RATE ANALYSIS

A GLANCE AT BASIC INFO REQUIRED FOR


RATE ANALYSIS !

www.civil4m.com
RATE ANALYSIS

 DEFINATION –
It is a method of deriving the construction cost of any
particular completed item per unit ,by considering the
cost of material ,labour , machineries and other
miscellaneous costs involved in the execution of the
item .

www.civil4m.com
RATE ANALYSIS

 Normally contractors profit ,at the rate 10 % to 20% is


added to the actual rate of quoting ,for the final rate of
the particular item .
 This Rate analysis for the completed items is required for
calculating the abstract of quantities .
 Rate analysis can be based on practical considerations as
per the local method of measurement of work ,scope of
labour work in item etc .
 Basic considerations may change from place to place
,contractor’s profits , contingencies etc and may vary as
per the conditions of contracts ,work place etc .

www.civil4m.com
BASIC INFORMATION REQUIRED FOR RATE
ANALYSIS

 The unit of that particular item i.e number,square feet


,cubic feet ,sq mt or cu.m etc .
 Rates of materials required as delivered at the site
,including transportation charges , all taxes etc
 Actual labour required to execute that standard
unit/work from available task work chart / available
labour rates .
 Running ,hiring and operational cost of machinery
,charges of tools and tackles .

www.civil4m.com
HOW TO PREPARE RATE ANALYSIS ?

RATE ANALYSIS

FOR : SITE ADDRESS : DATE


Item no Code No :
Description
Sr.No Quantity Rate per Amount Remarks
1 Materials
a]
b]
c]
d]
2 Labourers
a]
b]
c]
d]
3 Centering & Shuttering
Providing good specified material &
dismantling etc

4 Others
a]
b]
c]
d]
TOTAL {A}
5 Tools & Plants @ 1.5 - 2 % on {A}
6 Watercharges @ 1.0 % on total {A} TOTAL {B}
7 Overhead & Profit @ 10- 15% on total {B}
TOTAL

www.civil4m.com
HOW TO PREPARE RATE ANALYSIS ?

 Considering the above points in mind the following


format should be prepared and as per your site
situations and demands .
 Alongwith ,Descriptions of materials ,specifications
,work procedures ,Terms & conditions of execution
of work etc . Should be written .
 Since rates of materials and laboureres vary from
place to place the rates of different items of work also
vary .
 Hence ,preparing rate analysis is important for
finding out the exact rate of the concerned item .

www.civil4m.com
IMPORTANCE OF PREPARING RATE
ANALYSIS

 IT helps in preparing estimates of new projects .


 It helps in quoting for tenders ,comparing with other
tenders and similar projects .
 It guides to comparing actual expenditure vs the
estimated expenditure
 It helps in calculating completed item costs for extra
amenities .

www.civil4m.com
RESPONSIBILITIES OF ESTIMATION
ENGINEER

 ESTIMATION
 Work out the detailed quantities of the items .collect
and check all the updated drawings and thoroughly
study the drawings.
 Find out the costs per square meter of the various
items for various projects .
 Work out labour expenses and other expenses which
occur during construction i.e site development ,plot
development ,sanction expenses ,consultants and
other legal expenses.

www.civil4m.com
RESPONSIBILITIES OF ESTIMATION
ENGINEER

 By adding all above costs considered , total cost per


sq.m of the whole project should be found out .
 Futher ,the estimate made should be split item wise
and the cost incurred at various stages should be
worked out separately i.e plinth ,slabs ,masonary
,plaster ,flooring etc , split into an accurate % to find
out the expenses incurred in various stages .
 This records should be referred to while preparing
the construction progress chart for each site .

www.civil4m.com
 Before preparing the estimate ,one should have the
total rate ( Material + Labour ) of that particular
item .For this rate analysis is the must .
 Estimate engineer should prepare various required
rate analysis with proper mode of measurements
.This will be useful in estimation and billing .

www.civil4m.com
Daily Work Progress & Material Consumption

 To calculate consumption of various materials like


cement ,steel , bricks ,blocks etc as per
daily/weekly/monthly progress of work .To compare
actual quantities worked out as per rate analysis .
 To check and information to Project Head
management .
 To work out for various labour work involve at site
,using standard labour task work and to give the
percentage breakup either floor wise or work wise

www.civil4m.com
STANDARD REPETATIONS OF USE OF THE SHUTTERING MATERIALS

NUMBER OF REPETITIONS
SR. NO SHUTTERING MATERIALS (APPROXIMATE )

Columns and beams sides ( Plywood 12 mm


1 thick ) 15 nos from each side of plywood

2 Wooden Battens for slab ( Silver oak ) 30 to 40 repitations

3 Beam Bottom planks ( Silver oak 35mm thick )8 to 10 repitations


Min.150 repitations . Repairs of the
plates after every 25 repitations should
4 M.S plates be done

www.civil4m.com
CALCULATIONS OF SHUTTERING MATERIAL REQUIREMENT BY QUICK METHOD OF ESTIMATION FOR 2500
SQ.FT OF SLAB AREA

MULTIPLYING
CONSTANT BY APPROXIMATE QUANTITY OF
SR.NO MATERIAL REQUIRED UNIT THUMB RULE MATERIAL REQUIRED
Plywood 12 mm thick of size
1 2.44 m x 1.22 m ( 8' x 4') 2500 sft 0.02 50 nos of sheets
Battens Silver Oak size 75 mm 50 sheets of plywood
2 x40 mm ( 3'' / 1 1/2'') 2500 sft X 65 3250 RFT
Beam bottom planks 40 mm
3 thick ( 1 1/2'' ) 2500 sft 2500 sft X 0.24 600 RFT

4 Wodden Props

A} For beams 2500 sft600 RFT beam bottom X 0.5


300 nos

B} For Slab 2500 sft 2500 X 0.16 400 nos

5 Wooden Batten for


supporting slab plates ( 75 2500 sft 2500 X 0.4 1000 RFT
6 Steel plates size 60 cm X 90
cm {2' X 3'} 2500 sft 2500 X 0.16 400 nos

7 Wire nails 2500 sft 2500 X 0.020 50 kg

8 Shuttering Oil 2500 sft 2500 X 0.006 15 litres

9 M S Clamps ( Shikanja ) 2500 sft 2500 X 0.08 200 Nos

www.civil4m.com
CONSUMPTION OF STEEL IN KG PER SQM OF WORK

SR.NO ITEMS CONSUMPTION OF STEEL on Built up area


KG / SQ.M KG / SQ.FT
1 Footing 0.55 0.05
2 Columns up to plinth 2.15 0.2
3 Tie Beam 1.15 0.1
4 Column ( Super Structure ) 4.8 0.45
5 Slabs 7 0.65
6 Beam 7.5 70
7 Lofts/Lintel /Chajja 0.55 0.05
8 Over Head Water Tank 0.55 0.05
9
10
Total 24.25 KG/SQ.M 2.25 KG/SQ.FT

www.civil4m.com
CONSTANTS FOR ESTIMATING THE APPROXIMATE QUANTITIES OF VARIOUS ITEMS PER SQ.M
/SQ.FT OF BUILT UP AREA

SR.NO ITEMS APPROX.QTY PER


SQ.M SQ.FT
1 Exacavation 0.31 1
2 RCC below plinth 0.046 0.15
3 RCC above plinth 0.29 0.95
4 Internal Masonary 0.7 0.7
5 External Masonary 0.9 0.9
6 Internal Plaster /Paint 3.2 3.2
7 External Plaster/Paint 2.5 2.5
8 Oil Paint 0.62 0.62
9 Flooring
a MM Tile 0.75 0.75
b Skirting 0.82 RMT 0.25
c W.C/Bath 0.05 0.05
d Dado
10 Waterproofing 0.3 0.3
11 Door Frames 0.17 0.17
12 Windows 0.14 0.14

www.civil4m.com
THANK YOU

PREPARED BY :
ER.PAWAN DHAGATE
EMAIL : PAWAN@CIVIL4M.COM
PAWAN.DHAGATE@GMAIL.COM

www.civil4m.com