Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
In addition to the above, four nos. of Tie Transformers, five nos. of Auto
Transformers and two nos. of Shunt Reactors are provided as shown in the
switchyard line diagram.
.
2 400/220 Kv 250 MVA (TELK make) 2 Nos
.
3 400/220 Kv 315 MVA (Crompton Greevs 2 Nos
. Ltd. make)
Four nos. of Tie Transformers are provided for feeding power to station
auxiliaries like Cooling water & Raw water pumps, Coal Handling & water
treatment Plants, Ash & Fuel Handling pumps, Cooling towers and lighting
requirements of station & colony.
Long lines when lightly loaded, the receiving end voltage raises, due to
ferranti effect. Shunt Reactors produce lagging MVAR there by control the
receiving end voltages during lightly loaded conditions. Shunt reactors also
limit the short circuit fault levels. Therefore, Shunt reactors are provided on
both the ends of Nagarjuna Sagar lines 1 & 2, the length of these lines being
about 267 km.
2. SWITCHYARD OPERATION ACTIVITIES
As mentioned else where, RSTPS switchyard is handling bulk power and its
operation and Maintenance has become critical. Any ambiguity in the
operation of the switchyard may lead to such disasters like grid failure, station
outages crippling not only the normal life of people but also the very economy
of the country. Even in less serious situations such as cascade tripping of
Auto Transformers due to unplanned over loading has caused under utilization
of our generating capacity many times. The operation of switchyard calls for
a very alert staff that shall have to sense the abnormalities in time and prompt
to concern timely to enable normalcy of the system. The following are some
of the identified activities of 400 KV switchyard operations.
3.2 ISOLATORS
Earth switch is mounted on the isolator base on the line side or breaker side
depending upon the position of the isolator. The earth switch usually
comprises of a vertical break switch arm with the contact, which engages with
the isolator contact on the line side. Earth switch is required to discharge the
trapped charges on the line or equipment (under shut own) to earth for
maintaining safety. Earth switch can be operated only from local either by
electrical operation or manually.
3.4 BUSBAR
Surge Arresters are provided to ground the over voltage surges caused by
switching and lighting surges. Surge Arresters provide leakage path to the
ground whenever the system voltage rises above the specified value. They are
equipped with surge monitors, which measure the leakage currents and a
counter to record the number of surges taken place.
Current Transformers are provided to step down the current to low values
suitable for measuring protection and control instruments. Current
Transformers also isolate measuring and protective devices from high system
voltage. CTs in the switchyard consist of five secondary cores. Core 1&2 are
used for busbar protection, 4 & 5 are for main 1&2 protection and core 3 is for
measuring instruments.
3.7 CAPACITIVE VOLTAGE TRANSFORMER (CVT)
CVTs step-down the system voltage to sufficiently low value (110 V) for
measuring, protection and synchronizing circuits. CVT has a H.F. terminal
point for receiving & transmitting the high frequency signals for carrier
protection and communication.
The control room is the place where the conditions of the system are
monitored, controls initiated and operations are integrated. Control room
consists of the following equipment.
Relay panels are of cubicle type, flat independent boxes with a door at
backside. All the protective relay units related to one bay are divided into two
groups viz. Main 1 protection, stub protection, O/V protection and their
auxiliary & trip relays as group 1 and Main 2 protection, U/v protection and
their auxiliary & trip relays as group 2 relays. Group 1 & group 2 relays are
mounted on front side of two separate panels side by side. Fault locator and
disturbance recorder of the corresponding bay mounted on front side of the
third panel. A separate glass door is provided front side of all the panels to
cover the relays from dust.
4.3 EVENT LOGGER
Even Logger recognizes the changes in signal-input states, plus time data
allocation for sequential recording of events. It displays the events in a time
sequential of 1/ sec, such as opening/closing of breaker poles, Isolator poles,
E/S etc. pressure high/low of air, SF6, N2 Oil etc. Alarm Appeared/reset of all
protection / trip relays, it also displays the status of equipment, in service/ out
of service in a regular period say 8 hrs. This is one of the important
diagnostic equipment available to operation staff to understand the type of
emergency in a flick of a second.
TYPES OF DISPLAYS
All 400 KV lines connected to this switchyard are provide by the Disturbance
Recorders (D/R), D/R is a PC based or Microprocessor based on line
monitoring equipment D/R is the most vital diagnostic equipment in analysis
of post fault trippings.
a) Inter tripping
b) Permissive tripping
c) Blocking
Blocking commands are always monitored by a protection relay. The circuit
breaker can be operated only if the command is absent when the protection
relay is operated by a fault.
d) Telemetry
e) Telephone
A relay detects the faulty element in the integrated power system and removes
it, with the help of the circuit breaker, from the remaining healthy system as
quickly as possible to avoid damage and maintain security or reliability of
supply in the healthy system. The quality of relaying depends on its
sensitivity, selectivity, speed and reliability. Varieties of protection relays are
provided to protect EHV lines and Transformers. A brief Description is given
below about the relays used for protection of Transformers and lines
connected to switchyard.
1. Instantaneous OC relay
The DTOC Relay has two settings; the first one is the pick value in amperes
(plug setting.). Another setting is the constant or definite operating time of
the relay. The relay delivers trip output only when the current exceeds the
pickup value and that after a specified time delay.
The operating time of IDMT relay is inversely proportional to the square o the
relay input current (plug setting) and the travel time of the disk to close the
NO contacts. The travel time of the disk to close the NO contact can be
changed by moving the backstop of the relay (Time multiplier setting).
Conventional over current relays are non-directional, which means the relay
operates on current magnitude and not on its direction or phase shift. The
Directional over current relay comprises two elements, a directional element
and OC relay element. The OC element is inhibited for operating until the
directional element has operated. The directional element is a watt metric
device, which measures the direction of power flow.
Earth fault relay is a sensitive protection against earth faults, which responds
only to residual current of the system, since a residual component that exists
only when fault current flow to earth. The residual component is extracted by
connecting the line CTs in parallel.
The differential relay checks the difference between the input and output
currents for any power system element, either in amplitude or in phase or
both, to determine whether the state of the power system is healthy or faulty.
In the event of a substantial difference, the element is assumed to be faulty
and trip the concerned breakers.
Pilot wire protection scheme can be used for protection of transmission lines
of 220 KV and below voltages. Similar current Transformers at each end of
the protected zone are interconnected through pilot wires. Current transmitted
through the zone causes secondary current to circulate round the pilot circuit
without producing any current flow in relay. A fault within the protected zone
will cause secondary current flow in to protection relay.
5.9 PHASE COMPARISON RELAY
The basic principle of the phase comparison relay is to check the phase
difference of current at both ends of the protected line. The carrier channel is
used to convey the phase angle of the current at one relaying point to another
for comparison with the phase angle of the current at that point.
Distance relay is of the high speed class can provide both primary and back up
facilities in a single scheme. Distance relay operate only for faults occurring
between the relay location and the selected reach point, thus giving
discrimination for faults that may occur between different line sections. The
basic principle is comparing of the fault current ‘seen’ by the relay with
voltage at the relaying point; by comparing these two quantities sit is possible
to determine whether the impedance of the line up to the point of the fault is
greater than or less than the predetermined reach point independence.
For EHV, line where fast fault clearance and high reliability vital ‘full scheme
of distance relays are provided. Full distance scheme uses six measuring units
per zone, three for phase faults and three for earth faults. All 18 measuring
units in three zones operate independently to protect the line and provide
backup to the adjacent lines.
Power swings are variations in power flow which occur when the voltage of
generators at different points of the power system slip relative to ach other to
cater changes of load magnitude and direction or as a result of faults and their
subsequent clearance. In the case of a transient power swing, it is important
that the Distance relay should not trip and should allow the power system to
return to a stable condition. For this reason Distance, protection scheme has
an optional power swing-blocking feature.
SWITCHYARD EMERGENCIES AND
PLAN OF ACTION
6.1 CONDITION MONITORING
The details break down analysis can be done after checking the relays,
protections operated at relay panels. Disturbance recorder provides the
voltage and current graph with respect to time of pre and post incident of fault
conditions. D/R also provide the sequence of protections operated.
A brief description about the annunciations provided, and the plan of action to
be taken by the operation staff is as follows.
PLAN OF ACTION
2. Check for the event logger and D/R printouts for various relay
operations and events taken place.
3. Reset the CB auto trip indication by giving the trip impulse with the
breaker close/open handle at control panel.
All the three poles of a circuit breaker must open or close at a time when a trip
or close command initiated. If one of the pole fails or delayed to open or
close within a specified (0.02 secs) time, circuit breaker trips immediately
followed by C.B. pole discrepancy alarm.
PLAN OF ACTION
This annunciation appears when the master trip relay (86) operates in
response to a fault but the concerned circuit breaker fails to trip. Local
Breaker Breakup relay (50Z) acts and initiates the busbar protection of the
respective bus, which trips all other circuit breakers connected to the bus.
PLAN OF ACTION
1 Check for the protection relay, which caused operation of Group A/B
trip relays.
2 Check for the busbar protection trip relay (96) for Main/tie breaker
whichever LBB has operated.
3 Check for physical opening of breakers for which LBB relay
operated.
4 Inform Maintenance group for attending the problem.
5 Restore the normalcy through the other breaker (Tie breaker) in case
of Main breaker failed to trip and vice versa.
4. C.B. SF6 DENSITY LOW/ AIR PRESSURE LOW
This annunciation appears whenever SF6 gas pressure/ Air pressure falls
below the specified value.
PLAN OF ACTION
1 Check the SF6 pressure / Air pressure locally, and asses the rate of
leakage.
2 If the rate of leakage is high, after obtaining necessary clearance trip
and isolate the breaker as early as possible. Otherwise the breaker
may go into lockout state, which is to be avoided as much as
possible.
3 If leakage rate is low inform Maintenance group for attending the
problem.
5. CB OPERATION LOCKOUT
This annunciation appears whenever either air pressure (oil pressure in case of
hydraulic operated breakers) or SF6 gas pressure falls below specified values.
In operation lockout state circuit breaker will not operate. This feature is very
much required to prevent the breaker operation in adverse conditions of
operating system and/or arc quenching media (SF6 gas)
PLAN OF ACTION
1 Check for the air pressure and SF6 gas pressure locally.
2 Identify the problem. If heavy leakage is observed in SF6 gas/ AIR
system, then sough permission from IOCC for isolates the breaker from
connecting bus.
3 Isolate the breaker by opening the both the side isolators after making
the load flow zero.
B. ALARMS RELATED TO TRANSMISSION LINE FEEDER
PROTECTION
Over voltage relay operate when the line voltage rises above a specified value.
Instantaneous and definite time over voltage relay is provided for each line. If
the voltage exceeds 40% of the rated voltage (400 kv) instantaneous relay
picks up and trip the line. If voltage exceeds 10% of rated value for duration
of more than 5 sec. the time delay relay picks up and trip the line.
PLAN OF ACTION
This alarm appears when one of the main protections becomes unhealthy due
to D.C. supply failure for relay unit or some in built problem in the relay.
PLAN OF ACTION
PLAN OF ACTION
6 Nos of fuses are provided for the three secondary cores of a CVT. VT fuse
fail annunciation appears in case of one of the fuse fails.
PLAN OF ACTION
1 Check for the flag indication for the operation of the relay indication.
2 Inform Maintenance group for replacing the CVT fuse/rectifying the
problem.
3 In case the rectification of problem takes more time. The voltage inputs
to the over fluxing relay, directional over current relay and VT fuse
failure relay shall be shifted to other 400 KV bus.
PLAN OF ACTION
The protection scheme provided for the bay equipment are divided into two
groups and connected separately to two trip relays. Operation of any
protection relay will operate the trip relay connected to that group. The
operation of any one of the two trip relays initiates the above annunciation.
PLAN OF ACTION
PLAN OF ACTION
1 Collect the other end relay and breaker operation and correlate with the
operations of this end.
2 Do not charge the line until Maintenance clearance obtained.
This alarm appears whenever power supply unit of fault locator fails (power
switch off position etc.) or some in built problem in the unit arises.
PLAN OF ACTION
This alarm appears whenever power supply unit of D/R fails (power switch
off position etc.) Or some in built problem in the unit arises.
PLAN OF ACTION
Cooler trouble alarm appears when one or more of the following conditions.
PLAN OF ACTION
PLAN OF ACTION
After getting clearance from SCE, DGM (EM), IOCC and AP TRANSCO
PLAN OF ACTION
1 The Transformer can be charged only after carrying out tests including
DGA and obtaining clearance in writing from EM dept.
2 In case the gas is not found in buchholz relay, the reason shall be
established for operation of buchholz relay and then the Transformer
should charged.
3 In case of air accumulated in Buchholz relay, the Transformer can be
charged after releasing the air.
3. PRESSURE RELIEF DEVICE OPERATED
Pressure release device allows for the rapid release of excessive pressure that
may be generated in the event of a serious fault in the Transformer. A bright
colour coded Mechanical indicator pin in the cover moves with the valve disc
during operation of PRD and is held in position by an in the pin bushing. This
pin is clearly visible from the ground level indicating that the device is
operated.
PLAN OF ACTION
1 Check for any other protection relays operated to identify the problem.
2 Check for both LT and HT side breaker tripping. If any one of the
breaker in service hand trip the same.
3 Check for any gas accumulation in Buchholz relay
4 Transformer may be charged only after thorough investigation for the
reason of PRD operation and obtaining clearance from Maintenance
group.
Isolation and charging of high voltage equipment have great potential for
hazardous occurrences and need to consider safety at each juncture. Safety in
electrical system concerns three different areas; protection of life, protection
of equipment, protection of uninterrupted productive output. The protection
of human life is paramount. Equipment can be replaced lost production can
be made up. However, human life can never be recovered nor human
sufferings compensated. Therefore, only qualified and authorised persons
shall be allowed to operate switchyard equipment.
b) There must be checks and cross checks to confirm that you are at
right apparatus for the particular operation.
c) NO part of the body should touch any part of the equipment under
charging during isolation or normalization.
f) Operation staff for their own safety should use the personal
protective equipment like safety shoe, hand gloves etc. at work.
If the required shutdown is going to affect the power flow in the tie lines
connected to PGCIL substations, then shutdown concurrence must be
obtained from IOCC. For the line belongs to AP Transco, shutdown
concurrence must be obtained from LDC.
b) Inform orally to the other end substation shift in charge regarding the de
energisation of line/Transformer and hold him on line.
d) Check the line loads and ensure that the shutdown of the equipment,
should not make over loading the other lines or Transformers.
e) Identify the correct bay and concerned main and tie breakers to be
tripped for de energisation of the line/ Transformer.
f) Keep the Auto Recloser switches of the main and tie breakers in N.A.
position.
2. Confirm from the other end operator on telephone that the breaker at
their end tripped on intertrip signal.
1. Hand trip the main breaker of the line to be de energized if the line is
connected to main bus or the transfer bay breaker if the line is
connected to transfer bus.
2. Confirm from the other end operator on telephone that the breaker at
their end tripped on intertrip signal.
2. Hand trip line breaker (220 KV side) and inform the other end shift in
charge on phone that the Transformer is de energized and ensure that
the other end breaker tripped on intertrip signal.
D. DE ENERGISATION OF 400KV/132 KV AUTO TRANSFORMERS
2. Open the 400 KV side (HT) isolator from remote or local mode.
3. Open the 220kv/132kv side (LT) isolator either from remote or from
local position.
5. Close the 400 kv side isolator earth switch and 220 kv/132 kv side
earth switches and lock them.
6. Keep the danger tags at breakers on/off handle giving the details of
the permit being issued.
7. Note down on the permit card the isolations done along with the
precautions to be taken further by the recipient at time of work carrying
the work and issue the permit card to the applicant.
8.NORMALIZATION AND CHARGING OF LINES AND
TRANSFORMERS
For normalizing and charging the transmission lines and Transformers, certain
preconditions are required to be met so as to safely normalize and charge the
feeder or Transformer. As the transmission lines in 400 KV net work are so
long and Transformer s are of large capacities, certain conditions like enough
capacity of the system to absorb the line MVAR to be ensured. Safety of
personnel to be ensured. While synchronizing the feeder, enough precautions
to be taken to ensure that the grid system is compatible and within limits so
that there should not be power swings owing to a synchronism.
a) Check physically the work area for removal of men and Material.
d) Check for SF6 gas and air/ oil pressure of main/ tiebreakers.
e) Ensure that the Local / Remote switches of the Main/ Tie breakers
are kept on remote position.
i) Ensure that disturbance recorder, fault recorder, and event logger are
in service.
a) Open the earth switch of the line isolator. Also open the earth
switches of main and tie bay isolators if any closed position.
d) Close the tie bay isolators I the permits are not pending on Tie bay
equipment.
e) Close the shunt reactor isolator if shunt reactor available for the line
and it is in isolated condition.
In case of IOCC instructed to charge the line from this end and to synchronize
from the remote substation.
a) Inform IOCC that the line is ready for charging and take the final
clearance for charging the line.
b) Inform orally to the other end substation operator that the line is
ready for charging and hold him on line.
f) Close main/ tiebreaker which ever bay is made ready for charging
the line (dead line charging). Subsequently close the other breaker
also If the bay equipment not under permit.
g) Inform the remote end operator on telephone that the line is charged
and give clearance for synchronizing to the grid.
3. Check for heavy oil leaks if any from tank, radiator, pipes
and bushings.
d) Close 220 kv side isolators and 400 kv side main and tie
bay isolators provided the permits are not pending.
In case, AP Transco requested to change the 220 KV line from this end and to
synchronize at their substation.
a) Inform LDC that the 220 KV line is ready for charging and take the
final clearance for charging the line.
Despite of all precautions and protective measures, the integrity of the power
system is occasionally at risk owing to human error, malfunction of
equipment, lack of complete information, and natural disasters. The
emergency like grid failure/ partial grid failure may lead to total loss of power
supply in the region / station, which is called the blackout condition.
In case of total Blackout of station / region due to grid failure or partial grid
failure, operation staff are responsible.
3.To arrange startup power at the earliest to bring back the units.
2. Have a broad lock on the panel, see whether any unit has
survived on house load and / or any line feeding on house load
has survived.
3. Inform shift charge engineer and all units about the status on
emergency PA system through group call.
6. See that all outgoing feeder breakers have opened out, if not,
open them manually.
a) Close 400 KV breakers pertaining to above set feeder and thus charge
400 kV buses 1 or 2
b) Charge 400/33 kV Tie Transformer 1 or 2 or 3.
c) Charge 33 kV bus 1 and / r 2 and / or 3.
g) Due to lack of power, battery chargers had tripped and the ENTIRE D
Batteries supplied load.
k) Now situation is normal. Once units are ready for synchronization seek
instructions from IOCC and LDC, accordingly take lines in service and
synchronize the units.
OPERATION GUIDELINES OF 400 KV SWITCH YARD
Contents