Sei sulla pagina 1di 36

Part Length Width Thickness Pcs

Trpzdl. Footing slab 1.494 1.5 62


Cement
Sand
Gravel

Bond Beam 184 0.15 0.2 3


Cement
Sand
Gravel

Column 4.5 0.3 0.15 62


Cement
Sand
Gravel

WF Slab 184 0.7 0.3 1


Cement
Sand
Gravel

Column 4.5 0.3 0.15 62


Cement
Sand
Gravel
Total Volume Class AA (4000psi) Class A (3500psi) Class B (2500psi) Class B (2000psi)

138.942
1667.304 1250.478 1042.065 833.652
69.471 69.471 69.471 69.471
138.942 138.942 138.942 138.942

16.56
198.72 149.04 124.2 99.36
8.28 8.28 8.28 8.28
16.56 16.56 16.56 16.56

12.555
150.66 112.995 94.1625 75.33
6.2775 6.2775 6.2775 6.2775
12.555 12.555 12.555 12.555

38.64
463.68 347.76 289.8 231.84
19.32 19.32 19.32 19.32
38.64 38.64 38.64 38.64

1
12 9 7.5 6
0.5 0.5 0.5 0.5
1 1 1 1
DRY WALL
height Length hor. spacing vert. spacing stud pcs 3m
1.3 33.7 0.6 1.2 18.72
3 33.5 0.6 1.2 18.61
DRY WALL
track 3m Rod
29.83
39.33
Diameter hor bar = 1.4m * pcs * 4
Trape Footing 0.016 56

Length TB and BT(L/size)*#of hor bar


Bond Beam 184 170
note times splicing (tension 40d)

No. of long bars *(Th/6m) Total height +( 57d + 16 d)


C1 4 5.668

Perimeter or length Height


Outer wall 184 4.2

Length Width
WFT slab 184 0.7
TRAPEZOIDAL FOO
hor bar = 1.2 * pcs hor bar = 1 hor bar = .8
12 10 8

No. of beams total pcs of rebar size


3 510 6
(comp. 50d)

COLUMN
No. of column Total no. of bars (16*D)or(48*d)or(Shortest side)
62 1405.664 0.15

CHB
Area Vert. L of Bars per sq. m. total vert
772.8 1.6 1236.48

WFT SLAB
Thk spacing No. of L bar
0.3 0.300 3
TRAPEZOIDAL FOOTING
hor bar = .6 width bar =1.5 * pcs long bar = 1.2 + ld *pcs
6 69 16.5

BEAM
total m kg/m kg
3060 0.888 2717.28

COLUMN
Total height L of 1 square tie = (2(b+h)+24d) No. of cuts in 6m rebar
4.5 1.084 5.54

CHB
Hor L of Bars per sq. m. total hor total
1.72 1329.22 2566

WFT SLAB
rebar size Total L bars total w bars
6 570.0368 429.33
long bar = .9 + ld *pcs long bar = .6 + ld *pcs long bar = .3 + ld *pcs
13.50 10.5 7.5

L of 1 square tie = (2(b+h)+24d) no. of ties Total length of ties


0.74 614 454.36

Rounddown Total length of Square ties L of 1 straight tie = (b or h) + 18 d


5 2306.4 0.638

kg/m kg tie wire multiplier


0.616 1580 0.0014

kg/m kg No. of intersection


0.616 615.61 1840.00
No. of footing Total length 10 dia. Total length 16 dia.
62 9982 2976

kg/m kg no. of intersection


0.616 279.89 4

No. of cuts in 6m rebar Rounddown Total length of straight ties


9.40 9 5125.3333333333

25cm tie wire x chb pcs


6.26

Tie wire 25 cm
8.68
kg/m kg/m kg 10 kg 16
1.578 0.616 6148.912 4696.128

tiewire 25cm in kg
11.58

kg/m Total in kg Length of c + f no. of ties


0.616 4577.95 4.5 13
25cm Tie wire kg kg/m Longitudinal bar
114.06 1.578 2348.06
CHB
10x20x40
10x20x40

RW-1
Wall
Perimeter or length Height
119.3 3
58.7 3

CHB
height length
0.2 0.4
Mortar
Area No. per aq. m. Pcs Cement class Sand class
357.9 12.5 4474 0.328 0.04375
176.1 12.5 2201 0.328 0.04375

HB
thk wall height length or perimeter Total pcs Ave. laying thk
0.15 4.5 184 10350 0.0125
Mortar Plaster
Cement Bag Sand Cu. M. Faces to plaster Total area plastered Cement class
117 16 2 715.8 0.12
58 8 2 352.2 0.12

MORTAR LAYING
volume Cement class Sand class cement bags sand cu. m.
7.7625 7.5 1 58.22 7.7625
Plaster TOTAL
Sand class Cem. Bags Sand Cu. M. CEM SAND
0.016 86 11.45 203 27
0.016 42 5.64 100 13

MORTAR FILLER
height length thk cell Volume per block
0.2 0.075 0.05 4 0.003
Plaster
total volume cement bag sand cu. m. Faces to plaster Total area plastered
31.05 232.88 31.05 2 1656
Plaster
Ave. thk cement bags Sand Cu. M. Total Cem bags
0.016 198.72 26.50 489.81
Total Cu. M.
65.31
Project Title :
Location :
Owner :

BILL OF QUANTITIES

ITEM # DESCRIPTION QTY

I STRUCTURAL

A FOOTING
1.0 Cement 99.2
2.0 Gravel plus gravel bedding 16
3.0 Fine Sand 2
4.0 16 mm dia. Rebar 20618
5.0 Tie Wire 143

B COLUMN
1.0 Cement 36
2.0 Gravel 15
3.0 Fine Sand 2
4.0 16 mm dia. Rebar 202
5.0 Tie Wire 5
6.0 10 mm dia. Rebar 400
7.0 Phenolic 3/4 20
8.0 2x2x12 42
C FOOTING TIE BEAM , BEAM & GIRDER
1.0 Cement 100
2.0 Gravel 9
3.0 Fine Sand 2
4.0 16 mm dia. Rebar 2046
5.0 Tie Wire 16
6.0 10 mm dia. Rebar 542

D SLAB & WF slab


1.0 Cement 36
2.0 Gravel plus bedding 23
3.0 Fine Sand 4
4.0 10 mm dia. Rebar 608
5.0 Tie Wire 9

E MASONRY
1.0 100mm thk. CHB 10350
2.0 Mortar and Plastering
Cement 490
Sand 66
3.0 10mm Rebar 1580
4.0 Tie wire 7

F ROOFING
1.0 Prepainted G.I. Long span Rib-Type .50 thk 276.92
Insulation 276.92

II ARCHITECTURAL

A WALL FINISHES
1.0 Dry wall
a.) Inner wall 100.5
b.) Partition wall 43.81
2.0 Painting Works
a.) Complete painting works 686.41
B CEILING FINISHES
1.0 Flat Ceiling - 12 mm. tk. M.R. gypsum Board on #24 Metal Furring 201

III DOORS & WINDOWS (Supply & Install)


A Wooden Doors
1.0 1.8m 1
2.0 0.80m 2
3.0 0.70m 5
4.0 1.6m Double door 1
B PVC Door - Toilet Door
1.0 0.70m 8
C Plain Glass Sliding Windows
1.0 1.5 x 1.2 5
2.0 1.2x 1.2 8
3.0 Double 3
4.0 Single 1

IV DOORS & WINDOWS (Supply & Install)


A Wooden Doors
1.0 Toilet Fixtures
a.) Male Toilet - (2 Water Closet, 2 Urinal , 1 lavatory 1
b.) Female Toilet - (2 Water Closet, 1 lavatory 1
2.0 Plumbing Works 1

Material Cost
Labor Cost
Mobilization / Demobilization
Miscellaneous 5%
Profit and Overhead 10%
Contractors profit 10%
SUB TOTAL COST
EWT 2%
GRAND TOTAL

NOTE:
1. THIS CONSTRUCTION COST ESTIMATE IS IN ACCORDANCE TO THE CURRENT SPECIFICATIONS OF THE PROPO
2. ITEMS NOT INCLUDED HEREIN SHALL BE CONSIDERED AS AN ADDITIONAL WORK THUS ITEMS NOT MADE SH

DURATION:
Thirty (30) to Forty Five (45) Calendar Days.

EXCLUSION:
1. Electrical Works

TERMS OF PAYMENT:
50% - Down Payment
50% - Progress Billing
TEMPORARY FACILITY DETAILS
BONIFACIO GLOBAL CITY, TAGUIG
PHLIPPINE REALTY & HOLDING CORPORATION

LL OF QUANTITIES

MATERIAL COST LABOR COST


UNIT AMOUNT
Per Unit Total Per Unit Total

cu. M. 6250.00 620,000.00 2,500.00 248,000.00 868,000.00


cu. m. 600.00 9,600.00 240.00 3,840.00 13,440.00
cu. m. 550.00 1,100.00 220.00 440.00 1,540.00
kgs 45.00 927,810.00 18.00 371,124.00 1,298,934.00
kls 40.00 5,720.00 16.00 2,288.00 8,008.00
625,692.00

bags 250.00 9,000.00 100.00 3,600.00 12,600.00


cu. m. 600.00 9,000.00 240.00 3,600.00 12,600.00
cu. m. 550.00 1,100.00 220.00 440.00 1,540.00
kg 45.00 9,090.00 18.00 3,636.00 12,726.00
kls 40.00 200.00 16.00 80.00 280.00
kgs 25.00 10,000.00 10.00 4,000.00 14,000.00
pcs 1400.00 28,000.00 560.00 11,200.00 39,200.00
pcs 380.00 15,960.00 152.00 6,384.00 22,344.00

bags 250.00 25,000.00 100.00 10,000.00 35,000.00


cu. m. 600.00 5,400.00 240.00 2,160.00 7,560.00
cu. m. 550.00 1,100.00 220.00 440.00 1,540.00
kg 45.00 92,070.00 18.00 36,828.00 128,898.00
kls 40.00 640.00 16.00 256.00 896.00
kgs 25.00 13,550.00 10.00 5,420.00 18,970.00

bags 250.00 9,000.00 100.00 3,600.00 12,600.00


cu. m. 600.00 13,800.00 240.00 5,520.00 19,320.00
cu. m. 550.00 2,200.00 220.00 880.00 3,080.00
kgs 25.00 15,200.00 10.00 6,080.00 21,280.00
kls 40.00 360.00 16.00 144.00 504.00

Pcs 20.00 207,000.00 8.00 82,800.00 289,800.00


bags 250.00 122,500.00 100.00 49,000.00 171,500.00
cu. m. 550.00 36,300.00 220.00 14,520.00 50,820.00
kg 25.00 39,500.00 10.00 15,800.00 55,300.00
kls 25.00 175.00 10.00 70.00 245.00
162,190.00

sq. m. 420.00 116,306.40 250.00 69,230.00 185,536.40


sq. m. 120.00 33,230.40 55.00 15,230.60 48,461.00

sq. m. 450.00 45,225.00 180.00 18,090.00 63,315.00


sq. m. 450.00 19,714.50 180.00 7,885.80 27,600.30

sq. m. 140.00 96,097.40 150.00 102,961.50 199,058.90

sq. m. 462.00 92,862.00 184.80 37,144.80 130,006.80

set/s 7000.00 7,000.00 2,800.00 2,800.00 9,800.00


set/s 3850.00 7,700.00 1,540.00 3,080.00 10,780.00
set/s 3500.00 17,500.00 1,400.00 7,000.00 24,500.00
set/s 7000.00 7,000.00 2,800.00 2,800.00 9,800.00

set/s 3500.00 28,000.00 1,400.00 11,200.00 39,200.00

set/s 0.00 0.00 0.00 0.00 0.00


set/s 0.00 0.00 0.00 0.00 0.00
set/s 0.00 0.00 0.00 0.00 0.00
set/s 0.00 0.00 0.00 0.00 0.00

50000.00 50,000.00 20,000.00 20,000.00 70,000.00


30000.00 30,000.00 12,000.00 12,000.00 42,000.00
20000.00 20,000.00 8,000.00 15,000.00 35,000.00

2,801,010.70
2,004,454.70
240,273.27
240,273.27
480,546.54
480,546.54
6,247,105.02
124,942.10
6,372,047.12

IFICATIONS OF THE PROPOSED PLAN IS NOT YET FINAL.


THUS ITEMS NOT MADE SHALL BE CONSIDERED AS DEDUCTIVE WORKS.
3,122,525.00

CHECK

2,189,922.00

115,290.00

192,864.00

56,784.00

80619
277,865.00

185536.4
48461

90,915.30

130006.8

54,880.00

39200

147,000.00

3,609,343.50

4,805,465.40
IPM CONSTRUCTION & DEVELOPMENT CO

BILL OF QUANTITIES FOR BID


Document No: CON-PMG-003
Issue No. : 1
Page Number: Page _ of _

Project : 1126 - SOUTH BEACH DISTRICT


Locatio : Seaside Blvd., South Beach District, West City, Paraňaque

Scope of Works:CONSTRUCTION OF CHB FENCE AND RCP LAYING (LABOR ONLY)

ITEM DESCRIPTION UNIT Qty

I. GENERAL REQUIREMENTS
1.0 Mobilization/Demobilization 1 lot
2.0 Bonds and Insurances 1 lot
2.1 Surety bond (5%)
2.2 Performance Bond (20%)
2.3 Guarantee Bond (10%)
2.4 Group Insurance Poliy (copy only)
3.0 Temporary Facilities 1 lot
4.0 Utilities (Power & Water) 1 lot
5.0 Safety/EHS Requirements 1 lot
6.0 Project Management/Supervision 1 lot
7.0 As built plan 1 lot
8.0 Others:
8.1
Scaffoldings (scafoloders with NCII Certificate) 1 lot
8.2 Consumables 1 lot

Sub - total "I"


II. SITE WORKS
A. PERIMETER FENCE AT RETAINING WALL
a.1 CHB Wall Fence including Shear Key, Column & Bond
Beams
1.0 Formworks 828 sq.m
2.0 Rebars Gr. 40 20,761.00 kg.
3.0 Concreting 3000psi 414.00 cu.m
4.0 Masonry works 828.00 sq.m
5.0 Gravel Bedding 26.00 cu.m
Sub - total "A"
B. DRAINAGE SYSTEM
Pipe Laying including fittings, pipe joints and
b.1 concrete collaring works, tap to existing Main
Drainage Line. (RCP-OSM)
1.0 RCP 1050mmǿ l.m
2.0 RCP 750mmǿ l.m
3.0 RCP 600mmǿ l.m
4.0 RCP 525mmǿ l.m
5.0 RCP 450mmǿ l.m
6.0 RCP 375mmǿ l.m
7.0 RCP 300mmǿ l.m

b.2 Construction of concrete encasement collar


1.0 Formworks sq.m
2.0 Rebars kg
3.0 Concrete cu.m

Sub - total "II"

GRAND TOTAL CONTRACT AMOUNT (I+II)

Prepared By:

Authorized Representative

Designation

Date Submitted
N & DEVELOPMENT CORPORATION
Revision No.: 1
TIES FOR BID PROPOSAL Date Revised: August 11,
2012
Effective Date: August 12,
2012

Date:

MATERIALS LABOR EQUIPMENT TOTAL


WT %
UNIT COST AMOUNT UNIT COST AMOUNT UNIT COST AMOUNT UNIT COST AMOUNT

200.00 165600
7.00 145327
### 1E+06
300.00 248400
### 28080
BY IPMCDC -

Potrebbero piacerti anche