SUMMARY OF WORKS
Labor Materials
No. Description Amount (A+B)
(A) (B)
SECOND FLOOR
1 CARPENTRY WORKS 20,800.00 21,620.00 42,420.00
2 ELECTRICAL WORKS 52,000.00 65,019.25 117,019.25
3 PAINTING WORKS 75,000.00 90,810.00 165,810.00
THIRD FLOOR
4 CARPENTRY WORKS 20,800.00 21,620.00 42,420.00
5 ELECTRICAL WORKS 23,400.00 25,500.00 48,900.00
6 PAINTING WORKS 40,000.00 45,700.00 85,700.00
We estimate that are quotation work to be PESOS: SIX HUNDRED FORTY-TWO THOUSAND
FOUR HUNDRED NINE AND 64/100 (PHP 642,409.64). Proposal inclusive of supply of
materials and labor works.
(Please see Annex “A” and Annex “B” for tabulated costing per scope)
TERMS OF PAYMENT:
1. 50% Down payment before mobilization
2. 40% full payment upon completion of works
3. 10% Retention (to be release 1 month after turnover of works)
If the terms of this letter as set forth above are acceptable to you, please indicate your
acceptance by signing this letter in the appropriate space below.
Very yours Truly,
ENGR. JAYSON D. OROSA Acknowledged by: _______________________
JDO Construction Services Signature over printed name
PRC NO. 0138168 Date: ________________________
CIVIL ENGINEER
Prepared by:
Prepared by: