JOB HAZARD ANALYSIS

HOW TO USE THIS FORM : Installation / Facility PLATFORM


1) Crew performing task reviews ALL generic JHA considerations. Location BYDP-A
2) Review previous JHA update(s) for useful information which will help this task. Associated Work Permit Type COLD WORK
3) Create new JHA update with generic form and ALL considerations for this task. Associated Work Permit Number
4) Carry out task as per plan. If any conditions change---STOP & RE-ASSESS. Electrical Isolation Certificate Number
5) File JHA update for future reference. Physical Isolation Certificate Number
WORK ACTIVITY MANUAL HANDLING PIPE SPOOL JHA Cross-Reference Number SBII-MH-21

Job Description of Potential Control / Recovery


L S R L S R Result
Step Job Step Hazards Measures
1 Apply PTW 1.1 Conflict of works 1 2 2 1.1 Pre-discussion among 1 2 2 A
PTW applicant before
submitting PTW
2 Transfer material to work site 2.1 Sharp object. 2 2 4 2.1.1 Padding of sharp object 1 2 2 A
2.1.2 Cotton hand glove 1 2 2 A
3 Transfer pipe spool to location 2.2 Improper manual handling 1 2 2 2.3.1 Training on proper
manual handling / knetic lifting 1 2 2 A
3.1 Pinch point 2 2 4 3.1.1 Identify potential of pinch
point 1 2 2 A
3.2 Knocking against sensitive inst. 2 2 4 3.2.1 Extra precaution & identivy 1 1 1
3.3 Congested area 2 2 4 3.3.1 Minimised personnel working
on same area. 1 1 1 A
3.4 Lifting tackles failure 1 2 2 3.4.1 Check and test prior to use 1 2 2 A
3.5 Heavy load 1 2 2 3.5.1 Get help if load too heavy 1 1 1 A
3.6 Strike against equipment 1 2 2 3.6.1 Ensure transfer route is
free from obstruction 1 1 1 A

L - LIKELIHOOD S - SEVERITY R - RATING RESULT


CATEGORY DEFINITION CATEGORY DEFINITIONS H 3 6 9 6 - 9 UNACCEPTABLE
LOW 1 Remote LOW 1 No Injury No Damage No Pollution M 2 4 6 3 - 4 TOLERABLE
MEDIUM 2 Possible MEDIUM 2 First Aid Injury Minor Damage Minnor Pollution L 1 2 3 1 - 2 ACCEPTABLE
HIGH 3 Probable HIGH 3 Lost Time Injury Major Damage Major Pollution L M H
IS THERE A SAFER WAY TO COMPLETE THE JOB ? ARE THERE ALTERNATIVES WITH LESS RISK ? LIKELIHOOD

JHA NUMBER Date This JHA Created : 06.10.2005


SBII-MH-21 TASK SAFETY MANAGEMENT OUTLINE Date JHA Last Revised : 25.11.2005
WORK ACTIVITY EQUIPMENT
Type of Equipment Manufacturer Tag. No. Precise Work Site

WORK ACTIVITY PARTICIPANTS THIS JHA CREATED BY


Name Discipline Position Performed Name Discipline Position
DOLLAH ABAS RIGGING TEAM LEADER YES DOLLAH ABAS RIGGING/SCAFF TEAM LEADER
ALBERT ULOM RIGGING RIGGER YES ALBERT ULOM RIGGING RIGGER
DONY JUGAH RIGGING RIGGER YES DONY JUGAH RIGGING RIGGER
RAHMAT C RIGGING RIGGER YES RAHMAT C RIGGING RIGGER

WORK ACTIVITY RESPONSIBILITY JHA SUBMITTED BY JHA ACCEPTED BY


WORK LEADER RECEIVING AUTHORITY APPROVING AUTHORITY
Name :- DOLLAH ABAS Name :- HENRY BUJANG Name :-
Signature :- Signature :- Signature : -
Date :- Date :- Date :-
Time :- Time :- Time :-

SEEB BY : DESB F/SUPT. SEEN BY: PCSB C.S.R SEEN BY: PCSB PLATFORM SUPERINTENT

Name :- KASSIM PASAK Name :- JIMSON RANGKING Name :-


Signature :- Signature :- Signature : -
Date :- Date :- Date :-
Time :- Time :- Time :-
JOB HAZARD ANALYSIS

HOW TO USE THIS FORM : Installation / Facility PLATFORM


1) Crew performing task reviews ALL generic JHA considerations. Location BNDP-j
2) Review previous JHA update(s) for useful information which will help this task. Associated Work Permit Type COLD WORK
3) Create new JHA update with generic form and ALL considerations for this task. Associated Work Permit Number
4) Carry out task as per plan. If any conditions change---STOP & RE-ASSESS. Electrical Isolation Certificate Number
5) File JHA update for future reference. Physical Isolation Certificate Number
WORK ACTIVITY MANUALHANDLING JHA Cross-Reference Number SBII-MH-21

Job Description of Potential Control / Recovery


L S R L S R Result
Step Job Step Hazards Measures
1 Apply PTW 1.1 Conflict of works 1 2 2 1.1 Pre-discussion among 1 2 2 A
PTW applicant before
submitting PTW
2 Transfer material to work site 2.1 Sharp object. 2 2 4 2.1.1 Padding of sharp object 1 2 2 A
2.1.2 Cotton hand glove 1 2 2 A
2.2 Improper manual handling 1 2 2 2.3.1 Training on proper
manual handling / knetic lifting 1 2 2 A
3 Remove roller 3.1 Pinch point 2 2 4 3.1.1 Identify potential of pinch
point 1 2 2 A
3.2 Knocking against sensitive inst. 2 2 4 3.2.1 Extra precaution & identivy 1 1 1
3.3 Congested area 2 2 4 3.3.1 Minimised personnel working
on same area. 1 1 1 A
3.4 Lifting tackles failure 1 2 2 3.4.1 Check and test prior to use 1 2 2 A
3.5 Heavy load 1 2 2 3.5.1 Get help if load too heavy 1 1 1 A
3.6 Strike against equipment 1 2 2 3.6.1 Ensure transfer route is
free from obstruction 1 1 1 A

L - LIKELIHOOD S - SEVERITY R - RATING RESULT


CATEGORY DEFINITION CATEGORY DEFINITIONS H 3 6 9 6 - 9 UNACCEPTABLE
LOW 1 Remote LOW 1 No Injury No Damage No Pollution M 2 4 6 3 - 4 TOLERABLE
MEDIUM 2 Possible MEDIUM 2 First Aid Injury Minor Damage Minnor Pollution L 1 2 3 1 - 2 ACCEPTABLE
HIGH 3 Probable HIGH 3 Lost Time Injury Major Damage Major Pollution L M H
IS THERE A SAFER WAY TO COMPLETE THE JOB ? ARE THERE ALTERNATIVES WITH LESS RISK ? LIKELIHOOD

JHA NUMBER Date This JHA Created : 06.10.2005


SBII-MH-21 TASK SAFETY MANAGEMENT OUTLINE Date JHA Last Revised : .10.2005
WORK ACTIVITY EQUIPMENT
Type of Equipment Manufacturer Tag. No. Precise Work Site

WORK ACTIVITY PARTICIPANTS THIS JHA CREATED BY


Name Discipline Position Performed Name Discipline Position
1) JIMMY BUJANG RIGGING TEAM LEADER YES 1) JIMMY BUJANG RIGGING/SCAFF TEAM LEADER
2) HERRY BENTER RIGGING RIGGER YES 2) HERRY BENTER RIGGING RIGGER
3) STEPHEN WAK RIGGING RIGGER YES 3) STEPHEN WAK RIGGING RIGGER
4) PILIN JIBENG 4) PILIN JIBENG RIGGING
5) UBIL KAPI 5) UBIL KAPI

WORK ACTIVITY RESPONSIBILITY JHA SUBMITTED BY JHA ACCEPTED BY


WORK LEADER RECEIVING AUTHORITY APPROVING AUTHORITY
Name :- SANDIN PASAK Name :- SANDIN PASAK Name :-
Signature :- Signature :- Signature : -
Date :- Date :- Date :-
Time :- Time :- Time :-

SEEB BY : DESB F/SUPT. SEEN BY: PCSB C.S.R SEEN BY: PCSB PLATFORM SUPERINTENT

Name :- KASSIM PASAK Name :- JIMSON RANGKING Name :-


Signature :- Signature :- Signature : -
Date :- Date :- Date :-
Time :- Time :- Time :-
JOB HAZARD ANALYSIS

HOW TO USE THIS FORM : Installation / Facility PLATFORM


1) Crew performing task reviews ALL generic JHA considerations. Location BNDP-I
2) Review previous JHA update(s) for useful information which will help this task. Associated Work Permit Type COLD WORK
3) Create new JHA update with generic form and ALL considerations for this task. Associated Work Permit Number
4) Carry out task as per plan. If any conditions change---STOP & RE-ASSESS. Electrical Isolation Certificate Number
5) File JHA update for future reference. Physical Isolation Certificate Number
WORK ACTIVITY MANUALHANDLING JHA Cross-Reference Number SBII-MH-21

Job Description of Potential Control / Recovery


L S R L S R Result
Step Job Step Hazards Measures
1 Apply PTW 1.1 Conflict of works 1 2 2 1.1 Pre-discussion among 1 2 2 A
PTW applicant before
submitting PTW
2 Transfer material to work site 2.1 Sharp object. 2 2 4 2.1.1 Padding of sharp object 1 2 2 A
2.1.2 Cotton hand glove 1 2 2 A
2.2 Improper manual handling 1 2 2 2.3.1 Training on proper
manual handling / knetic lifting 1 2 2 A
3.1 Pinch point 2 2 4 3.1.1 Identify potential of pinch
point 1 2 2 A
3.2 Knocking against sensitive inst. 2 2 4 3.2.1 Extra precaution & identivy 1 1 1
3.3 Congested area 2 2 4 3.3.1 Minimised personnel working
on same area. 1 1 1 A
3.4 Lifting tackles failure 1 2 2 3.4.1 Check and test prior to use 1 2 2 A
3.5 Heavy load 1 2 2 3.5.1 Get help if load too heavy 1 1 1 A
3.6 Strike against equipment 1 2 2 3.6.1 Ensure transfer route is
free from obstruction 1 1 1 A

L - LIKELIHOOD S - SEVERITY R - RATING RESULT


CATEGORY DEFINITION CATEGORY DEFINITIONS H 3 6 9 6 - 9 UNACCEPTABLE
LOW 1 Remote LOW 1 No Injury No Damage No Pollution M 2 4 6 3 - 4 TOLERABLE
MEDIUM 2 Possible MEDIUM 2 First Aid Injury Minor Damage Minnor Pollution L 1 2 3 1 - 2 ACCEPTABLE
HIGH 3 Probable HIGH 3 Lost Time Injury Major Damage Major Pollution L M H
IS THERE A SAFER WAY TO COMPLETE THE JOB ? ARE THERE ALTERNATIVES WITH LESS RISK ? LIKELIHOOD

JHA NUMBER Date This JHA Created : 06.10.2005


SBII-MH-21 TASK SAFETY MANAGEMENT OUTLINE Date JHA Last Revised : .10.2005
WORK ACTIVITY EQUIPMENT
Type of Equipment Manufacturer Tag. No. Precise Work Site

WORK ACTIVITY PARTICIPANTS THIS JHA CREATED BY


Name Discipline Position Performed Name Discipline Position
1) DICKSON LISET RIGGING TEAM LEADER YES 1) DICKSON LISET RIGGING/SCAFF TEAM LEADER
2)KUTELI NEW RIGGING RIGGER YES 2)KUTELI NEW RIGGING RIGGER
3) JOE BADIE RIGGING RIGGER YES 3) JOE BADIE RIGGING RIGGER
RIGGING

WORK ACTIVITY RESPONSIBILITY JHA SUBMITTED BY JHA ACCEPTED BY


WORK LEADER RECEIVING AUTHORITY APPROVING AUTHORITY
Name :- DICKSON LISET Name :- DICKSON LISET Name :-
Signature :- Signature :- Signature : -
Date :- .10.2005 Date :- .10.2005 Date :- .10.2005
Time :- Time :- Time :-

SEEB BY : DESB F/SUPT. SEEN BY: PCSB C.S.R SEEN BY: PCSB PLATFORM SUPERINTENT

Name :- KASSIM PASAK Name :- JIMSON RANGKING Name :- RUSLAN GHANI


Signature :- Signature :- Signature : -
Date :- .10.2005 Date :- .10.2005 Date :- .10.2005