Sei sulla pagina 1di 13

OTC 14040

Malampaya Deep Water Gas Pipeline and Flowlines: Technical and Engineering
Challenges faced in the Execution of the Malampaya Pipeline Scope
J.C. Macara - Shell Philippines Exploration B.V.

Copyright 2002, Offshore Technology Conference


deep water subsea tieback to a shallow water platform was
This paper was prepared for presentation at the 2002 Offshore Technology Conference held in selected in June 1996 as the preferred option for the
Houston, Texas U.S.A., 6–9 May 2002.
development of the field (Fig. 1).
This paper was selected for presentation by the OTC Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
Common to all of the concepts under consideration
presented, have not been reviewed by the Offshore Technology Conference and are subject to however was the provision of a subsea trunk export pipeline
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Offshore Technology Conference or its officers. Electronic reproduction, from the Malampaya field to the gas markets situated on the
distribution, or storage of any part of this paper for commercial purposes without the written
consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print
island of Luzon. Of the technical challenges to be faced in the
is restricted to an abstract of not more than 300 words; illustrations may not be copied. The engineering of the Project, it was recognised the feasibility of
abstract must contain conspicuous acknowledgment of where and by whom the paper was
presented. the export a pipeline in the structurally complex and
seismically active terrain was critical. Early survey and data
gathering work was essential to resolve the feasibility
Abstract
question. Offshore survey field work was therefore kicked off
The Malampaya field development comprises subsea wells in
in December 1996 and continued throughout 1997 in one of
850 metres water-depth producing via a subsea manifold and
the most comprehensive offshore data gathering campaigns
two 16 inch diameter inconel clad flowlines to a shallow water
performed in the industry.
platform 30 km distant. Condensate is removed on the
In addition to the pipeline routing and design challenge the
platform and the dry gas is then transported via a 504 km long
deep waters of Malampaya were to throw-up a number of
24 inch export pipeline to an onshore gas plant at Tabangao
additional technical and engineering challenges in the
(Batangas, Luzon Island) for extraction of H2S. The
installation of the pipelines. These included:
condensate is stored in the platform CGS caisson prior to
export via a short 3 km long 24 inch diameter pipeline and • Installation of 16 inch PLES units in 820
CALM buoy. metres depth;
The field flowlines and export pipeline route selection,
• Rock dump optimisation (for span correction) in water
design and installation are at the forefront of deep-water
depths down to 600 metres depth;
technology. The pipelines traverse structurally complex terrain
with varied seabed characteristics and sections of high bottom These and other challenges were successfully overcome
relief. The Philippines archipelago is recognised as being one and in doing so the boundaries of existing pipeline design and
of the most seismically active areas in the world. The gas installation experience extended.
export pipeline crosses active faults, an extensive system of The Malampaya export pipeline and flowlines as part of
submarine channels and areas susceptible to mass gravity flow the overall Malampaya Development Project were put into
and other soil instabilities. service and supplying gas to the customer on time on 1st
This paper addresses the pipeline route selection, design October 2001.
process and some of the specialist techniques employed in the
seismic design of the Malampaya pipeline. Route Selection.
The paper also addresses some of the novel installation The route selection process adopted for the Malampaya
techniques employed and challenges encountered in the pipeline emphasised the avoidance of hazards while
execution phase of the project. In particular the deepwater minimising the length of the pipeline and the water depth. The
PLES installation, deepwater span rectification and the major tectonic feature between the Malampaya field and a
removal of ordnance in 460 metres water depth will pipeline landfall in Southern Luzon is the Manila-Mindoro-
be addressed. Negros subduction-collision zone (Fig. 2). A pipeline route
passing to the West of Mindoro Island would have needed to
Introduction cross the Manila trench with water depths in excess of 2000
Following detailed reviews of competing concepts for the metres. Instead, a routing passing to the East of Mindoro was
Malampaya field, the gas only development, comprising a selected. As a fallback option, the Project considered
2 J.C. MACARA OTC 14040

alternatives to the all-offshore pipeline route including various Slope failure in the immediate vicinity of the pipeline may
partially overland routes across Eastern Mindoro. result in free spanning of the pipeline if soil mass subsides
The offshore survey campaign was divided into a from underneath the pipeline or impose axial or transverse
Reconnaissance Survey, a Geohazard Study and a Detailed loads on the pipeline in landslide.
Survey. An interactive exchange of information was achieved The pipeline may also be at risk from slope instability
between the parties contributing to the route selection process occurring a distance away from the pipeline if the soil failure
through the use of a Rapid Data Transfer facility (RDT). This subsequently develops into a mass gravity flow. Other
enabled detailed images of the seabed to be transmitted from phenomena not discussed further here include vibration of
the vessel to project offices in The Netherlands within hours pipeline spans due to ground shaking and the impact of
of acquisition. Routing decisions could thus be made with an Tsunamis at the landfall.
unprecedented short turn-around. Results of the routing in Fault Movement. Faulting is the deformation associated with
geohazard areas are shown in Fig. 3 and 4, which were the relative displacement of adjacent parts of the earth’s crust.
produced using a bathymetric imaging tool (Fledermaus). Fault movements may be triggered by a seismic source at
depth where ground rupture is initiated. Depending on the
Meteocean relative movement of the soil masses, different fault types are
In addition to the geophysical and geotechnical surveys no distinguished (Fig. 6).
submarine pipeline design can be completed without a The Malampaya GEP traverses four areas of active fault
comprehensive understanding of the meteocean currents that movement (Fig. 2): the Mindoro Collision Zone to the South of
the pipelines is exposed to along its route. This information Mindoro, the Central Mindoro Fault Zone and the
was used to design the on bottom stability of the pipeline. Lubang/Aglubang fault system in the Verde Island Passage
Current measurements were made at over 40 sites along between Northern Mindoro and Luzon. The pipeline response
the pipeline route in order to provide data for calculating the when subjected to various types of fault movement was
amount of weighting that would be required for stability of the analysed using the finite element program ANSYS. The
line on the bottom. The near bottom measurements were made conservative assumption of distinct fault movements along a
with rotor and vane instruments moored approximately 3 single fault with well-defined edges was made. The model
meters off the bottom, while current profiles were made using takes into account frictional resistance of the seabed and soil
acoustic Doppler current profilers in the vicinity of the stiffness. In a sensitivity analysis, a flat seabed was displaced
shallow water platform and the subsea manifold. At least a to simulate the four types of fault movement.
year of measurements at a site are normally required to give Non-burial of the offshore pipeline greatly improves
extreme value statistics but after the first deployment it resistance to fault movements. Stresses and strains in the
became obvious that almost all of the measured currents were pipeline are minimised by allowing free deformation. The
due to tides. Since accurate tidal current predictions can be pipeline should be oriented to the fault line such that the pipe
made with only a few months of data, the eight near bottom will tend to go into tension with differential movement along
meters were therefore moved to different sites during each of the fault. The optimal crossing angle depends on the fault
the four remaining deployments. The complicated topography type. Initially, the sensitivity analysis indicated a potential
along the route produced striking differences in the observed problem only in the case of reverse fault movement as seen in
tidal currents from one site to another. For the sections of the the Mindoro Collision Zone (Fig. 2). However, detailed
line in relatively shallow water, typhoon generated currents modelling of the regional bathymetry found that the
and waves estimated by hindcasts were also important in compressive forces induced in the pipeline could be
setting the criteria. These factors were combined using a accommodated.
newly developed program which sums the simultaneously Slope Stability. Submarine slope failures have been
occurring velocity components perpendicular to the pipeline. documented in several locations around the world, particularly
in areas exposed to strong wave action, seismic activity or
Seismic Design. rapid deposition of deltaic sediments. Liquefaction occurs in
Front-End Engineering and Design of the pipeline commenced sandy soils when excess pore water pressures are generated
in April 1997 and entered Detailed Design in October 1997. due to ground shaking. If the intensity and duration of the
The pipelines design team adopted a limit state design earthquake are large enough, the soil behaves like a dense
approach based on the DNV Rules for Submarine Pipeline liquid and can flow down a slope.
System, 1996 design code. The general design process was Slumps along the Malampaya pipeline alignment were
supplemented by specialist assessments to investigate the initially identified from the geophysical and sub-bottom
seismic hazards particular to the Malampaya development. profiling data acquired during the feasibility survey. Areas of
Seismic hazards may be grouped under the general terms slumping were extensively surveyed in order to find the
Fault Movement and Ground Shaking (Fig. 5). These hazards optimal routing which minimises the risk to the pipeline. In
can engender a range of geotechnical consequences affecting areas showing evidence of slumping, it was essential to
the pipeline. Fault movements impose deflections on the determine the likelihood of future failure and the risk posed to
pipeline while ground shaking can cause slope instability. the pipeline.
MALAMPAYA DEEP WATER GAS PIPELINE AND FLOWLINES: TECHNICAL AND
OTC 14040 ENGINEERNG CHALLENGES FACED IN THE EXECUTION OF THE MALAMPAYA PIPELINE SCOPE 3

Slump features were investigated by acquiring additional for flowline rotation during installation.
sub-bottom profiling data, collecting soil samples and In addition the following operating requirements and
conducting cone penetration tests (CPT). The CPT data was installation constraints were set for the design:
interpreted using liquefaction correlations. Additional cores • The footprint of the supporting mud mat be sufficient to
were selected for cyclic triaxial testing to assess the provide support in the soft soil conditions at the location
liquefaction potential of actual Malampaya soils under of the manifold;
earthquake loading. A dating procedure using a combination • The flowlines ends be allowed to move axially by 2
of soil samples and sub-bottom profiling data was being meters to allow for the maximum expansion predicted for
developed to assess the age of slumps and, therefore, their the operational design case;
likelihood of occurence. The stability of submarine slopes was • The diverless subsea connectors positioned horizontally
analysed using an infinite slope model incorporating the and 1.5 meter above the seabed;
effects of pore pressure increases in sandy soil. • The PLES be lowered with pre-installed ROV-
Mass Gravity Flow. Mass gravity flows can develop as a recoverable pig receivers for controlled flooding of the
consequence of soil instability on slopes. The general term flowlines during pre-commissioning;
covers three types of gravity driven flows: mudslides, debris • All pressure containing piping to be clad with Inconel 825
flows and turbidity currents. Distinct flow channels have been CRA material;
identified along the pipeline route, primarily offshore the • The maximum weight of each PLES structure not exceed
Bongabong and Balete river deltas (Fig. 4). 40 tons Tonnes to allow offshore transfer from the
A Transport Model was developed by a specialist transportation vessel to the installation vessel and
consultant to assess the development of a turbidity flow. The handling during final attachment and lowering.
model was calibrated against experimental flume results and
against geophysical and geotechnical information collected in As a consequence of these requirements and design
the Bongabong channels. Likely flow velocities, flow widths optimisation to incorporate the lessons learned from previous
and flow densities were predicted using the model. Gulf of Mexico installations, the final design of the
The pipeline response analysis was performed using the Malampaya PLES differed in a number of ways from those of
finite element package ANSYS. The numerical simulation was earlier PLES structures. (Fig. 7)
based on the quasi-static analysis of a long pipeline with the A seven-by-twelve metre mud mat was selected to ensure,
unit load due to a turbidity current calculated from Morison’s with a large factor of safety, that loads from the PLES would
equation. The analysis explored the sensitivity of the not exceed the bearing capacity of the soil at the manifold
parameters load width, unit load, friction force and location. The PLES was also designed to accommodate the
net pressure. predicted flowline expansion without sliding of the mud mat
Relatively low unit loads distributed over a long length of over the seabed. The sliding system that provided the
pipeline are anticipated in the runout zone of the turbidity necessary two meters for flowline expansion consisted of
current in which the pipeline is located. By allowing free Inconel plated sliding rails mounted on the mud mat and
displacement of the pipeline on the seabed, stress levels in the Tufnel coated bearing surfaces on the sliding part of the PLES
pipeline due to bending remain low. Moreover, investigation structure. As a contingency future raising and leveling of the
of the specialist scenarios has shown that for the anticipated stationary mud mats will be possible using pile connectors that
flow conditions, even pinning of the pipeline on seabed were pre-installed on the mud mats.
obstacles is unlikely to result in failure of the pipeline. The hinged yoke, used to hold the PLES and suspended
flowlines section during installation, were aligned with the
PLES Design and Installation. axes of the flowlines which achieved a centre of gravity
Diverless tie-ins between a deepwater subsea manifold and (COG) for the PLES that was located below the hinges. This
flowline require a structure at the end of the flowline provided an up-righting moment from the weight of the PLES
commonly known as a PLES (Pipeline End Structure). in the event of flowline rotation, during installation of the
Several PLES structures have been installed for deepwater Malampaya PLES due to residual strains in the flowlines from
tie-backs in the Gulf of Mexico with flowline diameters pipelaying, as has been observed in some previous Projects.
ranging from 5 to 12 inches. Significant rotation of some A swivel ring anchor flange was built into the flowline to
PLES structures have been experienced during the installation secure it to a bulkhead in the PLES with a bolted connection.
and rotations in excess of 360o have been encountered. When Spacer rings and plates were installed between the anchor
this occurs, the PLES has to be recovered to surface and re- flange and bulkhead for alignment of the ends of the piping in
attached to the end of the flowline with a rotational offset to the PLES and flowline prior to making the closing weld.
compensate for the rotation during lowering. Settlement of the The configuration of the PLES around the closing weld
PLES into the seabed due to the sliding of the supporting was designed to provide full circumferential access of the
mudmat on the seabed has also occurred. completed weld for the automatic ultrasonic testing (AUT)
The design of the Malampaya PLES units included equipment used for the non-destructive testing of the root and
provision of a hinged yoke mechanism to reduce the potential hot pass of the CRA weld.
4 J.C. MACARA OTC 14040

The dynamically positioned pipelay installation vessel was SPAN Rectification.


used to install the Malampaya flowlines and PLES The seabed relief along the route of the Malampaya pipelines
installations. is varied and it was recognised early on in the design that there
A 275 tonne “hang-off” frame was installed on the portside were likely to be many areas that would require support
of the vessel for the securing and support of the flowline upon beneath the pipeline to avoid excessive spanning. Support by
recovery from the seabed and during the connection of the means of rock dumping was selected as the preferred method
PLES structure (Fig. 8). A 300 tonne crane was also installed on the basis of cost effectiveness and minimum maintenance
on the port side of the vessel for the handling of the flowline during the operational phase. Rock dumping also provided the
end and PLES on and of the hang-off frame. The design loads flexibility in terms of quantities necessary to correct the as
for the hang-off and the crane capacity were selected to then undetermined amount of spanning.
accommodate a wet flowline recovery. A first estimate of the scope of the span rectification by
The flowlines were laid in the (conventional) S-lay mode placement of rock supports was prepared on the basis of the
with the ends fitted with a tapered swivel ring anchor flange to route selection surveys conducted in 1997.
provide the support in a slot in the hang-off frame. The last This survey had to cover an extensive area in an
section of the flowlines was marked in the 12 o’clock position inhospitable and unknown terrain and at that time the survey
of rotation of the flowline during abandonment at the end of method chosen focussed on locating the major seabed features.
pipelay. ROV inspection of the abandoned pipeline head on The survey was undertaken with a surface towed multi-beam
the subsea confirmed the minimal rotation predicted during profiler to measure the extent of the seabed obstructions and
the installation engineering. provide a first indication of the relief to be expected during
Prior to recovery of the flowline ends, the abandonment pipeline construction. It was known that the conical shape of
and recovery (A&R) cable was routed to the hang-off frame the sonar waves transmitted from the surface would introduce
on the portside of the pipelay vessel. The flowlines were then inaccuracies due to the decrease in data density at greater
recovered in the J-lay mode and once above water the load on water depths. This was accepted as the primary objective of
the A&R cable was transferred to the crane to position the the 1997 survey was to locate major obstacles on the seabed
flowline in the hang-off frame (Fig. 8). All events during the and to provide a feasible pipeline route.
recovery and hang-off went as planned and the flowlines were A second survey, this time focussed close to the seabed
successfully hung-off at the required angle of 7.5o. along the selected pipeline route, was performed in 1999 to
The next step was the preparation of the flowline end for accurately define the seabed unevenness and to also locate the
welding and mating of the PLES structures. Stabbing guides smaller obstructions that could be a hazard to the pipeline
on the PLES were used for the initial alignment (Fig. 9). Spacer during installation and subsequent operation. An ROV-borne
plates were installed between the flowline anchor flange and multi-beam profiler was employed to achieve transmission of
PLES bulkhead for final alignment of the pipe ends in the sonar waves from a location near the seabed.
preparation for the closing weld (Fig. 10). Based on the results of the 1997 survey and applying the
Welding of the first two passes of the Inconel clad conventional method for span analysis, 94 locations had
pipework required a continuous high purity argon back purge. initially been identified that would require pipe support.
Since the back of the weld is inaccessible after mating of the Evaluation of the subsequent more accurate 1999 survey
pipe ends a pre-installed purge dam was aligned with the weld results employing the some methodology concluded that
bevel during the mating process. Purging hoses had been pre- supports would be necessary at 1073 locations. This increased
installed through openings in the pig receiver. the required volume of rock from 76,000 to 340,000 tonnes.
After acceptance of the root hot pass the argon was The dramatic increase underlined the need for accurate
stopped and the dam pulled back and secured in the pig profiling of the seabed when determining the scope of seabed
receiver. Welding was then completed with a final rectification work.
examination of the completed weld with external radiography. The difference in resolution of the two survey methods in
Once the PLES was connected to the flowline all illustrated in (Fig. 13).
temporary rigging was removed and the complete assembly The next step in determining the scope of the span
lifted sideways off the hang-off seat using the crane (Fig. 11). rectification work required a re-assessment of conventional
A controlled transfer was then made to the 3.5-inch diameter methods in order to arrive at the most cost and time effective
A&R cable before PLES and flowline were lowered to the execution of the span correction work.
seabed in J-mode (Fig. 12). Opportunities to reduce the amount of rock necessary were
Both PLES units were successful lowered on the first addressed first. Pipeline installation tolerances required a
attempt. No discernible rotations were observed and they were width of 16 metre of rock support along the pipeline
placed on the seabed within the specified target box of 5 by 10 installation corridor, whereas the width of a support with the
meters at 820 meters below sea level. pipeline already in-situ is less than 2 metre. Significant
volumes of rock would therefore be saved if supports were
placed after the pipeline was installed. Two refinements were
introduced in the model for span analysis:
MALAMPAYA DEEP WATER GAS PIPELINE AND FLOWLINES: TECHNICAL AND
OTC 14040 ENGINEERNG CHALLENGES FACED IN THE EXECUTION OF THE MALAMPAYA PIPELINE SCOPE 5

• Rigid seabed conditions had been assumed during the • Reliance on the as-built surveys rather than another pre-
earlier analysis. At this stage the settlement of the pipeline dump survey by the rock placement vessel to determine
into the seabed from the reaction forces at touchdown of the exact dimensions of the supports;
the pipeline during installation were calculated and • Allowing a natural slope for the supports instead of the
included in the span analysis. 1;4 slope specified in the installation specification;
• The original analysis did not permit the occurrence of • Reduction of over dumps for small supports.
vortex induced vibrations (VIVs) and this requirement
had been for 95% of the spans the governing factor for As a result of these measures, the number of supports
pre-lay pipe support. All such spans were subjected to a installed per day increased from 15 - 20 to 30 - 40 supports
fatigue analysis in order to determine whether VIVs could per day.
be permitted for the short period between the installation For the two 16 inch corrosion resistant alloy (CRA) clad
of pipeline and the provision of post-lay supports flowlines because of the anticipated slower pipe installation
immediately following pipeline installation. rates achieved by the pipe installation vessel, as compared to
the carbon steel gas export pipeline, it was foreseen that a
The 1999 route survey also indicated individual locations considerable amount of downtime for the rock placement
where support requiring more than 2000 MT of rock were vessel could occur. This prompted a re-examination of the
predicted. The seabed near these locations was re-surveyed flowlines span support strategy and the installation of grout
during the 2000 pipeline pre-lay survey, but only within the bags utilising a vessel already mobilised for other Project
footprints of earlier surveys. In the majority of cases the rock activities (umbilical installation) provided a considerable cost
volumes could be reduced significantly by minor deviations saving opportunity while also allowing the demobilisation of
off the route centre line. the rock placement spread. The grouting spread consisted of a
The above optimisations resulted in a reduction of the turntable to deploy the deflated grout bag to the seabed. The
number of rock supports required before pipeline laying from empty bag was pulled underneath the pipeline with the ROV
144 to 69 and a reduction in the required rock volume from and, once correctly placed, filled with gout by means of a
168,000 MT to 37,000 MT. grouting umbilical connected to the surface vessel.
A further incentive for minimising the placement of pre- Span analysis for the flowlines had indicated a six to eight
lay supports is the effectiveness of pre-lay supports. The as- meter high span at one location where the seabed was sloping
built surveys revealed that additional rock had to be placed to steeply into deeper water. The seabed also comprised of
provide the envisaged support for approximately 10% of the relatively soft material. The stability of supports with a height
pre-lay supports that were installed. of six to eight metres at this location was a concern. Further
Upon installation of the pipeline and while still empty, work was therefore undertaken to eliminate the requirement
prior to flooding and hydrotesting, an as laid survey was for the support.
conducted and this revealed that there remained 929 span The as-built survey of the installed flowlines conformed
locations which were in excess of the allowable span length the presence of the predicted spans but additional analysis
for the pressure testing and subsequent operational phase of work by the design consultant and independently verified
the pipeline. As such these spans would require post indicated that the spans would disappear once the flowlines
installation rock dump to provide support. For most of the had been hydrotested.
locations span rectification was only required to avoid As the first routine annual inspection programme for the
excessive stresses during pressure testing. Malampaya pipelines and flowlines is planned for 2002 a
However the analysis work performed on these spans had fatigue analysis of the eight metre high span was performed to
used a conservative model that assumed “simple beam” determine whether the flowline would be safe with respect to
theories with full axial (compressive) loading from the test fatigue until 2002. This was performed in the event that the
pressure. For each of these spans the sagging and release of span did not disappear following the hydrotest as had been
the axial load during hydro-testing was simulated in a finite predicted. The fatigue analysis concluded that indeed the span,
element analysis using the actual pipeline and seabed profiles if it still existed following the hydrotest, could be safely left
recorded during the post-lay survey and accounting for the until the 2002 inspection programme.
sagging of the span during testing. The result of this time Another considerations for not installing supports at this
consuming work was a reduction from 929 to 665 in the location at this time was that such man-made supports would
number of spans requiring rectification. The required rock hinder any future natural settlement of the flowlines in the soft
volume was also reduced from 170,000 to 110,000 tonnes. seabed. Allowing natural settlement should reduce the risk of
Progress of the rock placement operations was reviewed any future rectification work at this location. If following the
frequently during the execution of the work, in consultation 2002 inspection programme it is concluded that span
with the contractor to identify opportunities for improving rectification work is required at a future date, then the
efficiency. Measures agreed with the installation installation of half-helical strakes instead of providing span
contractor included: support will be one of the options considered. These strakes
suppress vortex-induced vibrations and have long been used
6 J.C. MACARA OTC 14040

for this purpose on catenary risers in the Gulf of Mexico. The


VIV suppressers are fabricated from fiber-glass and can be
lowered over a pipeline and set into place by an ROV.

Conclusions
Some of the conclusions that can be drawn from the
experience gained in the execution of the Malampaya pipeline
and flowline scope are as follows:

• Long, large diameter gas pipeline can be designed


effectively in areas of seismic activity;
• Early definition of the hazards are essential to facilitate
route selection;
• Techniques are available to adequately model and
evaluate pipeline behavior under seismic loading;
• A PLES design incorporating a hinged yoke mechanism
can assist in reducing the potential for rotation
during installation;
• High resolution close to bottom surveys are required to
provide the seabed data necessary to determine the scope
for any seabed intervention (span correction) work;
• Pre-lay intervention work is ineffective and costly and
that its requirement should be challenged through
detailed analysis.

Acknowledgements
The author acknowledge the valuable contributions made by
the Malampaya Project Team members in the preparation of
the paper, specifically Jan Oude Hengel, Luuk Wellens,
Martijn Dekker, Thomas Schneider and Jeff Rimmer.
MALAMPAYA DEEP WATER GAS PIPELINE AND FLOWLINES: TECHNICAL AND
OTC 14040 ENGINEERNG CHALLENGES FACED IN THE EXECUTION OF THE MALAMPAYA PIPELINE SCOPE 7

28 km 5 04 km
Upstream Downstream
Gas d ehydratio n Catenary Anch ored Sulp hur Reco very
Leg Mo oring ( CALM)
Gas d ewp oint ing H2S removal
Con densate stabilisatio n buo y for tan ker Meterin g
Export co mpression loadin g of cond ensate Sup ply base

Batangas Power Alternative


-0m
Stations Fuel

LU ZON

24" Dry gas Manil

pip eline
- 43 m
Condensate Condensate San Lorenzo
( FG P Co p
r )
Tabangao Refinery

3rd flow line storage export


Santa Rita Batangas Si gayau
( Fi rst G asP ow er
C orp) Ilija n(NPC) Bay

(2021)
So uth C hin aS ea
MINDORO

Sub sea
man ifold 2 x 16” CRA wet gas SC38 BusuangaI sland
B ula a
l cao
B ay

Semir ar aI sland
Cul o
i n Isl and
SC38

Malampaya

- 820 m SC38
PLATFORM
Linapacan Isl and

5 Developm ent w ells


4 Ad dition al d evelop ment w ells (2009)

Fig. 1 - Malampaya Development Concept


8 J.C. MACARA OTC 14040

Fig. 2 - Malampaya Pipeline Route and Seismic Hazards


MALAMPAYA DEEP WATER GAS PIPELINE AND FLOWLINES: TECHNICAL AND
OTC 14040 ENGINEERNG CHALLENGES FACED IN THE EXECUTION OF THE MALAMPAYA PIPELINE SCOPE 9

Fig. 3 - Fledermaus Bathymetric Image of the Mindoro Collision Zone West

Fig. 4 - Fledermaus Bathymetric Image of the Bongabong Channels


10 J.C. MACARA OTC 14040

Fault Ground

HAZARD
SEISMIC
Movement Shaking

Vibration Ground
CONSEQUENCES Acceleration
GEOTECHNICAL

Soil Liquefaction
Slope
Differential Soil
Instability
Ground Consolidation
Movement

Localised soil Mass Gravity


Failure Flow
BEHAVIOUR
PIPELINE

Pipeline Free Axial /


Beam mode Pipeline
Settlement spanning transverse
deflection Fatigue
pipeline loading

Fig. 5 - Seismic Hazard Assessment

c) Oblique Slip – Vertical, Horizontal & Tensional Axial Displacement

x
y
d) Reverse Slip – Vertical & Compressive Axial Displacement

Fig. 6 - Schematic Models of Fault Movement


MALAMPAYA DEEP WATER GAS PIPELINE AND FLOWLINES: TECHNICAL AND
OTC 14040 ENGINEERNG CHALLENGES FACED IN THE EXECUTION OF THE MALAMPAYA PIPELINE SCOPE 11

Fig. 7 – PLEM GA & Elevations


12 J.C. MACARA OTC 14040

Fig. 8- flowline end in hang-off frame Fig. 9 - Mating of the PLES with the flowline
on the portside of the Solitaire

Fig. 10 – Final alignment of PLES bulkhead Fig. 11 – PLES/flowline assembly in crane for lowering
to anchor flange
MALAMPAYA DEEP WATER GAS PIPELINE AND FLOWLINES: TECHNICAL AND
OTC 14040 ENGINEERNG CHALLENGES FACED IN THE EXECUTION OF THE MALAMPAYA PIPELINE SCOPE 13

Fig. 12 – PLES submerged after transfer to A&R cable

Fig. 13 – Survey resolution

Potrebbero piacerti anche