STRUCTURAL DEFECTS

Item Photo Location Defects Target Date of Completion


1
2nd sty GL 18:19 to A:C RC Parapet wall Casted to high, need to Maincon and Subcon to recheck
trim the level of the parapet wall if
need to trim or not, before July
17, 2019

2 2nd sty GL 15:18 to A RC Parapet wall Casted to high, need to Maincon and Subcon to recheck
trim the level of the parapet wall if
need to trim or not, before July
17, 2019

3 2nd sty mezzanine Beam to grind ang hack all excess July 16, 2019
GL 14:15 to A:B cement grout

4 2nd sty Lift F Lift opening expose rebar, to cast back July 13, 2019
GL 14;15 to F:F'

5 2nd sty mezzanine Beam to grind ang hack all excess July 16, 2019
GL 14:15 to A:B cement grout

6 2nd sty GL 07:18 to M RC Parapet wall to hack and grind all July 15, 2019
excess cement grout

7 2nd sty staircase B staircase construction joint need to July 13, 2019
GL 14:15 to M close, beam to hack and grind all excess

8 2nd sty GL 10:12 to G RC Parapet wall to hack and grind all July 15, 2019
excess cement grout

9 2nd sty GL 07:18 to M RC Parapet wall to hack and grind all July 15, 2019
excess cement grout

10
2nd sty GL 12:14 RC Parapet wall to patch back with July 16, 2019
cement grout

11
2nd sty all units To put backing rod and cement grout at July 15, 2019
the side of the unit staircase
STRUCTURAL DEFECTS
12 July 18, 2019
1st sty to 2nd sty Staircase B To hack and grind all cement grout at
staircase landing and steps

13 To put backing rod and cement grout at July 15, 2019


2nd sty all units
the side of the unit staircase

14 2nd sty all units Formworks and other materials inside July 17, 2019
of unit sump. to take out all rubbish

15 2nd sty Staircase K To cast the rc kerb July 15, 2019

16 July 18, 2019


2nd sty and 2nd sty mezzanine LIft walls and ceilings to grind and
all the lift walls hack all loose concrete and cement
grout. to patch back all holes.

17 2nd sty and 2nd sty mezzanine LIft walls and ceilings to grind and July 18, 2019
all the lift walls hack all loose concrete and cement
grout. to patch back all holes.

18 3rd sty Lift L July 16, 2019


Cut all extra rebars

19 RC Parapet wall Casted to high, need to Maincon and Subcon to recheck


3rd sty GL 05:18 to A
trim the level of the parapet wall if
need to trim or not, before July
17, 2019

20 3rd sty Lift L LIft walls and ceilings to grind and July 18, 2019
hack all loose concrete and cement
grout. to patch back all holes.

21 Cut all extra rebars


3rd sty and 3rd sty mezzanine July 18, 2019
corridors

22 3rd sty to 3rd sty mezzanine To patch back the beam with
cement grout July 13, 2019
staircase K
STRUCTURAL DEFECTS
23 Cut all extra rebars
3rd sty Lift C July 16, 2019

24 Cut all extra rebars July 16, 2019


3rd sty and 3rd sty mezzanine
corridors

25 3rd sty GL 18:19 to A:C RC Parapet wall Casted to high, need to Maincon and Subcon to recheck
trim the level of the parapet wall if
need to trim or not, before July
17, 2019

26
3rd sty to 3rd sty mezzanine Lift opening expose rebar, to cast back July 13, 2019
Lift F
GL 14;15 to F:F'

27 Maincon and Subcon to recheck


3rd sty mezzanine RC Parapet wall Casted to high, need to the level of the parapet wall if
GL 04:18 to A trim need to trim or not, before July
17, 2019

28 3rd sty mezzanine RC Parapet wall Casted to high, need to Maincon and Subcon to recheck
GL 04:18 to M trim the level of the parapet wall if
need to trim or not, before July
17, 2019

29 3rd sty mezzanine RC Parapet wall Casted to high, need to Maincon and Subcon to recheck
GL 04:18 to F trim the level of the parapet wall if
need to trim or not, before July
17, 2019

30 3rd sty and 3rd sty mezzanine Cut all extra rebars
July 13, 2019
corridors

31 3rd sty mezzanine RC Parapet wall Casted to high, need to Maincon and Subcon to recheck
GL 04:18 to G trim the level of the parapet wall if
need to trim or not, before July
17, 2019

32 Maincon and Subcon to recheck


3rd sty GL 15:17 to F RC Parapet wall Casted to high, need to the level of the parapet wall if
trim need to trim or not, before July
17, 2019

33 RC Parapet wall Casted to high, need to Maincon and Subcon to recheck


3rd sty GL 09:17 to F trim the level of the parapet wall if
need to trim or not, before July
17, 2019
STRUCTURAL DEFECTS
34 Maincon and Subcon to recheck
3rd sty mezzanine RC Parapet wall Casted to high, need to
GL 18:19 to A:C trim the level of the parapet wall if
need to trim or not, before July
17, 2019

35 3rd sty and 3rd sty mezzanine Cut all extra rebars
July 13, 2019
corridors

36
3rd sty Loading / Unloading bay To trim bulging at the column July 16, 2019
GL 10 to J

37 July 18, 2019


3rd sty GL 19 to J:K Cut all extra rebars

38
3rd sty to 3rd sty mezzanine Bulging at the beam and columns, to trim July 22, 2019
GL 10 to K:M all bulging

39 July 18, 2019


4th sty mezzanine GL 14:15 to A:B To grind and hack all excess cement
grout at the ceiling

40 4th sty mezzanine GL 04:05 to Bulging at mezzanine beam and colum July 13, 2019
K:M to trim and patch back using cement

41 July 18, 2019


4th sty mezzanine GL 12:13 to K Bulging at mezzanine beam to trim and
patch back using cement grout

42 4th sty mezzanine GL 14:15 to Honeycomb at beam mezzanine, to July 18, 2019
A:B hack the beam and clean put bonding

43 4th sty mezzanine GL 14:15 to A:B To grind and hack all excess cement
July 18, 2019
grout at the ceiling

44 Bulging at column to trim and patch July 18, 2019


4th sty mezzanine
back using cement grout
STRUCTURAL DEFECTS
45 July 18, 2019
4th sty to 4th mezzanine staircase K Staircase K steps not align to trim
excess cement grout

46 4th sty mezzanine staircase K Bulging at wall to trim and patch back
July 13, 2019
using cement grout

47 Bulging at column and beam to trim


4th sty to 4th mezzanine July 22, 2019
and patch back using cement grout

48 4th sty to 4th mezzanine Cut all extra rebars


July 13, 2019

49 4th sty mezzanine Bulging at column to trim and patch


July 19, 2019
back using cement grout

50 To trim and grind all cement grout at July 18, 2019


4th sty to 4th mezzanine Lift C
the wall, and patch back all the holes.

51 July 18, 2019


4th sty to 4th mezzanine Lift M To trim and grind all cement grout at
the wall, and patch back all the holes.

52 4th sty to 4th mezzanine Lift M To trim and grind all cement grout at July 18, 2019
the wall, and patch back all the holes.

53 4th mezzanine GL 11:12 to L:M Ceiling got water leaking, to put P.U. July 13, 2019
grout

54 5th sty mezzannine To trim and grind all cement grout at July 13, 2019
staircase K the wall, and patch back all the holes.

55 5th sty mezzanine Beam mezzanine to hacking all cement July 19, 2019
all units grout and patch back all holes.
STRUCTURAL DEFECTS
56 RC parapet wall to remove all cement July 19, 2019
5th sty GL 14:15 to A:C
grout

57 5th sty GL 10:11 to K:M RC parapet wall to remove all cement July 19, 2019
grout and patch back all holes

58 5th sty and 5th sty mezzanine RC parapet wall to remove all cement
July 19, 2019
grout and patch back all holes

59 3rd sty to 3rd sty mezzanine Bulging at the beam and columns, to trim July 22, 2019
GL 10 to K:M all bulging