DOCUMENT SUBMISSION STATUS: FOR INFORMATION

0 31.07.2019 FOR INFORMATION M.H.KIM J.I.KIM D.W.KANG


REV DATE DESCRIPTION PREPARED CHECKED APPROVED

PROJECT TITLE

SONG HAU 1 THERMAL POWER PLANT (2x600MW)

OWNER OWNER’S CONSULTANT

VIETNAM OIL AND GAS GROUP (PVN) FICHTNER GmbH & Co. KG PV ENGINEERING

EPC CONTRACTOR EPC CONTRACTOR’S CONSULTANT

VIETNAM MACHINERY INSTALLATION TOKYO ELECTRIC POWER SERVICES


CORPORATION (LILAMA) COMPANY LIMITED - TEPSCO
SUB-CONTRACTOR

DATE NAME SIGN DOCUMENT TITLE

Prepared 31.07.2019 M.H.KIM

METHOD STATEMENT
Checked. 31.07.2019 J.I.KIM
FOR 22KV POWER RECEIVING
Approved. 31.07.2019 D.W.KANG

DOCUMENT NO. REV.


SH1-DHI-P1BAT-E-M01-MS-00000 0
SONG HAU 1 THERMAL POWER PLANT PROJECT

CONTENTS
1. PURPOSE AND OUTLINE ................................................................................................ 2
2. SAFETY PRECAUTIONS .................................................................................................. 2
2.1. Restrict acess to the test area by authorized person only ............................................................... 2
2.2. Section and working area .................................................................................................................. 3
2.3. Pad Lock and Warning Sign ............................................................................................................. 4
2.4. Equipment Numbering ...................................................................................................................... 4

3. ORGANIZATION FOR MONITORING AND EMERGENCY CASE ......................... 5


4. DOCUMENT AND TEST EQUIPMENT ......................................................................... 6
4.1. Documents for Reference .................................................................................................................. 6
4.2. Test Equipment .................................................................................................................................. 6

5. BOUNDARY FOR POWER RECEIVING ....................................................................... 7


5.1.1. Scope of the 22kV Power Receiving.................................................................................................. 7

6. INSULATION CHECK....................................................................................................... 7
6.1. Final Insulation Check for UAT1A by DC 5000V 1 min. (Before Flexible Connection) .............. 7
6.2. Final Insulation Check for UAT1B by DC 5000V 1 min. (Before Flexible Connection) .............. 8
6.3. Final Insulation Check for SPB from UAT1A to MV SWGR (Before Flexible Connection) ....... 8
6.4. Final Insulation Check for SPB from UAT1B to MV SWGR (Before Flexible Connection) ....... 8
6.5. Overall Final Insulation Check for Cables from MV SWGR Incomer to (UAT-1A &1B)
(Including UAT Secondary Winding) ............................................................................................... 8

7. PRE-CONDITION FOR ENERGIZING .......................................................................... 9


7.1. Confirmation of Completion ............................................................................................................. 9
7.2. Settle for UAT Transformer Protection Panel ................................................................................. 9
7.3. Settle for DCS ..................................................................................................................................... 9
7.4. Settle for UAT (P1BBT01, P1BBT02) ............................................................................................ 10
7.5. Settle for SCNS System.................................................................................................................... 10
7.6. Settle for MV SWGR Incomers (P1BBA01, P1BBA02)................................................................ 10
7.7. IPB Pressurizing Cublicle (P1BAA01GH002) ............................................................................... 11
7.8. Visual Inspection .............................................................................................................................. 11

8. PROCEDURE FOR POWER RECEIVING FROM 22KV S/S (EVN) ........................ 12


8.1. STEP #1 (Action by concerned operator) ...................................................................................... 12
8.2. STEP #2 : Voltage Measurement – 11 kV SWGR #A Side ............................................................ 12
8.3. STEP #3 : Voltage Measurement – 11 kV SWGR #B Side ............................................................ 13
8.4. STEP #4 : Checking and Monitoring of Temperature Rising for UAT #A ................................. 13
8.5. STEP #5 : Checking and Monitoring of Temperature Rising for UAT #B .................................. 14

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 1 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

1. PURPOSE AND OUTLINE

The purpose of this document describes power receiving from 22 kV Phu Xuan S/S to primary
side of 11KV SWGR Incoming CB (P1BBA01GH001, P1BBA02GH002) through the UAT
Transformer (P1BBT01,P1BBT02). Its control and monitoring will be performed by DCS and
SCNS System in CCR Control Room.

CB Circuit Breaker
CT Current Transformer
DCS Distributed Control System
DS Disconnetor Switch
ECMS Electrical Control & Monitoring System
ES Earthing Switch
FCB Field Circuit Breaker
SCNS Switchgear Communication and Network system
GCB Generator Circuit Breaker
GCP Generator Control Panel
GSUT Generator Step-up Transformer
OLTC On Load Tap Changer
P/R Power Receiving
SWGR Switchgear
SWYD Switchyard
UAT Unit Aux Transformer

2. SAFETY PRECAUTIONS

Keep the follwing limitation during the testing.

2.1. Restrict acess to the test area by authorized person only


Check
Signed
Yes No

 Fence door must be locked and warning for and UAT transformer.

 Barricade and warning must be indicated in transformer for


Energizing Diamter.
 Protection Relay Panel and Metering Panel are to be locked and
barricaded
 DCS operator only and communication (phone, etc.) in good
condition

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 2 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

Check
Signed
Yes No

 Barricaded and warning sign for MV switchgear area

 Portable fire extinguisher are ready (MV SWGR, Relay panel,


battery room and DCS area)
 Barricaded and warning for block the road in front of UAT TR
from initial power energize up to 24 hours after power receiving.
 On duty operator, barricade and warning sign for Battery and DC
& UPS
 Fire Fighting System:
1) For ensuring of the security, watchman will be assigned with
two (2) shifts to patrol the power receiving area.
2) Appropriate numbers of fire extinguishers

3) UAT area will be ready by water spray and sprinkler system.

4) In case of main fire pump is not ready, temporary arrangement


from fire truck will be located nearby UAT during initial
energization 24 hours.
 HVAC System:
1) TBN Building Ground Floor, Mezzanine Floor
2) CCB Ground Floor Battery, DC, UPS Room

3) CCB Operation 3rd Floor, CCR and Protection Panel Room.

 NOE (NOTICE OF ENERGIZATION) Will be Posted on All Site Nice Board Prior to
Energization and Will be announced in Tool box meeting for all site.

2.2. Section and working area


Authorized
Person Name
Signed
Name Check

 Electrical Control Building 11kV MV SWGR Room

 UAT Area

 DCS Area

 Protection Relay Panel Area

 Metering Panel Area

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 3 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

2.3. Pad Lock and Warning Sign


Check
Signed
Yes No

 11kV MV Switchgear CB

 UAT Protection Relay Panel & Local control Panel

2.4. Equipment Numbering


Check
Signed
Yes No

 All Equipment Related to Power receiving Shall be Numbered as


per EVN Approved numbering drawing
 Drawings (11kV SWGR, UAT) and coordinated procedure are
available at DCS

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 4 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

3. ORGANIZATION FOR MONITORING AND EMERGENCY CASE


1. Qualified and authorized personnel only are allowed to commission test and maintain any
electrical equipment in the plant.
2. Walkie-talkie to be used for communication.
3. Emergency case contact to Mr. Junick Kim- Power receiving in charge person
(Mobile 033-779-0060)
4. Owner and LLM Shall be available at each below mentioned location.

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 5 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

4. DOCUMENT AND TEST EQUIPMENT

4.1. Documents for Reference

 Protection and Metering Single Line Diagram (SH1-DHI-P0ZEN-E-M01-DSL-5602)


 Key Single Line Diagram (SH1-DHI-P0ZEN-E-M01-DSL-5601)
 Electrical Control Logic Diagram for UAT,Line Protection(SH1-DHI-P0ZEN-E-M01-
DLG-5603)
 Electrical Control Logic Diagram for 11kV MV SWGR(SH1-DHI-P0ZEN-E-M01-DLG-
5601)
 Schematic Diagram for UAT A & B(SH1-DHI-P0BBT-E-M01-DSD-5606, 5607)
 Schematic Diagram for 11kV unit #1 & 2 MV SWGR(SH1-DHI-P1BBA-E-M01-DSD-
5601, SH1-DHI-P2BBA-E-M01-DSD-5601)
4.2. Test Equipment

Manufacturer /
No. Test Equipment
Model No.

1 Digital Multimeter Fluke / 87V or 789

2 Phase Rotation Meter Fluke / 9040

3 Insulation Megger Tester Fluke

4 Thermal Camera Fluke

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 6 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

5. BOUNDARY FOR POWER RECEIVING

5.1.1. Scope of the 22kV Power Receiving


Power Receiving will be conducted from Phu Xuan substation through UAT-A (P1BBT01) and
UAT-B (P1BBT02) until primary side of 11kV MV SWGR incomer CB (A, B), and disconnected
of flexible links at GSUT(secondary side) & GCB(GSUT side) as below

6. INSULATION CHECK

6.1. Final Insulation Check for UAT1A by DC 5000V 1 min. (Before Flexible Connection)

Witness/ Hold
No. Description Value (in MΩ) Result point

1 HV Winding – LV Winding + Earth W

2 LV Winding – HV Winding + Earth W

3 HV Winding – LV Winding W

4 Top Core – Earth W

*Winding IR value is minimum 1000 Mohm


Core & Frame IR value is minimum 100 Mohm

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 7 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

6.2. Final Insulation Check for UAT1B by DC 5000V 1 min. (Before Flexible Connection)

No Witness/ Hold
Description Value (in MΩ) Result point
.
1 HV Winding – LV Winding + Earth W

2 LV Winding – HV Winding + Earth W

3 HV Winding – LV Winding W

4 Top Core – Earth W

*Winding IR value is minimum 1000 Mohm


Core & Frame IR value is minimum 100 Mohm

6.3. Final Insulation Check for SPB from UAT1A to MV SWGR (Before Flexible Connection)
Test Voltage-5000V ; Test Time- 1Min

Witness/ Witness/
Test point Test Result Hold Test point Test Result Hold
point point
Phase A - E GΩ W Phase A – B GΩ W

Phase B – E GΩ W Phase B – C GΩ W

Phase C - E GΩ W Phase C - A GΩ W

6.4. Final Insulation Check for SPB from UAT1B to MV SWGR (Before Flexible Connection)
Test Voltage-5000V ; Test Time- 1Min

Witness/ Witness/
Test point Test Result Test point Test Result
Hold point Hold point
Phase A - E GΩ W Phase A – B GΩ W

Phase B – E GΩ W Phase B – C GΩ W

Phase C - E GΩ W Phase C - A GΩ W

6.5. Overall Final Insulation Check for Cables from MV SWGR Incomer to (UAT-1A &1B)
(Including UAT Secondary Winding)
Test Voltage-5000V ; Test Time- 1Min

Witness/ Witness/
Test point Test Result Test point Test Result
Hold point Hold point
Phase A - E GΩ W Phase A – B GΩ W

Phase B – E GΩ W Phase B – C GΩ W

Phase C - E GΩ W Phase C - A GΩ W

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 8 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

7. PRE-CONDITION FOR ENERGIZING

7.1. Confirmation of Completion


Witness
Check / Hold
Signed point
Yes No

 UAT #A and #B commissioning must be completed. W

 IPB/SPB commissioning must be completed. W

 11kV MV SWGR commissioning must be completed. W

 UAT Protection Panel commissioning and communication must be


W
completed

7.2. Settle for UAT Transformer Protection Panel


Witness
Check / Hold
Signed point
Yes No

 DC control power reading and healthy W

 AC control power reading and healthy W

 Protective relay and LOR (86) in normal W

 Confirm for CT terminal tighten connection


W
(If CT is not used, LV side must be shorted)
 Confirm for VT terminal tighten connection
W
(If VT is not used, LV side must be opened)
 Protection relay setting parameter of 500kV transmission line,
W
UAT must be accepted by EVN.

7.3. Settle for DCS


Witness/
Check Hold
Signed point
Yes No

 DC/UPS power available and healthy W

 Confirm for normal condition on screen in DCS. W

 Confirm for normal condition of any alarm or trip. W

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 9 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

Witness/
Check Hold
Signed point
Yes No

 Interface signal between energized equipment with DCS must be


W
checked before power receiving.
7.4. Settle for UAT (P1BBT01, P1BBT02)
Witness/
Check Hold
Signed point
Yes No

 AC power supply available and healthy W

 DC power available and healthy W

 CT HV side connection and link terminal check W

 CT LV side connection and link terminal check


W
(If CT is not used, LV side must be shorted)

 OLTC power on and tap position is middle tap W

7.5. Settle for SCNS System


Witness/
Check Hold
Signed point
Yes No

 AC power supply available and healthy W

 Required of relay shall be communicated to SCNS system W

 No active alarm or trip for power receiving equipment W

 PT fuse, PT MCB and PT in service position check W

7.6. Settle for MV SWGR Incomers (P1BBA01, P1BBA02)


Witness/
Check Hold
Signed point
Yes No

 AC power supply available and healthy W

 DC power available and healthy W

 CT connection and link terminal check


W
(If CT is not used, LV side must be shorted)

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 10 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

Witness/
Check Hold
Signed point
Yes No

 PT fuse, PT MCB and PT in service position check W

 Main VCB #1 (P1BBA01GH001) is open and LOTO W

 Main VCB #2 (P1BBA02GH002) is open and LOTO W

 ES (P1BBA01GH001) is open and LOTO W

 ES (P1BBA02GH002) is open and LOTO W

 Protection relay and lockout K86 normal condition W

7.7. IPB Pressurizing Cublicle (P1BAA01GH002)


Witness/
Check Hold
Signed point
Yes No

 AC Power Supply is available and Healthy W

 Service air line is connected and pressure range between (4-8 bar) W

 Check pressure reduction(5mbar) after pressure control by


W
reducing valve (1st &2nd stage )

7.8. Visual Inspection


Witness/
Check Hold
Signed point
Yes No

 22kV overhead & power cable line (outside power plant) W

 UAT #A and #B and IPB W

 MV SWGRs and Cables W

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 11 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

8. PROCEDURE FOR POWER RECEIVING FROM 22kV S/S (EVN)


8.1. STEP #1 (Action by concerned operator)
Check
Signed
Yes No

 Ready status for power receiving shall be reported to Phu Xuan S/S
by telephone communication.
 22kV CB “CLOSE” for “ENERGIZING” action by concerned
operator as per Phu Xuan S/S Switching procedure.

8.2. STEP #2 : Voltage Measurement – 11 kV SWGR #A Side


Measure voltage and check phase rotation of MV SWGR Incoming PT secondary side.

Check
Terminal No. : MCB_PT1 - 2, 4, 6 Signed
Yes No

 Phase rotation sequence of MV SWGR incoming


(P1BBA01GH001) PT at 2nd side is clockwise

MV SWGR (P1BBA01GH001) Incoming PT Secondary Measurement

Terminal
Phase Terminal No. Voltage Phase Voltage
No.

63.5 V 110.0 V
MCB_PT1 MCB_PT1
A-E A-B
2-G 2-4

63.5 V 110.0 V
MCB_PT1 MCB_PT1
B-E B-C
4-G 4-6

63.5 V 110.0 V
MCB_PT1 MCB_PT1
C-E C-A
6-G 6-2

MV SWGR Incomer Voltage Reading from Meter or Relay (P1BBA01GH001/002)

Reading Voltage Reading Voltage

Phase A kV Phase A-B kV

Phase B kV Phase B-C kV

Phase C kV Phase C-A kV

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 12 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

8.3. STEP #3 : Voltage Measurement – 11 kV SWGR #B Side


Measure voltage and check phase rotation of MV SWGR Incoming PT secondary side.

Check
Terminal No. : MCB_PT1 - 2, 4, 6 Signed
Yes No

 Phase rotation sequence of MV SWGR incoming


(P1BBA02GH001) PT at 2nd side is clockwise

MV SWGR (P1BBA02GH001) Incoming PT Secondary Measurement

Terminal
Phase Terminal No. Voltage Phase Voltage
No.

63.5 V 110.0 V
MCB_PT1 MCB_PT1
A-E A-B
2-G 2-4

63.5 V 110.0 V
MCB_PT1 MCB_PT1
B-E B-C
4-G 4-6

63.5 V 110.0 V
MCB_PT1 MCB_PT1
C-E C-A
6-G 6-2

MV SWGR Incomer Voltage Reading from Meter or Relay (P1BBA02GH001/002)

Reading Voltage Reading Voltage

Phase A kV Phase A-B kV

Phase B kV Phase B-C kV

Phase C kV Phase C-A kV

8.4. STEP #4 : Checking and Monitoring of Temperature Rising for UAT #A


Note :
1. After energization, check temperature 24hrs at UAT Outside
2. After energization, check alarm at DCS during 2 hours
3. Check for oil leaks at any connection such as Valves, flange bolt’s point
4. Check breather condition and conservator level
5. Check Tap Position at Nominal tap and Local mode

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 13 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

UAT #A (P1BBT01)

Temperature (°C) Sign.


Time
Oil HV Winding LV Winding

1st hour

2nd hour

3rd hour

4th hour

5th hour

6th hour

7th hour

8th hour

9th hour

10th hour

11th hour

12th hour

13th hour

14th hour

15th hour

16th hour

17th hour

18th hour

19th hour

20th hour

21st hour

22nd hour

23rd hour

24th hour

8.5. STEP #5 : Checking and Monitoring of Temperature Rising for UAT #B


Note :
1. After energization, check temperature 24hrs at UAT Outside.
2. After energization, check alarm at DCS during 2 hours.

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 14 of 15
SONG HAU 1 THERMAL POWER PLANT PROJECT

3. Check for oil leaks at any connection such as Valves, flange bolt’s point
4. Check breather condition and conservator level
5. Check Tap Position at Nominal tap and Local mode

UAT #B (P1BBT02)

Temperature (°C) Sign.


Time
Oil HV Winding LV Winding

1st hour

2nd hour

3rd hour

4th hour

5th hour

6th hour

7th hour

8th hour

9th hour

10th hour

11th hour

12th hour

13th hour

14th hour

15th hour

16th hour

17th hour

18th hour

19th hour

20th hour

21st hour

22nd hour

23rd hour

24th hour

SH1-DHI-P1BAT-E-M01-MS-00000 Rev.0 15 of 15