE (Figure 79). The laborers are installing

the formworks for the reservoir of the laboratory before concrete pouring (Figure 80).

Day 25 (March 14, 2019)


bed

Figure 81. Plastering of walls Figure 82. Fabrication of trusses

The mason laborer continued to plaster the wall. They used scaffolding since the

wall is high. It is unsafe for the workers to work without appropriate PPE (Figure 81). In

fabrication of trusses, the welder used welding machine to connect every member of the

bed CIVIL ENGINEERING APPRENTICESHIP Page 25


truss. They are nearly finished in the fabrication of truss and be ready for installation

(Figure 82).

Figure 83. Installation of trusses Figure 84. Installation of scaffoldings

The laborers are working and coordinating together in order to install the truss

since it is heavy and hard to lift without any equipment. First thing we notice is that they

did not use any equipment in lifting the trusses which is heavy for man to lift but they

lifted it anyway. It is not advisable for any construction site to do (Figure 81). The

scaffolds continued to erect by the laborers for the continuation of CHB laying. They are
bed
now starting to construct more in the next project (Figure 82).

CIVIL ENGINEERING APPRENTICESHIP Page 26


WEEK 8

Day 26 (March 18, 2019)

Figure 83. Plastering of walls Figure 84. Installation of utility box’s and
hose plate
The mason laborer continued to plaster the wall. They used scaffolding since the

wall is high (Figure 83). Another activity on this day is the electrician started to install

utility boxes and hose plate on the walls of the structure (Figure 84). As we continue our

bed we can now see the progress of the laborers working every day to finished
training,

project.

Figure 85. Installation of forms Figure 86. Installation of c-purlins

CIVIL ENGINEERING APPRENTICESHIP Page 27

bed
The laborers are installing the formworks for the reservoir of the laboratory before

concrete pouring (Figure 85). After the installation of truss the laborers started to install

c-purlins by using welding machine (Figure 86).

Day 27 (March 19, 2019)

Figure 87. Concrete pouring of column Figure 88. Installation of c-purlins

Concrete mix samples were poured into the column in a thoroughly and organized

fashion. The workers are working with coordination (Figure 87). Another activity on this

day is the laborers continued to install the c-purlins by using welding machine (Figure

88).
bed

Figure 89. Fabrication of forms Figure 90. Backfilling works

CIVIL ENGINEERING APPRENTICESHIP Page 28


The laborers continued to fabricate the formworks for the beams that will be

installed before concrete pouring (Figure 89). Backfilling is done by the laborer on some

parts of the structures (Figure 90).

Day 28 (March 20, 2019)

Figure 91. Removing of forms Figure 92. Plastering of walls

After the curing of beam, the laborer remove the formworks so that it may also be

used for other parts of the structure (Figure 91). Another activity on this day is the mason

laborer continued to plaster the wall on some parts of the structure. They use plumb bub

to level the plaster (Figure 92).


bed

Figure 93. Installation of Upvc pipe Figure 94. Backfilling works


and wires

CIVIL ENGINEERING APPRENTICESHIP Page 29


They started to dig on the wall for the installation of upvc pipe and wires for the

laboratory (Figure 93). Backfilling is done by the laborer on some parts of the structures

(Figure 94).

Day 29 (March 21, 2019)

Figure 95. Removing of forms Figure 96. Installation of flexible hose,


function box

After the curing of beam, the laborer remove the formworks so that it may also be

used for other parts of the structure (Figure 95). The electrician continued to install utility

boxes and hose plate on the walls of the structure (Figure 96).

bed

Figure 97. Installation of ceiling joist Figure 98. Cutting of RSB

CIVIL ENGINEERING APPRENTICESHIP Page 30


After the installing the truss and c purlins the laborers started to install ceiling

joist by using welding machine (Figure 97). The laborers continued to cut bars for the

reinforcement of beams and columns (Figure 98).

WEEK 9

Day 30 (March 25, 2019)

Figure 99. Plastering of walls Figure 100. Reinforcement of CHB`s

The mason laborer continued to plaster the wall. They used scaffolding since the

wall is high (Figure 99). The reinforcement for walls continued to erect on some parts of

thebed
structure (Figure 100). The following materials used for the activity are hammer,

nails, shovel, RSB (20-mm ø, 16-mm ø, 12-mm ø, 10-mm ø), G.I. Wires, Elf, for delivery

of CHB, metal cut off saw, formworks, crowbar, spacers.

CIVIL ENGINEERING APPRENTICESHIP Page 31


Day 31 (March 26, 2019)

Figure 101. Plastering of Walls Figure 102. Reinforcement of CHB`s


column

The laborers just continue the unfinished activity yesterday. The mason laborer

continued to plaster the wall. They used scaffolding since the wall is high (Figure 101).

The reinforcement for walls continued to erect on some parts of the structure (Figure

102).
bed

Figure 103. Installation of Stirrups and Figure 104. Compaction Works


Forms

The installation of wooden formworks for tie beam continues until all the

formworks are installed in the tie beam that will be molded (Figure 103). The

compaction works started by the laborer (Figure 104).

CIVIL ENGINEERING APPRENTICESHIP Page 32


bed
Day 32 (March 27, 2019)

Figure 105. Plastering of walls Figure 106. Reinforcement of CHB`s

The mason laborer continued to plaster the wall. They used scaffolding since the

wall is high (Figure 99). The reinforcement for walls continued to erect on some parts of

the structure (Figure 100). The following materials used for the activity are hammer,
bed
nails, shovel, RSB (20-mm ø, 16-mm ø, 12-mm ø, 10-mm ø), G.I. Wires, Elf, for delivery

of CHB, metal cut off saw, formworks, crowbar, spacers.

Figure 107. Cutting and Welding Figure 108. Backfilling Works


Works

The laborer used steel cutting machine to cut the steel bars according to its

required length. They used welding machine to install the ceiling (Figure 107). The

CIVIL ENGINEERING APPRENTICESHIP Page 33

bed
laborers started to backfilling to create more workspace since the excavated area is

narrow (Figure 108).

Day 33 (March 28, 2019)

Figure 109. Plastering of Walls Figure 110. Installation of Forms,


Stirrups, and Scaffoldings

The mason laborer continued to plaster the wall. It is unsafe for the workers to

work without appropriate PPE (Figure 109). The installation of wooden formworks for

tie beam continues until all the formworks are installed in the tie beam that will be

molded (Figure 110).

bed

CIVIL ENGINEERING APPRENTICESHIP Page 34


WEEK 10

Day 34 (April 1, 2019)

Figure 111. Plastering of walls Figure 112. Electrical works


Before plastering the walls of the reservoir in the laboratory, the mason laborers

chase the walls for strong connection of the plaster and the wall (Figure 111). The

electrician started to install conduits in the ceiling for later placement of electrical

wires (Figure 112). The following materials used for the activity are handsaw, water,
bed
cement, sand; plumb bub, bucket, hammer, screws, scaffolds, conduit, and utility box.

Day 35 (April 2, 2019)

Figure 113. Plastering of Walls Figure 114. Electrical works


column

CIVIL ENGINEERING APPRENTICESHIP Page 35

bed
The mason laborer continued to plaster the wall on some parts of the structure.

They use plumb bub to level the plaster (Figure 113). The electrician continued to install

utility boxes and hose plate on the walls of the structure (Figure 114).

Figure 115. Ceiling works Figure 116. Installation of scaffolds

The laborers continued the ceiling works by installing the plywood. Ceiling works

is also complicated to do because of the process of doing it. The workers need to be

careful in order not to fall in the platform they are stepping on (Figure 115). They

installed scaffolds for the installation of lateral ties and for concrete pouring of the

column (Figure 116).

bed
Day 36 (April 3, 2019)

Figure 117. Electrical works Figure 118. Installation of lateral ties

CIVIL ENGINEERING APPRENTICESHIP Page 36

bed
The electrician placed the electrical wires in the conduit on the ceiling (Figure

117). After the installation of the scaffolds the foreman starts the installing of lateral ties

of the column (Figure 118). The following materials used for the activity are handsaw,

water, cement, sand; plumb bub, bucket, hammer, screws, scaffolds, conduit, and utility

box.

Day 37 (April 4, 2019)

Figure 119. Removal of forms Figure 120. Plastering of walls

After the curing of column, the laborer removes the formworks so that it may also

be used for other parts of the structure (Figure 119). The mason laborers continued to

plaster the walls of the reservoir (Figure 120). The following materials used for the

activity are handsaw, water, and cement, sand; plumb bub, bucket, and hammer,

scaffolds, RSB, and G.I wires.


bed

CIVIL ENGINEERING APPRENTICESHIP Page 37


WEEK 11

Day 38 (April 1, 2019)

Figure 121. Installation of electrical Figure 122. Reinforcement of CHB and


pipe and utility box. RSB for septic tank

The electrician continued to install utility boxes and hose plate on the walls of the

structure (Figure 121). After excavating, the laborers layed the reinforcement bars for

wall footing and the reinforcement bars of CHB for the septic tank (Figure 122). The

following materials used for the activity are handsaw, water, cement, sand; plumb bub,
bed
bucket, hammer, screws, and scaffolds.

Figure 123. Application of wall putty Figure 124. Installation of forms

CIVIL ENGINEERING APPRENTICESHIP Page 38


The painter apply primer before applying putty on wall (Figure 123).The hydro

project walls are now being painted for finishing of walls. The installation of wooden

formworks for column continues until all the formworks are installed (Figure 124). The

following materials used for the activity are handsaw, water, cement, sand; plumb bub,

bucket, hammer, screws, and scaffolds.

Day 39 (April 24, 2019)

Figure 125. Plastering of columns Figure 126. Installation of forms and scaffolding
The mason laborer started to plaster the column on some parts of the structure
column
(Figure 125). The installation of wooden formworks for column continues until all the

formworks are installed (Figure 126).

bed

Figure 127. Painting works Figure 128. Excavation

CIVIL ENGINEERING APPRENTICESHIP Page 39


The laborers continued the paint the walls after applying primer. The workers

need to be careful in order not to fall in the platform they are stepping on (Figure 127).

Excavation is done by the laborer for wall footing construction. Make sure that the

excavated earth must store away from the edge of the trench (Figure 128).

Day 40 (April 25, 2019)

Figure 129. Electrical works Figure 130. Installation of forms and


scaffolding

The electrician continued to install utility boxes and hose plate on the walls of the

structure (Figure 129). The installation of wooden formworks for column continues until

all the formworks are installed (Figure 130). The following materials used for the activity
bed
are handsaw, water, cement, sand; plumb bub, bucket, hammer, screws, scaffolds,

conduit, and utility box.

CIVIL ENGINEERING APPRENTICESHIP Page 40


Figure 131. Painting Works Figure 132. Plastering Works

The laborers continued painting the finished walls with white primer paint

(Figure 129). The mason laborer continued to plaster the column on some parts of the

structure (Figure 130). The following materials used for the activity are handsaw, water,

cement, sand; plumb bub, bucket, hammer, screws, scaffolds, conduit, and utility box.
bed
Day 41 (April 26, 2019)

Figure 133. Electrical works Figure 134. Installation of forms and scaffolding
The electrician continued to install utility boxes and hose plate on the walls of the

structure (Figure 133). The installation of wooden formworks for column continues until

all the formworks are installed (Figure 134). The following materials used for the activity

CIVIL ENGINEERING APPRENTICESHIP Page 41

bed
are handsaw, water, cement, sand; plumb bub, bucket, hammer, scaffolds, RSB, and G.I

wires.

Figure 135. Electrical works Figure 136. Installation of forms and


scaffolding

And on our last day in the site, the following activities are being conduct. Even

we were not able to finish the whole project, a lot of learning’s and knowledge are

develop within us. The laborers continued to paint the walls after applying primer (Figure

135). The mason laborer continued to plaster the column on some parts of the structure

(Figure 136). The following materials used for the activity are handsaw, water, and

cement,
bed sand; plumb bub, bucket, and hammer, scaffolds, RSB, and G.I wires.

CIVIL ENGINEERING APPRENTICESHIP Page 42

Potrebbero piacerti anche