2019 1 23-Jul-19 14:16

Activity ID Activity Name Original Resources Planned Start Planned Finish Jul 21 Jul 28 Aug 04 Aug 11
Duration
Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun
SDM July 2019 16 24-Jul-19 08-Aug-19 16

SDM July.1 C 101 9 25-Jul-19 02-Aug-19 9

A1000 Open Top and bottom manholes of the column 1 Erick, Helper 1, Operator 25-Jul-19 25-Jul-19
A1010 Confined space safety precuations 2 Safety DPT 26-Jul-19 27-Jul-19
A1020 Dismantle the VEP distributor and mellapack Bed 1 2 Erick, Yosri, Marco 28-Jul-19 29-Jul-19
A1030 Clean the mellapck bed , nozzles and distributor 1 Yosri, CLNG GRP 30-Jul-19 30-Jul-19
A1040 Post work inspection of the Mellapack bed 1 Inspections 30-Jul-19 30-Jul-19
A1050 Reinstatement of Mellapck bed ,nozzles 1 Erick, Haroon, Helper 1 31-Jul-19 31-Jul-19
A1060 Reinstatement of VEP distributor 1 Erick, Helper 1, Operator 01-Aug-19 01-Aug-19
A1480 Close Top and Bottom manholes 1 Yosri, Helper 1 02-Aug-19 02-Aug-19

SDM July.2 C 201 16 24-Jul-19 08-Aug-19 16

A1070 Erection of sacffoldings for middle and bottom manholes 1 Contractor 24-Jul-19 24-Jul-19
A1080 Open Top ,middle and bottom manholes of the column 1 Yakoob, Helper 2 25-Jul-19 25-Jul-19
A1090 Confined space safety precuations 2 Safety DPT 26-Jul-19 27-Jul-19
A1100 Dismantle the VEP distributor of Bed 1 and spray nozzles 2 Yakoob, Mohammed, Helper 2 28-Jul-19 29-Jul-19
A1110 Remove the mellapck bed 01 2 Yakoob, Mohammed, Helper 2 28-Jul-19 29-Jul-19
A1120 Dismantle the liquid collector head and distributors of Bed 2 2 Yakoob, Mohammed, Helper 2 30-Jul-19 31-Jul-19
A1130 Remove the hold down grid and mellapack bed 2 2 Yakoob, Mohammed, Helper 2 30-Jul-19 31-Jul-19
A1140 Cleaning of the mellapack bed 1 ,bed 2 and ditributors 1 Yakoob, CLNG GRP 01-Aug-19 01-Aug-19
A1150 Clean the intermediate reflux nozzles 1 Yakoob, Helper 2, Operator 01-Aug-19 01-Aug-19
A1160 Reinstatement of mellapack 02 ,hold down grid and spray distributor 2 Yakoob, Helper 2, Operator 04-Aug-19 05-Aug-19

A1170 Reinstatement of mellapack 01 and spray distributor 2 Yakoob, Helper 2, Operator 06-Aug-19 07-Aug-19
A1180 Close Top ,middle and Bottom manholes 1 Yakoob, Helper 2 08-Aug-19 08-Aug-19

SDM July.3 C 301 16 24-Jul-19 08-Aug-19 16

A1190 Erection of sacffoldings for middle manholes 1 Contractor 24-Jul-19 24-Jul-19


A1200 Open Top ,middle and bottom manholes of the column 1 Rolando, Helper 3, Operator 25-Jul-19 25-Jul-19
A1210 Confined space safety precuations 2 Safety DPT 26-Jul-19 27-Jul-19
A1220 Dismantle the VEP distributor of Bed 1 , spray nozzles and spray nozzles 2 Rolando, Haroon, Helper 3 28-Jul-19 29-Jul-19
A1230 Remove the mellapck bed 01 2 Rolando, Haroon, Hussain 28-Jul-19 29-Jul-19
A1240 Remove the VEP distributor , spray nozzlesand and mellapck Bed 2 3 Rolando, Helper 3, Operator 30-Jul-19 01-Aug-19
A1250 Cleaning of the mellapack bed 1 and 2 and distributors 2 CLNG GRP 02-Aug-19 03-Aug-19
A1260 Post cleaning inspection of mellapack bed 1 and 2 and distributors 1 Inspections 04-Aug-19 04-Aug-19
A1270 Reinstatement of mellapack 02 ,hold down grid and spray distributor 3 Rolando, Haroon, Helper 3 04-Aug-19 06-Aug-19
A1280 Reinstatement of mellapack 01 and spray distributor 3 Rolando, Helper 3, Operator 05-Aug-19 07-Aug-19
A1290 Close Top ,middle and Bottom manholes 1 Rolando, Helper 3 08-Aug-19 08-Aug-19

Remaining Level of Effort Project Baseline Bar Remainin... Date Revision Checked Approved shelton@saudilubeoil.com
23-Jul-19 Rev 0
Early start Actual Work Critical R... © Oracle Corporation
2019 2 23-Jul-19 14:16

Activity ID Activity Name Original Resources Planned Start Planned Finish Jul 21 Jul 28 Aug 04 Aug 11
Duration
Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun
SDM July.4 E 102 10 25-Jul-19 03-Aug-19 10

A1300 Open Elliptical heads and install flanges for steam flusing 1 Hussain, Haroon, Marco 25-Jul-19 25-Jul-19
A1310 Tube cleaning 2 CLNG GRP 28-Jul-19 29-Jul-19
A1320 Install test rings on both ends for hydrotest 1 Hussain, Haroon, Marco 30-Jul-19 30-Jul-19

A1330 Tube side hydrotest 1 Hussain, Marco, Operator 31-Jul-19 31-Jul-19


A1420 Install floating head and inlet end elliptical head 1 Hussain, Haroon, Marco 01-Aug-19 01-Aug-19
A1430 Floating head gasket leak test and reinstatement 2 Marco, Yosri, Operator 02-Aug-19 03-Aug-19

SDM July.5 E 101 14 26-Jul-19 08-Aug-19 14

A1340 Open Elliptical heads and install flanges for steam flusing 1 Yosri, Marco, Operator 26-Jul-19 26-Jul-19
A1350 Tube cleaning 2 CLNG GRP 30-Jul-19 31-Jul-19
A1360 Install test rings on both ends for hydrotest 1 Yosri, Erick, Mohammed 04-Aug-19 04-Aug-19
A1370 Tube side hydrotest 1 Yosri, Operator 05-Aug-19 05-Aug-19
A1440 Install floating head and inlet end elliptical head 1 Marco, Haroon, Erick 06-Aug-19 06-Aug-19
A1450 Floating head gasket leak test and reinstatement 2 Marco, Haroon, Operator 07-Aug-19 08-Aug-19

SDM July.6 E 202 13 27-Jul-19 08-Aug-19 13

A1380 Open Elliptical heads and install flanges for steam flusing 1 Yosri, Mohammed, Erick 27-Jul-19 27-Jul-19

A1390 Tube cleaning 3 CLNG GRP 02-Aug-19 04-Aug-19


A1400 Install test rings on both ends for hydrotest 1 Mohammed, Erick, Haroon 05-Aug-19 05-Aug-19
A1410 Tube side hydrotest 1 Yosri, Operator 06-Aug-19 06-Aug-19
A1460 Install floating head and inlet end elliptical head 1 Yosri, Mohammed, Erick 07-Aug-19 07-Aug-19
A1470 Floating head gasket leak test and reinstatement 1 Erick, Mohammed, Operator 08-Aug-19 08-Aug-19

A1490 Finish shutdown Activities 0 08-Aug-19

Remaining Level of Effort Project Baseline Bar Remainin... Date Revision Checked Approved shelton@saudilubeoil.com
23-Jul-19 Rev 0
Early start Actual Work Critical R... © Oracle Corporation