Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
The S curve can be considered as an indicator and it's used for many
applications related to project management such as: target, baseline,
cost, time etc.
Variety of S-Curve
The Man Hours versus Time S Curve is appropriate for projects that are labour
intensive. It shows cumulative man hours expended over time for the duration of
the project. As man hours are a product of man power and working hours, these
may be adjusted together or individually in an attempt to keep the project on
schedule. Projects may require additional man hours to finish on time due to low
productivity, delays and disruptions, rework, variations, etc.
Cost S - Curve
The Costs versus Time S Curve is appropriate for projects that contain
labour and non-labour (e.g. material supply / hire / subcontract) tasks. It
shows cumulative costs expended over time for the duration of the
project, and may be used to assist in the calculation of the project's
cashflow, and cost to complete.
Baseline S - Curve
Prior to project commencement, a schedule is prepared outlining the
proposed allocation of resources and the timing of tasks necessary to
complete the project within a set time frame and budget. This schedule is
referred to as the Baseline Schedule. From this schedule, a Baseline S
Curve is generated. This S Curve reflects the planned progress of the
project. If the project requirements change prior to commencement (eg.
change of scope, delayed start), the Baseline Schedule may require
revision to reflect the changed requirements.
Target S - Curve
Following project commencement, modification of the Baseline Schedule is usually
required. Changes are continually made to the Production Schedule (which is
originally the same as the Baseline Schedule). The production schedule reflects the
actual progress of the project to date, and any revisions made to tasks yet to
commence or not yet completed. From this schedule, a Target S Curve may be
generated. This S Curve reflects the ideal progress of the project if all tasks are
completed as currently scheduled. In an ideal world, the Target S Curve will meet
the Baseline S Curve at the end of the project (On Time, On Budget) or finish below
and to the left of the Baseline S Curve (Early, Under Budget). In reality, it is not
uncommon for the Target S Curve to finish above and to the right of the Baseline S
Curve (Late, Over Budget).
Actual S - Curve
The production schedule is updated on a regular basis throughout the duration of
the project. These updates include the revision of percentage complete for each
task to date. Using this information, an Actual S Curve may be generated. This S
Curve reflects the actual progress of the project to date, and may be compared
with the Baseline and Target S Curves to determine how the project is progressing.
During the project, the Actual S Curve will terminate at the Cut Off Date. This is the
date the Production Schedule was last updated. At the completion of the project,
the Actual S Curve will meet the Target S Curve.
Sample Project S - Curve
% or COST etc.
Actual
ACTUAL
TIME
Construct a Gantt Chart with superimposed S-Curve base from the given
data.
3. Knowing the duration of project from step 1, construct the Gantt chart
based from the respective duration and precedence the activities.
Note: - Each cell is equivalent to single duration
A C E H
2 4 6
4 5 2 8
START
1 J 0 K 0 G 4
D 10 7 END
B F I
3 5
7 6 9
ACT PRECEDES DUR COST
A C, D, F 4 Php 10,000
B D, F 7 Php 20,000
C E, G, I 5 Php 15, 000
D E, G, I 10 Php 100,000
E H 2 Php 45,000
F G, I 6 Php 60,000
G H 4 Php 40,000
H END 8 Php 40,000
I END 9 Php 45,000
4 9 19
A C E H
2 4 6
4 5 2 8
0 17 21
29
START 1 J 0 K 0
D 10 G 4 7 END
0
4 17 26
B F I
7 3 13 5
7 6 9
ACT PRECEDES DUR COST
A C, D, F 4 Php 10,000
B D, F 7 Php 20,000
C E, G, I 5 Php 15, 000
D E, G, I 10 Php 100,000
E H 2 Php 45,000
F G, I 6 Php 60,000
G H 4 Php 40,000
H END 8 Php 40,000
I END 9 Php 45,000
4 12 9 19 19 21
A C E H
2 4 6
4 5 2 8
0 3 7 17 17 21 29 29
START 1 J 0 K 0
D 10 G 4 7 END
0 0
4 17 29 26
7 17
B F I
7 3 13 5
7 11 6 20 9
ACT PRECEDES DUR COST
A C, D, F 4 Php 10,000
B D, F 7 Php 20,000
C E, G, I 5 Php 15, 000
D E, G, I 10 Php 100,000
E H 2 Php 45,000
F G, I 6 Php 60,000
G H 4 Php 40,000
H END 8 Php 40,000
I END 9 Php 45,000
4 12 9 19 19 21
A C E H
2 4 6
4 5 2 8
0 3 7 17 17
21 29 29
START 1 J 0 K 0
D 10 G 4 7 END
0 0
4 17 26
7 17
B F I
7 3 13 5
7 11 6 20 9
Steps in constructing Gantt Chart with S-curve
1. Construct the PERT/CPM to verify the precedence of activities.
3. Knowing the duration of project from step 1, construct the Gantt chart
based from the respective duration and precedence the activities.
Note: - Each cell is equivalent to single duration
Determine the up to date overall status of the project based from the
given data below.