Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
II500.00/7en
© CCI
Installation
Guidelines Steam Conditioning Valves
Table of contents
1 General ....................................................................................................................... 3
1.1 Inlet pipe recommendations ................................................................................. 4
1.2 Straight pipe-run upstream recommendations ..................................................... 6
1.3 Distance to first bend ........................................................................................... 7
1.3.1 Distance to first bend for special cases ........................................................ 7
1.3.2 Dump to condenser with wet steam before dump device ............................. 8
1.4 Distance to the temperature sensor ..................................................................... 9
1.4.1 Minimum distance to temperature sensor ..................................................... 9
1.4.2 Distance to temperature sensor for special cases ........................................ 9
1.4.3 Minimum degree of superheat .................................................................... 11
1.5 Distance to flow dividers .................................................................................... 12
1.6 Distance to pressure sensor .............................................................................. 12
1.7 Downstream piping material .............................................................................. 12
1.8 Additional comments ......................................................................................... 13
1.9 Diffusers and plates ........................................................................................... 13
1.10 Drains / Vent to atmosphere .............................................................................. 13
1.11 Pipe pre-warming .............................................................................................. 16
1.12 Water valve location .......................................................................................... 22
1.13 Water piping connection to desuperheater connection ...................................... 22
1.14 Control system ................................................................................................... 23
1.15 Pressure control ................................................................................................ 24
1.16 Temperature control .......................................................................................... 24
1.17 Special for feed forward with dump to condenser .............................................. 29
1.18 Actuation............................................................................................................ 29
1.19 Preheating arrangement of upstream piping...................................................... 30
3 Accessibility .............................................................................................................. 38
II500.00/7en 1
Installation
Steam Conditioning Valves Guidelines
List of figures
Fig. 1 Pipe elbow upstream the valve ............................................................................ 4
Fig. 2 XYZ installation with T-piece ................................................................................ 4
Fig. 3 XY installation with T-piece .................................................................................. 5
Fig. 4 Installation with stop and control valve welded together ...................................... 6
Fig. 5 Straight pipe runs up- and downstream the valve ................................................ 6
Fig. 6a Downstream temperature vs. time in a dump to condenser or a similar
process application .............................................................................................. 8
Fig. 6b Downstream temperature vs. time in an HP to cold reheat or similar
process application .............................................................................................. 9
Fig. 7 Downstream temperature vs. time in a dump to condenser or similar
process application ............................................................................................ 11
Fig. 8 Protective shield................................................................................................. 12
Fig. 9 Horizontal inlet/vertical outlet ............................................................................. 14
Fig. 10 Drain/preheat system ......................................................................................... 15
Fig. 11 Drainage system (D) .......................................................................................... 16
Fig. 12 Vertical inlet/horizontal outlet ............................................................................. 17
Fig. 13 Horizontal inlet/outlet ......................................................................................... 17
Fig. 14 Vertical inlet/horizontal outlet ............................................................................. 17
Fig. 15 Horizontal inlet, outlet upwards and actuator downwards .................................. 18
Fig. 16 Drain in downstream piping – Drip leg (L) .......................................................... 19
Fig. 17 Valve in low installation ...................................................................................... 19
Fig. 18 Installation with bend welded direct to outlet ...................................................... 21
Fig. 19 Expansion welded direct to outlet or closer than 0.1 s x Vmax ............................ 21
Fig. 20 Installation with an expansion cone in the outlet ................................................ 22
Fig. 21 Feed forward control – example. ........................................................................ 26
Fig. 22 Feedback control – example .............................................................................. 27
Fig. 23 Feed forward when a dump device cannot be used as a flow meter.
Algorithm based on valve position with compensation for variations in inlet
pressure and temperature. Pin and Tin are also used in the heat balance......... 27
Fig. 24 Bypass to condenser. Recommended installation ............................................. 28
Fig. 25 When the valve is very large, the below installation helps simplifying maintenance 28
Fig. 26 Preheating arrangement utilizing the natural pressure drop in the steam pipe .. 31
Fig. 27 Preheating arrangement bypassing the control valve ........................................ 32
Fig. 28 Preheating arrangement utilizing a higher pressure level than the valve inlet pressure 34
Fig. 29 Vertical installation ............................................................................................. 35
Fig. 30 Horizontal installation ......................................................................................... 36
2 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
1 General
The steam conditioning valve is an important part of the system. However, also other parts and
parameters in the system can have a significant impact on the performance of the steam
conditioning valve. In the following we have described those factors and also given some
general guidelines on how you can achieve a proper system design.
Contents:
Inlet pipe recommendations
Straight pipe-run upstream recommendations
Distance to the first bend
Distance to the temperature sensor
Distance to flow dividers
Distance to pressure sensor
Downstream piping material
Additional comments
Drains
Control system
Pressure control
Temperature control
Preheating arrangement of upstream piping
Fix points and supports
Accessibility
First rule
All steam valves are designed for dry steam and exposing valves for wet steam
or condensate will damage the valve and this is not covered by any warranties.
Vent valves and drains are to take care of pipe pre-warming until those
conditions are fulfilled.
II500.00/7en 3
Installation
Steam Conditioning Valves Guidelines
L1 Elbow
The orientation of the closest pipe bend vs. the valve orientation is also very important.
An installation such as in figure 1 (two dimensional x-y) is far better than an installation
like the one shown in figure 2.
An installation like the one shown in figure 2 is known to create rotational forces in the
valve plug. If a valve for some reason must have a pipe bend oriented as in figure 2,
please inform CCI about this before the valve design specification is made.
4 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
A T-piece as shown in figure 3 is also known to cause vibration and other problems, and
should always be avoided. Upstream S-pipe bends should also be avoided.
If a T-piece is used, a straight pipe length of at least 20 x Ø pipe should be used before
the valve.
Undersized stop valves with reduced bore upstream a bypass valve are
known to cause noise and vibrations due to high vena contracta
velocities and ununiform velocity distribution.
WARNING
Undersized stop valves also give the bypass valve a nonlinear characteristic due to the
strong influence of the pressure drop on the flow through the stop valve.
Stop valves of this type must be installed as far upstream as is required to provide a
uniform flow pattern. It is the responsibility of the supplier of the stop valve to provide
information about necessary distance.
A stop valve of angle type and a control valve, specially designed, can be assembled as
one unit and be welded together without any distance piece. This is quite common for
dump to condenser applications.
II500.00/7en 5
Installation
Steam Conditioning Valves Guidelines
L4 PT
L2 PI
L1
L3
R
TE
6 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
The upstream instrumentation should always be a temperature sensor to make sure the
steam is dry before the valve opens. In case any kind of algorithm is used for the
control, a pressure sensor is required.
II500.00/7en 7
Installation
Steam Conditioning Valves Guidelines
For dump to condenser 0.05 s x Maximum velocity is the recommended distance from
water injection to condenser wall. The dump device drilling starts normally directly on
the inside of condenser wall.
If the installation does not allow for the required straight distance, both the dump device
and condenser may be damaged.
[ C]
500
400
300
200
160
4 bar
143,6
This diagram shows the typical temperature downstream of water injection of a steam
conditioning valve in a dump to condenser application as a function of time when steam is
minimum 10°C superheated.
8 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
[ C]
500
480
460
440
420
400
380
360
340
250,3
0 0,02 0,04 0,06 0,08 0,10 0,12 [s]
This diagram shows the typical temperature downstream of water injection of a steam
conditioning valve in an HP to cold reheat application as a function of time.
II500.00/7en 9
Installation
Steam Conditioning Valves Guidelines
The distance to the temperature sensor can be reduced to 0.15 s x maximum velocity if
the following conditions are fulfilled:
Downstream pressure 15-60 bar / 217 – 870 psi (lower value normally only
occurs during sliding pressure mode or start-up).
Degree of superheat 100°C / 212°F or higher.
Water temperature 140°C / 284°F or higher.
10 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
[ C]
500
400
300
200
160
4 bar
143,6
As can be seen from the diagram above, the temperature will decrease very quickly
when water is injected and will then decrease slower and slower.
The reason is that the droplets after a very short time after they have been injected into
the flow will be exactly at saturation temperature. The heat transfer mechanism is heat
transfer from the surrounding steam to the droplets with temperature differences as the
driving force. The closer to saturation temperature the slower the process, thus allowing
more time for the droplets to fall out.
This typically begins to be a problem when the degree of superheat is 20-30° and
become quite difficult at 10° or lower.
Another problem associated with this is the effect of one droplet or more hitting the
sensor. If one (or more) droplet hitting the sensor will cause a misreading, which is
unpredictable and even not possible to calculate.
During transient when the temperature swings around the set-point, this problem can
increase beyond stability and the system will not be possible to control with severe
water fall outs and temperature swings as a result.
II500.00/7en 11
Installation
Steam Conditioning Valves Guidelines
Rules
A protective shield should be used for 10° superheat or less.
To avoid misreading, a protective pocket must be used for 5-7°C / 9-11°F superheat to
minimize the effect of water hitting the sensor.
Below 5° superheat is not acceptable and no warranties will be given. Exceptions are,
however, possible in certain cases. Therefore please contact the factory. Problems like
this are always minimized with a valve like VST-SE with built in mechanical water
proportioning. For less than 7°C / 11°F special control and extra instrumentation often
must be used and the factory must always be contacted in such cases.
For dump to condenser applications where cold water, typically less than 50°C /122°F is
used for desuperheating, the degree of superheat should be at least 20°C / 68°F since
evaporation time otherwise can be very long. CCI strongly recommend you to avoid
feedback control for dump to condenser applications due to big risks for thermal fatigue
damages related to difficulties in control. CCI always recommend feed forward control
for dump to condenser applications.
12 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
II500.00/7en 13
Installation
Steam Conditioning Valves Guidelines
The steam conditioning valve performs an important function in the steam system. It is
therefore essential to protect the valve from damage that might occur if water enters the
valve. It is equally important to protect the downstream system from damage caused by
a malfunctioning temperature control system (see separate section). It is, therefore, nec-
essary to have drains both upstream and downstream of the valve.
Maximum condensate normally occurs during cold start-up. This must be considered
already at the design stage for sizing of the drainage system. Condensate volume that
must be removed during start up should of course be calculated each time based on real
data but as an estimation, a mass of typically 7-14 % of the upstream piping weight
need to be removed through the condensate system. There should always be a
temperature sensor to confirm that the upstream piping is dry before the valve is opened
to prevent damages.
The following shows examples of drain arrangements for different valve
positions, etc.
Note! In case of a valve position according to fig. 10 and 11, the position of the
drain connection must be exactly defined.
14 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
CCI
From DCS on/off Customer
Preheat flow
To handle
start up
condensate Drain of level
removal control type
L1
L2 LIC
Manual or on/off
from DCS
Y
Drain
On when contaminated
condensate
On when clean
condensate
To hotwell/condensate
recovery system
II500.00/7en 15
Installation
Steam Conditioning Valves Guidelines
Manual/motorized by-pass
for start-up
Steam trap
The main reason for installing a bypass to drain is normally to give extra capacity during start
up to get rid of the large volume of condensate formed during start-up with cold piping.
Specially combined cycle plants are difficult since the degree of superheat from HRSG is very
low at low load of GT. That results in steam reaching saturation after a short travel through the
cold piping.
A recommended location of the drain is 2/3 of the distance to the temperature sensor.
Level control type drains are recommended for pressure above 20 bar / 290 psi.
Displacement type condensate pumps are recommended for low pressure < 3 bar / 43 psi
process lines.
16 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
The inlet steam pipe shall have a drain connection at a low point close to the valve
Valves shall have a drain stud at the bottom of the valve body
II500.00/7en 17
Installation
Steam Conditioning Valves Guidelines
18 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
Min 1 x O/
II500.00/7en 19
Installation
Steam Conditioning Valves Guidelines
Locate the drain (D) on the downstream side, at the lowest point after the valve. Weld
a drip leg (L) to the pipe, and connect the drain to the bottom of the drip leg.
The drip leg shall have a diameter of 0.5 x pipe-diameter. The depth of the drip leg shall
be between 300 and 600 mm / 1-2 ft.
If possible, always avoid an installation where the valve outlet is at a low point. If the
drain is undersized or not working, water can accumulate and cause many serious
problems.
The weight of the accumulated water can seriously damage piping and supports.
Free water at the bottom of the piping can cause very serious vibrations and
pressure transients in the piping.
Downstream temperature sensor can be hit by non-evaporated water causing
severe control problems.
Minimum slope to drain at a low point should never be less than 100:1.
Water hammers.
A simple closed temperature control loop is in most cases too slow for this type
of installation. A feed forward system is always required to minimize the effect
of transients recommended for this installation.
Transient analysis is necessary and must always be performed before designing
the control system.
20 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
II500.00/7en 21
Installation
Steam Conditioning Valves Guidelines
Exception
In certain cases, the design below can be used after written confirmation from the
factory.
Water valves are always to be installed below the lowest point of the spray connection and
recommended distance is 4-6 m between water valve and inlet of the connection point is on the
bypass valve.
Any pressure drop between water valve outlet and connection point on the bypass valve must
always be specified in order to include this pressure drop when sizing.
The water pipe routing (isometric) must be done in such a way that the forces originating from
thermal expansion are not transferred to the connection point.
Note! Deviations from this point must be clearly stated before ordering, as they can be
critical for the design of the product
22 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
When steam atomized nozzles are used in combination with spring-loaded variable area
nozzles two separate water valves must be used. For steam atomized nozzles a separate
on/off valve is used to supply atomizing steam that must be interlocked to open only
after the steam valve has opened. Water valve associated with steam atomized
desuperheating system must open after atomizing steam valve.
Remember that water hammer can destroy all kinds of piping and valves and opening or
closing should therefore never be faster than what the process requires. A spray water
valve may never open quicker than a bypass valve.
Inexactness is normally a by-product of too short actuating times and incorrect PID
settings.
II500.00/7en 23
Installation
Steam Conditioning Valves Guidelines
To be considered
24 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
II500.00/7en 25
Installation
Steam Conditioning Valves Guidelines
To achieve good performance the control loop itself must also be analyzed to find out, within
which exactness the water flow can be controlled by the complete control loop. The most
important parameters are the following:
Sensor response time
Controller response time and exactness
Positioner exactness
Valve exactness
Valve characteristic
Valve position exactness
Dead band
Maximum transients
Actuator exactness and stiffness
This analysis also provides the answer regarding sizing of the drainage system
downstream of a desuperheater or steam conditioning valve.
PT
PT TT DCS
Steam
FT
Spray water
The algorithm is based on the dump device used as a flow meter and a heat
balance using inlet pressure and temperature
26 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
Steam
PT
PS
DCS TT
FT
Spray water
Fig. 23 Feed forward when a dump device cannot be used as a flow meter. Algorithm based on
valve position with compensation for variations in inlet pressure and temperature. Pin
and Tin are also used in the heat balance
II500.00/7en 27
Installation
Steam Conditioning Valves Guidelines
Desuperheater
Dump Tube Condenser
Fig. 25 When the valve is very large, the below installation helps simplifying maintenance
28 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
Note! Bends downstream can only be used if the enthalpy of the mixture is at
least 10°C / 18°F above saturation in the inlet of the dump device since all
bends create separation between steam and water.
Feed forward control is superior to temperature control since all transients that may damage the
pipe and condenser are avoided. Damages to valve outlet, piping, dump device, condenser, etc.
are very rare. Every year there are damages reported where the temperature control is used
especially when there is a long distance (more than 20 m / 65 ft) between water injection to
condenser.
A recommended set point for this application is to have approx 20°C / 36°F superheat after the
dump tube to avoid the risk of having free water after the dump tube. An enthalpy of 2650
Kj/kg is normally recommended for most applications.
For this application a water flow meter must be used in the water line for each water valve in
case of more than one water valve. There should also be a pressure sensor upstream and
downstream of the water valve to allow for good estimation of the water flow below the
effective range of the water flow meters. Those pressure sensors can also be used for back up
of the flow meter if it fails and as preventive maintenance measurement since deviations from
calculated values indicate the true cause of the problem before consequences as damages etc.
can occur.
1.18 Actuation
Actuator type is very important for the performance, especially for a control which requires
stable temperature close to saturation since wet steam hitting the temperature sensor during
transients are heavily amplified if the actuator makes any overshoot.
Electrical, hydraulic or double-acting piston actuators with a high performance smart positioner
must be used.
To avoid problems the actuator must be slower than the steam valve as stability is much more
important than speed.
II500.00/7en 29
Installation
Steam Conditioning Valves Guidelines
Arrange for preheating, in those cases when the control valve normally is closed under
operation – e.g. in a turbine bypass application.
Preheating of the piping upstream of the valve is not necessary when the valve is located
above the live steam line and the pipe slopes down to the main steam line.
When the valve has to be installed lower than the live steam header there are a number
of solutions for the preheating arrangement. The main objectives, when selecting the
arrangements are to:
Create an effective system so that the piping will be sufficiently preheated and
drained.
Minimize the energy losses due to preheating steam.
Figures 18 – 20 show a few arrangements that can be used. The piping layout will
determine the preheating arrangement that will be the most effective for a specific
application.
Note! CCI can give advice on the best solutions for different types of plants;
such as conventional reheaters, combined cycle, cogeneration plants and
others.
30 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
1 2
Main steam line
3
Preheating line
Bypass line
Fig. 26 Preheating arrangement utilizing the natural pressure drop in the steam pipe
The method above is the most energy effective, but it also requires a suitable system
design.
When the steam flows from (1) to (2) there will be a pressure drop p in the line. With
proper sizing of the preheater piping, (1) to (3) it is possible to have a sufficiently large
flow to keep the piping (3) to (2) free of water. Warning! Required pressure drop is
often practically difficult to achieve and requires often both a big pre-warming
pipe and restriction in the main line. Reasonable pressure drop is 0.2-0.5 bar.
7A
´
Bypass line
7B
Preheating flow
II500.00/7en 31
Installation
Steam Conditioning Valves Guidelines
To DCS PT
Set from
TIC TT
DCS
A
7
Bypass line
7B
Preheating flow
32 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
To DCS PT
Min 0,5 m
Set from
DCS
TIC TT 7A
Bypass
line
7B
Preheating flow
The method shown in fig. 27 is the easiest and most common way of preheating upstream
piping (valve). Here you simply connect the inlet with the outlet and use a restriction to limit
the steam flow.
The steam flow used for preheating shall be moderated according to required pipe / valve
temperature, to reduce energy loss. In most cases normal ”preheating flow is 50-200 kg/h /
134-535 lb/h.
This preheating with connecting inlet to outlet can cause very high temperature downstream
and special springs made of Nimonic or similar must be used. The factory must also be
informed prior to manufacturing if this method is used. Normally the downstream connecting
point must be used after the valve to prevent hotspots that may cause deformation of the valve
outlet.
II500.00/7en 33
Installation
Steam Conditioning Valves Guidelines
Preheating flow
Bypass line
Preheating line
Hot reheat line
Main steam line
The solution shown in above figure is energy effective but can sometimes require a long
preheating line.
34 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
Crane
for lifting
L1
Steam
Inlet Platform
Nozzle
L2
Dump
Tube
Duct
II500.00/7en 35
Installation
Steam Conditioning Valves Guidelines
Spring Spring
hanger hanger
Sliding
support Sliding
support
Vibration Vibration
absorber absorber
36 II500.00/7en
Installation
Guidelines Steam Conditioning Valves
2.1 Actuators with springs must always supported due to the weight to avoid excessive
forces on yoke and mounting details. Especially when the actuator is mounted
horizontally this must be considered and spring hangers are always recommended.
II500.00/7en 37
Installation
Steam Conditioning Valves Guidelines
3 Accessibility
Space must be provided for service and maintenance of the valve. If the valve is
installed in a pipe rack or any other location which is difficult to reach, you need to
provide a platform around the valve as well as a safe route to it. The platform shall be
sufficiently large to accept a minimum of two persons and temporary storage of valve
internals.
A bracket or other arrangement for a lifting device shall also be available. The capacity
shall be at least 5 tonnes.
To facilitate maintenance within scheduled time, lifting equipment as well as a working
platform must be provided.
Planning for future maintenance is a very good investment and should always be taken
into consideration.
38 II500.00/7en
Installation instructions
Valves
General recommendations
II500.50/4en
©CCI 2006
1 - Installation instructions
1 Installation instructions
1.1 Installation
A
Max.
Material in
temperature
valve body
(at point A)
X10CrMoVNb 9-1
ASTM GR. 91
Low alloy steel (2)
650°C/1200°F
X10CrMoVNb 9-1
ASTM GR. 91
We recommend you to use a GTAW (Gas Tungsten Arc Welding) for the
root pass. In doubtful cases, please contact BTG.
Ö Always ground the welding machine on the piping side - not on the
valve body!
(The packings may retain a small amount of acid, which may lead to stem
corrosion later on).
Service and maintenance of Grafoil stem seals - see SI500.11.
SI500.10/5en
©CCI 2002
-
Table of contents
List of illustrations
1.1.1.1 Exceptions
Trichloroethylene must not be used on austenitic stainless steel surfaces
and other alloys which are sensitive to stress corrosion attack in the
presence of halogens.
Paraffin (kerosene) and white spirit shall be free from lead and free from
contaminants containing halogen, if they are to be used on austenitic
stainless steel surfaces.
1.1.2 Procedure
1.1.2.1 Trichloroethylene
Place the components in a trichloroethylene degreasing unit. As the
vapor condenses on the component surfaces, oil, grease and similar
substances will dissolve and can be rinsed off. The degreasing takes
about 5 minutes. The effect can be improved by rinsing or dipping, thus
also assisting in the removal of solid impurities. The solvent must be
stabilized to ensure that no hydrochloric acid will separate and cause
corrosion damage.
Materials subjected to a trichloroethylene treatment must as soon as
possible be treated against corrosion unless further cleaning is to be
carried out.
1.2.1.3 Exceptions
Light metals, e.g. as zinc aluminium and their alloys, must not be
degreased with an alkaline solution, as there is a risk of surface corrosion.
Painted surfaces may be degreased only if the paint is an alkali-resistant
epoxy paint.
1.2.2 Procedure
Flush the component with the solution at high pressure or dip it in the
agent which simultaneously should be agitated. The cleaning takes 2 - 10
minutes, depending on the degree of fouling.
Thoroughly rinse the component in clean water containing a
corrosion-protective additive, e.g. 0.1 - 0.2% sodium nitrite.
Dry the component immediately after rinsing and give it an anticorrosion
treatment unless further cleaning is to be carried out.
1.3 Pickling
1.4 Blasting
1.4.1.1 Exceptions
Aluminium oxide or silicon oxide with a low contaminant content shall
be used for blasting surfaces of austenitic stainless steel. The blasting
agent must not have been used on other materials, e.g. carbon steel. It
shall be approved by BTG as regards chemical composition, contamina-
tion level and maximum particle size.
1.4.2 Procedure
Non-stainless steel and steel castings should normally be blasted with
steel shot. Components in contact with lubricating or hydraulic oils can
be blasted with steel shot only if the particle size is maximum 0.5 mm
(0.19 in).
After blasting, remove all residues of the blasting agent by brushing,
blowing or preferably vacuum-cleaning. Surfaces blasted with steel shot
should be carefully treated to remove any steel residues. Wet-blasted
surfaces should be brushed and rinsed with clean water.
All blasted components shall be given an anticorrosion treatment
immediately after cleaning.
1.5.1.1 Exceptions
The wire brush used for wire brushing of austenitic stainless steel
surfaces shall e.g. be made of austenitic stainless steel or of a plastic
containing aluminium oxide. The wire brush must not be used on other
materials.
1.5.2 Procedure
Manual wire brushing shall always be carried out after scraping. Scra-
ping should preferably be carried out by means of tools fitted with repla-
ceable cemented carbide inserts.
In case of a light corrosion attack, mechanical brushing at a peripheral
speed of the rotating brush of between 25 and 35 m/s (80 - 113 fps) can
be used instead of scraping and manual brushing. Do not press the brush
too hard against the surface.
Mechanical grinding provides the same results as scraping plus wire
brushing. The method is best suited to flat surfaces. Grit size should be
0.25 - 0.40 mm (0.098 - 0.157 in).
1.6.1.1 Exceptions
Steam used for steam blasting of austenitic stainless steel surfaces has a
conductivity of a condensed sample, measured after a strongly acidic
cation exchanger of below 0.3 S/cm at 20° C (68° F).
Increase the steam velocity if a lower steam pressure is used. The general
rule is: the dynamic pressure, ½ W² · d, should not be less than the
normal operation pressure
W - Steam velocity
d - Steam density
1.6.2 Procedure
Blasting with high pressure steam is primarily carried out when the
installation of the steam pipes is completed. Make several blastings and
let the pipe work cool down to room temperature (approximately 3 hours
between blastings). Make the first 2 - 4 blastings without target as lots of
particles will come with the steam. When the steam seems to be clean,
mount a target to check the cleaning effect.
Mount a target made of a square rod of carbon steel and with the faces
numbered 1 - 4, to the steam outlet, preferably into a U-bar. The target
surfaces shall be mirror-polished. The size of the target area should be
about 15% of the pipe area. (At Ø 250 mm (10 inch in diameter) a rod of
30 x 30 mm (1.18 in x 1.18 in) should be chosen.) Turn the rod 1/4 of a
full turn to expose a new surface to the blasting. Compare the target
surface to see how the cleanliness improves.
Interrupt the blasting when two target faces, from two subsequent blas-
tings, do not show any obvious difference, and the particle traces are
small enough not to harm the turbine or the valve interior. Impacts of
small particles are allowed, but not the crater type.
Ö If steam velocity is too low when blowing the pipe it will not be
cleaned from foreign matter like bolts, welding electrodes etc. This
will cause severe damage to the valve when in operation.
When the steam is shut off, foreign matter will fall back into the
pipe and become difficult to detect.
SI500.11/5e
©CCI 2002
Table of contents
The BTG valves are as standard fitted with Grafoil® (Reg. Trademark of
Union Carbide Corp.) graphite stem packings.
Grafoil is made of expanded graphite. The shaft seals withstand saturat-
ed, HP, superheated and condensated steam of up to 500 bar (7250 psi)
pressure and temperatures above 1000° C (1830° F) and to process, dem-
ineralized and hot water at all pressures and temperatures. Regarding
other fluids, please contact your local BTG office and/or Union Carbide
Corp. specialized distributor.
The Grafoil packing material is available in two styles, both used by
BTG, depending on operating conditions and type of steam conditioning
or control valve.
1.2.1 Sealing
The successful sealing of a valve stem with Grafoil is achieved if you
take the following guidelines into consideration:
1. The component to be sealed must be mechanically in sealable condi-
tion. Mechanical parts, such as stem, shaft, bearing, stuffing box
room, lantern rings, gland, follower-sleeve etc. have to be cross-
checked for surface condition and tolerances. Grafoil can under load
extrude through relatively small gaps, and the following tolerances
are therefore important:
a. Diameter tolerance between stem and stuffing box wall at the bot-
tom - <0,2 mm (0.008")
b. Diameter tolerance between stuffing box wall, gland, follower-
sleeve, bushing, distance sleeve or lantern ring - < 0,2 mm (0.008")
2. When working with die-moulded packing rings, purchased from offi-
cial Grafoil distributors, slightly higher gaps can be tolerated.
3. When pressure exceeds 100 bar (1500 psi) and higher, the above tol-
erances should be reduced by about 50% (consider the thermal expan-
sion). Metal washers or flat steel rings are sometimes required to fill
up large tolerance gaps. In this case, the outside diameter of such
washers or sleeves must correspond to a press fit and the inside diam-
eter should be precision machined to a tolerance of +0.1 mm (0.004").
1.2.2 Stem
1. Surface-polished to better than 0.8 Ra average surface roughness, free
of pits, burrs, scratches.
2. Check cylindricity (deviation max. 0.05 mm) and parallelity.
ST500.40/1en
©CCI 2003
1 - Storage
1 Storage