Proyecto : " MEJORAMIENTO DE CAMINO VECINAL ENTRE LAS LOCALIDADES DE LA SACILIA - CHOLOQUE"
Ubicación : CAJAMARCA - CUTERVO - TORIBIO CASANOVA
Fecha : DICIEMBRE 2011
N° DIAS
CUADRILLAS REQUER.
ITEM PARTIDAS RENDIM. UNIDAD METRADO N° DE DIAS
1.00 CAMINO VECINAL (4.36 KM)
1.00 TRABAJOS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS 0.00 GB/DIA 1.00
1.02 FABRICACION TRANQUERAS P/SE¥ALIZACION 1.00 UND/DIA 4.00 4.00 1.00 4.00
1.03 CARTELES TIPO ROMBO 4.00 UND/DIA 4.00 1.00 1.00 1.00
1.04 CAMPAMENTO PROVISIONAL DE OBRA 25.00 M2/DIA 24.00 1.00 1.00 1.00
1.05 CARTEL DE IDENTIFICACION DE OBRA 0.50 UND/DIA 1.00 2.00 1.00 2.00
1.06 LIMPIEZA Y DESBROCE DE TERRENO 6500.00 ML/DIA 4360.00 0.70 1.00 1.00
1.07 TRAZO Y REPALNTEO DEL EJE 0.50 KM/DIA 4.36 8.70 1.00
1.08 1IMPIEZA DE ACCESO A CANTERAS 1.00 GB/DIA 2.00 2.00 1.00 2.00
4 ALIVIADEROS DE CUNETAS
4.01 TRAZO Y REPLANTEO PRELIMINAR 200.00 M2/DIA 110.79 0.60 1.00 1.00
4.02 EXCAVACION MANUAL EN MATERIAL SUELTO 4.00 M3/DIA 0.00 0.00 1.00 0.00
4.03 NIVELACION Y COMPACT. CIMENTACION EN M.S 240.00 M3/DIA 110.69 0.50 1.00 1.00
4.04 ENCOFRADO Y DESENCOFRADO DE CABEZALES 12.00 M3/DIA 220.71 18.40 3.00 6.00
4.05 ACERO DE REFUERZO FY=4200 KG/CM2 200.00 M2/DIA 1225.40 6.10 2.00 3.00
4.06 CONCRETO F'C=175 KG/CM2 18.00 KG/DIA 26.54 1.50 1.00 2.00
4.07 ARMADO E INSTALACION DE ALCANTARILLA TMC 12.00 M/DIA 36.45 3.00 1.00 3.00
4.08 RELLENO Y COMPACTACION CON MATERIAL PROP 40.00 M3/DIA 45.68 1.10 1.00 1.00
4.09 ELIMINACION DE MATERIAL EXCEDENTE D=30M 6.00 M3/DIA 89.08 14.80 4.00 4.00
4.10, EMBOQUILLADO DE PIEDRA E=0.20 30.00 M2/DIA 16.52 0.60 1.00 1.00
4.11 SOLADO DE AFIRMADO E= 0.20 M 120.00 M2/DIA 36.99 0.30 1.00 1.00
4.12 CAMA DE APOYO E=0.10 M CON MATERIAL PROP 120.00 M2/DIA 48.60 0.40 1.00 1.00
6.00 AREAS VERDES GLB S/. 234,883.68 0.00 0.00 0.00 0.00
7.00 AMBIENTES ADMINISTRATIVOS Y DE SERVICIOS GLB S/. 87,751.19 0.00 0.00 0.00 0.00
8.00 INSTALACIONES SANITARIAS Interior de Cementerio GLB S/. 9,163.53 0.00 0.00 0.00 0.00
9.00 INSTALACIONES ELECTRICAS GLB S/. 10,019.63 0.00 0.00 0.00 0.00
EJECUCIÓN FISICA DE OBRA S/. 6,742,171.54 S/. 171,362.84 S/. 207,604.22 S/. 207,604.24 S/. 1,512,085.96
2.12% 2.57% 2.57% 18.72%
13.00 EXPEDIENTE TECNICO S/. 70,851.91
14.00 ESTUDIO DE IMPACTO AMBIENTAL S/. 35,019.69
15.00 UTILIDAD S/. 0.00
16.00 CIRA S/. 58,366.15
17.00 IGV S/. 1,172,023.88
COSTO INDIRECTO S/. 1,336,261.63
% VALORIZADO DE COSTO INDIRECTO 16.54%
AVANCE DE OBRA ACUMULADO S/. S/. 1,507,624.47 S/. 1,715,228.69 S/. 1,922,832.93 S/. 3,434,918.92
AVANCE DE OBRA ACUMULADO % 18.66% 21.23% 23.8% 42.5%
COSTO TOTAL DE OBRA S/. 8,078,433.17
QUINTO MES SEXTO MES SETIMO MES OCTAVO MES TOTAL
4° SEM. SUBTOTAL 1° SEM. 2° SEM. 3° SEM. 4° SEM. SUBTOTAL 1° SEM. 2° SEM. 3° SEM. 4° SEM. SUBTOTAL 1° SEM. 2° SEM. 3° SEM. 4° SEM. SUBTOTAL S/.
0.00 0.00 0.00 0.00 343709.40
280657.47 1122629.88 280657.47 280657.47 280657.47 280657.47 1122629.88 280657.47 280657.47 561314.94 0.00 3929204.58
7.14% 7.14% 7.14% 7.14% 7.14% 7.14% 7.14%
83165.77 332663.08 83165.77 83165.77 83165.77 83165.77 332663.06 83165.77 83165.77 166331.54 0.00 1164320.74
7.14% 7.14% 7.14% 7.14% 7.14% 7.14% 7.14%
0.00 50159.01 50159.01 100318.02 50159.01 50159.01 50159.01 50159.01 200636.04 50159.01 50159.01 100318.02 401272.08
12.50% 12.50% 12.50% 12.50% 12.50% 12.50% 12.50% 12.50%
0.00 29360.46 29360.46 58720.92 29360.46 29360.46 29360.46 29360.46 117441.84 29360.46 29360.46 58720.92 234883.68
12.50% 12.50% 12.50% 12.50% 12.50% 12.50% 12.50% 12.50%
0.00 0.00 14625.20 14625.20 14625.20 14625.20 58500.80 14625.20 14625.20 29250.40 87751.20
16.67% 16.67% 16.67% 16.67% 16.67% 16.67%
120.00%
100.00% 100.00%
96.35%
81.92%
80.00%
42.52%
40.00%
23.80%
20.00% 21.23%
18.66%
0.00% 0.00%
INICIO PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES SETIMO MES OCTAVO MES
PLAZO DE EJECUCION (MESES)
0.00% 0.00%
INICIO PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES SETIMO MES OCTAVO MES
PLAZO DE EJECUCION (MESES)
PROYECTO: “MEJORAMIENTO DEL SERVICIO DE INHUMACION DEL CEMENTERIO JARDINES DE LA PAZ DE LA LOCALIDAD DE TUCUME, DISTRITO DE TUCUME,
PROVINCIA DE LAMBAYEQUE – DEPARTAMENTO DE LAMBAYEQUE”.
Ubicación : LAMBAYEQUE - LAMBAYEQUE - TUCUME
Fecha
AVANCE ACUMULADO COSTO DIRECTO (S/.) : ABRIL 2014
8000000.00 8078433.17
7783943.83
7000000.00
6618129.84
6000000.00
5000000.00
4000000.00
Column F
3434918.92
3000000.00
2000000.00 1922832.93
1715228.69
1507624.47 1512086.00
1000000.00
0.00 0.00
INICIO PRIMER MES SEGUNDO TERCER MES CUARTO MES QUINTO MES SEXTO MES SETIMO MES OCTAVO MES
MES
25.00%
20.69%
20.00%
18.66% 18.72% 18.72%
15.00%
14.43%
10.00% Column F
5.00%
3.65%
2.57% 2.57%
0.00% 0.00%
INICIO PRIMER MES SEGUNDO TERCER MES CUARTO MES QUINTO MES SEXTO MES SETIMO MES OCTAVO MES
MES