1. During the initiating stage, which of the following elements will be identified to meet
the project goals?
9. A Project Manager is going through the Project Statement of Work provided by the
project sponsor. Which of the following will NOT be a part of this document?
SELECT THE CORRECT ANSWER
Business Need
Product Scope Description
Strategic Plan
Performance Measurement Baseline
10. You are the Project Manager of a project for which a prototype was recently delivered.
The sponsor of the project calls you and gives you an overall estimate for the project.
This form of estimate is known as ____
SELECT THE CORRECT ANSWER
Analogous Estimate
Parametric Estimate
Heuristic Estimate
Three Point Estimate
11. A Project Manager who has just been assigned to a new project has been asked by
his sponsor to come up with an initial cost estimate called a Rough Order of Magnitude
(ROM). This would typically fall in which range?
13. There are three projects A, B, and C. NPV for projects A, B, and C are $50,000, $
80,000, and $ 40,000 respectively. In a meeting, the management unanimously has
chosen projects A and C. What is the opportunity cost of the project?
SELECT THE CORRECT ANSWER
80000
130000
90000
0
14. A project is in the initiating stage, and the Project Manager is identifying project
communication constraints. Which of the following could be a valid constraint?
SELECT THE CORRECT ANSWER
The project could face high attrition rate
Management and customer expect detailed formal status reports on the project
Project team members would be required to work from different geographical locations
Many stakeholders of the project would not be able to attend the planned project kick-
off meeting
17. You have been assigned to a large construction project, and you are in the "Initiating"
process group. You have identified the project stakeholders using a stakeholder
analysis tool and defined the high-level scope of the project. During these activities,
you have identified a key project limitation regarding the project location. What is the
BEST option for you in this situation?
SELECT THE CORRECT ANSWER
Document the project limitation as a project constraint
Discuss the project constraint with the project sponsor and the customer
Document the project limitation as a project constraint and propose an implementation
approach to the sponsor and customer, if required
Ignore the project constraint and work toward getting approval for the project charter
19. Which of the following is NOT an input to the "Plan Stakeholder Management"
Process?
SELECT THE CORRECT ANSWER
Project Management Plan
Stakeholder Register
Stakeholder Management Plan
Enterprise Environmental Factors
20. John has been assigned to a project recently, and he is in the process of documenting
the project charter with the project sponsor. Which of the following MUST he include
in the Project Charter?
SELECT THE CORRECT ANSWER
Project purpose or justification
Positive risks
Budget estimates
Risk analysis
21. As a Project Manager of a large project with hundreds of stakeholders, which of the
following is the BEST course of action?
SELECT THE CORRECT ANSWER
Incorporate needs of only important stakeholders
Incorporate needs of all stakeholders
Ask your manager to manage the stakeholders
Eliminate some of the stakeholders
23. You are the Project Manager of a software telecom development project. You and your
team are working together to create a billing software. Which quadrant of the
Power/Influence Grid will the person(s) be responsible for sign-off of the deliverables?
SELECT THE CORRECT ANSWER
Keep Informed
Monitor
Manage Closely
Keep Satisfied
24. You are the Project Manager of a project in which team members have dual reporting
structure. In addition to reporting to you, they also report to their functional manager.
Also, the team members are expected to do the project work along with department
work. You are working in which form of organization?
SELECT THE CORRECT ANSWER
Functional
Projectized
Tight Matrix
Matrix
25. You are a Project Manager of an ambitious project in an organization. Although you
have successfully managed many critical projects before, this is a new organization
and you are working on this technology for the first time. However, you hear that the
company has proven expertise on the technology and has also done a similar project
in the past. In this situation, what is the BEST option available to you?
26. You are managing a large and complex project which is in the planning stage. After
assessing the detailed project requirements with the stakeholders, you ask the team
to create a Work Breakdown Structure (WBS). However, since most of the team is
new, you decide to brief them on some rules of creating a WBS. Which of the following
statements is INCORRECT about a Work Breakdown Structure?
28. You are the Project Manager of a large and complex project. Your project team has
finished creating a Work Breakdown Structure for the project. However, some of the
team members are still not sure of the kind of work included in each of their work
packages. Which of the following documents would you suggest they go through?
SELECT THE CORRECT ANSWER
Project scope statement
Project Management Plan
Work Break Structure (WBS) Dictionary
The Product Scope document
29. You are a Project Manager. In the process of sequencing activities for your project,
you create a schedule network diagram that uses boxes called nodes to represent
activities and connects them with arrows to represent logical relationships between
them. What is this popular scheduling diagram known as?
SELECT THE CORRECT ANSWER
Project scope statement
Project Management Plan
Work Break Structure (WBS) Dictionary
The Product Scope document
30. As a Project Manager, you are in the process of identifying and documenting
relationships among project activities. You are using the Precedence Diagramming
Method (PDM). Which of the following relationships are you UNLIKELY to use for this
purpose?
SELECT THE CORRECT ANSWER
Finish to Start (FS)
Finish to Finish (FF)
Start to Start (SS)
Start to Finish (SF)
31. As a Project Manager, you are estimating the duration of your project activities using
PERT (Program Evaluation and Review Technique). For a particular project activity,
your Optimistic estimate is 14 days, Pessimistic estimate is 47 days, and Most Likely
estimate is 27 days. What should be the expected duration of this activity?
SELECT THE CORRECT ANSWER
28.17
31
43
36
32. Sub network or fragment network templates are most useful when the project has
MANY:
SELECT THE CORRECT ANSWER
Mandatory Dependencies
Discretionary Dependencies
Undefined Variables
Identical or nearly identical deliverables
33. As a Project Manager, you have created a Resource Breakdown Structure (RBS) for
your project. Which of the following statements is NOT TRUE about Resource
Breakdown Structure (RBS)?
SELECT THE CORRECT ANSWER
It is a hierarchical structure of resources
It is used for estimating resource utilization
It is used for organizing and reporting project schedule
It has resources grouped by category and type
34. A Project Manager is managing a project that has constraints on the availability of
required resources throughout the project. He needs to rearrange the schedule in such
a way that a constant number of resources are used each month. Which of the
following techniques should the Project Manager use to achieve this?
36. Which estimate technique does the Program Evaluation and Review Technique (PERT)
use to define the approximate range of activity costs?
SELECT THE CORRECT ANSWER
Earned Value Technique
Parametric Estimation Technique
Three Point Estimate Technique
Historical Information
37. Your project team is involved in estimating the cost of the project as a part of project
cost management. Which of the following tools and techniques will NOT be applicable
for this purpose?
SELECT THE CORRECT ANSWER
Cost Benefit Analysis
Reserve Analysis
Cost of Quality
Alternatives Analysis
-
38. The common term for an authorized time-phased budget, which includes the Budget
at Completion (BAC), used to measure cost performance, and displayed in the form of
an S-curve is:
SELECT THE CORRECT ANSWER
Earned Value
Cost Performance Index
Cost Baseline
Project Budget
39. A project team is in the process of identifying quality requirements and standards for
the project. It is documenting how the project will demonstrate compliance. The team
has referred to organizational process assets and is using tools like statistical
sampling and control charts. Which process of Quality Management is the project
team performing?
SELECT THE CORRECT ANSWER
Plan Quality Management
Perform Quality Assurance
Perform Quality Control
Manage Project Team
40. Which of the following is true with respect to Plan Cost Management?
SELECT THE CORRECT ANSWER
Develop the high-level budget
Develop the cost management plan
Develop the budget plan
Develop both budget plan and cost management plan
42. A project team is ahead of its schedule, and its SPI and CPI are currently 1.4 and 1.2
respectively. The Project Manager and the team are brainstorming about the scope of
the next milestone delivery. They have found that including an additional feature
would enhance the usability of the product and can be compressed in the current
schedule. What should the project team do next?
SELECT THE CORRECT ANSWER
Add this feature in the next release as long as it doesn't affect the delivery date
Go through the change management and analyze the impact of this additional feature
Discuss it with the project sponsor
Drop this feature as it is gold plating and the customer does not need it
43. You are the Project Manager of a large team with people from diversified locations.
There are many groups within a project, such as architects, human resources, legal,
quality engineers, etc., with their own hierarchy and reporting structure. In order to
ensure that each team member has clarity on their own and other members' reporting
structure, you decide to capture all of this information graphically. Which of the
following documents will you be using for this purpose?
SELECT THE CORRECT ANSWER
Project Organization Chart
Resource Breakdown Structure
Organization Breakdown Structure
Resource Assignment Matrix
44. A Project Manager wants to capture information related to staff acquisition and
release, training needs, resource calendar, recognition, and rewards. Which of the
following documents would be most appropriate?
SELECT THE CORRECT ANSWER
Project Management Plan
Resource Management Plan
Project Team Assignments
Issue Log
45. You are a Project Manager in an organization with a functional structure; hence, it is
important that you negotiate suitable resources for your project from the functional
manager. Which of the following tools could be a valuable asset to prove your projec t
resource requirements to the functional manager?
SELECT THE CORRECT ANSWER
Staffing Management Plan
Network Diagram and Project Schedule
Resource Assignment Matrix
Project organization chart
46. In a project kick-off meeting, there is utter chaos, with all the attendees talking
simultaneously. The Project Manager is not able to present his report due to the
commotion, and the stakeholders feel that their expectations are not being met
properly. Also, many of the invited attendees are not present. What must have the
Project Manager done to avoid this situation?
SELECT THE CORRECT ANSWER
Communicate the agenda of the meeting clearly to all the Stakeholders
Postpone the meeting to ensure availability of all the Stakeholders
Conduct a brainstorming session to reach a consensus with Stakeholders
Establish ground rules for the meeting and communicate the rules to all the attendees
47. You have been assigned as a Project Manager of a newly initiated project and have 5
team members. There is a project sponsor (Mr. Smith) and a technical architect who
will be involved only during the planning stage. This project is for an external
customer. How many communication channels are possible in your project?
SELECT THE CORRECT ANSWER
36
72
28
Cannot be determined since project is in the initiating stage
49. A Project Manager is managing a short duration pilot project and has started with a
risk management planning process. He has identified new risks and arranged them
based on probability and the impact matrix. The Project Manager now proceeds to
plan responses for the risks without analyzing the risks numerically. According to you,
this decision of the Project Manager is:
SELECT THE CORRECT ANSWER
Incorrect. It is important to numerically analyze each risk in order to come up with
appropriate responses.
Correct. Quantitative Risk Analysis is a waste of time and is not required if risks are
already assessed qualitatively.
Incorrect. Quantitative risk analysis is important. We need to calculate EMV for each
risk and later move on to risk response planning.
Correct. This is a short duration project, and the Project Manager might skip
Quantitative Risk analysis if he feels it does not assist in the Risk Management process.
50. Which of the following elements are to be considered while developing the project
schedule? Pick the best answer.
SELECT THE CORRECT ANSWER
Project deliverables
Project timeline
Quality
Cost
51. As part of Quantitative Risk Analysis, a Project Manager has derived four packages
with the following probability and impact. Using EMV (Expected Monetary Value),
which one should he use in the project?
SELECT THE CORRECT ANSWER
Work package I: Probability 15% and Impact $20,000
Work package II: Probability 7 % and Impact $10,000
Work package III: Probability 7 % and Impact $15,000
Work package IV: Probability 15% and Impact $10,000
-------
52. A Project Manager is in the planning stage and is evaluating risks in the project. He
wants to improve the project's chances of success by evaluating all possible risks. As
a part of risk management planning and identification, he has used a standard
questionnaire to identify risks and has identified about 20 risks in the project. What
should he do before moving to the next process, "qualitative risk analysis"?
SELECT THE CORRECT ANSWER
Prioritize risk by determining each risk's probability and impact
Update project management plan and other project documents based on inputs from
these risks
Communicate the status of identified risks to stakeholders
Continue to identify more risks using other tools and techniques
53. A project team in a software project started with risk management planning and
identified new risks. Next, it conducted qualitative risk analysis using a probability and
impact matrix and thereafter completed the 'plan risk response' process. What is an
important step that the team needs to complete before moving to risk monitoring and
control?
SELECT THE CORRECT ANSWER
Evaluate risks quantitatively using any of the tools of Quantitative Risk Analysis
Identify risk owners among stakeholder and project team
Evaluate the amount of contingency time and cost reserve needed
Communicate the status of identified risks and response strategy to stakeholders
54. A project team is working on a risk response strategy by evaluating every risk and
coming up with suitable response strategies. However, one particular risk with a
negative impact cannot be avoided or mitigated. Furthermore, there is no way to
transfer risk by outsourcing or buying insurance. What is the best the team can do
about the risk?
SELECT THE CORRECT ANSWER
Treat it as a secondary risk and update it in the Risk Register
Share the risk by allocating ownership to a third party
Accept the risk and put it in the watch list
Revisit the Risk Response Strategy
55. You are a Project Manager in a construction company and urgently require some
expert welders for a short duration. You checked their availability internally with the
functional manager, but the functional manager is not able to match the skills
required. You decide to acquire these resources on contract. Which of the following is
the BEST type of contract for your requirements?
SELECT THE CORRECT ANSWER
Cost Reimbursable
Fixed Price
Time and Material
Cost Plus Incentive Fee
56. A contract type where the seller is reimbursed for all allowable costs for performing
the contract work and receives a predetermined incentive fee based on achieving
certain performance incentives is:
SELECT THE CORRECT ANSWER
Cost Plus Fixed Fee Contract
Cost Plus Incentive Fee Contract
Cost Plus Award Fee Contract
Fixed Price Incentive Fee Contract
57. A Project Manager is in the process of preparing a plan that documents how the
procurement process will be managed: from developing procurement documents to
contract closure. She is also going through project requirements and scope documents
with the team and discussing different contract types to decide the one most suitable
for the project. According to you, which process of procurement management is the
Project Manager in?
SELECT THE CORRECT ANSWER
Plan Procurement Management
Conduct Procurements
Control Procurements
Close Procurements
58. A Project Manager has used a popular cost estimating model to come up with cost
estimates for his upcoming project. However, the sponsor asks him to add 15% to the
total cost estimate as the customer always negotiates and asks the prices to be
reduced by 10% to 15%. What is the BEST option for the Project Manager?
SELECT THE CORRECT ANSWER
Do as the sponsor say as she is your senior and project sponsor
Recalculate the cost estimates using a more suitable technique and check the difference
between the estimates
Provide the sponsor with details on cost estimation and suggest that she share this with
the customer
Refuse to make any changes or increase the estimated cost
59. A large project with a team of 150 people is in the planning stage. It will span over a
duration of 3 years and is under strict budget. A Project Manager is using the project
charter to assess the detailed project requirements in consultation with the
stakeholders and to establish the key project deliverables. He sets his project quality
objective based on the organization capability baseline set by the quality policy.
However, one of the stakeholders refuses to accept this and asks him to reduce the
quality objective as it will help cut down cost of quality of the project. He also refuses
to approve the project if the Project Manager does not agree to his suggestion. What
should the Project Manager do?
SELECT THE CORRECT ANSWER
Explain to the stakeholder that Cost of Quality is less than cost of project
Explain to the stakeholder that if Quality objectives are set lower than expected, they
will be highlighted during Quality Audit
Explain to the stakeholder that the quality policy is used to set quality objectives for all
the projects in the organization and they need to abide by it
Agree to the stakeholder's suggestion and reduce the metric as he will not approve the
project otherwise
60. After a project management plan is prepared and approved, a project stakeholder
asks the Project Manager to correct some syntax and grammatical errors in the
project document as they could be misleading. What should the Project Manager do?
SELECT THE CORRECT ANSWER
Refuse as these are trivial changes and can be ignored
Refuse as the project management plan has already been discussed and approved
Refuse and ask the stakeholder to meet the project sponsor
Refuse and ask the stakeholder to raise a change request that can be considered by the
change control board
61. You are a Project Manager, and your project sponsor has asked you to come up with
the total funding requirements of the project. What will be the total funding
requirements for your project?
SELECT THE CORRECT ANSWER
The total approved budget by time period
The total project budget plus anticipated liabilities
The total funds, including the cost baseline and any management reserves
The total individual cost estimates
62. A project has a project manager, a sponsor, a human resource specialist, a quality
analyst, and seven team members. How many communication channels are possible in
the project?
SELECT THE CORRECT ANSWER
50
110
55
115
63. A Project Manager has submitted a formal document that describes the procurement
item in enough detail. This document allows prospective sellers to determine if they
are capable of providing the product and details methodology and results that will be
provided to the buyer. What is this called?
SELECT THE CORRECT ANSWER
Invitation for Bid
Request for Proposal
Request for Quotation
Contract Statement of Work
64. Which of the following is NOT true about the human resource plan created by the
Project Manager during the planning process group?
SELECT THE CORRECT ANSWER
Defines the roles and responsibilities of the project team members
Includes an effective project organization structure
Provides guidance about how resources will be utilized and managed
Defines the work breakdown structure
65. You are a Project Manager for a big project, and quality is a top priority. You have
devoted a lot of the project time to the creation of the quality management plan.
What is the advantage of the quality management plan?
SELECT THE CORRECT ANSWER
Prevents defects from reaching the customers
Guarantees improvement in project quality
Provides a systematic approach to meet the project's quality goals
Conforms to customers' testing methodology
66. A Project Manager is trying to successfully complete a project, but her role in the
organization is limited and she has no control over project budget. Although she has
some power to authorize decisions, she needs to seek approval on most of the major
decisions. Also, her team members work only part-time on the project. The Project
Manager is in a _______ organization.
SELECT THE CORRECT ANSWER
Functional
Projectized
Composite
Strong Matrix
67. How is the role of project expeditor different from project coordinator?
SELECT THE CORRECT ANSWER
Project coordinator has some power to make decisions
Project coordinator acts primarily as Staff assistant
Project coordinator acts as a communication coordinator
Project coordinator can control project budget
68. You are working on a critical project for a large enterprise. The project has a major
milestone delivery next week and is in the final testing phase. The project team is
working on two critical showstopper bugs that are affecting the project. One of the
senior members of the project has resigned, and the outsourced component that was
scheduled for delivery next week may be delayed. Additionally, the current
performance indices are 1.09 (CPI) and 1.90 (SPI). What is the MOST critical issue
faced by the project?
SELECT THE CORRECT ANSWER
Cost and Schedule
Delay in third party component
Resource movement
Testing defects
69. Which of the following is NOT an enterprise or environmental factor that can influence,
direct, and manage project work?
SELECT THE CORRECT ANSWER
Stakeholder risk tolerance
Organizational culture and structure
Project Management Information System (PMIS)
Standardized guidelines and work instructions
71. Which of the following processes does not have defect repair as one of the outputs?
SELECT THE CORRECT ANSWER
Perform Integrated Change Control Process
Control Procurements
Monitor and Control
Control Schedule
72. You are a Project Manager of a software project that is in a critical phase of testing
and bug fixing. An enthusiastic test engineer working on the project tells you that he
found a major bug the previous night during testing. He assures you that there is
nothing to worry about as he has 'patched' the code and it is working fine now. What
should be your main concern about this incident?
74. To acquire and manage the project team, which of the following plan or documents
should be referred to?
SELECT THE CORRECT ANSWER
Human Resource management plan
Procurement management plan
Project charter
Human Resource management plan and Procurement management plan
75. An instrument that has a screw of 15 mm diameter gives the following readings:
16.001 mm, 16.00015 mm, 16.0003 mm, and 15.900 mm. Assuming that the
instrument is capable of measuring up to the third-place decimal, what BEST can be
concluded about the performance of the instrument?
SELECT THE CORRECT ANSWER
The instrument is accurate and precise
The instrument is not accurate but is precise
The instrument is accurate but is not precise
The instrument is neither accurate nor precise
76. You are a Project Manager in a leading manufacturing company, and you are
managing a critical project for the company. Your project is facing severe cost
constraints, and you cannot delay the delivery date of the product. After consulting
stakeholders and the customers, you decide to lower both the quality and grade of the
product. The decision to lower the quality and grade of the product is _______.
78. According to Maslow's hierarchy of needs, what comes at the BOTTOM of the pyramid?
SELECT THE CORRECT ANSWER
Physiological
Social
Esteem
Self-Actualization
79. A project is in the final testing stage and is approaching a critical deadline. Two senior
members of the team who have already had disagreements throughout project
execution are caught up in a deadlock. The Project Manager has earlier tried his best
to sort out their differences, but it hasn't worked. What is the BEST the Project
Manager can do in this situation?
SELECT THE CORRECT ANSWER
Talk to the project sponsor since they are senior members of the project
Give them a final warning and make it clear that such behavior is not encouraged
Talk face-to-face with each of them individually to sort out their differences
Use an Autocratic approach and make a decision that is best for the project
80. Which of the following is the MOST COMMON reason for conflict?
SELECT THE CORRECT ANSWER
Schedules
Personalities
Technical Beliefs
Administrative policies and procedures
81. In order to achieve the project deliverables, the project manager must manage task
execution based on project management plan. In doing so, which of the following
elements should be considered?
SELECT THE CORRECT ANSWER
Budget and schedule
Leading and developing the project team
Quality and cost
Acquiring the team
82. You are managing a large diversified project team. In the initial days of the project,
the team members behaved like independent individuals and seemed reserved,
learning about their roles and responsibilities. Then, as the team began to work on the
project and participate in technical decisions, their trust level grew. The team
members now support each other's needs and work together. According to you, w hich
stage of team development is the team in?
SELECT THE CORRECT ANSWER
Norming
Performing
Forming
Adjourning
83. Which of the following is NOT a technique used in "develop project team" process?
SELECT THE CORRECT ANSWER
Training
Interpersonal Skills
Co-Location
Observation and Conversation.
84. You have delivered many complex and technically challenging projects in the past and
have won respect and appreciation for your work from the customers and senior
managers in the organization. Which form of power are you using?
SELECT THE CORRECT ANSWER
Formal (Legitimate)
Reward
Expert
Referent
85. You are managing a large project that has many stakeholders across various
departments in the organization. During the planning stage, you created a
communication management plan based on the project organization structure and
external stakeholder requirements in order to manage the flow of project information.
During project execution, one of the stakeholders contacts you and informs you that
his expectations have not been completely accounted for in the project. What should
be your BEST response to the situation?
SELECT THE CORRECT ANSWER
Understand his expectations and update project documents accordingly, starting with
stakeholder register
Since the stakeholder analysis has already been completed and all the other
stakeholders have been agreed to the project deliverables, the process cannot be
repeated for this stakeholder
Go through the stakeholder analysis with the team as there might be more unidentified
stakeholders in the project
Inform the stakeholder that he will be included in all project communications and he can
raise his concerns whenever he feels his requirements are not being addressed
86. A software project run in an IT company has 14 stakeholders and is in the final testing
stage. At this point, the technical architect leaves the project and two new test
engineers join. What is the change in the potential communication channels of the
project?
SELECT THE CORRECT ANSWER
Communication channel would remain unaffected by change in team members.
Number of communication channels will increase by 13.
Number of communication channels will increase by 26.
Number of communication channels will increase by 14.
87. Which of the following types of organizations would have the most complex
communication management?
SELECT THE CORRECT ANSWER
Functional Organization
Projectized Organization
Matrix Organization
Ad hoc Organization
88. You are a Project Manager of a software project that has finished the design stage and
is moving to the implementation stage. At the end of the design phase, you got the
document reviewed and you tracked and closed the defect logs. Also, as part of the
design stage review and kick-off for the implementation phase, you checked current
SPI and CPI and revisited the risks. What did you forget to do?
SELECT THE CORRECT ANSWER
Identify new risks for the next stage and update risk register
Take corrective and preventive actions from design review so that defects can be
minimized
Conduct an impact analysis of the defects found during the design review
Communicate project stage review findings to all the stakeholders.
89. In which of the following types of contracts does the buyer have the MAXIMUM cost
risk?
SELECT THE CORRECT ANSWER
Cost Reimbursable
Fixed Price
Time and Material
Cost Plus Fixed Fee
90. A cost reimbursable contract has an estimated cost of $20,000. If the seller beats the
cost, 80% of the savings will go to the buyer and 20% will go to the seller. If the
actual costs come in at $18,000, what is the final price?
SELECT THE CORRECT ANSWER
$18,000
$18,200
$18,400
$18,600
91. A project team is in the process of obtaining seller responses, selecting a seller, and
awarding a contract. For this purpose, the team is using some predefined selection
criteria to evaluate the bids and select the most appropriate seller. Which process of
project management is the project team working on?
SELECT THE CORRECT ANSWER
Plan Procurement Management
Conduct Procurements
Control Procurements
Proposal Evaluation
92. A Project Manager is involved in a procurement management process in a centralized
contracting environment. He is assigned a full-time contract manager who reports to
him for the project. In this scenario, which of the following is usually NOT the rol e of
the Project Manager?
SELECT THE CORRECT ANSWER
Provide increased expertise in contracting and also guide the team on standardized
company practices
Make sure the contract contains all project management requirements
Identify risks and incorporate mitigation and allocation of risks into contracts
Help tailor the contract to the unique needs of the project
93. A Project Manager is forced to give a contract to a preferred supplier as he has a strict
deadline to meet. What could be the BIGGEST risk in this situation for the Project
Manager?
SELECT THE CORRECT ANSWER
The seller has not proven that he has required expertise and resources to take this
assignment
The Project Manager didn't get a chance to evaluate other vendors who could be better
The seller may not fulfill the evaluation criteria to bid for the project
The seller may not meet acceptance criteria in the contract, and Project Manager might
have to accept what he gets
94. Your company is bidding for a major project from Company X. You have a friend in
Company X, and he requests your help in evaluating the proposals. What action
should you take?
SELECT THE CORRECT ANSWER
Accept the friend's request and work impartially while helping on the proposal
evaluation
Accept the friend's request and take care of your company's interests while helping on
the proposal evaluation
Reject the friend's request
Ask your Manager's opinion
95. As a Project Manager of a complex and relatively new technology, you have asked for
an expensive training for yourself and the team from the project sponsor. Although
the sponsor has agreed to your request, he asks you to start the project in the
meantime. Which of the following is NOT an option for you?
SELECT THE CORRECT ANSWER
Since you have already asked your sponsor for training, you can do nothing to enhance
your skills in the meantime
Visit PMO and Organization project database to go through lessons learned from
previous projects
Talk to fellow Project Managers who have executed similar projects in the organization
Join an organization or library to gain access to journals featuring the technology
96. A Project Manager has worked on many challenging projects and has managed teams
across the globe in the last 20 years of his career. Now, he intends to share his best
practices and lessons learned throughout his professional career. The Project Manager
is:
SELECT THE CORRECT ANSWER
Enhancing his professional skills by evaluating his experience and strengths
Contributing to the project management knowledge base
Capturing his professional stint in an autobiography
Informing others about project management principles and helping the profession grow
97. You work in a pharmaceutical company, and your client has shared some confidential
information with you. A medical university requests you to share the information
about the client for their research. What should you do?
SELECT THE CORRECT ANSWER
Share the information as it will be used purely for academic purposes
Share the information but hide all references that could expose the client
Never share any information about the client as you are bound by Non-Disclosure
Agreement
Contact your client and seek permission to disclose the information
99. A Project Manager defines a personal plan for his career and professional development
every year. As a part of this plan, he goes through his project experiences and lessons
learned and decides on the training needs to help him excel as a Project Manager and
contribute to his organization. In this scenario, the Project Manager is:
SELECT THE CORRECT ANSWER
Contributing to the Project Management knowledge base
Enhancing his Personal Professional Competence
Helping his organization through his project success
Putting the project's need before his own and making decisions in the best interest of
the project
100. Team development would be MOST difficult in a _______ organization.
SELECT THE CORRECT ANSWER
Weak Matrix
Projectized
Tight Matrix
Balance Matrix
102. One of the high-performing team members from a support group wants to
move on to the technical team as she finds that work more challenging. As a Project
Manager, you know that she is a valuable resource and moving her out of the support
group can affect group performance. You decide to give her a hike in salary. However,
the employee is still unhappy and dissatisfied. This is an example of _______ theory
SELECT THE CORRECT ANSWER
Maslow's
Herzberg's
McGregor's
Expectancy
103. A Project Manager is preparing for the next milestone release when he realizes
that he has missed an important feature in the project requirements plan. If
implemented, this feature would take at least one person a week of effort. What
should he do to address this?
SELECT THE CORRECT ANSWER
Discuss the change with Customer and seek his approval
Evaluate the impact of change on triple constraint
Look for alternatives to reduce the impact of change
Raise a change request to address the change through change control process
104. In negotiations, what is a fait accompli tactic?
SELECT THE CORRECT ANSWER
Making personal attacks that could be downright insulting
Playing the role of a good guy and bad guy in a team
Claiming an issue has already been decided and therefore cannot be changed
Hiding or partially disclosing information
106. Your customer asks for a small change in the project, which was not budgeted
initially. It is a small effort compared to the total project, and you need the goodwill of
the customer to be successful in a multi-million-dollar gas project. What will you do?
SELECT THE CORRECT ANSWER
Implement approved changes according to the change management plan to meet the
project requirements
Since you need to maintain goodwill, you agree to incorporate the change
Speak to the sponsor for his consent
Tell the customer to keep it a secret and not inform the sponsor about the change to be
implemented
107. During the project, you and your team discovered that a key project
component was stolen. As this was not planned for, the team decided to launch the
product without the stolen component. This is an example of:
SELECT THE CORRECT ANSWER
Work around
Risk Transfer
Risk Mitigation
Acceptance
108. During the project execution, the status report shows that an activity on the
critical path is delayed. As a Project Manager, what should you do?
SELECT THE CORRECT ANSWER
Deliver incomplete activity
Compress the schedule
Reduce the scope
Stop the project execution
109. As a Project Manager, you are assigned to a project that will be outsourced.
The next step is to organize a formal bidding process and select the vendor for the
project. You own stock in one of the vendor companies that participated in the bidding
process. What is the BEST course of action for you?
SELECT THE CORRECT ANSWER
Select the vendor company in which you own stock
Keep the information to yourself
Tell your manager and remove yourself from the vendor selection committee
Ask other members of the selection committee to select your vendor company
110. Which of the following is NOT a tool used in the "conduct procurements"
process?
SELECT THE CORRECT ANSWER
Bidders Conference
Independent Estimates
Procurement Negotiation
Contract Types
111. The Project Manager has discovered that two team members have had a
disagreement over the procurement of the project component. The Project Manager
suggests that the team members compromise. The team members are also willing to
resolve the conflict. Who should decide the best course of action?
SELECT THE CORRECT ANSWER
Sponsor
Customer
Project Manager
Team members
112. The primary communication skill the Project Manager will use when working
with the functional manager is:
SELECT THE CORRECT ANSWER
Problem Solving
Negotiation
Team Building
Public Relations
114. Herzberg divided motivation factors into two classes: satisfiers and
dissatisfiers. Examples of satisfiers are:
SELECT THE CORRECT ANSWER
Vacation time
Work satisfaction, fringe benefit
Plush offices space, performance-based salary hikes.
Sense of personal achievement, work satisfaction
115. A Project Manager is concerned about team building on her project. One of the
mandatory things that the project manager must have for good team building is:
SELECT THE CORRECT ANSWER
Commitment from top-level management
Co-location of team members
Establishment of clear negotiated goals
Open discussion of poor individual performance
-
116. A Project Manager is managing a project where there will be several persons
working together. She wants to enhance the ability of the team to work together and
perform as a team. One of the things she can do to enable this is:
SELECT THE CORRECT ANSWER
Cohabitation
Co-location
Staffing plan
WBS
117. Tom always delivers his projects on time and within budget. He believes that
his success can be explained by the fact that he makes all of the project decisions
himself and then enforces those decisions with an iron hand. His management style is
best described by:
SELECT THE CORRECT ANSWER
Force Field Theory
Expectation Theory
McGregor's Theory X
McGregor's Theory Y
119. A project is in the final stage of testing when it receives a major change
request from the customer. This would delay the final delivery of the project by 2
weeks. What should the Project Manager do NEXT?
SELECT THE CORRECT ANSWER
Create a change request and go through the change management process
Evaluate the impact of the change
Communicate the implication of the change to the customer
Adjust the project management plan and baseline
120. You are a Project Manager, and your team recently encountered a major
change in the project. This change was evaluated for its impact on the triple
constraints and went for approval to the Change Control Board (CCB). The CCB, which
is comprised of important stakeholders of the project, approved the change. The
project documents were updated through the configuration management system.
What should the project team do NEXT?
SELECT THE CORRECT ANSWER
Explore options to reduce the effect of change
Adjust the project management plan and baselines
Notify the stakeholders affected by the change
Prevent the root cause of change
121. A Project Manager working on a critical deliverable encounters a major change
that affects the schedule baseline and the next milestone deliverable. This change
cannot be accommodated within the current project management plan. What is the
BEST option for the Project Manager?
SELECT THE CORRECT ANSWER
Avoid the change as it gravely affects the project deadline
Explore options to reduce the effect of change
Communicate the implication of this change request to the customer
Seek approval from change control board or project sponsor
122. Measuring project performance using appropriate tools and techniques in order
to identify and quantify variances and corrective actions is part of _______ process
group.
SELECT THE CORRECT ANSWER
Planning
Executing
Monitoring and Controlling
Closing
124. During the project lifecycle, a Project Manager can change the schedule
baseline ONLY through:
SELECT THE CORRECT ANSWER
Customer-defined change in the schedule
Formally approved change through the change control process
Corrective action based on Performance Report
Project showing high deviation from the baseline
125. For a project, earned value = 600, Actual Cost = 400, and Estimate to
Completion= 700. What is the estimate at completion?
SELECT THE CORRECT ANSWER
1200
1100
1300
300
126. Your project is expected to be delayed by 6 days from the scheduled final
delivery date. Your current CPI is 1.5, and the project risks are low. You also have
many discretionary dependencies on the project. You don't have access to any more
resources for the project. Which of the following would be the BEST alternative to
bring the project back on schedule?
SELECT THE CORRECT ANSWER
Reduce the number of resources from an activity
Complete activities that involve external dependencies first
Remove a few activities from the project
Complete some activities concurrently
127. A Project Manager has to discuss project progress and track status with the
project team. Which of the following would be the MOST relevant format for this
purpose?
SELECT THE CORRECT ANSWER
Milestone Chart
Bar Chart
WBS
Schedule Baseline
128. A project has been severely delayed, and the Project Manager is trying his best
to bring it back on schedule. To expedite the work, he has added more resources and
has asked them to work overtime. Which of the following could NOT be a possible
outcome of crashing a project?
SELECT THE CORRECT ANSWER
Increase in Project Cost
Increase in Project Risk
Decrease in morale of team members
Increase in rewards and recognition
129. The project schedule should be measured against _______ to recommend
corrective and preventive actions.
SELECT THE CORRECT ANSWER
Schedule Baseline
Work Performance Measurement
Earned Value Technique
Variance Analysis
130. A project has initial budgeted cost, also called Budget at Completion (BAC), of
$100,000. As the project progresses, these are the current figures: Planned Value
(PV) is $20,000, Actual Cost (AC) is $25,000, and Earned Value (EV) is $15,000. What
is the Estimate at Completion (EAC), assuming the current variances are atypical of
the future?
SELECT THE CORRECT ANSWER
$110,000
$90,000
$100,000
$115,000
131. You are a Project Manager of a large and complex project that is partly
outsourced to a third party. Under these circumstances, your planned expenditure
sometimes overshoots the funding limits set for the project. As a Project Manager,
how do you best handle the situation?
132. You are working on a highly visible project for which it is critical to have
accurate cost estimates. While reviewing cost estimates for the project, you notice
that one of the WBS (Work Breakdown Structure) work packages is estimated at
almost 25% higher than two others similar WBS work packages. What should you do
in this case?
SELECT THE CORRECT ANSWER
Reduce the estimate but add an additional budget in management reserve
Reduce the estimate but add an additional budget in contingency reserve
Trust your team to come up with accurate estimates as they already had many team
discussions
Call the WBS owner to discuss the basis for estimating the work package
133. Your project has current CPI of 1.2 and SPI of 0.86. What does the figure
indicate about the project performance?
SELECT THE CORRECT ANSWER
The project has cost underrun and is delayed
The project has cost overrun and is delayed
The project has cost underrun and is ahead of schedule
The project has cost overrun and is ahead of schedule
135. A project has faced some unforeseen events that have affected its performance
with respect to cost and schedule. However, they are not bound to continu e in the
future. What is the value of Estimate at Completion (EAC)? Here, BAC is Budget at
completion, AC is Actual Cost, CPI is Cost Performance Index, and EV is earned Value.
SELECT THE CORRECT ANSWER
BAC/CPI
AC + ETC
AC + (BAC-EV)/CPI
AC + (BAC-EV)
138. You are heading a software development project team that has many new
members working for the first time. You ensure that the team diligently gets its work
products reviewed by an external reviewer and closes the defects before moving to
the next stage. However, the last few review reports have captured a high number of
defects, including many careless mistakes. According to you, what is the root cause of
the problem?
SELECT THE CORRECT ANSWER
Since most of the team members are new and inexperienced, a high number of defects
are expected
The team has, in all probability, not completely understood the scope of the work
The review is not efficient as most of the defects are not valid
The team is not doing proper self-review before submitting the work
139. A popular tool used to monitor project performance, including cost and
schedule variances, and ensure that process operates within acceptable limits is
called:
SELECT THE CORRECT ANSWER
Control Chart
Run Chart
Pareto Chart
Flowchart
140. A project team is analyzing a major, critical defect to determine the root cause.
In order to do this, the team considered various factors linked to the defect and
grouped them into categories such as Machine, Method, Material, and Manpower.
Which of the following tools of quality is the team using?
SELECT THE CORRECT ANSWER
Histogram
Cause and Effect Diagram
Control chart
Flowchart
141. Which of the following CANNOT be considered an indicator of a team's
effectiveness?
SELECT THE CORRECT ANSWER
Improvements in skills that allow the team to perform assignments more effectively
Improvements in competency that help the team perform better
Increased staff turnover rate
Increase in team cohesiveness and trust
142. During the testing phase in the project, a senior manager, who is also an
important stakeholder in the project, tells you that he no longer wishes to receive
weekly status reports. Instead, he wants periodical project performance reports. What
should your response be to his request?
SELECT THE CORRECT ANSWER
Make the manager understand that since he is a major stakeholder and the project is in
a critical stage, status reports will be important to know project progress
Continue to send him status reports to keep your project visibility high
Follow communication management plan and send reports as decided earlier
Follow his instructions and update project documents, including communication
management plan, accordingly
146. A senior technology manager in the organization wants to know the project
status with respect to major deliverables and key external interfaces. Which format
should the project manager use in his performance report to capture this graphically?
SELECT THE CORRECT ANSWER
Project Schedule Network Diagram
Milestone Chart
Bar Chart
S curve
147. During the audit, you realize that many of the risks were not identified during
the planning stage, so you decide to reassess project risks. Which process are you in?
SELECT THE CORRECT ANSWER
Identify Risks
Plan Risk Management
Perform Quantitative Risk Analysis
Monitor Risks
148. As a Project Manager, you have instructed your project team to update the
organizational process assets, including the "lessons learned" database and risk
management template of future projects, based on project audit findings. You are in
_______ process of project management.
SELECT THE CORRECT ANSWER
Control Procurements
Close Contracts
Monitor Risks
Perform Quality Assurance
149. A project has been delivered according to the contract by the project team;
however, the customer is not happy. The customer feels that the deliverable has some
serious defects and is far below expectations in terms of quality and functionality.
What should the Project Manager do in this situation?
SELECT THE CORRECT ANSWER
Talk to the project sponsor to discuss the issue
Proceed to project closure activity
Discuss the issues with the customer and find ways to resolve them
Brainstorm with technical experts, stakeholders, and team members to understand
issues in the project
150. A Project Manager notices that the seller has discontinued sending the weekly
status report, which is part of their contract. The Project Manager understands that
the seller is under tremendous pressure to meet the next milestone deliverables and
has been otherwise communicating the project status periodically. What should the
Project Manager do in this scenario?
SELECT THE CORRECT ANSWER
Ignore the incident as the seller is updating him about the project status periodically
Give the seller time until next milestone delivery and then bring up the issue informally
Send a formal, written communication regarding the issue of irregular status reports
Terminate the project contract
151. A Project Manager has signed a contract with the buyer and project is moving
toward completion. At this stage, the Project Manager realizes that he has missed an
important functionality in the product and the contract needs to be changed to
accommodate that. How should the Project Manager proceed to resolve this?
SELECT THE CORRECT ANSWER
Since the Project Manager has already signed the contract and the project is nearing
completion, this change need not be updated in the project
The Project Manager shall communicate the change request and its implication to the
seller in a meeting
The Project Manager can bring up this deviation during Procurement Performance
Review
The Project Manager should raise a formal change order that is signed by both the
parties to incorporate the change
152. A Project Manager has taken up a project midway and is going through project
schedules and status reports. He realizes that the previous Project Manager has
inaccurately calculated the project status and that the project would miss the next
milestone. What should the Project Manager do in this case?
SELECT THE CORRECT ANSWER
Call the previous Project Manager and ask him for an explanation
Inform the customer and stakeholder about the impeding delay
Look at the project schedule again to find alternatives to meet the schedule
Wait for the next milestone date to arrive to report the delay
153. A Project Manager wants to qualify for the PMP examination. However, while
going through the eligibility criteria, he finds that he falls short of the required
experience by a small margin. He discusses this with a certified PMP professional and
mentions that he is planning to lie about his experience as it is a very small margin.
The PMP professional is not convinced and warns him that he should not provide fals e
information at any point during the PMI Certification Program as it can result in:
SELECT THE CORRECT ANSWER
Revocation of your PMI membership
Revocation of your PMP certification
Both above are true
No impact
154. You are a Project Manager of a dynamic project team. Recently, there have
been some changes in the team structure, and you don't know if they would positively
or negatively affect the project. What is the BEST approach to address this?
156. A Project Manager wants to present project performance reports of his project.
Which of the following formats should he use?
SELECT THE CORRECT ANSWER
Pareto Chart
Responsibility Assignment Matrix
Bar Chart
Control Chart
157. While monitoring and controlling the projects, why is it necessary to manage
changes to the project by following the change management plan?
SELECT THE CORRECT ANSWER
To satisfy the customer
To align project goals with business needs
To satisfy project requirements
To satisfy the sponsor
159. An assembly line in a car manufacturing plant produces 250 components in one
shift. The QA randomly picks 10 of them for quality checking. This is an example of:
SELECT THE CORRECT ANSWER
Quality Audit
Inspection
Process Control
Process Analysis
160. As a part of the Monitoring and Controlling process group, you and your project
team have listed and are assessing the corrective actions in the issue register. What is
the NEXT step that you will perform?
SELECT THE CORRECT ANSWER
Determine steps to resolve issues by using appropriate tools to minimize the impact on
project cost, schedule, and resources
You have already listed the corrective actions and it is now the customer's responsibility
to decide the resolutions
Follow the Change control method
Communicate the corrective actions to the stakeholders
161. What is the key purpose of the Monitoring and Controlling process group?
SELECT THE CORRECT ANSWER
Measure project performance in order to identify and quantify any variances and
perform approved corrective actions
Perform preventive actions so that no variances ever occur in the project lifecycle
Conduct daily status meetings
None of the above
162. A project is terminated unexpectedly by the sponsor midway during the
execution phase. What should the Project Manager do FIRST?
SELECT THE CORRECT ANSWER
Update the process and templates based on lessons learned
Create and Distribute the final report of project performance
Analyze and document success and effectiveness of the project
Perform scope verification to verify level of completion
163. A Project Manager has just finished a Gantt (bar) chart representing the project
schedule. Which of the following documents does NOT get updated?
SELECT THE CORRECT ANSWER
Activity Resource Requirement
Risk Register
Resource Leveling
Calendar
164. Documentation of lessons learned is important in any project and forms the
main input to organizational process assets. In fact, continuous improvement of the
project management process cannot occur without lessons learned. This process is
completed by the project team and is BEST done:
SELECT THE CORRECT ANSWER
At the end of project completion stage before contract closure
Whenever the project implements any corrective action as part of Audit closure
As a part of corrective and preventive action, according to recommendations of the QA
Throughout the project, and finalized during project phase closing
165. A Project Manager is in the 'Control Procurements' process when his sponsor
asks him to terminate the contract. What should the Project Manager do NEXT?
SELECT THE CORRECT ANSWER
Revisit the Proposal Evaluation technique to understand issues with the seller
Update Records Management System
Proceed with Procurement Audit
Arrange Vendor conferences to invite new proposals to the contract
168. The Project Manager has obtained final acceptance of the project deliverables
by the customer. Which of the following is NOT an activity of the "project closing"
process?
SELECT THE CORRECT ANSWER
Collate lessons learned and update the organization's knowledge base
Distribute the final project report to all the stakeholders
Transfer ownership of deliverables to assigned stakeholders
Assess old risks and update risk register
172. Customer satisfaction should be measured at the end of the project to maintain
long-term relationships. Which of the following is NOT always an aspect of customer
satisfaction?
SELECT THE CORRECT ANSWER
The product meets its stated and unstated requirements
The project is profitable
The product is high quality
The customer's needs are met
173. At the close of your project, you measure the customer satisfaction and find
that some customer needs were not fully met. Your supervisor asks you the steps you
will take during your next project to improve customer satisfaction. Which subsidiary
plan would you consult to determine this information?
SELECT THE CORRECT ANSWER
Quality management plan
Communications management plan
Staffing management plan
Risk management plan
174. Your client has terminated your project before it has been completed. Which of
the following is true?
SELECT THE CORRECT ANSWER
You must stop all work and release the team immediately
You must work with the team to document the lessons learned
You must keep the team working on the project to give your senior management time
to talk to the client
You must update the project management plan to reflect this change
175. Your project team has completed the project work. Which of the following is
NOT done before the project is closed?
SELECT THE CORRECT ANSWER
Ensure that the schedule baseline has been updated
Get formal acceptance of the deliverables from the customer
Make sure that the scope of the project was completed
Verify that the product acceptance criteria have been met
176. Which of the following Quality Theorists advocated the 80/20 principle?
SELECT THE CORRECT ANSWER
W Edwards Deming
Philips Crosby
Joseph Juran
Walter A Shewhart
-
179. The aim of quality is to:
SELECT THE CORRECT ANSWER
Ensure fitness to use and conformance to requirements
Meet customer requirements
Fulfill quality objectives
Lower cost of quality
180. A network diagram drawing method that allows loops between activities is:
SELECT THE CORRECT ANSWER
Precedence Diagramming Method (PDM)
Arrow Diagramming Method (ADM)
Program Evaluation and Review technique (PERT)
Graphical Evaluation and Review Technique (GERT)
181. An organization has created a special project team to handle a critical project.
The team members of this project are dedicated full-time to the project and are pulled
from different functional departments. They also have their own set of operating
procedures. This organization structure is MOSTLY:
SELECT THE CORRECT ANSWER
Projectized
Functional
Composite
Matrix
182. What is the 100% rule in the Work Breakdown Structure creation?
SELECT THE CORRECT ANSWER
The total work at lowest level adds up to the higher levels, so no work is left out and no
extra work is completed
80% of the problems can be attributed to 20% of the causes
WBS must be detailed enough to cover 100% of the work since the beginning of the
project
WBS must contain 100% deliverables, both internal and external
186. Which of the following is NOT true about a weak matrix organization?
SELECT THE CORRECT ANSWER
Communication will be more complex
The team members may not always have a home
The team members may get directions from multiple people
Team members may not report to the Project Manager
187. An activity that does NOT require work or time and is inserted simply to show
dependency between activities is called:
SELECT THE CORRECT ANSWER
Milestone Activity
Critical Activity
Hammock Activity
Dummy Activity
196. Which of the following statements describes the relationship between project
phases and the project life cycle?
SELECT THE CORRECT ANSWER
The project lifecycle contains the iterative incremental elements of a project phase
Collectively, the project phases are known as the project life cycle
The project lifecycle is regarded as a sequence of project activities, while phases are
defined to control the overlapping of activities
The project lifecycle contains the repetitive elements inside a project phase
197. Which of the following is NOT true with regard to ROI (Return on Investment)?
SELECT THE CORRECT ANSWER
It defines the cumulated net income from an investment at a given point in time or
during a defined period.
It includes investment and direct and indirect costs and may include allowances for
capital cost, depreciation, risk of loss, and/or inflation
It is generally stated in currency units, as a percentage, or as an index figure.
It is the time when cumulated net income is equal to the investment.