Sei sulla pagina 1di 5

I-09

Elyakim M. Schragenheim

Make-to-Stock under Drum-Buffer-Rope and Buffer


Management Methodology

WHY MAKE-TO-STOCK? financial cost of carrying stock, including the pos-


sibility of goods being scrapped or dumped. The
At least from the theory of constraints (TOC)
second is the dedication of capacity that does not
perspective this is a valid question. The tradi-
generate value, and even worse, this captured
tional drum-buffer-rope (DBR) planning ap-
capacity results in goods required by the market
proach emphasizes make-to-order. There is
not being produced. TOC and JIT/lean see the
something sensible about producing only to
second waste as the more severe of the two. The
order: there is no waste of materials or capacity
lost capacity does not only mean waste of costs,
in making things that will not sell. As market
but also waste of opportunity.
demand is always a major constraint, make-to-
So there is a generic conflict here, make-to-
order is a straightforward subordination to the
stock or not make-to-stock. TOC presents such
market: make what is needed and refrain from
a problem as in Figure 1.
making what is not needed.
Each prerequisite is necessary in order to
There is only one reason that will make it
achieve the requirement it points to, and each
necessary to consider producing for stock and
requirement is necessary to achieve the objec-
that is when the time it takes to produce an or-
tive. These two prerequisites are in direct con-
der is longer than the time customers are willing
flict. So, on the one hand we certainly need, in
to wait. In this situation there is a need to start
certain situations, to make-to-stock in order to
production before the customer asks for the
deliver in acceptable response time to our cus-
product. A reduction in lead time is one of the
tomers, and satisfying the customers (by deliver-
targets of several methodologies, including lean
ing in acceptable time) is absolutely necessary in
and TOC. But lead time reduction may be not
order to make money. On the other hand, main-
enough, especially when the customer does not
taining stocks of finished goods generates sig-
want to wait at all. Same day shipment can be
nificant waste that is counter to the objective.
described as “off the shelf” for all practical pur-
Hence, we should not produce stocks.
poses, and in such a case there is a need to have
The direction of the solution in such a case
the products in stock, even in a very fast re-
is to challenge the necessity of one of the pre-
sponse manufacturing environment.
requisites. In this particular case, if we succeed
Supply chains make the need for make-to- in holding a very low stock of finished goods,
stock even more universal. Even if every link in then the waste practically vanishes. Carrying
the chain has succeeded in drastically shrinking costs won’t be more than normal in a make-to-
the lead time, the overall lead time throughout order environment, and practically everything
the chain coupled with the fast-changing de- that is produced is going to be sold pretty soon.
mands would make it imperative to hold some The emphasis is on very low stocks! That means
stocks between the links. that within a short time all the stock will have
The objective of finished goods stock is to gone. In order to continue to satisfy the cus-
protect sales, but maintaining too much stock tomer the replenishment of those low stocks
causes two types of waste. The first is the direct needs to be VERY FAST.

Figure 1. A Generic Conflict

2002 International Conference Proceedings, © 2002 APICS—The Educational Society for Resource Management 1
Make-to-Stock under Drum-Buffer-Rope and Buffer Management Methodology

FAST REPLENISHMENT AND THE is not to say that without formal or computer-
CLASH WITH CURRENT ized forecasting the answer will be more accu-
PRACTICES rate; nevertheless, we’re well aware that we don’t
really know the answer and thus prepare for
The replenishment time is very significant in different scenarios. When we realize we don’t
evaluating the stock levels. Two common prac- know, we try not to look too far ahead and keep
tices directly clash with the idea of shrinking the to a reasonably short lead time. It seems that in
stock replenishment time to the extent that forecasting some organizations try to look too
make-to-stock won’t generate the two types of far ahead, creating huge batches, and then chase
waste discussed above. the market trends using frequent reforecasting to
The first practice that clashes with fast re- correct the actions taken before the last forecast.
plenishment is the norm of batching. TOC and One of the characteristics of any forecast is that
JIT/lean are in total agreement regarding the its quality deteriorates pretty fast from the hori-
huge damage caused by batching. Figure 1 zon. If the forecast for next week can be pretty
shows two necessary requirements for achieving good, the forecast for next month is much more
the common objective. Note that both require- exposed to variance and the forecast for next
ments are tempered by the use of batches. The year is probably meaningless.
above requirement is straightforward, but An important point is that what really
through the use of batches more inventory is counts most of the time is not the average de-
produced than is considered absolutely neces- mand, but how much it might be. Hence, the
sary. The rest is pure waste in terms of carrying concept of safety stock comes to mind. In many
both costs and capacity. The end requirement is cases the “noise” in the actual sales is the same
the expectation of immediate and reliable deliv- as, or even more, than the official forecast,
ery. The use of batches weakens the ability to which tried to predict the average demand.
respond quickly. Hence, both requirements are Maintaining stocks for protecting sales needs
at odds with the objective of making money. to consider not only the fluctuations in demand,
TOC, however, recognizes that in some but also the fluctuations in replenishment time.
cases batching cannot be avoided. Thus, there is a After all, the protection is active when a request
need to clearly define when batching is absolutely for replenishment is issued. Until then the sales
required and to ascertain the minimum size of a depend upon the availability of stock. So, the
batch that will overcome a particular obstacle. safety stock serves not only to cover deviations
A case in point can occur when very small from the forecast, but also the deviations from
batches might turn a specific non-constraint the lead time/replenishment time.
resource into a bottleneck, due to the accumula-
tion of setup time. It is important to verbalize it
that way in order to come up with a clear idea of FAST REPLENISHMENT IN THE
what is the minimum batch that will not turn the TOC WAY
specific resource into a bottleneck. Certainly we The TOC approach to make-to-stock might be
do not need to increase batches just in order to considered similar to lean/JIT in several parame-
improve “efficiencies.” The only place where ters. But, the TOC control part (buffer man-
efficiency is important is at the capacity- agement) is quite different.
constraint resource (CCR). Instead of trying to be very precise in very
Stock levels are frequently managed accord- uncertain situations (like using sophisticated
ing to min-max levels. The batching policy is forecasting techniques), TOC strives to build a
hidden under the size of the max minus the min. robust design that is good enough. The initial
The stock that should clearly protect sales is the parameters are based on crude forecasting that is
“min” or order point. Anything above that is complemented by crude assessment of the vari-
surplus inventory that generates the above two ability of both market demand and replenish-
types of waste. ment time. What complements good-enough
The second clash is the use of forecasts. planning is a very flexible and priority-driven
Any production for stock involves some sort of execution control system that is capable of tak-
forecasting. The “order point” level is a crude ing care of the exceptions.
forecast regarding possible sales during the re- The key parameter is the replenishment level
plenishment time. However, a sophisticated that has to be defined per product. This is the
make-to-forecast instead of make-to-stock can equivalent of the shipping buffer used in the DBR
result in a waste of effort and could turn out to methodology for make-to-order. The behavior of
be disastrous. Eventually even with all the so- the replenishment buffer is similar to the min-
phistication and high stock levels, shortages oc- max method, but the min equals the max. Hence,
cur regularly. every day when some units of the product are
Forecasting tries to answer the following sold, a work order for the same amount is gener-
question: How many units shall we sell during ated for the next day. The default thinking is that
the next period? However, the answer given by no minimum batch is used. As we’ll see later, the
any type of forecasting is not very reliable. That system regulates itself, so that when the load is

2002 International Conference Proceedings, © 2002 APICS—The Educational Society for Resource Management 2
Make-to-Stock under Drum-Buffer-Rope and Buffer Management Methodology

severe, perhaps because of too many setups, then The buffer status of a product is the ratio
larger batches would naturally be released. But, between the quantity missing to the replenish-
TOC is not an extremist approach. In some cases ment level divided by the replenishment level. A
there should be a need to dictate a minimum buffer status of 70 percent means that the on-
batch, otherwise the load on the CCR would be hand stock is 30 percent of the replenishment
too large. So, minimum batch is an option, but it level. Considering the default value of the emer-
does not “hide” behind the difference between gency level and the buffer status of 70 percent,
two parameters. the emergency level has been penetrated. The
The size of the replenishment level should buffer status for each product dictates the priori-
cover the average demand plus the safety stock ties on the shop floor. It seems common sense
to properly protect possible peaks of demand that when two replenishment orders show up at
and possible delays of replenishment orders. If a work center, one belonging to a product with a
we like to maintain very low stocks, the replen- buffer status of 36 percent and the other a
ishment time should be as short as possible. buffer status of 50 percent, then it is clear that
The regular DBR approach is able to main- the latter has a higher priority.
tain very fast replenishment, based on the load
and capacity of the CCR—the weakest link in BUFFER MANAGEMENT AS
the production chain. In establishing very short FEEDBACK TO THE PLANNING
lead times, the role of the shop-floor control PARAMETERS
becomes extremely important.
As already mentioned, buffer management identi-
fies exceptions where the protection is almost
BUFFER MANAGEMENT IN A exhausted. This identification serves to keep the
MAKE-TO-STOCK ENVIRONMENT planning intact by setting the priorities and expe-
Buffer management is a control mechanism. The diting them when needed. But the occurrence of
idea behind it can be summarized as identifying an exception might have a longer-term impact as
situations where the planned protection is al- well. The number and intensity of occurrences in
most exhausted. Once such a local case is identi- a period of time testifies to the effectiveness of
fied, a warning is issued, resulting in high the replenishment and emergency levels.
priority being given to the problematic orders Suppose product P10 had been below the
and then utilizing the rest of the protection to emergency level for 10 days (“in the red”) last
remedy the local disruption. month. Assuming 22 working days in a month,
In the make-to-order DBR, the buffers are then 10 out of 22 being in emergency is quite
all time-buffers. Exhausting the buffers means substantial. The reaction in such a case should be
coming too close to the critical date. In the to increase the buffer (the replenishment level).
make-to-stock environment, the main buffer is The buffer should not be increased by a small
real finished goods stock. By almost exhausting percentage that is well within the “noise” (the
the protection means, in this case, very low on- regular fluctuation level) in the system; rather it
hand stock—low to the extent that it could be should be something like a 25 percent increase.
exhausted before any reinforcement would ar- An opposite situation also holds true. Sup-
rive. This emergency level, sometimes called the pose product P15 did not penetrate even once
“red-line level” or “zone 1,” represents an ex- the “red-line” (the emergency level), and also did
ception that should trigger action. When the on- not cross the 2/3 line of the replenishment
hand stock goes down below the emergency buffer—this would enable a reduction of the
level—efforts must be made to expedite com- buffer by 25 percent.
pletion of the work-order for that item as soon This kind of analysis is a crude forecast, but
as possible. it takes into account all the parameters that im-
The default for the emergency level is one-third pact the stock: the average market demand, the
(33 percent) of the replenishment level. The emer- average replenishment time, and the level of fluc-
gency level size should conform to two criteria: tuations of both. Hence, it is the ultimate sensor
1. The remaining stock still leaves time to ex- for the validity of the planning parameters.
pedite the work-in-process and reach the
finished-goods stock on time. If this is not
THE REPLENISHMENT ORDER
the case the emergency level should be RELEASE PROCEDURE UNDER
higher, which might have a similar impact DBR METHODOLOGY
on the replenishment level as well. Every day a check must be made for all products
2. Crossing the emergency level is neither too that are make-to-stock. When the on-hand stock
frequent nor too rare. If this is not true the is lower than the replenishment level, a further
replenishment level should be changed. check is needed to verify how much work-in-
Our experience shows that 33 percent is a process (WIP) exists for that product. If the sum-
good initial guess, and the two criteria above mation of the on-hand plus the WIP is still lower
should help to “tune” the relationship between than the replenishment level, then a new
the replenishment and the emergency levels. replenishment order has to be released. However,

2002 International Conference Proceedings, © 2002 APICS—The Educational Society for Resource Management 3
Make-to-Stock under Drum-Buffer-Rope and Buffer Management Methodology

before we do that, the total load on the capacity- Replenishment orders should NOT be
constraint resource (CCR), needs to be checked. given due dates. The material release is done
Each replenishment order does have a priority for according to the above procedure. Once the
being released at that day. The priority is, the re- materials have been released, the urgency of a
plenishment order size divided by the replenish- replenishment order does not depend on the
ment level. This might be different than the time that has passed but on the product buffer-
buffer status for the product because the buffer status. If, after the release of materials, sales for
status takes into account only the on-hand fin- that product are high, then that order should
ished goods stock, while the priority for the new become very urgent. If sales are lower than aver-
replenishment orders takes the WIP for the prod- age, then there is no pressure.
uct into account. The author considers that it is a mistake to
Under DBR methodology the CCR is pro- attach an artificial due date for a replenishment
tected by the CCR time-buffer. Every day re- order. It would be stupid to expedite such an
plenishment orders are launched up to the limit order if the finished goods stock is not low. And
of the CCR time-buffer. When the CCR is it would be stupid not to push the replenishment
loaded more than that, then the scheduling algo- order when the due date is not close, but the
rithm would delay the material release until stock level is dangerously low.
CCR-time-buffer before the scheduled start of Buffer management maintains the right pri-
the CCR. As more sales are done every day, the orities for both make-to-order and make-to-
replenishment orders that were not released on a stock. The buffer status of a customer order
particular day, due to relatively low priority and (make-to-order) is based on how much time
high load on the CCR, would be larger the next passed since material release divided by the time-
day (more to replenish due to additional sales) buffer size. For replenishment orders, the buffer
with higher priority to be released. status depends on the missing quantity for re-
This procedure self-adjusts the average plenishment level divided by the replenishment
batch according to the load on the CCR. In off- level. Even though the calculation of the buffer
peak periods the load on the CCR is not high, status is different, they are fully comparable.
hence most replenishment orders would be re- An example:
leased on the first day, meaning relatively small Suppose on March 1, three orders are at the
batches. When the load on the CCR is high, the CCR:
replenishment orders would compete on being • A large customer order (make-to-order) for
released—hence the average batch would grow. 900 units of P3, due at March 28. The ship-
Thus the system ensures self-adjusting to ping buffer is 2 weeks.
the load. Both the replenishment levels and the • Replenishment order (make-to-stock) for
average load grow when the load grows, and go 500 units of product P1. The replenishment
down when the load goes down. Thus the sys- buffer is 1,000 units. On-hand stock is 430
tem is stable, as long as the CCR has still enough units.
capacity to deal with the market demand. • Replenishment order (make-to-stock) for
100 units of P2. The replenishment buffer is
FUNCTIONING UNDER MIX- 300 units. On-hand stock is 106 units.
MODEL—MAKE-TO-ORDER AND The emergency zones for both make-to-
MAKE-TO-STOCK stock and make-to-order are 30 percent of the
buffer, or 70 percent penetration into the buffer.
In many environments it makes sense to use a What should the CCR work on first?
mix-model of make-to-stock and make-to-order. Certainly not the customer order for P3. That order
The more common products are better handled has four weeks until its due date, and the shipping
as make-to-stock, thus providing immediate de- buffer is only two weeks. The shipping buffer
livery while keeping low-enough stocks that will status, which is equal to the shipping buffer minus
soon be sold. Less common products, sometimes the time left until the due date, then divided by the
called “slow products,” while important to the shipping buffer, is –100 percent penetration.
market, are more problematic to handle as make- How could an order be in negative penetra-
to-stock. In many cases customers for the slow tion into the buffer?
products are ready to wait a short time for deliv- Several possible explanations:
ery. With a short time response, these products • Someone has released the order too early—
can be handled as make-to-order. against the DBR schedule.
How does the above procedure match both • Noting that we look here only at the ship-
types of orders? The DBR scheduling algorithm ping buffer, while that order is still behind
can load the CCR according to the due dates and the CCR. This opens the way to a further
the shipping-time-buffer as dictated by the due explanation of the amount of negative ship-
dates for the slow product, then complement the ping buffer:
CCR schedule with the replenishment orders − The CCR buffer is relatively long, but
that do not have any specific due date. that order reached the CCR early.

2002 International Conference Proceedings, © 2002 APICS—The Educational Society for Resource Management 4
Make-to-Stock under Drum-Buffer-Rope and Buffer Management Methodology

− The original CCR schedule has placed CONCLUSIONS


the order very early due to scheduling I hope one message has been clarified through
considerations on the CCR. the discussion about make-to-stock under DBR
The buffer status for P1: (1000-430=570) and buffer management. Make-to-stock implies
units to be replenished. The ratio to the replen- a somewhat different approach than make-to-
ishment level is 570/1000 = 0.57, meaning 57 order, because the priorities are constantly
percent penetration. changing based on the immediate market de-
The buffer status for P2: (300-106)/300 = 0.65, mand and the finished goods stock.
meaning 65 percent penetration into the buffer. Converting replenishment orders to
If we have the flexibility to reassess the pseudo-customer orders by sticking an artificial
schedule on the CCR, then the current priorities due date to them is, to my mind, wrong. At
should be P2 first, then P1, then P3. most, it reflects the right priorities when the
Suppose now there were more orders at the planning is carried out, but, the fictional due
CCR and somehow the same three orders re- dates might lose their relevancy pretty soon.
mained a further 10 days at the CCR. What Buffer management, using the same con-
should be the priorities then? cept of buffer status, and the percentage of the
We don’t need more information about the consumption of the planned protection, suc-
customer order for P3. Its buffer status is still ceeds in bringing together both types of orders
negative. and noting the current priorities.
We should need updated information about Being able to hold very low finished goods
the finished goods stock for P1 and P2. Suppose stock and being very agile in replenishing them,
we find out that 200 units of P1 are left, and 102 provides a very good stable solution to immedi-
units of P2. ate delivery while keeping the excess capacity for
The buffer status for P1 is (1000-200)/1000 what is truly needed—providing flexibility to
= 0.8, or 80 percent. grab more opportunities.
The buffer status for P2 is (300-102)/300 =
0.66, or 66 percent.
So, the priorities have now changed due to ABOUT THE AUTHOR
an alteration in the market demand for both Eli Schragenheim is an international consultant
products. Now P1 is the most urgent. As a mat- and educator. He is the author of Management
ter of fact it crossed the red-line level and is in Dilemmas, co-author of Manufacturing at Warp
an emergency situation. Hence, it may be neces- Speed (with William H. Dettmer) and of Dr.
sary to take urgent measures. Goldratt's new business novel Necessary But Not
Note the difference between make-to-stock Sufficient (also with Carol A. Ptak). He is the
order, whose priorities lie with the state of the developer of several educational simulators that
finished goods stock, and make-to-order for are used to experience the problems in running
which each order is evaluated according to its manufacturing and projects and the TOC
own due date. solutions.

2002 International Conference Proceedings, © 2002 APICS—The Educational Society for Resource Management 5

Potrebbero piacerti anche