CC28 – Balanced Cantilever Bridge
I. 34 + 60 + 34 m
II. 60 + 60 m
CC28 – Balanced Cantilever Bridge
I. 34m + 60m + 34m
Structure Type : Cast-in-Situ PSC Box Girder
CC28 – Balanced Cantilever Bridge
I. 34 + 60 + 34m Span - General Arrangement
CC28 – Balanced Cantilever Bridge
I. 34 + 60 + 34 Cross Sections
Overall Width of Deck = 8.844 m
Depth of the Box Girder: Varies from 5m at intermediate Piers to 2.1m at Mid-Span
- Midas Civil has been used for numerical modelling and Structural Analysis
- Super Structure (Box Girder) Piers and Piles have been modelled as Line Element
- Pile Cap has been modelled as plate element.
- Point Spring Supports to take the effect of soil.
CC28 – Balanced Cantilever Bridge
I. 34 + 60 + 34 Analysis & Design
- Concrete has been modelled with time dependent properties in Midas Civil
- Creep and Shrinkage and compressive strength gain behaviour has been defined as
per CEB-FIP
CC28 – Balanced Cantilever Bridge
I. 34 + 60 + 34 Analysis & Design
- Internal Prestressing
- 19T15 and 12T15 anchorages
CC28 – Balanced Cantilever Bridge
I. 34 + 60 + 34 Analysis & Design
- Precision: Only 6mm of difference between the theoretical value and the
observed value of deflection at the cantilever tips, just before stitching.
CC28 – Balanced Cantilever Bridge
I. 34 + 60 + 34 Analysis & Design
- Deformation, including the effect of creep after 120 years
- Midas Civil has been used for numerical modelling and Structural Analysis
- Super Structure (Box Girder) Piers and Piles have been modelled as Line Element
- Pile Cap has been modelled as plate element.
- Point Spring Supports to take the effect of soil.
CC28 – Balanced Cantilever Bridge
II. 60 + 60m Construction Sequence & Analysis
CC28 – Balanced Cantilever Bridge
II. 60 + 60m Construction Sequence contd…
CC28 – Balanced Cantilever Bridge
II. 60 + 60m Construction Sequence contd…
CC28 – Balanced Cantilever Bridge
II. 60 + 60m Construction Sequence contd…
CC28 – Balanced Cantilever Bridge
II. 60 + 60m Analysis & Design
- Internal Prestressing
- 19T15 and 12T15 anchorages
CC28 – Balanced Cantilever Bridge
II. 60 + 60m Analysis & Design
- Maximum Stress (Tension) at Top Fibre Envelope (during construction)
Intermediate Piers
P235: Free Pier
P236: Integral Pier
P237: Integral Pier
P238: Free Pier
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Construction Sequence contd…
- Internal Prestressing
- 19T15 and 12T15 anchorages
CC26R – Balanced Cantilever Bridge
I. 37 + 69.9 + 67 + 55 + 34m Analysis & Design
Stress Check for Service Loads: Normal Case