Merass 132-11kv Garden City Substation

Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
339 02-Dec-17 A 31-Dec-18 0 31-Dec-18, Merass 132-11k V Garden City S
Merass 132-11k V Garden City Substation
30 02-Dec-17 A 04-Jan-18 A 04-Jan-18 A, Site Establishment
Site Establishment
Establishme
GCS00010 Site Establishment 30 100% 02-Dec-17 A 04-Jan-18 A Site Establishment
GCS00020 NTP1 ( Site Fencing and Site Establishment ) 0 100% 02-Dec-17 A NTP1 ( Site Fencing and Site Establishment )
124 02-Dec-17 A 25-Apr-18 64 25-Apr-18, Milestones
Milestones
GCSM0100 Receiving ( Permits & Drawings ) to Security Room 0 100% 02-Dec-17 A Receiving ( Permits & Drawings ) to Security Room
GCSM0020 Receiving NTP 2 ( Permits & Drawings ) to Main Bulding 0 100% 02-Dec-17 A Receiving NTP 2 ( Permits & Drawings ) to Main Bulding
GCSM0010 NTP1 ( Site Fencing and Site Establishment ) 0 100% 02-Dec-17 A NTP1 ( Site Fencing and Site Establishment )
GCSM0060 Receiving ( Permits & Drawings ) to Shunter Room 0 100% 04-Jan-18 A Receiving ( Permits & Drawings ) to Shunter Room
GCSM0080 Receiving ( Drawings ) Steel Truss at Roof 0 100% 10-Jan-18 A Receiving ( Drawings ) Steel Truss at Roof
GCSM0050 Receiving ( Permits & Drawings ) to Fire Pump Room 0 100% 21-Feb-18 A Receiving ( Permits & Drawings ) to Fire Pump Room
GCSM0030 Receiving ( Permits & Drawings ) to Under Ground Oil/ Water Tank 0 100% 06-Mar-18 A Receiving ( Permits & Drawings ) to Under Ground Oil/ Water Tank
GCSM0040 Receiving ( Permits & Drawings ) to ET Room 0 100% 17-Mar-18 A Receiving ( Permits & Drawings ) to ET Room
GCSM0070 Receiving ( Permits & Drawings ) to Fire Trench 0 0% 25-Apr-18 40 Receiving ( Permits & Drawings ) to Fire Trench
GCSM0090 Receiving ( Permits & Drawings ) to Boundary Wall 0 0% 25-Apr-18 44 Receiving ( Permits & Drawings ) to Boundary Wall
101 04-Sep-18 31-Dec-18 0 31-Dec-18, Clean Access Contractual Milest
Clean Access Contractual
C Milestones
GCSM0120 Access for Capacitor Bank 0 0% 04-Sep-18 83 Access for Capacitor Bank
GCSM0220 Access for Cable Basement 132Kv 0 0% 13-Sep-18 75 Access for Cable Basement 132Kv
GCSM0110 Access for Cable Basement 11Kv 0 0% 13-Sep-18 75 Access for Cable Basement 11Kv
GCSM0130 Access for 11 kV SWGR Room 0 0% 13-Sep-18 75 Access for 11 kV SWGR Room
GCSM0180 Access for Transformer 0 0% 01-Oct-18 60 Access for Transformer
GCSM0140 Access for 132 kV GIS Room 0 0% 09-Oct-18 53 Access for 132 kV GIS Room
GCSM0160 Clean Access to Roof Floor 0 0% 09-Oct-18 53 Clean Access to Roof Floor
GCSM0150 Access for Pump Room 0 0% 25-Oct-18 40 Access for Pump Room
GCSM0170 Access for F.F Rooms 0 0% 25-Oct-18 40 Access for F.F Rooms
GCSM0190 Access for Security Room 0 0% 21-Nov-18 34 Access for Security Room
GCSM0200 External Works including Filling & Boundary Wall 0 0% 21-Nov-18 34 External Works including Filling & Boundary Wall
GCSM0230 Access for FWT 0 0% 24-Nov-18 33 Access for FWT
GCSM0210 All Balance Civil Works Including Final Finishing Works 0 0% 31-Dec-18 0 All Balance Civil Works Including Final Finish
246 10-Dec-17 A 29-Oct-18 54 29-Oct-18, Summary of Concrete Works
Summary of Co
Concrete Works
Main Building 194 10-Dec-17 A 29-Aug-18 106 29-Aug-18, Main Building
Substructure Works
Wo 73 10-Dec-17 A 04-Mar-18 A 04-Mar-18 A, Substructure Works
GCSS0010 Substructure Works Start 0 100% 10-Dec-17 A Substructure Works Start
GCSS0020 Concrete to Raft Foundation 0 100% 04-Mar-18 A Concrete to Raft Foundation
11kv Switchgear Room & Capacitor Bank 88 25-Apr-18 05-Aug-18 127 05-Aug-18, 11kv Switchgear Room & Capacitor Bank
GCSS0030 Concrete Works to R.Wall to Capacitor Complete 0 0% 25-Apr-18 215 Concrete Works to R.Wall to Capacitor Complete
GCSS0040 Concrete Works R.Wall & Columns to Cable Basement Complete 0 0% 29-Apr-18 211 Concrete Works R.Wall & Columns to Cable Basement Complete
GCSS0050 Concrete Works to G.F Slab Cable Basement Complete 0 0% 15-May-18 197 Concrete Works to G.F Slab Cable Basement Complete
GCSS0060 Concrete Works to Columns and Wall to G.F. Slab Completion 0 0% 27-May-18 187 Concrete Works to Columns and Wall to G.F. Slab Completion
GCSS0070 Concrete Work to 1st Floor Slab at 11kv Switchgear Room Completion 0 0% 25-Jun-18 162 Concrete Work to 1st Floor Slab at 11kv Switchgear Room Completion
GCSS0080 Concrete Works to Columns and Wall to F.F Floor Completion 0 0% 10-Jul-18 149 Concrete Works to Columns and Wall to F.F Floor Completion
GCSS0090 Concrete Work to Roof Slab at 11kv Switchgear Room Completion 0 0% 05-Aug-18 127 Concrete Work to Roof Slab at 11kv Switchgear Room Completion
132kv GS Room 29 02-Jul-18 05-Aug-18 127 05-Aug-18, 132kv GS Room
GCSS0100 Concrete Works to Columns and Wall to F.F Floor Completion 0 0% 02-Jul-18 156 Concrete Works to Columns and Wall to F.F Floor Completion
GCSS0110 Concrete Work to Roof Slab at 132 kv GS Room 0 0% 05-Aug-18 127 Concrete Work to Roof Slab at 132 kv GS Room
Transformer Roo
Room 22 27-May-18 21-Jun-18 165 21-Jun-18, Transformer Room
GCSS0120 Concrete Works to R.Wall 1st Lift 0 0% 27-May-18 187 Concrete Works to R.Wall 1st Lift
GCSS0130 Concrete Works to R.Wall 2nd Lift 0 0% 09-Jun-18 176 Concrete Works to R.Wall 2nd Lift
GCSS0140 Concrete Works to R.Wall 3rd Lift 0 0% 21-Jun-18 165 Concrete Works to R.Wall 3rd Lift
Stair Case 63 18-Jun-18 29-Aug-18 106 29-Aug-18, Stair Case
GCSS0160 Concrete Works to Stair Case 01 Start 0 0% 18-Jun-18 169 Concrete Works to Stair Case 01 Start
GCSS0150 Concrete Works to Stair Case 02 Start 0 0% 18-Jun-18 169 Concrete Works to Stair Case 02 Start
GCSS0170 Concrete Works to Stair Case 01 Complete 0 0% 25-Aug-18 110 Concrete Works to Stair Case 01 Complete

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 1 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCSS0180 Concrete Works to Stair Case 02 Complete 0 0% 29-Aug-18 106 Concrete Works to Stair Case 02 Complete
Security Room 57 09-Jul-18 12-Sep-18 94 12-Sep-18, Security Room
GCSS0230 Substructure Works Start 0 0% 09-Jul-18 151 Substructure Works Start
GCSS0240 Concrete Works to Foundation Completion 0 0% 20-Aug-18 114 Concrete Works to Foundation Completion
GCSS0250 Concrete Works to Roof Slab Completion 0 0% 12-Sep-18 94 Concrete Works to Roof Slab Completion
Under Ground Oil / Water Tank 57 24-May-18 29-Jul-18 133 29-Jul-18, Under Ground Oil / Water Tank
GCSS0340 Substructure Works Start 0 0% 24-May-18 190 Substructure Works Start
GCSS0350 Concrete Works to Foundation Completion 0 0% 24-Jun-18 163 Concrete Works to Foundation Completion
GCSS0360 Concrete Works to Wall Completion 0 0% 29-Jul-18 133 Concrete Works to Wall Completion
Shunt Reactor 53 10-Jun-18 09-Aug-18 123 09-Aug-18, Shunt Reactor
GCSS0260 Substructure Works Start 0 0% 10-Jun-18 176 Substructure Works Start
GCSS0270 Concrete Works to Foundation Completion 0 0% 10-Jul-18 149 Concrete Works to Foundation Completion
GCSS0280 Concrete Works to R.Wall 1st Lift 0 0% 21-Jul-18 140 Concrete Works to R.Wall 1st Lift
GCSS0290 Concrete Works to R.Wall 2nd Lift 0 0% 30-Jul-18 132 Concrete Works to R.Wall 2nd Lift
GCSS0300 Concrete Works to R.Wall 3rd Lift 0 0% 09-Aug-18 123 Concrete Works to R.Wall 3rd Lift
ET Room 67 11-Jul-18 26-Sep-18 82 26-Sep-18, ET Room
GCSS0310 Substructure Works Start 0 0% 11-Jul-18 149 Substructure Works Start
GCSS0320 Concrete Works to Wall Completion 0 0% 12-Sep-18 94 Concrete Works to Wall Completion
GCSS0330 Concrete Works to Transformer Foundation Completion 0 0% 26-Sep-18 82 Concrete Works to Transformer Foundation Completion
Fire Trench 60 21-Aug-18 29-Oct-18 54 29-Oct-18, Fire Trench
GCSS0370 Substructure Works Start 0 0% 21-Aug-18 114 Substructure Works Start
GCSS0380 Concrete Works Completion 0 0% 29-Oct-18 54 Concrete Works Completion
Boudary Wall 63 16-Jun-18 27-Aug-18 108 27-Aug-18, Boudary Wall
GCSS0390 Excavation Works Start- Elevation 04 0 0% 16-Jun-18 171 Excavation Works Start- Elevation 04
GCSS0400 Excavation Works Start- Elevation 01 0 0% 16-Jun-18 171 Excavation Works Start- Elevation 01
GCSS0410 Excavation Works Start- Elevation 02 0 0% 16-Jun-18 171 Excavation Works Start- Elevation 02
GCSS0420 Excavation Works Start- Elevation 03 0 0% 16-Jun-18 171 Excavation Works Start- Elevation 03
GCSS0460 Concrete Works Completion Elevation 03 0 0% 23-Aug-18 111 Concrete Works Completion Elevation 03
GCSS0440 Concrete Works Completion Elevation 01 0 0% 26-Aug-18 109 Concrete Works Completion Elevation 01
GCSS0430 Concrete Works Completion Elevation 04 0 0% 27-Aug-18 108 Concrete Works Completion Elevation 04
GCSS0450 Concrete Works Completion Elevation 02 0 0% 27-Aug-18 108 Concrete Works Completion Elevation 02
102 25-Aug-18 22-Dec-18 8 22-Dec-18, Summary of Finishes Works
Summary of Fin
Finishes Works
Cable Basement 0 11-Sep-18 11-Sep-18 95 11-Sep-18, Cable Basement
GCSS0470 Cable Basement 11 kV Basement 01 Completion 0 0% 11-Sep-18 95 Cable Basement 11 kV Basement 01 Completion
GCSS0480 Cable Basement 11 kV Basement 02 Completion 0 0% 11-Sep-18 95 Cable Basement 11 kV Basement 02 Completion
GCSS0490 Cable Basement 132 kV Basement 01 Completion 0 0% 11-Sep-18 95 Cable Basement 132 kV Basement 01 Completion
GCSS0500 Cable Basement 132 kV Basement 02 Completion 0 0% 11-Sep-18 95 Cable Basement 132 kV Basement 02 Completion
Main Building 102 25-Aug-18 22-Dec-18 8 22-Dec-18, Main Building
G.F 29 04-Sep-18 08-Oct-18 72 08-Oct-18, G.F
GCSS0530 G.F Capacitor Bank Room 01 0 0% 04-Sep-18 101 G.F Capacitor Bank Room 01
GCSS0510 G.F Capacitor Bank Room 02 0 0% 04-Sep-18 101 G.F Capacitor Bank Room 02
GCSS0520 G.F Capacitor Bank Room 03 0 0% 04-Sep-18 101 G.F Capacitor Bank Room 03
GCSS0540 G.F. 11kv SWGR Room 1 0 0% 13-Sep-18 93 G.F. 11kv SWGR Room 1
GCSS0550 G.F. 11kv SWGR Room 2 0 0% 13-Sep-18 93 G.F. 11kv SWGR Room 2
GCSS0560 G.F. Rooms 132 kv GIS Completion 0 0% 08-Oct-18 72 G.F. Rooms 132 kv GIS Completion
F.F 21 15-Sep-18 09-Oct-18 53 09-Oct-18, F.F
GCSS0620 F.F Control Room 0 0% 15-Sep-18 74 F.F Control Room
GCSS0600 F.F Charger Room 0 0% 24-Sep-18 66 F.F Charger Room
GCSS0630 FF. LVAC Room 0 0% 26-Sep-18 64 FF. LVAC Room
GCSS0610 F.F Telecom Room 0 0% 02-Oct-18 59 F.F Telecom Room
GCSS0640 F.F Nitrogen Room 0 0% 04-Oct-18 57 F.F Nitrogen Room
GCSS0580 F.F Battery Room 1 0 0% 08-Oct-18 54 F.F Battery Room 1
GCSS0590 F.F Battery Room 2 0 0% 08-Oct-18 54 F.F Battery Room 2
GCSS0650 F.F. HVAC Shaft Room 0 0% 09-Oct-18 53 F.F. HVAC Shaft Room

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 2 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Transformer 0 01-Oct-18 01-Oct-18 78 01-Oct-18, Transformer
GCSS0660 Transformer Room 01 0 0% 01-Oct-18 78 Transformer Room 01
GCSS0670 Transformer Room 02 0 0% 01-Oct-18 78 Transformer Room 02
GCSS0680 Transformer Room 03 0 0% 01-Oct-18 78 Transformer Room 03
Stair Case 14 17-Nov-18 03-Dec-18 24 03-Dec-18, Stair Case
GCSS0690 Stair Case 01 0 0% 17-Nov-18 38 Stair Case 01
GCSS0700 Stair Case 02 0 0% 21-Nov-18 34 Stair Case 02
GCSS860 Stair Case 03 0 0% 28-Nov-18 28 Stair Case 03
GCSS862 Stair Case 04 0 0% 03-Dec-18 24 Stair Case 04
External Elevation
Elevatio 98 29-Aug-18 22-Dec-18 8 22-Dec-18, External Elevation
GCSS0710 Elevation 04 0 0% 29-Aug-18 106 Elevation 04
GCSS0720 Elevation 02 0 0% 31-Oct-18 52 Elevation 02
GCSS0730 Elevation 03 0 0% 25-Nov-18 31 Elevation 03
GCSS0740 Elevation 01 0 0% 22-Dec-18 8 Elevation 01
Auxiliary Buildings
Building 77 25-Aug-18 22-Nov-18 33 22-Nov-18, Auxiliary Buildings
GCSS0750 Under Ground Tank 0 0% 25-Aug-18 110 Under Ground Tank
GCSS0770 Shunter Reactor 0 0% 09-Oct-18 71 Shunter Reactor
GCSS0810 Boundary Wall Elevation 04 0 0% 29-Oct-18 54 Boundary Wall Elevation 04
GCSS0830 Boundary Wall Elevation 01 0 0% 31-Oct-18 52 Boundary Wall Elevation 01
GCSS0840 Boundary Wall Elevation 02 0 0% 31-Oct-18 52 Boundary Wall Elevation 02
GCSS0860 Boundary Wall Elevation 03 0 0% 05-Nov-18 48 Boundary Wall Elevation 03
GCSS0850 Fire Trench 0 0% 14-Nov-18 40 Fire Trench
GCSS0790 ET Room 02 0 0% 19-Nov-18 36 ET Room 02
GCSS0800 ET Room 03 0 0% 19-Nov-18 36 ET Room 03
GCSS0820 Security Room 0 0% 21-Nov-18 34 Security Room
GCSS0780 ET Room 01 0 0% 21-Nov-18 34 ET Room 01
GCSS0760 Fire Pump Room 0 0% 22-Nov-18 33 Fire Pump Room
219 10-Dec-17 A 22-Dec-18 8 22-Dec-18, Main Building
Main Building
Concrete Works 138 10-Dec-17 A 18-Sep-18 60 18-Sep-18, Concrete Works
Substructure Works
Wo 79 10-Dec-17 A 11-Jul-18 119 11-Jul-18, Substructure Works
GCS0010 Excavation to Main Building , Transformer Room , Capacitor ) 6 100% 10-Dec-17 A 16-Dec-17 A Excavation to Main Building , Transformer Room , Capacitor )
GCS0030 Leveling & Compaction ,Plate Test , Anti Termite and PCC 6 100% 11-Dec-17 A 15-Jan-18 A Leveling & Compaction ,Plate Test , Anti Termite and PCC
GCS0040 Earthing Grid Installation 3 100% 07-Jan-18 A 13-Jan-18 A Earthing Grid Installation
GCS0050 Water Proofing Works & Screed 8 100% 03-Feb-18 A 21-Feb-18 A Water Proofing Works & Screed
GCS0060 Steel Works to Raft Foundation 12 100% 21-Feb-18 A 03-Mar-18 A Steel Works to Raft Foundation
GCS0080 Authority Inspection 1 100% 03-Mar-18 A 03-Mar-18 A Authority Inspection
GCS0090 DEWA Inspection 1 100% 04-Mar-18 A 04-Mar-18 A DEWA Inspection
GCS0100 Casting Concrete to Raft Foundation 1 100% 04-Mar-18 A 04-Mar-18 A Casting Concrete to Raft Foundation
GCS0020 BBS , S.D Transmit to SIEMENS of Main Building 14 100% 21-Mar-18 A 22-Mar-18 A BBS , S.D Transmit to SIEMENS of Main Building
Capacitor Bank
Ban 44 06-Mar-18 A 31-May-18 20 31-May-18, Capacitor Bank
GCS0120 Steel Works to R.Wall 6 100% 06-Mar-18 A 24-Apr-18 A Steel Works to R.Wall
GCS0130 Form Works to R.Wall 6 100% 10-Mar-18 A 24-Apr-18 A Form Works to R.Wall
GCS0110 BBS , S.D Transmit to SIEMENS 14 100% 21-Mar-18 A 22-Mar-18 A BBS , S.D Transmit to SIEMENS
GCS0140 Concrete Works to R.Wall 6 100% 26-Mar-18 A 24-Apr-18 A Concrete Works to R.Wall
GCS0150 Waterproofing Works including Screed and Wall Protections 7 0% 25-Apr-18 02-May-18 20 Waterproofing Works including Screed and Wall Protections
GCS0160 Backfilling with Compaction inside Building 11 0% 03-May-18 15-May-18 20 Backfilling with Compaction inside Building
GCS0170 Road Base with Compaction inside Building 5 0% 16-May-18 21-May-18 20 Road Base with Compaction inside Building
GCS0180 PCC Works 1 0% 22-May-18 22-May-18 20 PCC Works
GCS0190 Waterproofing 4 0% 23-May-18 27-May-18 20 Waterproofing
GCS0200 Slab on Grade 4 0% 28-May-18 31-May-18 20 Slab on Grade
Cable Basement
Baseme Access 79 07-Mar-18 A 11-Jul-18 119 11-Jul-18, Cable Basement Access
GCS0220 Steel Works to R.Wall & Columns 21 85.71% 07-Mar-18 A 28-Apr-18 0 Steel Works to R.Wall & Columns
GCS0230 Form Works to R.Wall & Columns 21 85.71% 10-Mar-18 A 28-Apr-18 0 Form Works to R.Wall & Columns
GCS0240 Concrete Works to R.Wall & Columns 19 84.21% 13-Mar-18 A 29-Apr-18 0 Concrete Works to R.Wall & Columns
GCS0210 BBS , S.D Transmit to SIEMENS 14 100% 21-Mar-18 A 22-Mar-18 A BBS , S.D Transmit to SIEMENS

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 3 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCS0250 Form Works to G.F Slab 12 50% 04-Apr-18 A 02-May-18 0 Form Works to G.F Slab
GCS0260 Steel Works to G.F Slab 10 0% 03-May-18 14-May-18 0 Steel Works to G.F Slab
GCS0270 Authority Inspection to G.F Slab 1 0% 14-May-18 14-May-18 0 Authority Inspection to G.F Slab
GCS0290 Casting Concrete to G.F Slab 1 0% 15-May-18 15-May-18 0 Casting Concrete to G.F Slab
GCS0280 DEWA Engineer Inspection to G.F Slab 1 0% 15-May-18 15-May-18 0 DEWA Engineer Inspection to G.F Slab
GCS0300 Curing Works to G.F. Slab 14 0% 16-May-18 31-May-18 71 Curing Works to G.F. Slab
GCS0310 De- Shuttering 7 0% 02-Jun-18 09-Jun-18 71 De- Shuttering
GCS0320 Water Proofing to Outside of R.Wall 14 0% 10-Jun-18 25-Jun-18 119 Water Proofing to Outside of R.Wall
GCS0330 Backfilling Works 14 0% 26-Jun-18 11-Jul-18 119 Backfilling Works
Super Structure W
Works 116 07-May-18 18-Sep-18 30 18-Sep-18, Super Structure Works
11kv Switchge
Switchgear Room & Capacitor Bank 95 07-May-18 25-Aug-18 51 25-Aug-18, 11kv Switchgear Room & Capacitor Bank
G.F 59 07-May-18 14-Jul-18 75 14-Jul-18, G.F
GCS0340 BBS , S.D Transmit to SIEMENS 8 0% 07-May-18 15-May-18 0 BBS , S.D Transmit to SIEMENS
GCS0350 Steel Works to Columns and Wall to G.F. Slab 7 0% 16-May-18 23-May-18 0 Steel Works to Columns and Wall to G.F. Slab
GCS0360 Form Works Columns and Wall to G.F. Slab 7 0% 19-May-18 26-May-18 0 Form Works Columns and Wall to G.F. Slab
GCS0370 Concrete Works to Columns and Wall to G.F. Slab 5 0% 22-May-18 27-May-18 0 Concrete Works to Columns and Wall to G.F. Slab
GCS0380 From Work to 1st Floor Slab at 11kv Switchgear Room 21 0% 28-May-18 20-Jun-18 0 From Work to 1st Floor Slab at 11kv Switchgear Room
GCS0390 Steel Work to 1st Floor Slab at 11kv Switchgear Room 21 0% 30-May-18 23-Jun-18 0 Steel Work to 1st Floor Slab at 11kv Switchgear Room
GCS0400 Authority Inspection to 1st Floor Slab at 11kv Switchgear Room 1 0% 23-Jun-18 23-Jun-18 0 Authority Inspection to 1st Floor Slab at 11kv Switchgear Room
GCS0410 DEWA Engineer Inspection to 1st Floor Slab at 11kv Switchgear Room 1 0% 24-Jun-18 24-Jun-18 0 DEWA Engineer Inspection to 1st Floor Slab at 11kv Switchgear Room
GCS0420 Casting Concrete to G.F Slab 1st Floor Slab at 11kv Switchgear Room 1 0% 25-Jun-18 25-Jun-18 0 Casting Concrete to G.F Slab 1st Floor Slab at 11kv Switchgear Room
GCS0430 Curing Works to 1st Floor Slab at 11kv Switchgear Room 14 0% 26-Jun-18 11-Jul-18 75 Curing Works to 1st Floor Slab at 11kv Switchgear Room
GCS0440 De- Shuttering 2 0% 12-Jul-18 14-Jul-18 75 De- Shuttering
F.F 87 16-May-18 25-Aug-18 51 25-Aug-18, F.F
GCS0450 BBS , S.D Transmit to SIEMENS 14 0% 16-May-18 31-May-18 20 BBS , S.D Transmit to SIEMENS
GCS0460 Steel Works Columns to F.F Floor 11 0% 25-Jun-18 07-Jul-18 0 Steel Works Columns to F.F Floor
GCS0470 Form Works Columns and Wall to F.F Floor 11 0% 27-Jun-18 09-Jul-18 0 Form Works Columns and Wall to F.F Floor
GCS0480 Concrete Works to Columns and Wall to F.F Floor 5 0% 05-Jul-18 10-Jul-18 0 Concrete Works to Columns and Wall to F.F Floor
GCS0490 From Work to Roof Slab at 11kv Switchgear Room 15 0% 11-Jul-18 28-Jul-18 0 From Work to Roof Slab at 11kv Switchgear Room
GCS0500 Steel Work to Roof Slab Slab at 11kv Switchgear Room 15 0% 16-Jul-18 01-Aug-18 0 Steel Work to Roof Slab Slab at 11kv Switchgear Room
GCS0510 Authority Inspection to Roof Slab at 11kv Switchgear Room 1 0% 02-Aug-18 02-Aug-18 0 Authority Inspection to Roof Slab at 11kv Switchgear Room
GCS0520 DEWA Engineer Inspection to Roof Slab at 11kv Switchgear Room 1 0% 04-Aug-18 04-Aug-18 0 DEWA Engineer Inspection to Roof Slab at 11kv Switchgear Room
GCS0530 Casting Concrete to Roof Slab at 11kv Switchgear Room 1 0% 05-Aug-18 05-Aug-18 0 Casting Concrete to Roof Slab at 11kv Switchgear Room
GCS0540 Curing Works to Roof Slab at 11kv Switchgear Room 12 0% 06-Aug-18 19-Aug-18 51 Curing Works to Roof Slab at 11kv Switchgear Room
GCS0550 De- Shuttering 5 0% 20-Aug-18 25-Aug-18 51 De- Shuttering
132kv GS Room
Roo 84 16-May-18 21-Aug-18 53 21-Aug-18, 132kv GS Room
GCS0560 BBS , S.D Transmit to SIEMENS 14 0% 16-May-18 31-May-18 0 BBS , S.D Transmit to SIEMENS
GCS0570 Steel Works Columns and Fire Wall to F.F Floor 24 0% 02-Jun-18 28-Jun-18 0 Steel Works Columns and Fire Wall to F.F Floor
GCS0580 Form Works Columns and Fire Wall to F.F Floor 24 0% 04-Jun-18 01-Jul-18 0 Form Works Columns and Fire Wall to F.F Floor
GCS0590 Concrete Works to Columns and Fire Wall to F.F Floor 10 0% 21-Jun-18 02-Jul-18 0 Concrete Works to Columns and Fire Wall to F.F Floor
GCS0600 From Work to Roof Slab at 132 kv GS Room 21 0% 03-Jul-18 26-Jul-18 0 From Work to Roof Slab at 132 kv GS Room
GCS0610 Steel Work to Roof Slab at 132 kv GS Room 14 0% 17-Jul-18 01-Aug-18 0 Steel Work to Roof Slab at 132 kv GS Room
GCS0620 Authority Inspection to Roof Slab at 132 kv GS Room 1 0% 02-Aug-18 02-Aug-18 0 Authority Inspection to Roof Slab at 132 kv GS Room
GCS0640 DEWA Engineer Inspection to Roof Slab at 132 kv GS Room 1 0% 04-Aug-18 04-Aug-18 0 DEWA Engineer Inspection to Roof Slab at 132 kv GS Room
GCS0650 Casting Concrete to Roof Slab at 132 kv GS Room 1 0% 05-Aug-18 05-Aug-18 0 Casting Concrete to Roof Slab at 132 kv GS Room
GCS0630 Concrete Works to Parapet 14 0% 06-Aug-18 21-Aug-18 53 Concrete Works to Parapet
GCS0660 Curing Works to Roof Slab at 132 kv GS Room 6 0% 06-Aug-18 12-Aug-18 6 Curing Works to Roof Slab at 132 kv GS Room
GCS0670 De- Shuttering 2 0% 20-Aug-18 21-Aug-18 0 De- Shuttering
Stair Case 94 02-Jun-18 18-Sep-18 6 18-Sep-18, Stair Case
GCS0850 BBS , S.D Transmit to SIEMENS 14 0% 02-Jun-18 17-Jun-18 6 BBS , S.D Transmit to SIEMENS
Stair Case 01 76 18-Jun-18 13-Sep-18 10 13-Sep-18, Stair Case 01
GCS0860 Stair Case between Basement and G.F 17 0% 18-Jun-18 07-Jul-18 18 Stair Case between Basement and G.F
GCS0870 Stair Case between G.F and 1st Floor 17 0% 08-Jul-18 26-Jul-18 18 Stair Case between G.F and 1st Floor
GCS0880 Stair Case between 1st Floor and Roof 17 0% 06-Aug-18 25-Aug-18 10 Stair Case between 1st Floor and Roof
GCS0890 Curing to Concrete 14 0% 26-Aug-18 10-Sep-18 10 Curing to Concrete

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 4 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCS0900 De- Shuttering Works 3 0% 11-Sep-18 13-Sep-18 10 De- Shuttering Works
Stair Case 02 80 18-Jun-18 18-Sep-18 6 18-Sep-18, Stair Case 02
GCS0910 Stair Case between Basement and G.F 21 0% 18-Jun-18 11-Jul-18 6 Stair Case between Basement and G.F
GCS0920 Stair Case between G.F and 1st Floor 21 0% 12-Jul-18 05-Aug-18 6 Stair Case between G.F and 1st Floor
GCS0930 Stair Case between 1st Floor and Roof 21 0% 06-Aug-18 29-Aug-18 6 Stair Case between 1st Floor and Roof
GCS0940 Curing to Concrete 14 0% 30-Aug-18 15-Sep-18 6 Curing to Concrete
GCS0950 De- Shuttering Works 3 0% 16-Sep-18 18-Sep-18 6 De- Shuttering Works
Transformer Room 165 07-May-18 14-Nov-18 22 14-Nov-18, Transformer Room
GCS0680 BBS , S.D Transmit to SIEMENS 8 0% 07-May-18 15-May-18 22 BBS , S.D Transmit to SIEMENS
1st Lift 10 16-May-18 27-May-18 22 27-May-18, 1st Lift
GCS0690 Scaffolding till 1st Lift 1 0% 16-May-18 16-May-18 22 Scaffolding till 1st Lift
GCS0700 Steel Works to R.Wall 1st Lift 5 0% 17-May-18 22-May-18 22 Steel Works to R.Wall 1st Lift
GCS0710 Form Works to R.Wall 1st Lift 5 0% 20-May-18 24-May-18 22 Form Works to R.Wall 1st Lift
GCS0720 Concrete Works to R.Wall 1st Lift 5 0% 22-May-18 27-May-18 22 Concrete Works to R.Wall 1st Lift
2nd Lift 11 28-May-18 09-Jun-18 22 09-Jun-18, 2nd Lift
GCS0730 Scaffolding till 2nd Lift 2 0% 28-May-18 29-May-18 22 Scaffolding till 2nd Lift
GCS0740 Steel Works to R.Wall 2nd Lift 5 0% 30-May-18 04-Jun-18 22 Steel Works to R.Wall 2nd Lift
GCS0750 Form Works to R.Wall 2nd Lift 5 0% 02-Jun-18 06-Jun-18 22 Form Works to R.Wall 2nd Lift
GCS0760 Concrete Works to R.Wall 2nd Lift 5 0% 04-Jun-18 09-Jun-18 22 Concrete Works to R.Wall 2nd Lift
3rd Lift 94 10-Jun-18 26-Sep-18 35 26-Sep-18, 3rd Lift
GCS0770 Scaffolding till 3rd Lift 2 0% 10-Jun-18 11-Jun-18 22 Scaffolding till 3rd Lift
GCS0780 Steel Works to R.Wall 3rd Lift 5 0% 12-Jun-18 17-Jun-18 22 Steel Works to R.Wall 3rd Lift
GCS0790 Form Works to R.Wall 3rd Lift 5 0% 14-Jun-18 19-Jun-18 22 Form Works to R.Wall 3rd Lift
GCS0800 Concrete Works to R.Wall 3rd Lift 5 0% 17-Jun-18 21-Jun-18 22 Concrete Works to R.Wall 3rd Lift
GCS0810 De- Shuttering 4 0% 23-Jun-18 26-Jun-18 22 De- Shuttering
GCS0820 Transformer Foundation 15 0% 27-Jun-18 14-Jul-18 22 Transformer Foundation
GCS0830 Concrete Works of Cable Trench 15 0% 15-Jul-18 31-Jul-18 22 Concrete Works of Cable Trench
GCS0840 Fixing I Beam and Grating Channel at Trench 14 0% 11-Sep-18 26-Sep-18 35 Fixing I Beam and Grating Channel at Trench
Transformer 101 16-May-18 10-Sep-18 35 10-Sep-18, Transformer
Shop Drawings
Drawing 101 16-May-18 10-Sep-18 35 10-Sep-18, Shop Drawings
GCS2920 Shop Drawings & Calculation by Steel Truss S/C 21 0% 16-May-18 09-Jun-18 35 Shop Drawings & Calculation by Steel Truss S/C
GCS2930 DEWA Eng. Approval to Shop Drawings & Calculation 40 0% 10-Jun-18 25-Jul-18 35 DEWA Eng. Approval to Shop Drawings & Calculation
GCS2940 Fabrication and Delivery to Site 40 0% 26-Jul-18 10-Sep-18 35 Fabrication and Delivery to Site
Finishing 91 01-Aug-18 14-Nov-18 22 14-Nov-18, Finishing
Transformer 01
0 91 01-Aug-18 14-Nov-18 22 14-Nov-18, Transformer 01
GCS2950 Floor Screed 5 0% 01-Aug-18 06-Aug-18 22 Floor Screed
GCS2960 Scaffolding 3 0% 07-Aug-18 09-Aug-18 22 Scaffolding
GCS2970 Internal Paint 1 Coat 14 0% 11-Aug-18 26-Aug-18 22 Internal Paint 1 Coat
GCS3000 Removing Scaffolding 3 0% 27-Aug-18 29-Aug-18 22 Removing Scaffolding
GCS3010 Floor Epoxy coating 10 0% 30-Aug-18 10-Sep-18 22 Floor Epoxy coating
GCS3020 Fixing of Grating with Steel Support 4 0% 27-Sep-18 01-Oct-18 35 Fixing of Grating with Steel Support
GCS3050 Gravel Spread and Leveled Works 7 0% 07-Oct-18 14-Oct-18 35 Gravel Spread and Leveled Works
GCS3030 Sand Backfilling & Concrete Tiles inside The Trench 5 0% 16-Oct-18 21-Oct-18 22 Sand Backfilling & Concrete Tiles inside The Trench
GCS3040 Fixing Chequre Plate inside Sump Area 7 0% 22-Oct-18 29-Oct-18 22 Fixing Chequre Plate inside Sump Area
GCS5340 Installation of Steel Truss at the Roof 14 0% 30-Oct-18 14-Nov-18 22 Installation of Steel Truss at the Roof
GCS3060 Aluminum Cluster 14 0% 30-Oct-18 14-Nov-18 22 Aluminum Cluster
Transformer 02
0 91 01-Aug-18 14-Nov-18 22 14-Nov-18, Transformer 02
GCS3070 Floor Screed 5 0% 01-Aug-18 06-Aug-18 22 Floor Screed
GCS3080 Scaffolding 3 0% 07-Aug-18 09-Aug-18 22 Scaffolding
GCS3090 Internal Paint 1 Coat 14 0% 11-Aug-18 26-Aug-18 22 Internal Paint 1 Coat
GCS3120 Removing Scaffolding 3 0% 27-Aug-18 29-Aug-18 22 Removing Scaffolding
GCS3130 Floor Epoxy coating 10 0% 30-Aug-18 10-Sep-18 22 Floor Epoxy coating
GCS3140 Fixing of Grating with Steel Support 4 0% 27-Sep-18 01-Oct-18 35 Fixing of Grating with Steel Support
GCS3170 Gravel Spread and Leveled Works 7 0% 07-Oct-18 14-Oct-18 35 Gravel Spread and Leveled Works
GCS3150 Sand Backfilling & Concrete Tiles inside The Trench 5 0% 16-Oct-18 21-Oct-18 22 Sand Backfilling & Concrete Tiles inside The Trench

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 5 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCS3160 Fixing Chequre Plate inside Sump Area 7 0% 22-Oct-18 29-Oct-18 22 Fixing Chequre Plate inside Sump Area
GCS5350 Installation of Steel Truss at the Roof 14 0% 30-Oct-18 14-Nov-18 22 Installation of Steel Truss at the Roof
GCS3180 Aluminum Cluster 14 0% 30-Oct-18 14-Nov-18 22 Aluminum Cluster
Transformer 03
0 91 01-Aug-18 14-Nov-18 22 14-Nov-18, Transformer 03
GCS3190 Floor Screed 5 0% 01-Aug-18 06-Aug-18 22 Floor Screed
GCS3200 Scaffolding 3 0% 07-Aug-18 09-Aug-18 22 Scaffolding
GCS3210 Internal Paint 1 Coat 14 0% 11-Aug-18 26-Aug-18 22 Internal Paint 1 Coat
GCS3240 Removing Scaffolding 3 0% 27-Aug-18 29-Aug-18 22 Removing Scaffolding
GCS3250 Floor Epoxy coating 10 0% 30-Aug-18 10-Sep-18 22 Floor Epoxy coating
GCS3260 Fixing of Grating with Steel Support 4 0% 27-Sep-18 01-Oct-18 35 Fixing of Grating with Steel Support
GCS3290 Gravel Spread and Leveled Works 7 0% 07-Oct-18 14-Oct-18 35 Gravel Spread and Leveled Works
GCS3270 Sand Backfilling & Concrete Tiles inside The Trench 5 0% 16-Oct-18 21-Oct-18 22 Sand Backfilling & Concrete Tiles inside The Trench
GCS3280 Fixing Chequre Plate inside Sump Area 7 0% 22-Oct-18 29-Oct-18 22 Fixing Chequre Plate inside Sump Area
GCS5360 Installation of Steel Truss at the Roof 14 0% 30-Oct-18 14-Nov-18 22 Installation of Steel Truss at the Roof
GCS3300 Aluminum Cluster 14 0% 30-Oct-18 14-Nov-18 22 Aluminum Cluster
Finishes Works 175 02-Jun-18 22-Dec-18 8 22-Dec-18, Finishes Works
Shop Drawings 138 02-Jun-18 08-Nov-18 24 08-Nov-18, Shop Drawings
Rasied Floor 138 02-Jun-18 08-Nov-18 24 08-Nov-18, Rasied Floor
GCS0960 Shop Drawings Raised Floor by S/C 18 0% 02-Jun-18 21-Jun-18 24 Shop Drawings Raised Floor by S/C
GCS0970 DEWA Eng. Approval to Shop Drawings 30 0% 23-Jun-18 26-Jul-18 24 DEWA Eng. Approval to Shop Drawings
GCS0980 Fabrication and Delivery to Site 90 0% 28-Jul-18 08-Nov-18 24 Fabrication and Delivery to Site
Aluminum Works
Wo 84 02-Jun-18 06-Sep-18 47 06-Sep-18, Aluminum Works
GCS0990 Shop Drawings Aluminum Works by S/C 18 0% 02-Jun-18 21-Jun-18 47 Shop Drawings Aluminum Works by S/C
GCS1000 DEWA Eng. Approval to Shop Drawings 21 0% 23-Jun-18 16-Jul-18 47 DEWA Eng. Approval to Shop Drawings
GCS1010 Fabrication and Delivery to Site 45 0% 17-Jul-18 06-Sep-18 47 Fabrication and Delivery to Site
Cable Basement 11 kV 81 10-Jun-18 11-Sep-18 77 11-Sep-18, Cable Basement 11 kV
Cable Basement
Baseme 11 kV Basement 01 81 10-Jun-18 11-Sep-18 77 11-Sep-18, Cable Basement 11 kV Basement 01
GCS1020 Block Works ( Longitudinal Wall) 10 0% 10-Jun-18 20-Jun-18 89 Block Works ( Longitudinal Wall)
GCS1030 Concrete screed in basement including laying of sleeves 5 0% 21-Jun-18 26-Jun-18 89 Concrete screed in basement including laying of sleeves
GCS1040 Concrete screed ( Second Layer ) in basement including laying of sleeves 12 0% 27-Jun-18 10-Jul-18 89 Concrete screed ( Second Layer ) in basement including laying of sleeves
GCS1050 Block work in basement inner walls (Transverse wall) 8 0% 11-Jul-18 19-Jul-18 89 Block work in basement inner walls (Transverse wall)
GCS1060 Basement Inner wall Plastering works 10 0% 21-Jul-18 31-Jul-18 89 Basement Inner wall Plastering works
GCS1070 Basement Inner wall and Ceiling Painting works 1st coat 14 0% 01-Aug-18 16-Aug-18 89 Basement Inner wall and Ceiling Painting works 1st coat
GCS1080 Floor Epoxy screed with Painting 10 0% 01-Sep-18 11-Sep-18 77 Floor Epoxy screed with Painting
GCS1090 Installation of Aluminum Works 4 0% 08-Sep-18 11-Sep-18 77 Installation of Aluminum Works
Cable Basement
Baseme 11 kV Basement 02 81 10-Jun-18 11-Sep-18 77 11-Sep-18, Cable Basement 11 kV Basement 02
GCS1100 Block Works ( Longitudinal Wall) 10 0% 10-Jun-18 20-Jun-18 89 Block Works ( Longitudinal Wall)
GCS1120 Water Proofing Works to Retaining Wall (outside) 14 0% 18-Jun-18 03-Jul-18 95 Water Proofing Works to Retaining Wall (outside)
GCS1110 Concrete screed in basement including laying of sleeves 5 0% 21-Jun-18 26-Jun-18 89 Concrete screed in basement including laying of sleeves
GCS1130 Concrete screed ( Second Layer ) in basement including laying of sleeves 12 0% 27-Jun-18 10-Jul-18 89 Concrete screed ( Second Layer ) in basement including laying of sleeves
GCS1140 Block work in basement inner walls (Transverse wall) 8 0% 11-Jul-18 19-Jul-18 89 Block work in basement inner walls (Transverse wall)
GCS1150 Basement Inner wall Plastering works 10 0% 21-Jul-18 31-Jul-18 89 Basement Inner wall Plastering works
GCS1160 Basement Inner wall and Ceiling Painting works 1st coat 14 0% 01-Aug-18 16-Aug-18 89 Basement Inner wall and Ceiling Painting works 1st coat
GCS1170 Floor Epoxy screed with Painting 10 0% 01-Sep-18 11-Sep-18 77 Floor Epoxy screed with Painting
GCS1180 Installation of Aluminum Works 4 0% 08-Sep-18 11-Sep-18 77 Installation of Aluminum Works
Cable Basement 81 10-Jun-18 11-Sep-18 95 11-Sep-18, Cable Basement
Cable Basement
Baseme 132 kV 81 10-Jun-18 11-Sep-18 95 11-Sep-18, Cable Basement 132 kV
Cable Basement
Base 132 kV Room 01 81 10-Jun-18 11-Sep-18 77 11-Sep-18, Cable Basement 132 kV Room 01
GCS1190 Block Works ( Longitudinal Wall) 8 0% 10-Jun-18 18-Jun-18 88 Block Works ( Longitudinal Wall)
GCS1200 Concrete screed in basement including laying of sleeves 5 0% 19-Jun-18 24-Jun-18 88 Concrete screed in basement including laying of sleeves
GCS1210 Concrete screed ( Second Layer ) in basement including laying of sleeves 12 0% 25-Jun-18 08-Jul-18 88 Concrete screed ( Second Layer ) in basement including laying of sleeves
GCS1220 Block work in basement inner walls (Transverse wall) 5 0% 09-Jul-18 14-Jul-18 88 Block work in basement inner walls (Transverse wall)
GCS1230 Basement Inner wall Plastering works 10 0% 15-Jul-18 25-Jul-18 88 Basement Inner wall Plastering works
GCS1240 Basement Inner wall and Ceiling Painting works 1st coat 12 0% 26-Jul-18 08-Aug-18 88 Basement Inner wall and Ceiling Painting works 1st coat
GCS1250 MEP Works by SIEMENS 10 0% 09-Aug-18 20-Aug-18 88 MEP Works by SIEMENS

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 6 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCS1260 Floor Epoxy screed with Painting 8 0% 03-Sep-18 11-Sep-18 77 Floor Epoxy screed with Painting
GCS1270 Installation of Aluminum Works 4 0% 08-Sep-18 11-Sep-18 77 Installation of Aluminum Works
Cable Basement
Base 132 kV Room 02 81 10-Jun-18 11-Sep-18 95 11-Sep-18, Cable Basement 132 kV Room 02
GCS1280 Block Works ( Longitudinal Wall) 8 0% 10-Jun-18 18-Jun-18 71 Block Works ( Longitudinal Wall)
GCS1310 Water Proofing Works to Retaining Wall (outside) 14 0% 18-Jun-18 03-Jul-18 75 Water Proofing Works to Retaining Wall (outside)
GCS1290 Concrete screed in basement including laying of sleeves 5 0% 19-Jun-18 24-Jun-18 71 Concrete screed in basement including laying of sleeves
GCS1300 Concrete screed ( Second Layer ) in basement including laying of sleeves 12 0% 25-Jun-18 08-Jul-18 71 Concrete screed ( Second Layer ) in basement including laying of sleeves
GCS1320 Block work in basement inner walls (Transverse wall) 5 0% 09-Jul-18 14-Jul-18 71 Block work in basement inner walls (Transverse wall)
GCS1330 Basement Inner wall Plastering works 10 0% 15-Jul-18 25-Jul-18 106 Basement Inner wall Plastering works
GCS1340 Basement Inner wall and Ceiling Painting works 1st coat 12 0% 26-Jul-18 08-Aug-18 106 Basement Inner wall and Ceiling Painting works 1st coat
GCS1350 MEP Works by SIEMENS 10 0% 09-Aug-18 20-Aug-18 106 MEP Works by SIEMENS
GCS1360 Floor Epoxy screed with Painting 8 0% 03-Sep-18 11-Sep-18 95 Floor Epoxy screed with Painting
GCS1370 Installation of Aluminum Works 4 0% 08-Sep-18 11-Sep-18 95 Installation of Aluminum Works
Cable Riser 47 15-Jul-18 06-Sep-18 47 06-Sep-18, Cable Riser
GCS1380 Block Works 4 0% 15-Jul-18 18-Jul-18 71 Block Works
GCS1390 Concrete screed including laying of sleeves 1 0% 19-Jul-18 19-Jul-18 71 Concrete screed including laying of sleeves
GCS1410 Concrete screed ( Second Layer ) in including laying of sleeves 1 0% 21-Jul-18 21-Jul-18 71 Concrete screed ( Second Layer ) in including laying of sleeves
GCS1400 Plastering works 7 0% 22-Jul-18 29-Jul-18 71 Plastering works
GCS1420 Painting Works 10 0% 27-Aug-18 06-Sep-18 47 Painting Works
Ground Floor Rooms
Roo 132 kv GIS 41 22-Aug-18 08-Oct-18 54 08-Oct-18, Ground Floor Rooms 132 kv GIS
GCS1430 Block works at G.F. 132 kv 12 0% 22-Aug-18 04-Sep-18 0 Block works at G.F. 132 kv
GCS1450 Ground Floor Plastering works 6 0% 05-Sep-18 11-Sep-18 0 Ground Floor Plastering works
GCS1910 Ceiling and wall painting upto corbel 5 0% 12-Sep-18 17-Sep-18 0 Ceiling and wall painting upto corbel
GCS1460 MEP Works by SIEMENS 6 0% 18-Sep-18 24-Sep-18 0 MEP Works by SIEMENS
GCS1440 Concrete screed works 3 0% 25-Sep-18 27-Sep-18 0 Concrete screed works
GCS1470 Wall Painting 6 0% 29-Sep-18 04-Oct-18 0 Wall Painting
GCS1480 Floor Epoxy coating 3 0% 06-Oct-18 08-Oct-18 54 Floor Epoxy coating
GCS1490 Installation of Aluminum Works 2 0% 06-Oct-18 07-Oct-18 0 Installation of Aluminum Works
Ground Floor Rooms
Roo 11kv SWGR 53 15-Jul-18 13-Sep-18 75 13-Sep-18, Ground Floor Rooms 11kv SWGR
G.F. 11kv SWGR
SW Room 1 53 15-Jul-18 13-Sep-18 75 13-Sep-18, G.F. 11kv SWGR Room 1
GCS1500 Block works at G.F. 11 kv 8 0% 15-Jul-18 23-Jul-18 75 Block works at G.F. 11 kv
GCS1510 Concrete screed works 7 0% 24-Jul-18 31-Jul-18 75 Concrete screed works
GCS1520 Ground Floor Plastering works 9 0% 01-Aug-18 11-Aug-18 75 Ground Floor Plastering works
GCS1530 Ceiling Fair Facing Works 5 0% 12-Aug-18 16-Aug-18 75 Ceiling Fair Facing Works
GCS1540 Ceiling Painting Works 5 0% 18-Aug-18 22-Aug-18 75 Ceiling Painting Works
GCS1550 MEP Works by SIEMENS 8 0% 23-Aug-18 01-Sep-18 75 MEP Works by SIEMENS
GCS1560 Ground Floor Painting 1st coat 6 0% 02-Sep-18 08-Sep-18 75 Ground Floor Painting 1st coat
GCS1570 Floor Epoxy coating 5 0% 09-Sep-18 13-Sep-18 75 Floor Epoxy coating
GCS1580 Installation of Aluminum Works 5 0% 09-Sep-18 13-Sep-18 75 Installation of Aluminum Works
G.F. 11kv SWGR
SW Room 2 53 15-Jul-18 13-Sep-18 75 13-Sep-18, G.F. 11kv SWGR Room 2
GCS1590 Block works at G.F. 11 kv 8 0% 15-Jul-18 23-Jul-18 75 Block works at G.F. 11 kv
GCS1600 Concrete screed works 7 0% 24-Jul-18 31-Jul-18 75 Concrete screed works
GCS1610 Ground Floor Plastering works 9 0% 01-Aug-18 11-Aug-18 75 Ground Floor Plastering works
GCS1620 Ceiling Fair Facing Works 5 0% 12-Aug-18 16-Aug-18 75 Ceiling Fair Facing Works
GCS1630 Ceiling Painting Works 5 0% 18-Aug-18 22-Aug-18 75 Ceiling Painting Works
GCS1640 MEP Works by SIEMENS 8 0% 23-Aug-18 01-Sep-18 75 MEP Works by SIEMENS
GCS1650 Ground Floor Painting 1st coat 6 0% 02-Sep-18 08-Sep-18 75 Ground Floor Painting 1st coat
GCS1660 Floor Epoxy coating 5 0% 09-Sep-18 13-Sep-18 75 Floor Epoxy coating
GCS1670 Installation of Aluminum Works 5 0% 09-Sep-18 13-Sep-18 75 Installation of Aluminum Works
Ground Floor Rooms
Roo Capacitor Bank Rooms 47 15-Jul-18 06-Sep-18 81 06-Sep-18, Ground Floor Rooms Capacitor Bank Rooms
G.F Capacitor Bank Room 01 47 15-Jul-18 06-Sep-18 81 06-Sep-18, G.F Capacitor Bank Room 01
GCS1680 Block works at G.F. Capacitor Bank 7 0% 15-Jul-18 22-Jul-18 81 Block works at G.F. Capacitor Bank
GCS1690 Concrete screed works 6 0% 23-Jul-18 29-Jul-18 81 Concrete screed works
GCS1700 Ground Floor Plastering works 5 0% 30-Jul-18 04-Aug-18 81 Ground Floor Plastering works
GCS1710 Ceiling Fair Facing Works 4 0% 05-Aug-18 08-Aug-18 81 Ceiling Fair Facing Works

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 7 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCS1720 Ceiling Painting Works 5 0% 09-Aug-18 14-Aug-18 81 Ceiling Painting Works
GCS1730 MEP Works by SIEMENS 8 0% 15-Aug-18 23-Aug-18 81 MEP Works by SIEMENS
GCS1740 Ground Floor Painting 1st coat 5 0% 25-Aug-18 29-Aug-18 81 Ground Floor Painting 1st coat
GCS1750 Floor Epoxy coating 5 0% 30-Aug-18 04-Sep-18 81 Floor Epoxy coating
GCS1760 Installation of chain link fence 2 0% 05-Sep-18 06-Sep-18 81 Installation of chain link fence
G.F Capacitor Bank Room 02 47 15-Jul-18 06-Sep-18 81 06-Sep-18, G.F Capacitor Bank Room 02
GCS1770 Block works at G.F. Capacitor Bank 7 0% 15-Jul-18 22-Jul-18 81 Block works at G.F. Capacitor Bank
GCS1780 Concrete screed works 6 0% 23-Jul-18 29-Jul-18 81 Concrete screed works
GCS1790 Ground Floor Plastering works 5 0% 30-Jul-18 04-Aug-18 81 Ground Floor Plastering works
GCS1800 Ceiling Fair Facing Works 5 0% 05-Aug-18 09-Aug-18 81 Ceiling Fair Facing Works
GCS1810 Ceiling Painting Works 4 0% 11-Aug-18 14-Aug-18 81 Ceiling Painting Works
GCS1820 MEP Works by SIEMENS 8 0% 15-Aug-18 23-Aug-18 81 MEP Works by SIEMENS
GCS1830 Ground Floor Painting 1st coat 5 0% 25-Aug-18 29-Aug-18 81 Ground Floor Painting 1st coat
GCS1840 Floor Epoxy coating 5 0% 30-Aug-18 04-Sep-18 81 Floor Epoxy coating
GCS1850 Installation of chain link fence 2 0% 05-Sep-18 06-Sep-18 81 Installation of chain link fence
G.F Capacitor Bank Room 03 47 15-Jul-18 06-Sep-18 81 06-Sep-18, G.F Capacitor Bank Room 03
GCS1860 Block works at G.F. Capacitor Bank 7 0% 15-Jul-18 22-Jul-18 81 Block works at G.F. Capacitor Bank
GCS1870 Concrete screed works 6 0% 23-Jul-18 29-Jul-18 81 Concrete screed works
GCS1880 Ground Floor Plastering works 5 0% 30-Jul-18 04-Aug-18 81 Ground Floor Plastering works
GCS1890 Ceiling Fair Facing Works 4 0% 05-Aug-18 08-Aug-18 81 Ceiling Fair Facing Works
GCS1900 Ceiling Painting Works 5 0% 09-Aug-18 14-Aug-18 81 Ceiling Painting Works
GCS2000 MEP Works by SIEMENS 8 0% 15-Aug-18 23-Aug-18 81 MEP Works by SIEMENS
GCS2010 Ground Floor Painting 1st coat 5 0% 25-Aug-18 29-Aug-18 81 Ground Floor Painting 1st coat
GCS2020 Floor Epoxy coating 5 0% 30-Aug-18 04-Sep-18 81 Floor Epoxy coating
GCS2030 Installation of chain link fence 2 0% 05-Sep-18 06-Sep-18 81 Installation of chain link fence
F.F. 68 26-Aug-18 12-Nov-18 24 12-Nov-18, F.F.
F.F Control R
Room 68 26-Aug-18 12-Nov-18 24 12-Nov-18, F.F Control Room
GCS2130 Block work to FF roof level 5 0% 26-Aug-18 30-Aug-18 71 Block work to FF roof level
GCS2150 Plastering works 3 0% 01-Sep-18 03-Sep-18 71 Plastering works
GCS2170 First Floor Painting 1st coat 3 0% 04-Sep-18 06-Sep-18 76 First Floor Painting 1st coat
GCS2180 Black Painting Works above False Ceiling 1 0% 04-Sep-18 04-Sep-18 71 Black Painting Works above False Ceiling
GCS2160 MEP Works above False Ceiling Works by SIEMENS 5 0% 05-Sep-18 10-Sep-18 71 MEP Works above False Ceiling Works by SIEMENS
GCS2200 False Ceiling works 2 0% 11-Sep-18 12-Sep-18 71 False Ceiling works
GCS2190 Dust proof paint under Raised floor & Bitumen paint under False ceiling works 2 0% 13-Sep-18 15-Sep-18 71 Dust proof paint under Raised floor & Bitumen paint under False ceiling
GCS2210 Raised floor in FF 1 0% 10-Nov-18 10-Nov-18 24 Raised floor in FF
GCS2220 Final Painting 2 0% 11-Nov-18 12-Nov-18 24 Final Painting
GCS2230 Installation of Aluminum Works 2 0% 11-Nov-18 12-Nov-18 24 Installation of Aluminum Works
FF. LVAC Room 38 26-Aug-18 08-Oct-18 54 08-Oct-18, FF. LVAC Room
GCS2240 Block work to FF roof level 5 0% 26-Aug-18 30-Aug-18 54 Block work to FF roof level
GCS2260 First Floor Plastering works 3 0% 01-Sep-18 03-Sep-18 54 First Floor Plastering works
GCS2270 Black Painting Works above False Ceiling 2 0% 04-Sep-18 05-Sep-18 54 Black Painting Works above False Ceiling
GCS2280 MEP Works above False Ceiling Works by SIEMENS 6 0% 06-Sep-18 12-Sep-18 54 MEP Works above False Ceiling Works by SIEMENS
GCS2290 First Floor Painting 1st coat 5 0% 13-Sep-18 18-Sep-18 54 First Floor Painting 1st coat
GCS2300 Dust proof paint under Raised floor & Bitumen paint under False ceiling works 3 0% 19-Sep-18 22-Sep-18 54 Dust proof paint under Raised floor & Bitumen paint under False ceilin
GCS2310 False Ceiling works 4 0% 23-Sep-18 26-Sep-18 54 False Ceiling works
GCS2320 Raised floor in FF 5 0% 27-Sep-18 02-Oct-18 54 Raised floor in FF
GCS2330 Final Painting 5 0% 03-Oct-18 08-Oct-18 54 Final Painting
GCS2340 Installation of Aluminum Works 5 0% 03-Oct-18 08-Oct-18 54 Installation of Aluminum Works
F.F Charger R
Room 29 26-Aug-18 27-Sep-18 63 27-Sep-18, F.F Charger Room
GCS2350 Block work 6 0% 26-Aug-18 01-Sep-18 63 Block work
GCS2370 Plastering works 3 0% 02-Sep-18 04-Sep-18 63 Plastering works
GCS2380 Black Painting Works above False Ceiling 2 0% 05-Sep-18 06-Sep-18 63 Black Painting Works above False Ceiling
GCS2390 MEP Works above False Ceiling Works by SIEMENS 6 0% 08-Sep-18 13-Sep-18 63 MEP Works above False Ceiling Works by SIEMENS
GCS2400 First Floor Painting 1st coat 4 0% 15-Sep-18 18-Sep-18 63 First Floor Painting 1st coat
GCS2410 Dust proof paint under Raised floor & Bitumen paint under False ceiling works 2 0% 19-Sep-18 20-Sep-18 63 Dust proof paint under Raised floor & Bitumen paint under False ceiling

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 8 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCS2420 False Ceiling works 3 0% 22-Sep-18 24-Sep-18 63 False Ceiling works
GCS2430 Raised floor 1 0% 25-Sep-18 25-Sep-18 63 Raised floor
GCS2440 Installation of Aluminum Works 2 0% 26-Sep-18 27-Sep-18 63 Installation of Aluminum Works
GCS2450 Final Painting 1 0% 27-Sep-18 27-Sep-18 63 Final Painting
F.F Telecom Room 36 26-Aug-18 06-Oct-18 56 06-Oct-18, F.F Telecom Room
GCS2460 Block work to FF roof level 6 0% 26-Aug-18 01-Sep-18 56 Block work to FF roof level
GCS2480 First Floor Plastering works 4 0% 02-Sep-18 05-Sep-18 56 First Floor Plastering works
GCS2490 Black Painting Works above False Ceiling 3 0% 06-Sep-18 09-Sep-18 56 Black Painting Works above False Ceiling
GCS2500 MEP Works above False Ceiling Works by SIEMENS 8 0% 10-Sep-18 18-Sep-18 56 MEP Works above False Ceiling Works by SIEMENS
GCS2510 First Floor Painting 1st coat 6 0% 19-Sep-18 25-Sep-18 56 First Floor Painting 1st coat
GCS2520 Dust proof paint under Raised floor & Bitumen paint under False ceiling works 3 0% 26-Sep-18 29-Sep-18 56 Dust proof paint under Raised floor & Bitumen paint under False cei
GCS2530 False Ceiling works 3 0% 30-Sep-18 02-Oct-18 56 False Ceiling works
GCS2540 Raised floor in FF 1 0% 03-Oct-18 03-Oct-18 56 Raised floor in FF
GCS2550 Final Painting 2 0% 04-Oct-18 06-Oct-18 56 Final Painting
GCS2560 Installation of Aluminum Works 2 0% 04-Oct-18 06-Oct-18 56 Installation of Aluminum Works
F.F Battery Rooms
Ro 38 26-Aug-18 08-Oct-18 54 08-Oct-18, F.F Battery Rooms
F.F Battery Room 1 38 26-Aug-18 08-Oct-18 54 08-Oct-18, F.F Battery Room 1
GCS2570 Block work to FF roof level 6 0% 26-Aug-18 01-Sep-18 54 Block work to FF roof level
GCS2580 First Floor Plastering works 5 0% 02-Sep-18 06-Sep-18 54 First Floor Plastering works
GCS2590 Ceiling Fair Facing Works 3 0% 08-Sep-18 10-Sep-18 54 Ceiling Fair Facing Works
GCS2600 Ceiling & Wall Painting Works 7 0% 11-Sep-18 18-Sep-18 54 Ceiling & Wall Painting Works
GCS2610 MEP Works by SIEMENS 6 0% 19-Sep-18 25-Sep-18 54 MEP Works by SIEMENS
GCS2620 Water Proofing & Leak Test 6 0% 26-Sep-18 02-Oct-18 54 Water Proofing & Leak Test
GCS2640 Acid resistance tile fixing 5 0% 03-Oct-18 08-Oct-18 54 Acid resistance tile fixing
F.F Battery Room 2 38 26-Aug-18 08-Oct-18 54 08-Oct-18, F.F Battery Room 2
GCS2650 Block work to FF roof level 6 0% 26-Aug-18 01-Sep-18 54 Block work to FF roof level
GCS2660 First Floor Plastering works 5 0% 02-Sep-18 06-Sep-18 54 First Floor Plastering works
GCS2670 Ceiling Fair Facing Works 3 0% 08-Sep-18 10-Sep-18 54 Ceiling Fair Facing Works
GCS2680 Ceiling Painting Works 7 0% 11-Sep-18 18-Sep-18 54 Ceiling Painting Works
GCS2690 MEP Works by SIEMENS 6 0% 19-Sep-18 25-Sep-18 54 MEP Works by SIEMENS
GCS2700 Water Proofing & Leak Test 6 0% 26-Sep-18 02-Oct-18 54 Water Proofing & Leak Test
GCS2720 Acid resistance tile fixing 5 0% 03-Oct-18 08-Oct-18 54 Acid resistance tile fixing
F.F Nitogen RRoom 41 26-Aug-18 11-Oct-18 51 11-Oct-18, F.F Nitogen Room
GCS2730 Block Work 8 0% 26-Aug-18 03-Sep-18 51 Block Work
GCS2740 Concrete screed works 5 0% 04-Sep-18 09-Sep-18 51 Concrete screed works
GCS2750 First Floor Plastering works 6 0% 10-Sep-18 16-Sep-18 51 First Floor Plastering works
GCS2760 Ceiling Fair Facing Works 2 0% 17-Sep-18 18-Sep-18 51 Ceiling Fair Facing Works
GCS2770 Ceiling Painting Works 4 0% 19-Sep-18 23-Sep-18 51 Ceiling Painting Works
GCS2790 First Floor Painting 1st coat 5 0% 24-Sep-18 29-Sep-18 51 First Floor Painting 1st coat
GCS2800 Floor Epoxy screed with Painting 5 0% 30-Sep-18 04-Oct-18 51 Floor Epoxy screed with Painting
GCS2810 Final Painting 6 0% 06-Oct-18 11-Oct-18 51 Final Painting
F.F. HVAC Shaft
Sha Room 39 26-Aug-18 09-Oct-18 53 09-Oct-18, F.F. HVAC Shaft Room
GCS2830 Block Work 7 0% 26-Aug-18 02-Sep-18 53 Block Work
GCS2840 Concrete screed works 5 0% 03-Sep-18 08-Sep-18 53 Concrete screed works
GCS2850 First Floor Plastering works 7 0% 09-Sep-18 16-Sep-18 53 First Floor Plastering works
GCS2860 MEP Works by SIEMENS 5 0% 17-Sep-18 22-Sep-18 53 MEP Works by SIEMENS
GCS2870 First Floor Painting 1st coat 4 0% 23-Sep-18 26-Sep-18 53 First Floor Painting 1st coat
GCS2880 False Ceiling works 4 0% 27-Sep-18 01-Oct-18 53 False Ceiling works
GCS2890 Floor Epoxy screed with Painting 2 0% 02-Oct-18 03-Oct-18 53 Floor Epoxy screed with Painting
GCS2900 Final Painting 5 0% 04-Oct-18 09-Oct-18 53 Final Painting
GCS2910 Installation of Aluminum Works 2 0% 04-Oct-18 06-Oct-18 56 Installation of Aluminum Works
Roof Works 42 22-Aug-18 09-Oct-18 53 09-Oct-18, Roof Works
GCS3310 Foam Concrete Works 10 0% 22-Aug-18 02-Sep-18 53 Foam Concrete Works
GCS3320 Water Proofing Membrane Including Leak Test 12 0% 03-Sep-18 16-Sep-18 53 Water Proofing Membrane Including Leak Test
GCS3330 Insulation System and Serration Sheet 5 0% 17-Sep-18 22-Sep-18 53 Insulation System and Serration Sheet

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 9 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCS3340 Cement Tiles Works 13 0% 23-Sep-18 07-Oct-18 53 Cement Tiles Works
GCS3350 Aluminum Flashing Fixing 2 0% 08-Oct-18 09-Oct-18 53 Aluminum Flashing Fixing
Cable/HVAC/Riser Shafts
Cable/HVAC/Rise 34 08-Sep-18 16-Oct-18 47 16-Oct-18, Cable/HVAC/Riser Shafts
GCS3360 Block Works to Shafts 10 0% 08-Sep-18 18-Sep-18 47 Block Works to Shafts
GCS3370 Plaster Works to Shaft 14 0% 19-Sep-18 04-Oct-18 47 Plaster Works to Shaft
GCS3380 Painting Works 10 0% 06-Oct-18 16-Oct-18 47 Painting Works
Stair Case 69 15-Sep-18 03-Dec-18 6 03-Dec-18, Stair Case
Stair Case 01 55 15-Sep-18 17-Nov-18 20 17-Nov-18, Stair Case 01
GCS3390 Block Work 10 0% 15-Sep-18 25-Sep-18 10 Block Work
GCS3400 Plastering Works 14 0% 26-Sep-18 11-Oct-18 20 Plastering Works
GCS3410 Painting to Wall 10 0% 13-Oct-18 23-Oct-18 20 Painting to Wall
GCS3420 Aluminum Handrail Installation 14 0% 24-Oct-18 08-Nov-18 20 Aluminum Handrail Installation
GCS3430 Epoxy Paint to Stairs 7 0% 10-Nov-18 17-Nov-18 20 Epoxy Paint to Stairs
Stair Case 02 55 19-Sep-18 21-Nov-18 16 21-Nov-18, Stair Case 02
GCS3440 Block Work 10 0% 19-Sep-18 30-Sep-18 6 Block Work
GCS3450 Plastering Works 14 0% 01-Oct-18 16-Oct-18 16 Plastering Works
GCS3460 Painting to Wall 10 0% 17-Oct-18 28-Oct-18 16 Painting to Wall
GCS3470 Aluminum Handrail Installation 14 0% 29-Oct-18 13-Nov-18 16 Aluminum Handrail Installation
GCS3480 Epoxy Paint to Stairs 7 0% 14-Nov-18 21-Nov-18 16 Epoxy Paint to Stairs
Stair Case 03 55 26-Sep-18 28-Nov-18 10 28-Nov-18, Stair Case 03
GCS5846 Block Work 10 0% 26-Sep-18 07-Oct-18 10 Block Work
GCS5848 Plastering Works 14 0% 08-Oct-18 23-Oct-18 10 Plastering Works
GCS5850 Painting to Wall 10 0% 24-Oct-18 04-Nov-18 10 Painting to Wall
GCS5842 Aluminum Handrail Installation 14 0% 05-Nov-18 20-Nov-18 10 Aluminum Handrail Installation
GCS5844 Epoxy Paint to Stairs 7 0% 21-Nov-18 28-Nov-18 10 Epoxy Paint to Stairs
Stair Case 04 55 01-Oct-18 03-Dec-18 6 03-Dec-18, Stair Case 04
GCS5856 Block Work 10 0% 01-Oct-18 11-Oct-18 6 Block Work
GCS5858 Plastering Works 14 0% 13-Oct-18 28-Oct-18 6 Plastering Works
GCS5860 Painting to Wall 10 0% 29-Oct-18 08-Nov-18 6 Painting to Wall
GCS5852 Aluminum Handrail Installation 14 0% 10-Nov-18 25-Nov-18 6 Aluminum Handrail Installation
GCS5854 Epoxy Paint to Stairs 7 0% 26-Nov-18 03-Dec-18 6 Epoxy Paint to Stairs
External Works 119 06-Aug-18 22-Dec-18 8 22-Dec-18, External Works
GCS3490 Water Proofing Works to R.Wall of Basement - Outside 12 0% 06-Aug-18 19-Aug-18 21 Water Proofing Works to R.Wall of Basement - Outside
GCS3500 Backfilling Works 21 0% 20-Aug-18 12-Sep-18 21 Backfilling Works
Elevation 02 21 08-Oct-18 31-Oct-18 0 31-Oct-18, Elevation 02
GCS3510 Scaffolding Works to Elevation 02 3 0% 08-Oct-18 10-Oct-18 0 Scaffolding Works to Elevation 02
GCS3520 Plastering Works to Elevation 02 8 0% 11-Oct-18 20-Oct-18 0 Plastering Works to Elevation 02
GCS3530 Primer & 1st Coat Painting Works to Elevation 02 8 0% 21-Oct-18 29-Oct-18 0 Primer & 1st Coat Painting Works to Elevation 02
GCS3540 Removing Scaffolding Works to Elevation 02 2 0% 30-Oct-18 31-Oct-18 0 Removing Scaffolding Works to Elevation 02
Elevation 03 21 01-Nov-18 25-Nov-18 0 25-Nov-18, Elevation 03
GCS3550 Scaffolding Works to Elevation 03 3 0% 01-Nov-18 04-Nov-18 0 Scaffolding Works to Elevation 03
GCS3560 Plastering Works to Elevation 03 8 0% 05-Nov-18 13-Nov-18 0 Plastering Works to Elevation 03
GCS3570 Primer & 1st Coat Painting Works to Elevation 03 8 0% 14-Nov-18 22-Nov-18 0 Primer & 1st Coat Painting Works to Elevation 03
GCS3580 Removing Scaffolding Works to Elevation 03 2 0% 24-Nov-18 25-Nov-18 0 Removing Scaffolding Works to Elevation 03
Elevation 01 23 26-Nov-18 22-Dec-18 8 22-Dec-18, Elevation 01
GCS3590 Scaffolding Works to Elevation 01 2 0% 26-Nov-18 27-Nov-18 0 Scaffolding Works to Elevation 01
GCS3600 Plastering Works to Elevation 01 8 0% 28-Nov-18 06-Dec-18 0 Plastering Works to Elevation 01
GCS3610 Primer & 1st Coat Painting Works to Elevation 01 8 0% 08-Dec-18 16-Dec-18 0 Primer & 1st Coat Painting Works to Elevation 0
GCS3620 Removing Scaffolding Works to Elevation 01 5 0% 17-Dec-18 22-Dec-18 8 Removing Scaffolding Works to Elevation 01
105 25-Apr-18 25-Aug-18 110 25-Aug-18, Under Ground Oil / Water Tank
Under Ground O
Oil / Water Tank
GCS4950 BBS & S.D Transmite to SIEMENS 15 0% 25-Apr-18 12-May-18 0 BBS & S.D Transmite to SIEMENS
GCS4960 Shoring Works by Siemens 10 0% 13-May-18 23-May-18 0 Shoring Works by Siemens
GCS4970 Excavation Works 6 0% 24-May-18 30-May-18 0 Excavation Works
GCS4980 Leveling & Compaction , Anti Termite and PCC 2 0% 31-May-18 02-Jun-18 0 Leveling & Compaction , Anti Termite and PCC
GCS4990 Earthing Grid Installation by SIEMENS 2 0% 03-Jun-18 04-Jun-18 0 Earthing Grid Installation by SIEMENS

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 10 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCS5000 Water Proofing Works under Raft Foundation 8 0% 05-Jun-18 13-Jun-18 0 Water Proofing Works under Raft Foundation
GCS5010 Steel Works to Foundation 12 0% 09-Jun-18 21-Jun-18 0 Steel Works to Foundation
GCS5020 Authority Inspection 1 0% 23-Jun-18 23-Jun-18 89 Authority Inspection
GCS5030 DEWA Engineer Inspection 1 0% 24-Jun-18 24-Jun-18 89 DEWA Engineer Inspection
GCS5040 Casting Concrete 1 0% 24-Jun-18 24-Jun-18 89 Casting Concrete
GCS5050 Steel & Concrete Works to Water Tank Wall 15 0% 25-Jun-18 11-Jul-18 89 Steel & Concrete Works to Water Tank Wall
GCS5060 Steel & Concrete Works to Water Tank Roof Slab Including Authority & DEWA Eng. Ins 15 0% 12-Jul-18 29-Jul-18 89 Steel & Concrete Works to Water Tank Roof Slab Including Authority & DEWA Eng. I
GCS5070 Water Proofing Works to Wall 8 0% 30-Jul-18 07-Aug-18 89 Water Proofing Works to Wall
GCS5080 Curing Works to Water Tank Roof Slab 14 0% 30-Jul-18 14-Aug-18 110 Curing Works to Water Tank Roof Slab
GCS5090 Backfilling Works 7 0% 08-Aug-18 15-Aug-18 89 Backfilling Works
GCS5100 De- Shuttering of W.T Slab 2 0% 15-Aug-18 16-Aug-18 110 De- Shuttering of W.T Slab
GCS5110 GRE Works to Water Tank 7 0% 18-Aug-18 25-Aug-18 110 GRE Works to Water Tank
173 13-May-18 29-Nov-18 9 29-Nov-18, Shunt Reactor
Shunt Reactor
Concrete Works 99 13-May-18 04-Sep-18 19 04-Sep-18, Concrete Works
GCS4130 BBS & S.D Transmite to SIEMENS 15 0% 13-May-18 29-May-18 9 BBS & S.D Transmite to SIEMENS
GCS4140 Excavation Works 2 0% 10-Jun-18 11-Jun-18 0 Excavation Works
GCS4150 Leveling & Compaction ,Plate Test , Anti Termite and PCC 5 0% 12-Jun-18 17-Jun-18 0 Leveling & Compaction ,Plate Test , Anti Termite and PCC
GCS4160 Earthing Grid Installation 2 0% 18-Jun-18 19-Jun-18 0 Earthing Grid Installation
GCS4170 Water Proofing Works & Screed 6 0% 20-Jun-18 26-Jun-18 0 Water Proofing Works & Screed
GCS4180 Steel & Concrete Works to Raft Foundation 12 0% 27-Jun-18 10-Jul-18 0 Steel & Concrete Works to Raft Foundation
1st Lift 9 11-Jul-18 21-Jul-18 9 21-Jul-18, 1st Lift
GCS4190 Scaffolding till 1st Lift 2 0% 11-Jul-18 12-Jul-18 9 Scaffolding till 1st Lift
GCS4200 Steel Works to R.Wall 1st Lift 4 0% 14-Jul-18 17-Jul-18 9 Steel Works to R.Wall 1st Lift
GCS4210 Form Works to R.Wall 1st Lift 4 0% 16-Jul-18 19-Jul-18 9 Form Works to R.Wall 1st Lift
GCS4220 Concrete Works to R.Wall 1st Lift 1 0% 21-Jul-18 21-Jul-18 9 Concrete Works to R.Wall 1st Lift
2nd Lift 8 22-Jul-18 30-Jul-18 9 30-Jul-18, 2nd Lift
GCS4230 Scaffolding till 2nd Lift 2 0% 22-Jul-18 23-Jul-18 9 Scaffolding till 2nd Lift
GCS4240 Steel Works to R.Wall 2nd Lift 3 0% 24-Jul-18 26-Jul-18 9 Steel Works to R.Wall 2nd Lift
GCS4250 Form Works to R.Wall 2nd Lift 3 0% 26-Jul-18 29-Jul-18 9 Form Works to R.Wall 2nd Lift
GCS4260 Concrete Works to R.Wall 2nd Lift 1 0% 30-Jul-18 30-Jul-18 9 Concrete Works to R.Wall 2nd Lift
3rd Lift 31 31-Jul-18 04-Sep-18 19 04-Sep-18, 3rd Lift
GCS4270 Scaffolding till 3rd Lift 2 0% 31-Jul-18 01-Aug-18 9 Scaffolding till 3rd Lift
GCS4280 Steel Works to R.Wall 3rd Lift 4 0% 02-Aug-18 06-Aug-18 9 Steel Works to R.Wall 3rd Lift
GCS4290 Form Works to R.Wall 3rd Lift 4 0% 05-Aug-18 08-Aug-18 9 Form Works to R.Wall 3rd Lift
GCS4300 Concrete Works to R.Wall 3rd Lift 1 0% 09-Aug-18 09-Aug-18 9 Concrete Works to R.Wall 3rd Lift
GCS4310 De- Shuttering 3 0% 11-Aug-18 13-Aug-18 9 De- Shuttering
GCS4320 Transformer Foundation 9 0% 14-Aug-18 23-Aug-18 9 Transformer Foundation
GCS4330 Fixing I Beam and Grating Channel 10 0% 25-Aug-18 04-Sep-18 19 Fixing I Beam and Grating Channel
Finishes Works 84 25-Aug-18 29-Nov-18 9 29-Nov-18, Finishes Works
GCS4340 Floor Screed 3 0% 25-Aug-18 27-Aug-18 9 Floor Screed
GCS4350 Scaffolding 3 0% 28-Aug-18 30-Aug-18 9 Scaffolding
GCS4360 Internal Paint 1 Coat 12 0% 01-Sep-18 13-Sep-18 9 Internal Paint 1 Coat
GCS5370 Removal of scaffolding 2 0% 15-Sep-18 16-Sep-18 9 Removal of scaffolding
GCS4390 Floor Epoxy coating 10 0% 17-Sep-18 27-Sep-18 9 Floor Epoxy coating
GCS4400 Fixing of Grating with Steel Support 10 0% 29-Sep-18 09-Oct-18 9 Fixing of Grating with Steel Support
GCS4380 External painting works 21 0% 10-Oct-18 03-Nov-18 9 External painting works
GCS4410 Gravel Spread and Leveled Works 5 0% 10-Oct-18 15-Oct-18 25 Gravel Spread and Leveled Works
GCS4420 Aluminum Claustra 5 0% 04-Nov-18 08-Nov-18 9 Aluminum Claustra
GCS4370 Installation of Steel Truss at the Roof 18 0% 10-Nov-18 29-Nov-18 9 Installation of Steel Truss at the Roof
141 12-Jun-18 24-Nov-18 33 24-Nov-18, Fire Pump Room
Fire Pump Room
Concrete Works 113 12-Jun-18 21-Oct-18 33 21-Oct-18, Concrete Works
A3320 Excavation 3 0% 12-Jun-18 14-Jun-18 0 Excavation
A3330 Earthing & Roadbase 6 0% 16-Jun-18 21-Jun-18 33 Earthing & Roadbase
A3340 Blinding 1 0% 23-Jun-18 23-Jun-18 33 Blinding

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 11 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
A3350 Waterproofing & Screed 2 0% 24-Jun-18 25-Jun-18 33 Waterproofing & Screed
A3360 Reinforcement and shuttering work for the raft 6 0% 26-Jun-18 02-Jul-18 33 Reinforcement and shuttering work for the raft
A3370 Authority / DEWA Inspection 1 0% 03-Jul-18 03-Jul-18 33 Authority / DEWA Inspection
A3380 Casting of Raft 1 0% 04-Jul-18 04-Jul-18 33 Casting of Raft
A3390 Reinforcement, shutter and casting of walls 5 0% 05-Jul-18 10-Jul-18 33 Reinforcement, shutter and casting of walls
A3470 Column Reinforcement, shutter & Casting 8 0% 11-Jul-18 19-Jul-18 49 Column Reinforcement, shutter & Casting
A3400 Surface preparation and Internal Waterproofing 5 0% 11-Jul-18 16-Jul-18 33 Surface preparation and Internal Waterproofing
A3410 Backfilling and making of profile for trenches 8 0% 17-Jul-18 25-Jul-18 33 Backfilling and making of profile for trenches
A3420 Blinding 1 0% 26-Jul-18 26-Jul-18 33 Blinding
A3430 Waterproofing & Screed 2 0% 28-Jul-18 29-Jul-18 33 Waterproofing & Screed
A3440 Reinforcement and shuttering works for GF Slab 6 0% 30-Jul-18 05-Aug-18 33 Reinforcement and shuttering works for GF Slab
A3450 Authority / DEWA Inspection 1 0% 06-Aug-18 06-Aug-18 33 Authority / DEWA Inspection
A3460 Casting of GF Slab 1 0% 07-Aug-18 07-Aug-18 33 Casting of GF Slab
A3480 Scaffolding & Decking for the Fire Pump Room Roof Slab 5 0% 08-Aug-18 13-Aug-18 33 Scaffolding & Decking for the Fire Pump Room Roof Slab
A3490 Reinforcement and shuttering works for Fire Pump roof slab 6 0% 14-Aug-18 20-Aug-18 33 Reinforcement and shuttering works for Fire Pump roof slab
A3500 Authority / DEWA Inspection 1 0% 21-Aug-18 21-Aug-18 33 Authority / DEWA Inspection
A3510 Casting of FPR Roof Slab 1 0% 22-Aug-18 22-Aug-18 33 Casting of FPR Roof Slab
A3660 Column & Walls reinforcement shutter & Casting above FPR Roof slab 6 0% 23-Aug-18 29-Aug-18 33 Column & Walls reinforcement shutter & Casting above FPR Roof slab
A3520 Curing time for the fire pump room slab 14 0% 23-Aug-18 05-Sep-18 47 Curing time for the fire pump room slab
A3670 Decking & Shutter for FWT Bottom slab 5 0% 26-Aug-18 30-Aug-18 33 Decking & Shutter for FWT Bottom slab
A3680 Reinforcement & Shuttering works for FWT Bottom slab 5 0% 01-Sep-18 05-Sep-18 33 Reinforcement & Shuttering works for FWT Bottom slab
A3690 Authority / DEWA Inspection 1 0% 06-Sep-18 06-Sep-18 33 Authority / DEWA Inspection
A3530 Deshuttering works for Fire Pump Room Roof slab 3 0% 06-Sep-18 09-Sep-18 40 Deshuttering works for Fire Pump Room Roof slab
A3700 Casting of FWT Bottom slab 1 0% 08-Sep-18 08-Sep-18 33 Casting of FWT Bottom slab
A3710 Reinforcement, Shutter and Casting of FWT Walls 10 0% 09-Sep-18 19-Sep-18 33 Reinforcement, Shutter and Casting of FWT Walls
A3720 Decking & Shuttering for FWT Roof slab 5 0% 17-Sep-18 22-Sep-18 33 Decking & Shuttering for FWT Roof slab
A3730 Reinforcement & Shuttering works for FWT Roof slab 6 0% 23-Sep-18 29-Sep-18 33 Reinforcement & Shuttering works for FWT Roof slab
A3740 Authority / DEWA Inspection 1 0% 30-Sep-18 30-Sep-18 33 Authority / DEWA Inspection
A3750 Casting of FWT Roof slab 1 0% 01-Oct-18 01-Oct-18 33 Casting of FWT Roof slab
A3760 Curing time for FWT Roof slab 14 0% 02-Oct-18 15-Oct-18 38 Curing time for FWT Roof slab
A3770 Deshuttering works for FWT Roof slab 5 0% 16-Oct-18 21-Oct-18 33 Deshuttering works for FWT Roof slab
Finishes Works for
fo Fire Pump Room 39 10-Sep-18 25-Oct-18 40 25-Oct-18, Finishes Works for Fire Pump Room
A3540 Blockworks 10 0% 10-Sep-18 20-Sep-18 40 Blockworks
A3600 Ceiling fairfacing 5 0% 10-Sep-18 15-Sep-18 45 Ceiling fairfacing
A3550 Plastering works 5 0% 22-Sep-18 26-Sep-18 40 Plastering works
A3560 Removal of scaffolding 1 0% 27-Sep-18 27-Sep-18 40 Removal of scaffolding
A3570 Floor concrete screed 6 0% 29-Sep-18 04-Oct-18 40 Floor concrete screed
A3580 Pump foundation reinforcement, shutter and casting 3 0% 06-Oct-18 08-Oct-18 40 Pump foundation reinforcement, shutter and casting
A3590 Scaffolding erection for ceiling for ceiling & Wall Painting 2 0% 09-Oct-18 10-Oct-18 40 Scaffolding erection for ceiling for ceiling & Wall Painting
A3610 Ceiling painting 4 0% 11-Oct-18 15-Oct-18 40 Ceiling painting
A3620 Wall Painting 5 0% 13-Oct-18 17-Oct-18 40 Wall Painting
A3630 Removal of scaffolding 2 0% 18-Oct-18 20-Oct-18 40 Removal of scaffolding
A3640 Floor epoxy screed and Paint 4 0% 21-Oct-18 24-Oct-18 40 Floor epoxy screed and Paint
A3650 Fire Pump Room Access 0 0% 25-Oct-18 40 Fire Pump Room Access
Finishes Works for
fo Fire Water Tank 28 22-Oct-18 24-Nov-18 33 24-Nov-18, Finishes Works for Fire Water Tank
A3780 Surface preparation inside the FWT 5 0% 22-Oct-18 27-Oct-18 47 Surface preparation inside the FWT
A3790 Internal Epoxy Paint / GRP Lining 7 0% 28-Oct-18 04-Nov-18 47 Internal Epoxy Paint / GRP Lining
A3800 Leak Test 2 0% 05-Nov-18 06-Nov-18 47 Leak Test
A3810 FWT Access 0 0% 24-Nov-18 33 FWT Access
External Works 28 22-Oct-18 22-Nov-18 33 22-Nov-18, External Works
A3820 External Walls Plastering works 14 0% 22-Oct-18 06-Nov-18 33 External Walls Plastering works
A3830 External walls painting works 14 0% 07-Nov-18 22-Nov-18 33 External walls painting works
176 30-May-18 20-Dec-18 9 20-Dec-18, ET Room
ET Room
Concrete Works 139 30-May-18 07-Nov-18 9 07-Nov-18, Concrete Works
GCS4430 BBS & S.D Transmite to SIEMENS 15 0% 30-May-18 16-Jun-18 21 BBS & S.D Transmite to SIEMENS
Primary Baseline Remaining Work Milestone IAS Lootah Contracting 12 of 15
Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCS4440 Excavation Works 2 0% 11-Jul-18 12-Jul-18 0 Excavation Works
GCS4450 Leveling & Compaction ,Plate Test , Anti Termite and PCC 5 0% 14-Jul-18 18-Jul-18 9 Leveling & Compaction ,Plate Test , Anti Termite and PCC
GCS4460 Earthing Grid Installation 2 0% 18-Jul-18 19-Jul-18 9 Earthing Grid Installation
GCS4470 Water Proofing Works & Screed 6 0% 21-Jul-18 26-Jul-18 9 Water Proofing Works & Screed
GCS4480 Steel & Concrete Works to Raft Foundation 17 0% 28-Jul-18 15-Aug-18 9 Steel & Concrete Works to Raft Foundation
1st Lift 8 16-Aug-18 25-Aug-18 9 25-Aug-18, 1st Lift
GCS4490 Scaffolding till 1st Lift 2 0% 16-Aug-18 18-Aug-18 9 Scaffolding till 1st Lift
GCS4500 Steel Works to R.Wall 1st Lift 3 0% 19-Aug-18 21-Aug-18 9 Steel Works to R.Wall 1st Lift
GCS4510 Form Works to R.Wall 1st Lift 3 0% 21-Aug-18 23-Aug-18 9 Form Works to R.Wall 1st Lift
GCS4520 Concrete Works to R.Wall 1st Lift 1 0% 25-Aug-18 25-Aug-18 9 Concrete Works to R.Wall 1st Lift
2nd Lift 8 26-Aug-18 03-Sep-18 9 03-Sep-18, 2nd Lift
GCS4530 Scaffolding till 2nd Lift 2 0% 26-Aug-18 27-Aug-18 9 Scaffolding till 2nd Lift
GCS4540 Steel Works to R.Wall 2nd Lift 3 0% 28-Aug-18 30-Aug-18 9 Steel Works to R.Wall 2nd Lift
GCS4550 Form Works to R.Wall 2nd Lift 3 0% 30-Aug-18 02-Sep-18 9 Form Works to R.Wall 2nd Lift
GCS4560 Concrete Works to R.Wall 2nd Lift 1 0% 03-Sep-18 03-Sep-18 9 Concrete Works to R.Wall 2nd Lift
3rd Lift 56 04-Sep-18 07-Nov-18 9 07-Nov-18, 3rd Lift
GCS4570 Scaffolding till 3rd Lift 2 0% 04-Sep-18 05-Sep-18 9 Scaffolding till 3rd Lift
GCS4580 Steel Works to R.Wall 3rd Lift 3 0% 06-Sep-18 09-Sep-18 9 Steel Works to R.Wall 3rd Lift
GCS4590 Form Works to R.Wall 3rd Lift 3 0% 09-Sep-18 11-Sep-18 9 Form Works to R.Wall 3rd Lift
GCS4600 Concrete Works to R.Wall 3rd Lift 1 0% 12-Sep-18 12-Sep-18 9 Concrete Works to R.Wall 3rd Lift
GCS4610 De- Shuttering 2 0% 13-Sep-18 15-Sep-18 9 De- Shuttering
GCS4620 Transformer Foundation 10 0% 16-Sep-18 26-Sep-18 9 Transformer Foundation
GCS4630 Concrete Works of Cable Trench 14 0% 27-Sep-18 13-Oct-18 17 Concrete Works of Cable Trench
GCS4640 Fixing I Beam and Grating Channel at Trench 14 0% 23-Oct-18 07-Nov-18 9 Fixing I Beam and Grating Channel at Trench
Finishes Works 73 27-Sep-18 20-Dec-18 9 20-Dec-18, Finishes Works
ET 01 73 27-Sep-18 20-Dec-18 9 20-Dec-18, ET 01
GCS4650 Floor Screed 5 0% 27-Sep-18 02-Oct-18 9 Floor Screed
GCS4660 Scaffolding 5 0% 03-Oct-18 08-Oct-18 9 Scaffolding
GCS4670 Internal Paint 1 Coat 12 0% 09-Oct-18 22-Oct-18 9 Internal Paint 1 Coat
GCS4700 Removing Scaffolding 4 0% 23-Oct-18 27-Oct-18 9 Removing Scaffolding
GCS4710 Floor Epoxy coating 11 0% 28-Oct-18 08-Nov-18 9 Floor Epoxy coating
GCS4720 Fixing of Grating with Steel Support 11 0% 10-Nov-18 21-Nov-18 9 Fixing of Grating with Steel Support
GCS4730 Gravel Spread and Leveled Works 8 0% 22-Nov-18 01-Dec-18 9 Gravel Spread and Leveled Works
GCS5380 Installation of Steel Truss at the Roof 12 0% 02-Dec-18 15-Dec-18 9 Installation of Steel Truss at the Roof
GCS4740 Aluminum Claustra 5 0% 16-Dec-18 20-Dec-18 9 Aluminum Claustra
ET 02 73 27-Sep-18 20-Dec-18 9 20-Dec-18, ET 02
GCS4750 Floor Screed 5 0% 27-Sep-18 02-Oct-18 9 Floor Screed
GCS4760 Scaffolding 5 0% 03-Oct-18 08-Oct-18 9 Scaffolding
GCS4770 Internal Paint 1 Coat 12 0% 09-Oct-18 22-Oct-18 9 Internal Paint 1 Coat
GCS4800 Removing Scaffolding 4 0% 23-Oct-18 27-Oct-18 9 Removing Scaffolding
GCS4810 Floor Epoxy coating 10 0% 28-Oct-18 07-Nov-18 9 Floor Epoxy coating
GCS4820 Fixing of Grating with Steel Support 10 0% 08-Nov-18 19-Nov-18 9 Fixing of Grating with Steel Support
GCS4830 Gravel Spread and Leveled Works 10 0% 20-Nov-18 01-Dec-18 9 Gravel Spread and Leveled Works
GCS5390 Installation of Steel Truss at the Roof 12 0% 02-Dec-18 15-Dec-18 9 Installation of Steel Truss at the Roof
GCS4840 Aluminum Claustra 5 0% 16-Dec-18 20-Dec-18 9 Aluminum Claustra
ET 03 73 27-Sep-18 20-Dec-18 9 20-Dec-18, ET 03
GCS4850 Floor Screed 5 0% 27-Sep-18 02-Oct-18 9 Floor Screed
GCS4860 Scaffolding 5 0% 03-Oct-18 08-Oct-18 9 Scaffolding
GCS4870 Internal Paint 1 Coat 12 0% 09-Oct-18 22-Oct-18 9 Internal Paint 1 Coat
GCS4900 Removing Scaffolding 4 0% 23-Oct-18 27-Oct-18 9 Removing Scaffolding
GCS4910 Floor Epoxy coating 10 0% 28-Oct-18 07-Nov-18 9 Floor Epoxy coating
GCS4920 Fixing of Grating with Steel Support 10 0% 08-Nov-18 19-Nov-18 9 Fixing of Grating with Steel Support
GCS4930 Gravel Spread and Leveled Works 10 0% 20-Nov-18 01-Dec-18 9 Gravel Spread and Leveled Works
GCS5400 Installation of Steel Truss at the Roof 12 0% 02-Dec-18 15-Dec-18 9 Installation of Steel Truss at the Roof
GCS4940 Aluminum Claustra 5 0% 16-Dec-18 20-Dec-18 9 Aluminum Claustra

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 13 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
144 17-Jun-18 01-Dec-18 26 01-Dec-18, Security Room
Security Room
Concrete Works 96 17-Jun-18 06-Oct-18 0 06-Oct-18, Concrete Works
GCS3910 BBS & S.D Transmite to SIEMENS 6 0% 17-Jun-18 23-Jun-18 29 BBS & S.D Transmite to SIEMENS
GCS3920 Excavation Works 4 0% 09-Jul-18 12-Jul-18 0 Excavation Works
GCS3930 Leveling & Compaction , Anti Termite and PCC 3 0% 14-Jul-18 16-Jul-18 0 Leveling & Compaction , Anti Termite and PCC
GCS3940 Earthing Grid Installation 3 0% 17-Jul-18 19-Jul-18 0 Earthing Grid Installation
GCS3950 Water Proofing Works & Screed 6 0% 21-Jul-18 26-Jul-18 0 Water Proofing Works & Screed
GCS3960 Steel & Concrete Works to Foundation 21 0% 28-Jul-18 20-Aug-18 0 Steel & Concrete Works to Foundation
GCS3970 Concrete Works to Columns 10 0% 21-Aug-18 01-Sep-18 0 Concrete Works to Columns
GCS3980 Concrete Works to Roof Slab including Authority Inspection 10 0% 02-Sep-18 12-Sep-18 0 Concrete Works to Roof Slab including Authority Inspection
GCS3990 Curing Works to Roof Slab 12 0% 13-Sep-18 26-Sep-18 0 Curing Works to Roof Slab
GCS4010 Backfilling Works 5 0% 26-Sep-18 01-Oct-18 0 Backfilling Works
GCS4000 De- Shuttering 4 0% 27-Sep-18 01-Oct-18 0 De- Shuttering
GCS4020 Concrete Works to Grade Slab 4 0% 02-Oct-18 06-Oct-18 0 Concrete Works to Grade Slab
Finishes Works 40 07-Oct-18 21-Nov-18 34 21-Nov-18, Finishes Works
GCS4030 Block works 7 0% 07-Oct-18 14-Oct-18 0 Block works
GCS4040 Concrete screed works 7 0% 15-Oct-18 22-Oct-18 0 Concrete screed works
GCS4050 Ground Floor Plastering works 10 0% 23-Oct-18 03-Nov-18 0 Ground Floor Plastering works
GCS4060 Ground Floor Painting 1st coat 8 0% 04-Nov-18 12-Nov-18 34 Ground Floor Painting 1st coat
GCS4070 Tiles to Floor 8 0% 13-Nov-18 21-Nov-18 34 Tiles to Floor
External Works 24 04-Nov-18 01-Dec-18 0 01-Dec-18, External Works
GCS4090 Scaffolding Works to Elevations 2 0% 04-Nov-18 05-Nov-18 0 Scaffolding Works to Elevations
GCS4100 Plastering Works to Elevations 10 0% 06-Nov-18 17-Nov-18 0 Plastering Works to Elevations
GCS4110 Primer & 1st Coat Painting Works to Elevations 10 0% 18-Nov-18 28-Nov-18 0 Primer & 1st Coat Painting Works to Elevations
GCS4120 Removing Scaffolding Works to Elevations 2 0% 29-Nov-18 01-Dec-18 0 Removing Scaffolding Works to Elevations
84 09-Aug-18 14-Nov-18 40 14-Nov-18, Fire Trench
Fire Trench
GCS5120 BBS & S.D Transmite to SIEMENS 10 0% 09-Aug-18 20-Aug-18 40 BBS & S.D Transmite to SIEMENS
GCS5130 Excavation Works 14 0% 21-Aug-18 05-Sep-18 40 Excavation Works
GCS5140 Leveling & Compaction , Anti Termite and PCC 14 0% 29-Aug-18 13-Sep-18 40 Leveling & Compaction , Anti Termite and PCC
GCS5150 Earthing Grid Installation by SIEMENS 7 0% 15-Sep-18 22-Sep-18 40 Earthing Grid Installation by SIEMENS
GCS5160 Water Proofing Works under Raft Foundation 14 0% 23-Sep-18 08-Oct-18 40 Water Proofing Works under Raft Foundation
GCS5170 Steel & Concrete Works to Fire Trench Wall 18 0% 09-Oct-18 29-Oct-18 40 Steel & Concrete Works to Fire Trench Wall
GCS5180 Water Proofing Works to Wall (Outside) 14 0% 15-Oct-18 30-Oct-18 53 Water Proofing Works to Wall (Outside)
GCS5190 GRE Works to Wall (Inside) 14 0% 30-Oct-18 14-Nov-18 40 GRE Works to Wall (Inside)
GCS5200 Concrete Cover Works 14 0% 30-Oct-18 14-Nov-18 40 Concrete Cover Works
123 16-Jun-18 05-Nov-18 48 05-Nov-18, Boudary Wall
Boudary Wall
Elevation 04 117 16-Jun-18 29-Oct-18 54 29-Oct-18, Elevation 04
GCS5220 Excavation Works 6 0% 16-Jun-18 21-Jun-18 0 Excavation Works
GCS5230 Leveling & Compaction , Anti Termite and PCC 14 0% 23-Jun-18 08-Jul-18 55 Leveling & Compaction , Anti Termite and PCC
GCS5210 BBS & S.D Transmite to SIEMENS 14 0% 24-Jun-18 09-Jul-18 54 BBS & S.D Transmite to SIEMENS
GCS5240 Steel & Concrete Works to Boudary Wall Foundation 21 0% 10-Jul-18 02-Aug-18 54 Steel & Concrete Works to Boudary Wall Foundation
GCS5250 Steel & Concrete Works to to Boudary Wall Columns 21 0% 04-Aug-18 27-Aug-18 54 Steel & Concrete Works to to Boudary Wall Columns
GCS5260 Block Works to Boundary Wall 21 0% 21-Aug-18 13-Sep-18 54 Block Works to Boundary Wall
GCS5270 2*10 Nos. Upvc Sleeves to Basement for 11kv Cables 5 0% 21-Aug-18 26-Aug-18 59 2*10 Nos. Upvc Sleeves to Basement for 11kv Cables
GCS5280 Plastering Works to to Boundary Wall 21 0% 02-Sep-18 25-Sep-18 54 Plastering Works to to Boundary Wall
GCS5290 Backfilling Works 11 0% 26-Sep-18 08-Oct-18 54 Backfilling Works
GCS5300 Painting Works to Boundary Wall 18 0% 09-Oct-18 29-Oct-18 54 Painting Works to Boundary Wall
Elevation 01 119 16-Jun-18 31-Oct-18 52 31-Oct-18, Elevation 01
GCS5310 Excavation Works 6 0% 16-Jun-18 21-Jun-18 0 Excavation Works
GCS5320 Leveling & Compaction , Anti Termite and PCC 14 0% 23-Jun-18 08-Jul-18 52 Leveling & Compaction , Anti Termite and PCC
GCS5330 Steel & Concrete Works to Boudary Wall Foundation 21 0% 09-Jul-18 01-Aug-18 52 Steel & Concrete Works to Boudary Wall Foundation
GCS5540 Steel & Concrete Works to to Boudary Wall Columns 21 0% 02-Aug-18 26-Aug-18 52 Steel & Concrete Works to to Boudary Wall Columns
GCS5550 Block Works to Boundary Wall 21 0% 27-Aug-18 19-Sep-18 52 Block Works to Boundary Wall
GCS5560 4(2*4) Nos. Upvc Sleeves to Basement for 132kv Cables 5 0% 28-Aug-18 02-Sep-18 56 4(2*4) Nos. Upvc Sleeves to Basement for 132kv Cables

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 14 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation
Merass 132-11kv Garden City Substation
Recovery Program
Activity ID Activity Name Orig. Dur. % Start Finish Total 2018 2019
Compl. Float
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
GCS5570 2*10 Nos. Upvc Sleeves to Basement for 11kv Cables 5 0% 28-Aug-18 02-Sep-18 56 2*10 Nos. Upvc Sleeves to Basement for 11kv Cables
GCS5580 Plastering Works to to Boundary Wall 21 0% 08-Sep-18 01-Oct-18 52 Plastering Works to to Boundary Wall
GCS5590 Backfilling Works 11 0% 29-Sep-18 10-Oct-18 52 Backfilling Works
GCS5600 Painting Works to Boundary Wall 18 0% 11-Oct-18 31-Oct-18 52 Painting Works to Boundary Wall
Elevation 02 118 16-Jun-18 30-Oct-18 53 30-Oct-18, Elevation 02
GCS5610 Excavation Works 7 0% 16-Jun-18 23-Jun-18 0 Excavation Works
GCS5620 Leveling & Compaction , Anti Termite and PCC 14 0% 24-Jun-18 09-Jul-18 53 Leveling & Compaction , Anti Termite and PCC
GCS5630 Steel & Concrete Works to Boudary Wall Foundation 21 0% 10-Jul-18 02-Aug-18 53 Steel & Concrete Works to Boudary Wall Foundation
GCS5640 Steel & Concrete Works to to Boudary Wall Columns 21 0% 04-Aug-18 27-Aug-18 53 Steel & Concrete Works to to Boudary Wall Columns
GCS5650 Block Works to Boundary Wall 21 0% 21-Aug-18 13-Sep-18 53 Block Works to Boundary Wall
GCS5660 Plastering Works to to Boundary Wall 21 0% 02-Sep-18 25-Sep-18 53 Plastering Works to to Boundary Wall
GCS5670 Backfilling Works 12 0% 26-Sep-18 09-Oct-18 53 Backfilling Works
GCS5680 Painting Works to Boundary Wall 18 0% 10-Oct-18 30-Oct-18 53 Painting Works to Boundary Wall
Elevation 03 123 16-Jun-18 05-Nov-18 22 05-Nov-18, Elevation 03
GCS5690 Excavation Works 6 0% 16-Jun-18 21-Jun-18 0 Excavation Works
GCS5700 Leveling & Compaction , Anti Termite and PCC 12 0% 23-Jun-18 05-Jul-18 0 Leveling & Compaction , Anti Termite and PCC
GCS5710 Steel & Concrete Works to Boudary Wall Foundation 21 0% 07-Jul-18 30-Jul-18 0 Steel & Concrete Works to Boudary Wall Foundation
GCS5720 Steel & Concrete Works to to Boudary Wall Columns 21 0% 31-Jul-18 23-Aug-18 0 Steel & Concrete Works to to Boudary Wall Columns
GCS5730 Block Works to Boundary Wall 21 0% 25-Aug-18 17-Sep-18 0 Block Works to Boundary Wall
GCS5740 Plastering Works to to Boundary Wall 21 0% 08-Sep-18 01-Oct-18 0 Plastering Works to to Boundary Wall
GCS5750 Backfilling Works 12 0% 02-Oct-18 15-Oct-18 22 Backfilling Works
GCS5760 Painting Works to Boundary Wall 18 0% 16-Oct-18 05-Nov-18 22 Painting Works to Boundary Wall
78 02-Oct-18 31-Dec-18 0 31-Dec-18, External Works
External Works
GCS5770 Manhole Works 48 0% 02-Oct-18 26-Nov-18 0 Manhole Works
GCS5780 Backfilling Works , Leveling and Compaction Works including Compaction test 40 0% 18-Oct-18 03-Dec-18 0 Backfilling Works , Leveling and Compaction Works
GCS5800 Interlock paving work 25 0% 28-Nov-18 26-Dec-18 0 Interlock paving work
GCS5790 Kerbstone Works 18 0% 29-Nov-18 19-Dec-18 0 Kerbstone Works
GCS5810 GRC Works 20 0% 09-Dec-18 31-Dec-18 0 GRC Works
GCS5830 Final Coat Painting Works 18 0% 11-Dec-18 31-Dec-18 0 Final Coat Painting Works
GCS5820 Gravel Laying Works 6 0% 25-Dec-18 31-Dec-18 0 Gravel Laying Works
26 02-Dec-18 31-Dec-18 0 31-Dec-18, METAL WORKS
METAL WORKS
GCS5840 Access ladders and Hand rails 26 0% 02-Dec-18 31-Dec-18 0 Access ladders and Hand rails

Primary Baseline Remaining Work Milestone IAS Lootah Contracting 15 of 15


Actual Work Critical Remaining Work Summary
Recovery Program © Oracle Corporation