Complete the sentence

High utilisation...

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

increases efficiency and use of


resources 0

increases variability
0

is a leading indicator for a well


functioning system 0

reduces project slippage


0

This is part of principle #6 – Visualize and limit WIP, reduce batch sizes, and manage queue
lengths

“Operating a product development process near full utilization is an economic disaster. —


Donald Reinertsen”

For more information read:

http://www.scaledagileframework.com/visualize-and-limit-wip-reduce-batch...
Question 2
In SAFe(r) a constant sense of danger refers to what?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer

PI Planning
0

System Demos
0

Launching the ART


0

Continuous Improvement
1

A constant sense of dander when modelled through proactive leadership fuels continuous
improvement and is part of heling the organisation reach the tipping point

For more information see:

http://www.scaledagileframework.com/reaching-the-tipping-point/
http://www.scaledagileframework.com/
Question 3
Which of the following is NOT a purpose of the IP iteration

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

To carry out the program level


retrospective (Inspect and Adapt) 0

To provide an opportunity for


innovation 0

To plan the next PI


0
Your Correct
Choice Correct? Score Feedback
answer answer

To provide an opportunity to identify


strategic themes 0

To carry out the program level demo to


stakeholders (Inspect and Adapt) 0

To give the team a rest from software


delivery 0

To provide an opportunity to carry out


hardening activities for the PI
0
deliverables

Identify strategic themes happens atthe enterprise portfolio level and is not part of the IP iteration

Read more at: http://www.scaledagileframework.com/guidance-six-safe-practices-for-s-sized-


teams/
Question 4
The notion that more frequent and forced integration points reduce risk is part of which lean-
agile principle?

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

#4 Build incrementally with fast,


integrated learning cycles 0

#7 Apply Cadence and synchronise


with cross domain planning 0
Your Correct
Choice Correct? Score Feedback
answer answer

#5 base milestones on objective


valuation of working systems 0

#3 Assume variability, preserve


options 0

#8 Unlock the intrinsic motivation of


knowledge workers 0

#9 Decentralise Decision Making


0

#6 Visualise and limit WIP, reduce


batch sizes and manage queue lengths 0

#2 Apply systems thinking


0

#1 Take an economic view


0

For more information on SAFe Lean-Agile principles go to the links below:

http://www.scaledagileframework.com/safe-lean-agile-principles/
http://www.scaledagileframework.com/build-incrementally-with-fast-integrated-learning-cycles/

Question 5
What approach allows us to foster innovation, manage risk and investment incrementally, and
leverage the flow and visibility of work?

Score: 1 of 1
Your Correct
Choice Correct? Score Feedback
answer answer

The Portfolio Canvas


0

The Architectural Runway


0

Backlog and Guardrails


0

The Lean Start-up cycle and Lean


Budgeting 1

The Lean Start-up cycle and Lean Budgeting provide this capability. for more information
see:https://www.scaledagileframework.com/epic/
Question 6
Complete the following phrase:

SAFe(r) is ..

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

... a freely revealed, online knowledge


base of proven success patterns, for
enterprise Lean-Agile Development
0

... a framework that provides alignment,


collobation and delivery for multiple
-1
waterfall teams working together
Your Correct
Choice Correct? Score Feedback
answer answer

... a consolidated replacement for agile


scrum and XP 0

... a way that small startup companies


can rapidly engage with implementing
0
agile cheaply and fast

See this page for a complete definition of the nature of


SAFe: http://www.scaledagileframework.com/what-is-safe/
SAFe is primarily for large scale implementations of Agile and the basis of SAFe is laid out
freely on the website. It does not replace scrum and XP, it incorporates them. It does not align
and coordinate waterfall approaches, it replaces it.

Question 7
Deliver Value Incrementally is part of which lean-agile principle?

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

#2 Apply systems thinking


0

#7 Apply Cadence and synchronise


with cross domain planning 0

#9 Decentralise Decision Making


0

#8 Unlock the intrinsic motivation of


knowledge workers 0
Your Correct
Choice Correct? Score Feedback
answer answer

#5 base milestones on objective


valuation of working systems 0

#1 Take an economic view


0

#6 Visualise and limit WIP, reduce


batch sizes and manage queue lengths 0

#4 Build incrementally with fast,


integrated learning cycles 0

#3 Assume variability, preserve


options 0

For more information on SAFe Lean-Agile principles go to the link below:

http://www.scaledagileframework.com/safe-lean-agile-principles/
Question 8
Match the following characteristics to the role

Score: 1 of 3

Your Correct
Choice Correct? Score Feedback
answer answer

Product Is Co-located with Product


1
Manager marketing/business Manager

Product
Agile team Is Co-located with agile teams 0
Owner

Product Coordinates Dependencies and


0 Agile team
Owner fosters collaboration
Question 9
What SAFE® principle allows people to do the following:

 Communicate across functional boundaries.


 Make decisions based on an understanding of the economics.
 Receive fast feedback about the efficacy of their solution.
 Participate in continuous, incremental learning and mastery.
 Participate in a more productive and fulfilling solution development process.

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

#2 – Apply systems thinking


0

#4 – Build incrementally with fast,


integrated learning cycles 0

#3 – Assume variability; preserve


options 0

#1 – Take an economic view


0

#6 – Visualize and limit WIP, reduce


batch sizes, and manage queue lengths 0

#7 – Apply cadence, synchronize with


cross-domain planning 0

#9 – Decentralize decision-making
0

#8 – Unlock the intrinsic motivation of


knowledge workers 0
Your Correct
Choice Correct? Score Feedback
answer answer

#5 – Base milestones on objective


evaluation of working systems 0

This is part of principle 8 – Unlock the intrinsic motivation of knowledge workers

For more information read:

http://www.scaledagileframework.com/unlock-the-intrinsic-motivation-of-knowledge-workers/
Question 10

Fill in the blanks

The principle of ______ tells us that :

 Most problems with our process will surface as ______


 Most of the time spent getting to market is as a result of _______
 Reducing _____ is the fastest way to reduce time to market

Score: 1 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

Systems Thinking; Delays; Delays;


Delays 1

Build incrementally with fast integrated


learning cycles; Delays; Delays; Delays 0

Build incrementally with fast integrated


learning cycles; Defects; Delays;
0
Defects
Your Correct
Choice Correct? Score Feedback
answer answer

Systems Thinking; Defects; Delays;


Delays 0

For more information on SAFe Lean-Agile principles go to the links below:

http://www.scaledagileframework.com/safe-lean-agile-principles/
http://www.scaledagileframework.com/apply-systems-thinking/
Question 11
Peter Drucker says that "to effectively lead, workers must be heard and respected".

What principle applies to this?

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

#3 – Assume variability; preserve


options 0

#8 – Unlock the intrinsic motivation of


knowledge workers 0

#4 – Build incrementally with fast,


integrated learning cycles 0

#7 – Apply cadence, synchronize with


cross-domain planning 0
Your Correct
Choice Correct? Score Feedback
answer answer

#5 – Base milestones on objective


evaluation of working systems 0

#2 – Apply systems thinking


0

#9 – Decentralize decision-making
0

#6 – Visualize and limit WIP, reduce


batch sizes, and manage queue lengths 0

#1 – Take an economic view


0

This is part of principle 8 – Unlock the intrinsic motivation of knowledge workers

- Create an Environment of Mutual Influence

For more information read:

http://www.scaledagileframework.com/unlock-the-intrinsic-motivation-of-knowledge-workers/
Question 12
What do the following activities relate to:
- Pick the first value stream
- Select the first ART
- Create a preliminary plan for additional ARTs and value streams

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

Create the implementation plan


0

Reaching the Tipping point


0
Your Correct
Choice Correct? Score Feedback
answer answer

Create a Lean-Agile Centre of


Excellence 0

Identify value streams and ARTs


0

Did you choose "Identify value streams and ARTs"?


That is the previous critical step in the SAFe Implementation Roadmap.

Read more at: http://www.scaledagileframework.com/create-the-implementation-plan/


Question 13
What is being described in the following statement:It applies Lean-Agile principles, frameworks
and practices to the specification, engineering and deployment of large solutions
Score: 0 of 1

Your
Choice Correct? Score Feedback
answer

It is a
description
of Business
Solutions
0
and Lean
Systems
Engineering

It is a
description
of DevOps
0
and Release
on Demand

It is a
description 0
of Team and
Your
Choice Correct? Score Feedback
answer

Technical
Agility

It is a
description
of Lean-
0
Agile
leadership

It is a Lean Portfolio Management is described as the alignment


description of strategy and execution by means of applying Lean
of Lean and systems thinking approaches to strategy and
0
Portfolio investment funding, Agile portfolio operations, and
Management governance.https://www.scaledagileframework.com/lean-
portfolio-management/
Question 14
Match the following

Score: 1 of 4

Your answer Choice Correct? Score Feedback Correct answer

Large (standalone)
solutions do not require
Overlays the portfolio management.
strategy and Often the situation where a Complex
governance Large consulting firm is developments not
0
necessary to Solution providing a solution to requiring wider
manage a wide their customers. Portfolio management
range of work management exists on the
customer side, not on the
engineering side

The most basic Large integrated


This configuration is for
configuration of solutions that
Full 0 the largest and most
the framework; require alignment
complex organisations
Provides the both for delivery
Your answer Choice Correct? Score Feedback Correct answer

minimal elements and for strategy and


necessary to be funding
successful

The most basic The most basic


configuration of Essential SAFe is the bare configuration of the
the framework; minimum that can be framework;
Provides the Essential 1 implemented successfully. Provides the
minimal elements This is the place where minimal elements
necessary to be most organisations start. necessary to be
successful successful

Large integrated In this situation an Overlays the


solutions that organization is running strategy and
require alignment multiple value streams that governance
Portfolio 0
both for delivery require coordination for necessary to
and for strategy funding and other manage a wide
and funding resources range of work
These definitions can be understood at the landing page for scaled agile
- http://www.scaledagileframework.com

Question 15
What is:

 submitted by the Epic owner,


 based on the Lean Business Case,
 at the end of 'Analysing', and
 is enacted by the Lean Portfolio Management

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

The Epic Hypothesis Statement


0
Your Correct
Choice Correct? Score Feedback
answer answer

Lean Business Case


0

Weighted Shortest Job First


(WSJF) 0

Solution Alternatives
0

The Go/No-Go decision


0

The Minimum Viable product


(MVP) 0

Submitting the Lean Business Case to Lean Portfolio Management (LPM) is one of the
responsibilities of the Epci Ownerhttps://www.scaledagileframework.com/epic-owner/
Question 16
Which of the following statements is not true about queues

Score: 1 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

Motivation of team decreases as queue


length increases 0

Cycle times, risk, and variability of


outputs increase as queue length
0
increases
Your Correct
Choice Correct? Score Feedback
answer answer

Control of inputs increase as queue


length increases 1

Quality of outputs decreases as queue


length increases 0

Principle #6 – Visualize and limit WIP, reduce batch sizes, and manage queue lengths

http://www.scaledagileframework.com/visualize-and-limit-wip-reduce-batch-sizes-and-manage-
queue-lengths/
Question 17
In SAFe(r) - How many dedicated individuals does it take to create an effective LACE team and
accomplish the change?

Score: 1 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

The size is dependent on the size of the


organisation but can often start with 2-3
people, with 4-6 able to support a few 1
hundred practitioners.

It must contain the system architect, the


business owner, the RTE and at least one
0
STE

No less than 3 and no more than 9. An


ideal size is 7 people plus or minus 2. 0

Read more at: http://www.scaledagileframework.com/LACE/

Question 18
What is the primary reason that requires the establishment of some form of LACE in SAFe(r)
Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

because we need to "Train everyone;


Launch the Train" 0

True - but not


People naturally resist change and for
part of the
this reason the organisation must reach
LACE, thisis
the point where the compelling
0 part of reaching
imperative is to achieve the change
the tipping
rather than resist it
point

Because we need to take an agile,


incremental, approach to
implementation, just as we do with 0
solution development

The people qualified to drive the


change usually have full-time
responsibilities in their current roles;
While they can support change with a
portion of their time, a smaller, more
dedicated group of people is required to 0
drive the transformation throughout the
organization. The primary task of these
latter group of people is to drive and
implement change.

The other answers are all valid concepts but do not relate to the question.

Read more at: http://www.scaledagileframework.com/LACE/


Question 19
The concept that a 'system must be managed, it will not manage itself' is part of which lean-agile
principle?

Score: 0 of 1
Your Correct
Choice Correct? Score Feedback
answer answer

#6 Visualise and limit WIP, reduce


batch sizes and manage queue lengths 0

#4 Build incrementally with fast,


integrated learning cycles 0

#9 Decentralise Decision Making


0

#7 Apply Cadence and synchronise


with cross domain planning 0

#2 Apply systems thinking


0

#5 base milestones on objective


valuation of working systems 0

#1 Take an economic view


0

#3 Assume variability, preserve


options 0

#8 Unlock the intrinsic motivation of


knowledge workers 0

For more information on SAFe Lean-Agile principles go to the link below:

http://www.scaledagileframework.com/safe-lean-agile-principles/
Question 20
In the context of the Lean Portfolio, which three of the following elements relate to Agile
Portfolio Operations (Choose 3)
Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

Coordinate Value Streams


1

Fund Value Streams


-1

Support Agile PMO, LACE, RTE and


Scrum Master communities of practice 0

Connect the Portfolio to Enterprise


Strategy 0

Sustain and Improve


1

Measure Lean Portfolio Performance


0

Forecast and Budget Dynamically


0

Establish Portfolio Flow


0

Coordinate Continuous Compliance


0

Question 21
What does LACE mean?

Score: 1 of 1
Your Correct
Choice Correct? Score Feedback
answer answer

Lean Agile Centre of Excellence


1

Low Automation; Clear


Expression 0

Look; Assess; Change; Extend


0

Read more at: http://www.scaledagileframework.com/LACE/


Question 22
When Peter Drucker describes knowledge workers as "individuals that know more about the
work they perform than their bosses do", what SAFe® principle applies?

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

#5 – Base milestones on objective


evaluation of working systems 0

#7 – Apply cadence, synchronize with


cross-domain planning 0

#4 – Build incrementally with fast,


integrated learning cycles 0

#2 – Apply systems thinking


0

#8 – Unlock the intrinsic motivation of


knowledge workers 0
Your Correct
Choice Correct? Score Feedback
answer answer

#9 – Decentralize decision-making
0

#1 – Take an economic view


0

#3 – Assume variability; preserve


options 0

#6 – Visualize and limit WIP, reduce


batch sizes, and manage queue lengths 0

This is part of principle 8 – Unlock the intrinsic motivation of knowledge workers

For more information read:

http://www.scaledagileframework.com/unlock-the-intrinsic-motivation-of-knowledge-workers/
Question 23
Understanding, exploiting and managing variability, and frequent integrations are part of :

Score: 0 of 1

Your answer Choice Correct? Score Feedback Correct answer

Leadership
0

Innovation
0

Flow
0

Agile-scrum
0

Quality
0
Your answer Choice Correct? Score Feedback Correct answer

Relentless improvement
0

Value
0

The concepts are part of the House of Lean pillar of FLOW

http://www.scaledagileframework.com/lean-agile-mindset/
Pillar 2 - Flow

Question 24
In SAFe(r) which of the following is not a feature of setting a vision for change

Score: 1 of 1

Your answer Choice Correct? Score Feedback Correct answer

Better Alignment
0

Improved Motivation
0

Clarified Purpose
0

Faster Deployment
1

Establishing the vision for change is part of reaching the tipping point.

For more information see:

http://www.scaledagileframework.com/reaching-the-tipping-point/
http://www.scaledagileframework.com/
Question 25
Decentralise Decision making, is part of which element of the House of Lean?

Score: 0 of 1

Your answer Choice Correct? Score Feedback Correct answer

Respect for people and culture


0

Flow
0

Leadership
0

Governance
0

Value
0

Relentless Improvement
0

Innovation
0

Quality
0

The concepts are part of the House of Lean foundation of Leadership

http://www.scaledagileframework.com/lean-agile-mindset/
Foundation - Leadership

Question 26
You are a Business manager, wanting togain supoprt for a large initiave that you think will have
great benefit for the orgnaisation.You have worked up an Epic Hypothesis and are at the point
where you are ready to define an experiment to test assumptions, what are you doing?(Choose
best answer)

Score: 1 of 1
Your Correct
Choice Correct? Score Feedback
answer answer

Defining the Lean Business Case


0

Defining Solution Alternatives


0

Refining Understanding
0

Defining the Minimum Viable


product (MVP) 1

An Epic, in SAFE(r) is defined as a large product initiave, which has a hypothesis and which
defines the MVP as an experiment to test
assumptions.https://www.scaledagileframework.com/epic-owner/
Question 27
Who approves epics, using what as an input?

Score: 0 of 1

Your
Choice Correct? Score Feedback
answer

The Epic Owner, The Epic Hypothesis is just the starting point, and the
using the Epic Epic Owner alone cannot approve it for
Hypothesis 0 implementation (although they may be part of the LPM
Statement team)

The Lean
Portfolio
Management
These elements are defined after approval, not before
team, using 0
decomposed
solution/program
Epics,
Your
Choice Correct? Score Feedback
answer

capabilities and
features

The Lean
Portfolio
Management
team, using the Defined in the POPM courseware and at this
Lean Business 0 link: https://www.scaledagileframework.com/portfolio
Case and backlog/
associated
artefacts

Question 28
Lead the change, is part of which element of the House of Lean?

Score: 0 of 1

Your answer Choice Correct? Score Feedback Correct answer

Governance
0

Flow
0

Value
0

Respect for people and culture


0

Leadership
0

Quality
0
Your answer Choice Correct? Score Feedback Correct answer

Innovation
0

Relentless Improvement
0

The concepts are part of the House of Lean foundation of Leadership

http://www.scaledagileframework.com/lean-agile-mindset/
Foundation - Leadership

Question 29
In the context of the ART and the core compentency of DevOps and release on demand, what are
three influencers?(Choose three)

Score: 0 of 1

Your answer Choice Correct? Score Feedback Correct answer

Vision
0

Automated Testing Tools


0

UX
0

The DevOps Institute


0

Architecture
1

Automated Deployment Tools


0

Per the SAFe(r) tarining course material ARTs in a DevOps and Release on Deman context
operate with guidance from Vision, Architecture, and UX

Question 30
What is being described in the following statement:It aligns strategy with execution; affecting
the way in which we set strategy, fund change, and manage the governance of change delivery
Score: 0 of 1

Your
Choice Correct? Score Feedback
answer

It is a
description
of Lean-
0
Agile
leadership

It is a
description
of Team and
0
Technical
Agility

It is a
description
of Lean
0
Portfolio
Management

It is a
description Business Solutions and Lean Systems Engineering is
of Business described as the application of lean-Agile principles and
Solutions practices to the design, engineering and deployment of
0
and Lean software applications and cyber-physical
Systems systemshttps://www.scaledagileframework.com/business-
Engineering solutions-and-lean-systems

It is a
description
of DevOps
0
and Release
on Demand
Question 31
Consider Carefully; Act Quickly, is part of which pillar of the House of Lean?

Score: 0 of 1

Your answer Choice Correct? Score Feedback Correct answer

Leadership
0

Respect for people and culture


0

Relentless Improvement
0

Quality
0

Innovation
0

Flow
0

The concepts are part of the House of Lean pillar of Relentless Improvement

http://www.scaledagileframework.com/lean-agile-mindset/
Pillar 4 – Relentless Improvement

Question 32
The need to understand behavour and architecture at a higher level is part of which lean-agile
principle?

Score: 0 of 1
Your Correct
Choice Correct? Score Feedback
answer answer

#4 Build incrementally with fast,


integrated learning cycles 0

#6 Visualise and limit WIP, reduce


batch sizes and manage queue lengths 0

#3 Assume variability, preserve


options 0

#5 base milestones on objective


valuation of working systems 0

#9 Decentralise Decision Making


0

#7 Apply Cadence and synchronise


with cross domain planning 0

#2 Apply systems thinking


0

#1 Take an economic view


0

#8 Unlock the intrinsic motivation of


knowledge workers 0

For more information on SAFe Lean-Agile principles go to the link below:

http://www.scaledagileframework.com/safe-lean-agile-principles/
Question 33
What are the relationships in respect of bringing Epics from the Go/no-go point to being 'Done'?

Score: 0 of 1
Your Correct
Choice Correct? Score Feedback
answer answer

The PO/PM drives the activity and the


Epic owners are key stakeholders 0

The Epic owner drives the activity and


the PO/PM are key stakeholders 0

Form the decision point (go/no-go) the PO/PM takes over the driving role.Epic Owners remain
key stakeholders and may also 'shepherd' the Epic through the implementation process, but the
driver has shifted to the PO/PM role.https://www.scaledagileframework.com/epic-
owner/https://www.scaledagileframework.com/product-
owner/https://www.scaledagileframework.com/product-and-solution-management/
Question 34
The development manager is not a role that is included in the configuration role definitions for
team, program, large solution, nor for Portfolio.

So why is this role important?

Score: 1 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

Although we have self-organising and


autonomous teams in place, they will still
require direction in their day to day work, 0
this is the role of the development manager

It is not important. It is a waterfall/Industrial


paradigm role that is not neccessary under
SAFe because SAFe has a full set of roles to 0
manage all requirements
Your Correct
Choice Correct? Score Feedback
answer answer

At each level of SAFe configuration the


development manager runs the three key
roles (Product/solution management, 0
Development/architectire, and coordination)

SAFe teams are focused on delivery, and to


do that job are empowered in many ways,
but there still remains a need for
management outside of the ARTs to provide
1
for aspects such as pastoral care, risks and
issues management, and for building
capacity and capability in the teams.

The Development management (or analgous) role does exist outside the formal structures of
SAFe and this recognition identifies that line management of some kind is still required, for
many good reasons.

Read more at: http://www.scaledagileframework.com/lean-agile-leaders/


Question 35
What order should the following things be done in?

Score: 0 of 5

Your Correct
Choice Correct? Score Feedback
answer answer

Identify the Operational Value


2 0 1
Stream(s)

Identify the systems that support the


3 0 2
value stream(s)

Identify the people that support the


4 0 3
systems

Define the Development Value


5 0 4
Stream(s)
Your Correct
Choice Correct? Score Feedback
answer answer

Understand how Development Value


1 0 5
Streams go across boundaries
Read more at: http://www.scaledagileframework.com/identify-value-streams-and-arts/
Question 36
Trading off and sequencing for maximum benefit is part of which lean-agile principle?

Score: 1 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

#7 Apply Cadence and synchronise


with cross domain planning 0

#5 base milestones on objective


valuation of working systems 0

#6 Visualise and limit WIP, reduce


batch sizes and manage queue lengths 0

#9 Decentralise Decision Making


0

#4 Build incrementally with fast,


integrated learning cycles 0

#2 Apply systems thinking


0

#8 Unlock the intrinsic motivation of


knowledge workers 0
Your Correct
Choice Correct? Score Feedback
answer answer

#1 Take an economic view


1

#3 Assume variability, preserve


options 0

For more information on SAFe Lean-Agile principles go to the link below:

http://www.scaledagileframework.com/safe-lean-agile-principles/
Question 37
Informed decision making via fast feedback is part of what?

Score: 0 of 1

Your answer Choice Correct? Score Feedback Correct answer

Leadership
0

Flow
0

Relentless Improvement
0

Quality
0

Value
0

Respect for people and culture


0

The concepts are part of the House of Lean pillar of FLOW

http://www.scaledagileframework.com/lean-agile-mindset/
Pillar 2 - Flow

Question 38
Emphasize life-long learning, is part of which element of the House of Lean?

Score: 0 of 1

Your answer Choice Correct? Score Feedback Correct answer

Leadership
0

Value
0

Flow
0

Relentless Improvement
0

Quality
0

Innovation
0

Respect for people and culture


0

Governance
0

The concepts are part of the House of Lean foundation of Leadership

http://www.scaledagileframework.com/lean-agile-mindset/
Foundation - Leadership

Question 39
Implement a constant sense of danger is part of which pillar of the House of Lean?

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer

Flow
0

Relentless Improvement
0

Innovation
0

Leadership
0

Respect for people and culture


0

Quality
0

The concepts are part of the House of Lean pillar of Relentless Improvement

http://www.scaledagileframework.com/lean-agile-mindset/
Pillar 4 – Relentless Improvement

Question 40
Select the item that is not an aspect of systems thinking

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

Optmising a component does not


optimise a system 0

Synchronise with cross domain


planning 0
Your Correct
Choice Correct? Score Feedback
answer answer

The organisation building the


solution is a system 0

The value of a system passes through


its interconnections 0

The solution itself is a system


0

Optimise the full value stream


0

For more information on SAFe Lean-Agile principles go to the link below:

http://www.scaledagileframework.com/safe-lean-agile-principles/

Apply cadence and synchronise with cross domain planning is a principle in its own right (#7)

Question 41
What uses the concept of Minimum Viable Product and quantifiable metrics focused on
outcomes to support company strategy

Score: 0 of 1

Your answer Choice Correct? Score Feedback Correct answer

GEMBA
0

MUDA
0

Innovation Accounting
0
Your answer Choice Correct? Score Feedback Correct answer

Lean Product Development


0

MBWA
0

Lean Governance
0

Agile-Scrum
0

Business owners
0

Innovation Accounting (Eric Ries) uses the following three basic steps:

1) It uses a minimal viable product (MVP) to establish real data on where the company stands at
any
given juncture. An MVP is the fastest way to establish a customer feedback loop with minimal
output of effort.

Its primary goal is to test fundamental business hypotheses without having to perfect the product
or service in question too prematurely.

2) Using the MVP, start-ups, through many attempts, move from the baseline to the ideal, when
the company then reaches a decision point.

3) At this juncture, a company is either making solid progress toward the ideal enough that it
makes sense to continue, or persevere. If not, the strategy must be deemed flawed and in need of
serious change―or as Ries labels it, a pivot, which starts the process all over again and in a more
productive fashion than before.

Links:

http://lexicon.ft.com/Term?term=innovation-accounting
http://theleanstartup.com/
https://www.businessopportunity.com/Blog/innovation-accounting-lean-star...
Question 42
Match the following characteristics to the role

Score: 1 of 5

Correct
Your answer Choice Correct? Score Feedback
answer

Chief Scrum Master for the Release Train


Systems Team 0
Train Engineer

owns, defines and


Product Product
prioritizes the Program 1
Management Management
Backlog

Provide guidance and


System Architect-
Business Owners technical enablement for 0
Engineering
the Train

Provides process and tools


System Architect-
to integrate assets early and 0 Systems Team
Engineering
often

Release Train Key stakeholders on the


0 Business Owners
Engineer ART
Question 43
In SAFe(r) - What is the purpose of an development value stream?

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

This is the
It is used to deliver customer
recommended scrum
end value. 0
team size
Your Correct
Choice Correct? Score Feedback
answer answer

It is used to identify the steps,


value, people and systems and
0
lead time.

It is used to build systems and


capabilities that enable
0
operational value streams.

Read more at: http://www.scaledagileframework.com/identify-value-streams-and-arts/


Question 44
What Core Competency is described by the following?

 Self organising agile teams


 organized around continuous delivery
 delivers working tested system increments at a regular cadence and synchronized
 Operates within guidance fom Vision, Architecture, and UX
 Performs face-to-face planning

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

Lean Portfolio Management


0

Team and Technical Agility


0

Lean-Agile Leadership
0

DevOps and Release on Demand


0
Your Correct
Choice Correct? Score Feedback
answer answer

Business Solutions and Lean


Systems 0

https://www.scaledagileframework.com/blog/welcome-to-safe-4-6-for-lean-e...
Question 45
Select the item in the list below that is NOT part of forming the 'sufficiently powerful guiding
coalition' in SAFe(r)

Score: 0 of 1

Your Correct
Choice Correct? Score Feedback
answer answer

Train a number of Lean-Agile change


agents as SAFe Program Consultants
0
(SPCs)

Train everyone; Launch the Train


0

Charter a LACE
0

Train executives, managers, and other


leaders 0

"Train Everyone; Launch the train" is not part of forming the guiding coalition, it is part of the
implementation roadmap.

Read more at: http://www.scaledagileframework.com/LACE/


Question 46
Match the following defintions of LACE:

Score: 0 of 3
Your answer Choice Correct? Score Feedback Correct answer

Independent business Single portfolio, modest


units, autonomous SAFe size, values streams and
portfolios. Funding for ARTS under common
LACE tools, people and Centralised 0 budget. Funding for
coaching under LACE tools, people and
individual business unit coaching all under the
budget. same budget

Core practices developed


centrally, shared and Independent business
adapted locally. units, autonomous SAFe
Effective 2-way portfolios. Funding for
communication local to Decentralised 0 LACE tools, people and
central. Funding for coaching under
LACE split, some individual business unit
centrally and some budget.
locally

Core practices developed


Single portfolio, modest centrally, shared and
size, values streams and adapted locally.
ARTS under common Effective 2-way
Hub-and-
budget. Funding for 0 communication local to
spoke
LACE tools, people and central. Funding for
coaching all under the LACE split, some
same budget centrally and some
locally
Read more at: http://www.scaledagileframework.com/LACE/
Question 47
Match the following governance characteristics to the role

Score: 3 of 3

Your Correct
Choice Correct? Score Feedback
answer answer

Product Product
Owns Program backlog 1
Manager Manager
Your Correct
Choice Correct? Score Feedback
answer answer

Product Product
Owns Team Backlog 1
Owner Owner

Contributes to Intentional
Agile teams 1 Agile teams
Architecture, owns Emergent Design
Question 48
GEMBA is part of which pillar of the House of Lean?

Score: 0 of 1

Your answer Choice Correct? Score Feedback Correct answer

Leadership
0

Quality
0

Respect for people and culture


0

Innovation
0

Flow
0

Relentless Improvement
0

The concepts are part of the House of Lean pillar of INNOVATION

http://www.scaledagileframework.com/lean-agile-mindset/
Pillar 3 - Innovation

Question 49
The Epic owner is responsible for defining the Epic, it's MVP and Lean Business Case and
getting it approved; after that they hand over to the Business Owner for implementaiton, with no
further responsibilities.
Score: 0 of 1

Your answer Choice Correct? Score Feedback Correct answer

True 0

False 0
It is correct that the Epic Owner is responsible for driving the Epic through to the Go/no-go
decision point (approval). But their responsibilities do not end there. After the Epic has been
accepted for implementation the Epic Owner must collaborate with Agile teams to shepherd the
development and realize the benefits. Depending on the situation the Epic Owner may stay
engaged on an ongoing basis.https://www.scaledagileframework.com/epic-owner/
Question 50
Deliver early and often is part of which lean-agile principle?

Score: 0 of 1
Your Correct
Choice Correct? Score Feedback
answer answer

Your Correct
Choice Correct? Score Feedback
answer answer

#9 Decentralise Decision Making


0

#7 Apply Cadence and synchronise


with cross domain planning 0

#3 Assume variability, preserve


options 0

#2 Apply systems thinking


0

#1 Take an economic view


0
Your Correct
Choice Correct? Score Feedback
answer answer

#8 Unlock the intrinsic motivation of


knowledge workers 0

#4 Build incrementally with fast,


integrated learning cycles 0

#5 base milestones on objective


valuation of working systems 0

#6 Visualise and limit WIP, reduce


batch sizes and manage queue lengths 0

For more information on SAFe Lean-Agile principles go to the link below

http://www.scaledagileframework.com/safe-lean-agile-principles/