Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
138.942
1667.304 1250.478 1042.065 833.652
69.471 69.471 69.471 69.471
138.942 138.942 138.942 138.942
16.56
198.72 149.04 124.2 99.36
8.28 8.28 8.28 8.28
16.56 16.56 16.56 16.56
12.555
150.66 112.995 94.1625 75.33
6.2775 6.2775 6.2775 6.2775
12.555 12.555 12.555 12.555
38.64
463.68 347.76 289.8 231.84
19.32 19.32 19.32 19.32
38.64 38.64 38.64 38.64
1
12 9 7.5 6
0.5 0.5 0.5 0.5
1 1 1 1
DRY WALL
height Length hor. spacing vert. spacing stud pcs 3m
1.3 33.7 0.6 1.2 18.72
3 33.5 0.6 1.2 18.61
DRY WALL
track 3m Rod
29.83
39.33
Diameter hor bar = 1.4m * pcs * 4
Trape Footing 0.016 56
Length Width
WFT slab 184 0.7
TRAPEZOIDAL FOO
hor bar = 1.2 * pcs hor bar = 1 hor bar = .8
12 10 8
COLUMN
No. of column Total no. of bars (16*D)or(48*d)or(Shortest side)
62 1405.664 0.15
CHB
Area Vert. L of Bars per sq. m. total vert
772.8 1.6 1236.48
WFT SLAB
Thk spacing No. of L bar
0.3 0.300 3
TRAPEZOIDAL FOOTING
hor bar = .6 width bar =1.5 * pcs long bar = 1.2 + ld *pcs
6 69 16.5
BEAM
total m kg/m kg
3060 0.888 2717.28
COLUMN
Total height L of 1 square tie = (2(b+h)+24d) No. of cuts in 6m rebar
4.5 1.084 5.54
CHB
Hor L of Bars per sq. m. total hor total
1.72 1329.22 2566
WFT SLAB
rebar size Total L bars total w bars
6 570.0368 429.33
long bar = .9 + ld *pcs long bar = .6 + ld *pcs long bar = .3 + ld *pcs
13.50 10.5 7.5
Tie wire 25 cm
8.68
kg/m kg/m kg 10 kg 16
1.578 0.616 6148.912 4696.128
tiewire 25cm in kg
11.58
RW-1
Wall
Perimeter or length Height
119.3 3
58.7 3
CHB
height length
0.2 0.4
Mortar
Area No. per aq. m. Pcs Cement class Sand class
357.9 12.5 4474 0.328 0.04375
176.1 12.5 2201 0.328 0.04375
HB
thk wall height length or perimeter Total pcs Ave. laying thk
0.15 4.5 184 10350 0.0125
Mortar Plaster
Cement Bag Sand Cu. M. Faces to plaster Total area plastered Cement class
117 16 2 715.8 0.12
58 8 2 352.2 0.12
MORTAR LAYING
volume Cement class Sand class cement bags sand cu. m.
7.7625 7.5 1 58.22 7.7625
Plaster TOTAL
Sand class Cem. Bags Sand Cu. M. CEM SAND
0.016 86 11.45 203 27
0.016 42 5.64 100 13
MORTAR FILLER
height length thk cell Volume per block
0.2 0.075 0.05 4 0.003
Plaster
total volume cement bag sand cu. m. Faces to plaster Total area plastered
31.05 232.88 31.05 2 1656
Plaster
Ave. thk cement bags Sand Cu. M. Total Cem bags
0.016 198.72 26.50 489.81
Total Cu. M.
65.31
Project Title :
Location :
Owner :
BILL OF QUANTITIES
I STRUCTURAL
A FOOTING
1.0 Cement 99.2
2.0 Gravel plus gravel bedding 16
3.0 Fine Sand 2
4.0 16 mm dia. Rebar 20618
5.0 Tie Wire 143
B COLUMN
1.0 Cement 36
2.0 Gravel 15
3.0 Fine Sand 2
4.0 16 mm dia. Rebar 202
5.0 Tie Wire 5
6.0 10 mm dia. Rebar 400
7.0 Phenolic 3/4 20
8.0 2x2x12 42
C FOOTING TIE BEAM , BEAM & GIRDER
1.0 Cement 100
2.0 Gravel 9
3.0 Fine Sand 2
4.0 16 mm dia. Rebar 2046
5.0 Tie Wire 16
6.0 10 mm dia. Rebar 542
E MASONRY
1.0 100mm thk. CHB 10350
2.0 Mortar and Plastering
Cement 490
Sand 66
3.0 10mm Rebar 1580
4.0 Tie wire 7
F ROOFING
1.0 Prepainted G.I. Long span Rib-Type .50 thk 276.92
Insulation 276.92
II ARCHITECTURAL
A WALL FINISHES
1.0 Dry wall
a.) Inner wall 100.5
b.) Partition wall 43.81
2.0 Painting Works
a.) Complete painting works 686.41
B CEILING FINISHES
1.0 Flat Ceiling - 12 mm. tk. M.R. gypsum Board on #24 Metal Furring 201
Material Cost
Labor Cost
Mobilization / Demobilization
Miscellaneous 5%
Profit and Overhead 10%
Contractors profit 10%
SUB TOTAL COST
EWT 2%
GRAND TOTAL
NOTE:
1. THIS CONSTRUCTION COST ESTIMATE IS IN ACCORDANCE TO THE CURRENT SPECIFICATIONS OF THE PROPO
2. ITEMS NOT INCLUDED HEREIN SHALL BE CONSIDERED AS AN ADDITIONAL WORK THUS ITEMS NOT MADE SH
DURATION:
Thirty (30) to Forty Five (45) Calendar Days.
EXCLUSION:
1. Electrical Works
TERMS OF PAYMENT:
50% - Down Payment
50% - Progress Billing
TEMPORARY FACILITY DETAILS
BONIFACIO GLOBAL CITY, TAGUIG
PHLIPPINE REALTY & HOLDING CORPORATION
LL OF QUANTITIES
2,801,010.70
2,004,454.70
240,273.27
240,273.27
480,546.54
480,546.54
6,247,105.02
124,942.10
6,372,047.12
CHECK
2,189,922.00
115,290.00
192,864.00
56,784.00
80619
277,865.00
185536.4
48461
90,915.30
130006.8
54,880.00
39200
147,000.00
3,609,343.50
4,805,465.40
IPM CONSTRUCTION & DEVELOPMENT CO
I. GENERAL REQUIREMENTS
1.0 Mobilization/Demobilization 1 lot
2.0 Bonds and Insurances 1 lot
2.1 Surety bond (5%)
2.2 Performance Bond (20%)
2.3 Guarantee Bond (10%)
2.4 Group Insurance Poliy (copy only)
3.0 Temporary Facilities 1 lot
4.0 Utilities (Power & Water) 1 lot
5.0 Safety/EHS Requirements 1 lot
6.0 Project Management/Supervision 1 lot
7.0 As built plan 1 lot
8.0 Others:
8.1
Scaffoldings (scafoloders with NCII Certificate) 1 lot
8.2 Consumables 1 lot
Prepared By:
Authorized Representative
Designation
Date Submitted
N & DEVELOPMENT CORPORATION
Revision No.: 1
TIES FOR BID PROPOSAL Date Revised: August 11,
2012
Effective Date: August 12,
2012
Date:
200.00 165600
7.00 145327
### 1E+06
300.00 248400
### 28080
BY IPMCDC -