Sei sulla pagina 1di 5

Proceedings of the 4th Asian Regional Conference on Geosynthetics 651

June 17 - 20, 2008 Shanghai, China

APPLICATION OF PREFABRICATED VERTICAL DRAINS TO THE CHANGI LAND


RECLAMATION PROJECT, SINGAPORE

A. Arulrajah1, M.W. Bo2, J. Chu3 and H. Nikraz4

ABSTRACT: The Changi East Reclamation Project in the Republic of Singapore involved the filling of approximately
200 million cubic of sand for the land reclamation of a total area of about 2500 hectares. Land reclamation was carried
out using fill materials obtained from dredging granular material from the seabed at the borrow source. The ground
improvement technique which involved combination of prefabricated vertical drain (PVD) with preloading was
successfully applied in this project to improve the underlying compressible soils. The project comprises the installation
of prefabricated vertical drains and the subsequent placement of surcharge to accelerate the consolidation of the
underlying marine clay. In order to monitor the performance of ground improvement and to validate the performance of
the prefabricated vertical drain system, several geotechnical instruments were installed to monitor the degree of
consolidation at both area with PVD and area without PVD as control area. This paper provides a case study of the
ground improvement works carried out with prefabricated vertical drains at the Changi East Reclamation Project and
their subsequent performance assessment.

KEYWORDS: land reclamation, field instrumentation, ground improvement, prefabricated vertical drains

INTRODUCTION Settlement gauges including deep settlement gauges


were installed at the top of each sub layers whereas
From 1992 till mid 2004, the Changi East Reclama- piezometers were installed at the centre of each com-
tion Project in the Republic of Singapore involved the pressible sub layer in order to monitor the settlement and
filling of approximately 200 million cubic of sand for the pore pressure dissipation. Settlement and pore pressure
reclamation of a total land area of about 2500 hectares. were monitored with close interval in the first three months
The land reclamation works were carried out in 5 phases. and wider interval at the later part of monitoring. Ultimate
Land reclamation was carried out using fill materials settlements were predicted using the field settlement
obtained from dredging granular material from the seabed results applying the Asaoka and hyperbolic methods.
at the borrow source. The combination of prefabricated This paper provides a case study of the ground
vertical drain (PVD) with preloading ground improvement improvement works carried out with prefabricated vertical
technique was successfully applied in this project to drains at the Changi East Reclamation Project.
improve the underlying compressible soils. The project
comprises the installation of prefabricated vertical drains
and the subsequent placement of surcharge to accelerate PREFABRICATED VERTICAL DRAINS
the consolidation of the underlying marine clay.
In the entire project, a total of 142 million linear The prefabricated vertical drain (PVD) with preload-
meters of vertical drains were installed making this one ing method was considered the most feasible one and
of the largest projects in the world in which pre- this method was used in the project. The objective of
fabricated vertical drains were used. In order to monitor using the vertical drains with preloading technique is to
the performance of ground improvement and to validate accelerate the rate of consolidation and to minimize
the efficiency of the prefabricated vertical drain system future settlement of the treated area under the future
several geotechnical instruments were installed to dead and live loads. Soil improvement works is carried
monitor the degree of consolidation at both area with out in such a way that a specified degree of primary
PVD and area without PVD as control area. consolidation is designed to be attained within the desired
time frame by improving the soil drainage system.

1
Senior Lecturer, Swinburne University of Technology, Melbourne, AUSTRALIA. Email: aarulrajah@swin.edu.au
2
Director (Geo-services), DST Consulting Engineers, Thunder Bay, Ontario, CANADA. Email: drmwbo@yahoo.co.uk
3
Associate Professor, Nanyang Technological University, SINGAPORE. Email: CJCHU@ntu.edu.sg
4
Associate Professor, Curtin University of Technology, Perth, AUSTRALIA. Email: H.Nikraz@curtin.edu.au
652
The primary use of prefabricated vertical drains is to INSTRUMENTATION ASSESSMENT
accelerate consolidation to greatly decrease the duration
of consolidation process caused by embankment built Assessment of degree of consolidation could be
over soft soils. This will ensure that the final construction carried out by means of field instrument monitoring at
can be completed in a reasonable time and with minimal regular time intervals. Degree of improvement can be
post construction settlement. Preloading increases the monitored and assessed throughout the period. Two
effective stress and reduces the compressibility of weak simple instruments that can assess the degree of
ground by forcing soft soils to consolidate. By doing so, consolidation are settlement plates and piezometers.
the consolidation process also improves the strength of Details on assessment of degree of consolidation have
in-situ soft soils. been discussed by Bo et al. (1997) and Arulrajah et al.
(2005, 2004a, 2004b).
Degree of consolidation for settlement gauges can be
GEOTECHNICAL FIELD INSTRUMENTATION computed based on the field settlement. Degree of
consolidation is defined as percentage of magnitude of
Geotechnical instrumentation is the only means settlement that occurred at time t upon ultimate primary
available of providing continuous records of the ground consolidation settlement as indicated in Eq. 1. From
behavior from the point of instruments installation. measured field settlement and predicted ultimate
Without a proper geotechnical instrumentation method settlement, degree of consolidation can be estimated.
or programme, it would be difficult to monitor at any Ultimate settlement can be predicted for marine clays
point of time the current degree of improvement of the treated with vertical drains and preload by the Asaoka
soil. By analyzing the instrument monitoring results, it is (Asaoka 1978) or Hyperbolic (Tan 1995) methods.
possible to determine the degree of consolidation of the
foundation soil before allowing the removal of the Us (%) = St / Sα (1)
surcharge load and it is possible to ascertain the
achievement of required effective stress and to indicate where St = field settlement at any time t; Sα = ultimate
the necessity for remedial action. settlement; and Us (%) = average degree of consolidation.
In order to study the performance of compressible Piezometers are utilized to measure the pore pressure
soils under reclaimed fill, geotechnical instruments have in the soil. If regular monitoring is carried out to
to be installed. Various geotechnical field instruments measure the piezometric head together with static water
were installed in instrumentation clusters to enable the level, dissipation of excess pore pressure can be detected
instruments functions to complement each other. All and thus degree of consolidation can be assessed.
instruments found in the instrument clusters were also Average residual excess pore pressure is defined as ratio
extended and protected throughout the surcharge placement of excess pore pressure at time t upon initial excess pore
operations. In coastal land reclamation projects, instruments pressure. Therefore degree of consolidation for a soil
were installed either off-shore prior to reclamation or on- element, Uu can be defined as shown in Eq. 2.
land after reclamation to the vertical drain installation
platform level. Uu (%) = 1- (Ut / Ui) (2)
Field instruments suitable for the study of
consolidation behavior of underlying soils and monitoring where Uu (%) = degree of consolidation for a soil
of land reclamation works included surface settlement element; Ut = the excess pore pressure at time t; and Ui =
plates, deep settlement gauges, multi-level settlement initial excess pore pressure which is equal to the
gauges, liquid settlement gauges, pneumatic piezometers, additional load.
electric piezometers, open-type piezometers, water
standpipes, inclinometers, deep reference points and total
earth pressure cells. A total of 7246 geotechnical instru- CASE STUDY AREA
ments were installed at the Changi East Reclamation
Projects. Instrument monitoring was carried out at Singapore marine clay at Changi is a quartenary
regular intervals so that the degree of improvement could deposit that lies within valleys cut in the Old Alluvium.
be monitored and assessed throughout the period of the The Case Study Area comprises of two distinct layers of
soil improvement works for the project. Instruments marine clay which are the “Upper Marine Clay” layer
were monitored at close intervals of up to 3 times a week and the “Lower Marine Clay” layer. The “Intermediate
during sandfilling and surcharge placement operations. Stiff Clay” layer separates these two distinct marine clay
layers.
The upper marine clay is soft with undrained shear
strength values ranging from 10 to 30 kPa. Marine or
653
organic matter is found in the upper marine clay. The reclamation in off-shore instrument platforms. These
intermediate layer is a silty clay layer. The lower marine instruments were protected as the reclamation filling
clay is lightly overconsolidated with an undrained shear works commenced in the area. Fig. 1 shows the geologi-
strength varying from 30 to 50 kPa. It is not homo- cal profile of the Case Study Area and the typical details
geneous but occasionally interbeded with sandy clay, of on-land and adjacent off-shore field instrumentation
peaty clay and sand layers. Below the lower marine clay clusters.
is a stiff sandy clay layer locally known as Old Alluvium. Instruments in the Vertical Drain Area were installed
The characteristics of the marine clay found at Changi, on-land at the vertical drain platform level of +4 m CD
Singapore has been discussed previously by Bo et al. just before or soon after vertical drain installation at 1.5
(1997, 1998) and Arulrajah et al (2004a, 2004b). meter square spacing. Surcharge was subsequently placed
The Case Study Area consists of a Vertical Drain to +10 m CD. The analysis of the instrumentation results
Area at which vertical drains were installed at 1.5 meters was carried out for both the Vertical Drain Area and
spacing to depths of 35 meters, as well as an adjacent Control Area after a monitoring period of about 26 months
Control Area where no vertical drains were installed. which equates to a surcharging period of 20 months.
This enabled comparisons to be made between an area Fig. 2 shows the construction sequence of works at
treated with vertical drains with an untreated area. Both the Case Study Area. The profile of the field
the areas were treated with the same height of surcharge instrumentation elevations at the Case Study Area has
preload. Instruments were installed and monitored at been recently described by Arulrajah et al. (2005, 2004a,
both the Vertical Drain Area and the Control Area. The 2004b).
instruments in the Control Area were installed prior to

Fig. 1 Geological profile and details of field instrumentation at Case Study Area
11
10
Ground Elevation (m CD)

9
8
7
6
Install v.d.
5
4
3
2 Ground Elevation (SP95)
1 Water Level (WS-20)
0
0 60 120 180 240 300 360 420 480 540 600 660 720 780 840
Time (days)
Fig. 2 Construction sequence of works at Case Study Area
654
Settlement Measurements 0

-5
Fig. 3 indicates the magnitudes of settlements in the
Vertical Drain Area. The deep settlement gauges that -10

Elevation (m CD)
were installed in the different sub-layers indicate -15
decreasing settlement with depth as would be expected.
-20
As expected, the Vertical Drain Area indicated much Vertical Drain Area: 3 months after surcharge
greater settlement magnitudes as compared to the -25 Vertical Drain Area: 9 months after surcharge
Vertical Drain Area: 20 months after surcharge
Control Area. This indicates that the vertical drains are Control Area: 3 months after surcharge
-30
functioning. The settlement plates (SP-95) and the deep Control Area: 9 months after surcharge
Control Area: 20 months after surcharge
settlement gauge (DS-93) that were installed at the -35
0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
original seabed level gave similar reading for the Settlement (m)
magnitude and rate of settlement.
Fig. 4 compares the settlement plate results between Fig. 5 Comparison of field settlement isochrones
the Vertical Drain Area and Control Area. The vast
improvement of the Vertical Drain Area as compared to
the Control Area is clearly evident in the figure. Fig. 5 Pore Pressure Measurements
compares the field settlement isochrones between the
Vertical Drain Area and Control Area for various The piezometer monitoring data in the Vertical Drain
surcharge durations. As expected the magnitude and rate Area after correction of the piezometer tip settlement is
of settlement of the Vertical Drain Area is much higher shown in Fig. 6. Fig. 7 indicates the comparison of
than that of the Control Area. excess pore pressure isochrones between the Vertical
Drain Area and Control Area at various periods after
0.0 surcharge placement.
DS-110
DS-109
-0.5 160
DS-108 PP-76 (-6.92 m CD)
DS-107 140 PP-77 (-9.91 m CD)
-1.0
Settlement (m)

PP-79 (-17.8 m CD)


Excess Pore Pressure (kPa)

120 PP-80 (-22.9 mCD)


-1.5 DS-106 PP-81 (-27.8 m CD)
100 PP-82 (-32.08 m CD)
SP-95 (-3.29 mCD)
-2.0 DS-93 (-4.1 mCD) 80
DS-106 (-10.9 mCD) DS-93 PP-76
DS-107 (-14.8 m CD) 60 PP-77
-2.5 DS-108 (-20 m CD) SP-95
PP-80
DS-109 (-27.1 m CD) 40
DS-110 (-34.1 m CD) PP-79
-3.0 PP-81
20
0 60 120 180 240 300 360 420 480 540 600 660 720 780 840
Time (days) PP-82
0
0 60 120 180 240 300 360 420 480 540 600 660 720 780 840
Fig. 3 Field settlement results at Vertical Drain Area Time (days)

Fig. 6 Excess pore pressures at Vertical Drain Area


0.0
0.2
0.4 -5
0.6
-10
0.8
Settlement (m)

1.0 -15
1.2
Elevation (m CD)

1.4 -20

1.6
-25
1.8
2.0 -30
2.2 Vertical Drain Area: SP-95
-35 Vertical Drain Area: 3 months after surcharge
2.4 Control Area: SP-04 Vertical Drain Area: 9 months after surcharge
Vertical Drain Area: 20 months after surcharge
2.6 Control Area: 3 months after surcharge
-40 Control Area: 9 months after surcharge
0 60 120 180 240 300 360 420 480 540 600 660 720 780 840 Control Area: 20 months after surcharge
Submerged Additional Load 20 months after surcharge= 158.51 kPa
Time (days) -45
0 20 40 60 80 100 120 140 160 180 200
Fig. 4 Comparison of field settlement at Case Study Excess Pore Pressure (kPa)

Area
Fig. 7 Comparison of piezometer excess pore pressure
isochrones
655
The rapid dissipation of excess pore water pressure CONCLUSION
with time is clearly evident in the Vertical Drain Area.
The slow rate of dissipation of excess pore water The ultimate settlement predicted from the settlement
pressure with time is also noted at the Control Area. It is gauges by application of the Hyperbolic and Asaoka
evident that the degree of consolidation of the Vertical prediction methods was found to be about 3 meters. The
assessment of degree of consolidation is found to be in
Drain Area is far greater than that of the Control Area.
good agreement for the Asaoka, Hyperbolic and
piezometer methods. The settlement gauges and
Degree of Consolidation piezometers indicate that the degree of consolidation of
the Vertical Drain Area had attained a degree of
The degree of consolidation was assessed from the consolidation of about 80%. The piezometers indicate
settlement plates by the Asaoka (Asaoka 1978) and that the Control Area had only attained a degree of
Hyperbolic (Sridharan & Sreepada 1981; Tan 1995) methods. consolidation of about 20%. The instrumentation results
The method of application of these methods for land in the Vertical Drain Area indicates much higher degree
reclamation projects on marine clay have been discussed of improvements as compared to the Control Area which
by Arulrajah et al. (2004b) and Bo et al. (1997). indicates that the vertical drains are performing to
improve the soil drainage system. In addition to the field
Fig. 8 compares the degree of consolidation as obtained
instrumentation case study, this paper also discusses the
from the settlement gauge and piezometer results. Table methods of land reclamation and field instrumentation.
1 compares the degree of consolidation as obtained by
the observational methods at the Vertical Drain Area. It
is seen that the methods give consistent results. The degree REFERENCES
of consolidation of the piezometers was obtained from the
isochrones of the piezometers. The degree of consolidation Arulrajah A (2005) Field Measurements and Back-
estimated from the pore pressure measurements is found Analysis of Marine Clay Geotechnical Characte-
to tie in well with that of the settlement gauges at the ristics under Reclamation Fills. PhD thesis, Curtin
Vertical Drain Area which is about 80%. The degree of University of Technology, Perth, Australia
Arulrajah A, Nikraz H, Bo MW (2004a) Observational
consolidation estimated from the pore pressure measure-
Methods of Assessing Improvement of Marine Clay.
ments in the Control Area is less than 20%. Ground Improvement 8(4): 151-169
0
Vertical Drain Area Piezometers
Arulrajah A, Nikraz H, Bo MW (2004b) Factors
Vertical Drain Area Settlement gauges(Hyperbolic method)
Vertical Drain Area Settlement gauges (Asaoka method) Affecting Field Instrumentation Assessment of
-5 Control Area Piezometers
Marine Clay Treated With Prefabricated Vertical
-10 Drains. Geotextiles and Geomembranes 22(5): 415-
437
Elevation (m CD)

-15
Asaoka A (1978) Observational Procedure of Settlement
-20
Prediction. Soil and Foundations 18(4): 87-101
Bo MW, Chu J, Low BK, Choa V (2003) Soil Improve-
-25 ment–Prefabricated Vertical Drain Techniques.
Thomson Learning. Singapore
-30
Bo MW, Arulrajah A, Choa V (1997) Assessment of
-35 degree of consolidation in soil improvement project.
0 10 20 30 40 50 60 70 80 90 100 Proceedings of the International Conference on
Degree of Consolidation (%)
Ground Improvement Techniques. Macau: 71-80
Bo MW, Arulrajah A, Choa V (1998) Instrumentation
Fig. 8 Comparison of degree of consolidation between and monitoring of soil improvement work in Land
Vertical Drain Area and Control Area reclamation projects. 8th International IAEU
Congress, Balkema, Rotterdam: 1333-1392
Table 1 Degree of consolidation comparisons at Sridharan A, Sreepada Rao A (1981) Rectangular
Vertical Drain Area Hyperbola Fitting Method for One-dimensional
Asaoka Hyperbolic Piezometer Consolidation. Geotechnical Testing Journal 4(4):
161-168
Ultimate
3.000 3.005 - Tan SA (1995) Validation of Hyperbolic Method for
Settlement (m)
Settlement in Clays with Vertical Drains. Soil and
Settlement to
2.404 2.404 - Foundations 35(1): 101-113
Date(m)
U (%) 80.1 80.0 80.0

Potrebbero piacerti anche