Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
The complete ‘Instructions for Completing and Submitting Assignments’ and ‘Technical Instructions for
Completing Assignments’ must be downloaded from eLearn. It is essential that the complete
instructions be studied prior to commencing your assignment. The following points highlight only a few
important notes.
5) If you fail to follow these instructions carefully, the IMM Graduate School cannot accept responsibility
for the return of the assignment. It may even result in your assignment not being marked.
6) Retain a copy of your assignment before submitting it, in case of a system error.
1.2 Select the best example of work that can be defined as a project.
a. A contract to construct sports stadia for each year of the Olympic games.
b. The manufacturing of production cars.
c. The process to make a vat of beer.
d. To design and implement a new financial product for a high street bank.
1.3 From the following, choose the statement that best defines project
management.
a. The application of knowledge to project activities to meet the project
requirements.
b. The design of the project.
c. The operation of the project when it is complete.
d. The application of processes, methods, knowledge, skills, tools and
experience to achieve the project objectives.
1.6 Identify the responsibility that relate to the project sponsor from the following:
a. Manage the disposal process
b. Realise benefits for the company
c. Select the project team
d. Manage the sub-contractors
1.7 A project manager’s job description will include which task from the ones listed
below?
a. To achieve the critical success factors of finishing the project on time and
within budget
b. To select the company’s employees
c. To take minutes at meetings
d. To do all the project administration
1.8 Among others, the responsibilities of the Project Steering Board are?
a. The project steering board consists of a small group of eminent
professionals
b. They provide an independent overview of the project’s feasibility
c. They manage the project
d. They do the books of the project
1.9 Which of the following could the project manager use to define project success?
a. The project was finished before another company project
b. The project was mentioned in the local paper
c. The project finished on time
d. The project was undergoing careful review
1.10 Choose the attributes of a project life cycle from the following.
a. The project is may be subdivided into phases.
b. Each phase produces a distinct deliverable.
c. Each phase repeats itself many times over the duration of the project
d. Subdivide the project into work packages.
Questions 1.11 to 1.21 are based on the following two projects that are being
considered during a selection process at a discount rate of 12%.
Project Planet
Year Cash Flow
0 60 000
1 35 000
2 20 000
3 15 000
4 10 000
Project Quad
Year Cash Flow
0 45 000
1 30 000
2 15 000
3 10 000
4 10 000
1.18 Give the value of the present value for Project Quad in year 4.
a. 6 355
b. 6 300
c. 6 400
d. 6 360
1.22 As project manager you have been asked by the project sponsor to produce a
Project Charter. Which of the following relates to a Project Charter?
a. A document issued by the project initiator or sponsor that formally
authorises the existence of a project.
b. A document that quantifies the project’s profit and loss accounts.
c. A certificate of completion that is given to the project sponsor by the
project manager on completion of the project.
d. A document that provides the floor manager with the authority to use
organisational resources.
1.23 The feasibility study confirms that the project is feasible within the identified
constraints. Which of the following constraint would normally be considered?
a. The product life cycle
b. The execution strategy
c. The company’s organisation structure
d. The project life cycle
components.
ASSIGNMENT TOTAL: 50