Sei sulla pagina 1di 6

GTT Pluto II Subsea Cryogenic Pipeline

Approved by

As the LNG market is growing continuously, elements of the LNG value chain have to
adapt constantly to new needs. Some new LNG import and export terminals have to be built
near populated areas or have to accommodate with bad soil conditions. Cryogenic sub sea
pipeline offers an opportunity to built terminals in those areas: environmental impact is
reduced to a minimum, unloading platform can be moved away from shore line to reach a
sufficient water depth; pipeline can be laid on a wide range of soil offering a cheaper solution
than complex trestles.

As pipeline statistics show that accident can always occur, GTT developed a double
containment pipeline offering the very high level of safety needed for service during 30 years
or more without maintenance. The design philosophy is inspired both by traditional pipeline
codes which tends to eliminate very improbable failure modes and by the International Gas
Code which focuses more on catastrophic failure chain.

Pluto II Pipe structure 6

The pipe structure from the inner element to 5


the outer is: 4
 Flow line (1) made of 36% nickel
alloy. 3
 Primary insulation layer (2). 2
 Secondary 36% Nickel alloy Barrier
(3). 1
 Secondary insulation layer (4).
 HD Concrete weight lining (5).
 Carbon steel carrier pipe (6). S
 Foam spacers (S)

Double barrier pipe structure

A fully redundant pipe structure


which offers a very high reliability
Materials and Component detail

Materials Component detail


Materials used in the PLUTO II technology  36% Nickel alloy barriers
permit to reach a high level of security, to Low CTE alloy barriers are fabricated
avoid any expansion loop or bellows and to using the spiral forming process. For
grant a good thermal efficiency: pipes with a high D/t ratio, spirally
welded pipes offer:
 36% Nickel alloy used for barriers is - Better tolerances than LWP.
widely used in GTT’s NO96 - Higher burst and critical pressures.
containment systems. It has a low CTE - Similar weld quality.
Value (< 2.10-6 /°C) and very good Moreover SWP are easier to handle and
mechanical properties at cryogenic manipulate during the prefabrication
temperatures. Expansion loops are stage.
avoided, assembly is simplified, space is Welds on barriers are 100% X-Ray
saved and pressure drops are minimized. tested and visually inspected.
Prototype spirally welded pipes in 36%
 The base insulating material is Nickel alloy have been manufactured
nanoporous silica also called aerogels or using the TIG welding process.
nanogels. It is currently the best
insulating material for atmospheric  Insulating blankets
pressure applications. This passive Insulation blankets commercialized by
insulating material ensures a constant Aspen Aerogels were initially made of
thermal efficiency; it consequently 6.4mm thick plies assembled together in
permits to reach an expected lifetime of a reinforced paper bag in order to reach a
more than 30 years. given thickness. A new version is
currently under approval. A single
 The foam used for spacers is a coated ply is rolled around the pipe to
common material for LNG applications. reach the required thickness.
Spacers permit to center components Both versions lead to the same thermal
while avoiding significant local thermal and mechanical performances, with the
leak. They also ensure insulation only difference being the insulated
integrity during pipe in pipe sheathing barrier prefabrication method.
and field jointing operations.
 Weighted carrier pipe
 The base design carrier pipe is made In the classical design, PLUTO II
of common carbon steel. Its main roles technology uses a HD concrete lined
are to act as an armor for internal parts, carbon steel pipe. Concrete liner is
to prevent any water ingress from manufactured using the centrifugal lining
surrounding media, and finally to ensure process. A drying line (a simple duct) is
the adequate rigidity and strength for the molded in the concrete liner. An
laying operation. Conventional corrosion alternative version has been designed
protection is applied to prevent any with a standard carbon steel pipe
external corrosion; cathodic protection externally weighted or not which is more
will be used for sub sea applications. adapted for onshore applications.
Peripheral systems
 Nitrogen sweeping

During line service, gaseous nitrogen is Fiber optic sensor is deployed using the
swept in both insulation spaces. The floating technique: small stainless steel
roles of sweeping are to: ducts are inserted in the secondary
- Avoid presence of oxygen to insulation during prefabrication; they are
eliminate risks of explosive jointed during section assembly. The
mixture due to potential fiber is finally floated in this duct using a
porosities. Removing oxygen low viscosity liquid which density is
also ensures internal corrosion slightly higher than fiber’s average
inhibition. density.
- Detect potential leak or
porosity thanks to sweeping gas  Cryogenic Flanges / Abutments
analysis at the outlet.
- Ensure an accurate control of At both line extremities, special flanges
insulation spaces pressure are needed to retain the three pipes. This
during transient phases. flange described on the figure below is
mainly composed of an internal low CTE
alloy flange (1) to which Low CTE alloy
barriers (4) are welded. This internal
flange is maintained in an outer flange
(2) connected to the carrier pipe thanks
to densified wood rings (3) which can
withstand thermal and pressure loads.

Nitrogen sweeping

 Temperature monitoring

During transient phases and service,


temperatures of the secondary insulation
space are monitored thanks to a
distributed temperature sensor (fiber
optic & Raman effect based sensor). 1
Temperatures can be measured every 1
meter along the line. 4 3
It permits to: Cryogenic flange / abutment
- Detect any change in temperature
due to potential porosity (LNG
leak & water ingress). Redundant monitoring system,
- Detect, localize and monitor any
anomaly in insulation. no maintenance needed
Design basis / System efficiency
 Thermal efficiency

PLUTO II technology’s main interest is


to replace traditional trestles. The
maximum requested length for lines is
probably ranging between 15 and 20km.

LNG
Overall thermal efficiency is divided in
two parts: pressure drops and thermal
flux through the pipes. Classical
diameters (~ 30-32’’) allow a reduction
Service Radius
of pressure drop contribution to a low
enthalpy increase in cargo (~50W/m).
The thermal contribution is reduced
thanks to the thermal insulation and is of

LNG
LNG
the same order of magnitude (50 to
100W/m depending on surrounding
media temperature and nature). The
overall heat transfer coefficient in 30°C
water is lower than 0.21W/m2.K. (The LNG Leak Radius

average value is 0.17W/m2.K)

 Pressure containment

Water
LNG

Pluto II pipeline has been designed under


the following assumptions:

- Design pressure: 30 Bars


- Service pressure : 15 Bars Water Ingress Radius

- Shortest valve closure: 5s Temperature profiles Vs Scenarios

 Double barrier principle In the water ingress scenario (Water


Ingress graph), while the secondary
As shown in the figure on the right, the insulation loses part of its efficiency, the
double barrier pipe principle relies on the primary insulation remains fully
total redundancy of tightness and operational.
insulation.
During service, the temperature gradient
is divided between the two insulation
layers (Service graph).
In the LNG Leak scenario (LNG Leak
graph), the secondary barrier remains
tight and the secondary insulation
prevents the carbon steel pipe from High thermal and tightness
cooling down. That is the reason why
carbon steel pipe can be used as carrier
performances ensured by the
pipe avoiding the use of expensive alloys. double barrier principle
Tests, studies and prototypes
 Characterization of materials:  Fabrication tests:

- CTE Measurements - Mechanical tests on spacers


- Conductibility Measurement - 36% Ni alloy SWP fabrication
- Mechanical test - Orbital welding on barriers
- Thermal shocks & cycling - Welding processes improvements
- Sea water compatibility (The welding speed has been
- Fiber optic validation increased from 30cm/min to
250cm/min)

Cryogenic tests on concrete Welding process validation tests


 FEM analyses:  Full scale tests done on the
prototype:
For the pipeline itself:
- Steady state heat transfer - Sections fabrication validation
- Transient heat transfer - Jointing procedures validation
- Thermo mechanical study - Flanges fabrication
- Collapse pressure evaluation - Steady state & transient thermal
For the cryogenic flanges: validation.
- Steady state heat transfer - Validation of sweeping procedures
- Thermo mechanical validation - Loss of containment.
- The pipe has been tested in
cryogenic conditions during
more than 110 days.

FEM analyses on the flange and pipe

 Mock-up tests:
~30 m
- Fabrication procedures validation
- Thermal model validation
- Tolerances validation Artist view of the test bench
- Collapse behavior of the assembly

Collapse tests and first mock-up


GTT Pluto II prototype

Barriers sheathing Installation on the test bench

Concrete Abutments

Abutments prefabrication

Pipe under water

Assembled prototype

Potrebbero piacerti anche