Sei sulla pagina 1di 7

Shop Drawings and Submittals: Purposes,

Process, and Problems


By Kenneth A. Slavens

Submittals are a formalized means uments’ requirements as typical. “fully execute the Work described in
of communication in construction Sometimes, the design profession- the Contract Documents . . . . “3 You
and a building block to a successful al may only tell the contractors the need to determine what is defined
project. They can also have unwel- performance requirements the com- as the “Contract Documents.”4 The
come consequences. pleted work must meet. The specific items constituting contract docu-
design of how to achieve that perfor- ments are drawings, specifications,
I. The Role of Shop mance is left to the general contrac- the agreement, general conditions,
Drawings and Submittals tor and those under its contractual etc., which is a definition that has
umbrella. This allows those with remained consistent for decades.
AIA Document A201-2017, Gen-
more knowledge and greater ex- The notable absence from the list is
eral Conditions of the Contract for
pertise to design and install certain submittals and shop drawings. The
Construction (General Conditions)
components. Common examples General Conditions state specifically
defines the role of shop drawings as
are curtain walls, steel connections, “submittals are not Contract Docu-
the means to demonstrate “how the
or HVAC systems. The submittal ments.”5
Contractor proposed to conform to
the information given and the design process forces the contractor to show
how it intends to execute the work
II. Contractor and Architect’s
concept expressed in the Contractor Contractual Obligations
Documents for those portions of the and allows the design professional
Work . . . require[ing] submittals . . . .”1 to review those intentions for com- The contract documents assign
pliance with the design intent. primary responsibilities for shop
Submittals, which include shop
drawings, fill various functions in Of equal importance is understand- drawings to the contractor and sec-
construction administration. Some ing that submittals are not part of the ondarily to the design professional.
are purely administrative, such “Work.”2 The contract for construc-
tion and the General Conditions in- A. Contractor’s Contractual
documenting that operating or train- Obligations
ing manuals have been provided. corporate into the owner-contractor
Other submittals are the contractor’s agreement obligates the contractor to The AIA’s General Conditions de-
means of communicating what it in-
tends to construct or what the gen- 1. AIA Document A201-2017, General Conditions of the Contract for Construction §3.12.4.
eral contractor or its subcontractors 2. AIA Document A201-2017, General Conditions of the Contract for Construction,
may have to design. §1.1.3. (The 2017 version of AIA Family of documents was recently released; how-
ever, the language related to the submittal process has remained unchanged in
Delegation of aspects of the design the decennial revisions of these documents.)
by the lead design professional is
common. No architect or engineer 3. Article 2, AIA Document A101-2017, Standard Form Agreement between Owner
and Contractor.
can design every detail of a project.
Owners cannot afford the cost of a 4. Article 1, AIA Document, A101-2017, Standard Form of Agreement between
design professional trying to design Owner and Contractor; AIA Document A201-2017, General Conditions of the
Contract for Construction, §1.1.1.
the minute details. Some design re-
sponsibilities are routinely delegated 5. AIA Document A201-2017, General Conditions of the Contract for Construction, § 3.12.4.
to contractors. The shop drawing Kenneth A. Slavens, a partner at Husch Blackwell LLP, represents architecture, en-
process formalizes the method for a gineering and construction clients in the areas of litigation and alternative dispute
contractor to demonstrate how it will resolution. He is the co-leader of the firm’s Construction and Design group. In addi-
tion to being a trusted client advisor, Ken is a member of the American Arbitration As-
accomplish these design obligations. sociation Master Mediator Panel. He frequently mediates and arbitrates construction
The American Institute of Archi- disputes. Ken is the past chair of both the Missouri Bar Construction Law Committee
tects (AIA) family of contract docu- and the Defense Research Institute Construction Law Committee. Ken has been recog-
nized by his peers for inclusion in Best Lawyers in America, Litigation-Construction,
ments is reportedly the most widely 2005-2017 and was twice the St. Louis Litigation-Construction “Lawyer of the Year.”
used standard form contracts in the He also has been named to the Missouri & Kansas Super Lawyers for Construction
construction industry. This article Litigation, 2006-2016, and a Top 50 St. Louis Lawyer for 2008, 2013-2015. He is AV-
will reference the AIA Contract Doc- Preeminent Rated in Martindale Hubble. Ken received a B.A. and M.A. in Political
Science from the University of Missouri – St. Louis and J.D. from St. Louis University.

10 THE ST. LOUIS BAR JOURNAL/ FALL 2017


THE ST. LOUIS BAR JOURNAL/WINTER 2008 11
fine shop drawings as “drawings, dia- tation, the contractor remains at risk The architect must review submittals
grams, schedules, and other data spe- for the deviation in the submittals.16 and take the appropriate action. The
cifically prepared for the Work by the When the design professional del- architect’s obligations are in the Gen-
Contractor or a Subcontractor, manu- egates full or partial design responsi- eral Conditions and in AIA Document
facturer, supplier, or distributor to il- bility to the contractor, responsibility B101-2017, Standard Form Agreement
lustrate some portion of the work.”6 becomes a bit more enigmatic. As between Owner and Architect.
The contractor is obligated to re- a general proposition, the General The architect’s obligations are lim-
view the submittal for compliance Conditions acknowledge contractors ited by comparison to the contrac-
with the contract documents and do not provide professional design tor’s. Review is limited to checking
approve it prior to submission to services.17 The common exceptions for conformance with information in
the design professional.7 Contrac- may involve the contractor’s means, the contract documents and the de-
tor must provide submittals with methods, sequences, and procedures sign concept.22
“reasonable promptness” absent a to accomplish the work.18 The architect’s review must meet
submittal schedule.8 If a there is an However, when the contractor is the approved schedule or, absent
approved schedule, the contractor delegated part of the design obliga- a schedule, it must be reasonably
must comply to “cause no delay” to tions, the contract documents sort prompt.23 The review responsibil-
the work, the activities of the owner, out responsibility. Contractors may ity explicitly excludes obligations
or other separate contractors.9 rely on the adequacy and accuracy of for the accuracy and completeness of
By sending the submittal to the the design provided in the contract details such as dimension and quan-
design professional for review, the document.19 The owner and archi- tities, or installation instructions, or
contractor represents to the owner tect, however, may rely on the design equipment performance.24 These re-
and the architect it (1) reviewed and from the contractor if the work con- main the contractor’s obligations.
approves of the submittal, (2) deter- tains the appropriate required writ- Strangers to the project agree-
mined and verified materials, field ten certification.20 The architect’s ments may try to impose liability on
measurements, and field construc- review of the delegated design is the design professional based on the
tion criteria, or will do so, and (3) limited to conformance with the de- review and approval of shop draw-
checked and coordinated the infor- sign concept.21 ings. Careful attention must be paid
mation in the submittal with the con- to the contracts. The General Con-
tract requirements.10 B. Design Professional’s ditions are clear that the architect’s
Until the submittal is approved by Obligations review does not constitute approval
the architect or engineer, the contrac-
tor is prohibited by contract from 6. AIA Document A201-2017, General Conditions of the Contract for Construction, §3.12.1.
performing any work covered by the
7. AIA Document A201-2017, General Conditions of the Contract for Construction, §3.12.5.
submittal.11 However, once the sub-
mittal is approved, contractors must 8. Id.
perform the work in accord with the 9. Id.
approved submittal.12 Contractors
10. AIA Document A201-2017, General Conditions of the Contract for Construction, § 3.12.6.
should take caution. Even if the ar-
chitect’s approves a shop drawing 11. AIA Document A201-2017, General Conditions of the Contract for Construction, § 3.12.7.
that includes a deviation from the 12. AIA Document A201-2017, General Conditions of the Contract for Construction, § 3.12.8.
contract documents, the contractor
13. Id.
still must comply with the contract
documents.13 14. Id.
There is a means to address an in- 15. Id.
tentional deviation. The contractor 16. Id.
can proposed something other than
17. AIA Document A201-2017, General Conditions for Construction, § 3.12.10.
as called out in the contract docu-
ments. The contractor must notify 18. Id.
the architect of the deviation when 19. AIA Document A201-2017, General Conditions for Construction, § 3.12.10.1.
submitting the shop drawing.14 If
20. Id.
the proposed change is accepted dur-
ing the review process, the architect 21. Id.
must give written approval of the
22. AIA Document B101-2017, Standard Form of Agreement between Owner and Archi-
deviation as a minor change in the tect, §3.6.4.2, AIA Document A201-2017, General Conditions for Construction, §4.2.7.
work or process a change order or
change directive.15 Contractors must 23. AIA Document B101-2017, Standard Form of Agreement between Owner and Archi-
proceed carefully. If the architect ap- tect, §3.6.4.1, AIA Document A201-2017, General Conditions for Construction, §4.2.7, .
proves the shop drawing but does
24. AIA Document B101-2017, Standard Form of Agreement between Owner and Archi-
not provide the required documen-
tect, §3.6.4.2, AIA Document A201-2017, General Conditions for Construction, §4.2.7.

12 THE ST. LOUIS BAR JOURNAL/ FALL 2017


of safety precautions or construction issue were special connections, mean- ements to bring the connection into
means or methods, techniques, se- ing they were “non-redundant.”27 If compliance with the building code.33
quences, or procedures.25 a non-redundant connection fails, The court concluded that shop
the structure will collapse.28 drawing review by the engineer
III. Failure to Review, Non- The change in the connections was was contractually required and uni-
delegable Duties, and Gross due to fabrication issues. The steel versally accepted as part of the de-
Negligence supplier proposed to the structural sign engineer’s responsibility.34 The
No discussion of shop draw- engineer to use a two-rod system, engineers conduct from initial re-
ing review and liability can be had as opposed to one continuous rod view through shop drawing review
without discussing the 1981 Hyatt as shown in the engineer’s design to showed a conscious indifference to
Regency skywalk collapse in Kan- suspend the second and fourth floor his professional duty.35 The court
sas City, Missouri. The collapse of a skywalks. The supplier submitted concluded Duncan breached a non-
set of skywalks during a social event shop drawings to the structural engi- delegable duty.36
resulted in 114 deaths and 186 other neer for review and approval show-
ing this change. IV. Good Faith and Fair
injuries. The structural engineer’s
licensing hearing gave rise to an ap- The licensing board concluded Dan- Dealing in the Review of
peal reported in Duncan v. Missouri iel Duncan did not review the shop Shop Drawings
Board for Architects, Professional Engi- drawings for compliance with the The parties must deal with each
neers and Land Surveyors.26 This Mis- Kansas City Building Code, for con- other in good faith during the shop
souri Court of Appeals opinion is formance with the design concept as drawing review process. An exam-
discussed in almost every commen- required by the structural engineer’s ple is the appeal that arose from a
tary on this topic. It is a valuable, contract, or for the information in the contractor’s suit following termina-
though somewhat nuanced, lesson. contract documents. Regardless, he tion in Nova Contracting, Inc. v. City
The landmark Duncan opinion approved the shop drawings.29 of Olympia.37
arose, in part, from the licensing The Missouri Court of Appeals Nova contracted with the City of
board’s discipline of the structural found review and approval of these Olympia to replace a culvert. Under
engineer, Daniel Duncan. At the shop drawings is an engineering the contract, Nova had to provide
hearing level, Mr. Duncan was disci- function.30 The court noted the various submittals to the city’s engi-
plined due to his gross negligence in structural engineer’s in-house policy neer for approval before construction
failing to review shop drawings and called for a detailed check of all spe- could begin. The contract made two
other professional misconduct. cial connections during shop draw- things clear: the city’s engineer’s ap-
During the shop drawing process, ing review.31 The structural engineer proval was a prerequisite to starting
changes were made to the steel con- knew of the change to a two-rod work covered by a submittal, and
nections used to suspend the sky- system, but he did not review the the city’s decision to accept or reject
walks, which differed from the en- connection.32 In addition, the shop a submittal was final.
gineer’s design. The connections at drawings did not show necessary el-
The city rejected many of Nova’s
submittals and re-submittals, which
Nova argued was done improperly
25. Id.
and motivated by an effort to pre-
26. 744 S.W.2d 524 (Mo. Ct. App. 1988). vent its performance. The termina-
27. The court discussed the difference between simple, complex, and special connec- tion of Nova was initiated in part
tions. Id. at 528-29. due to Nova’s failure to provide ap-
28. Id. at 529. propriate submittals.
29. Id. at 530. The trial court agreed with the own-
er and Nova appealed. The Wash-
30. Id. ington State Court of Appeals found
31. Id. at 540. sufficient questions of fact to send the
32. Id. at 540-41. dispute back to the trial court.38
The State of Washington imposes
33. Id. at 541.
an implied duty of good faith and
34. Id. fair dealing in every contract as does
35. Id. most states.39 This requires the parties
to cooperate so each may benefit from
36. Id.
full performance of the contract.40
37. 2017 Wash. App. LEXIS 913; 2017 WL 1382883. The court looked to the Restate-
38. Id. at 14. ment (Second) of Contracts for
39. Id. at 6. guidance on the good faith and fair
dealing question, quoting from the
40. Id.

THE ST. LOUIS BAR JOURNAL/ FALL 2017 13


comments to section 205.41 that shop drawings were required shop drawings. The court of appeals
The city argued there was no duty for the work.47 The shop drawings found a reasonable inference that the
of good faith because the city had were returned without approval or disputed areas were within the con-
unconditional authority, i.e.: the city disapproval and the only comment tract, in part, because the definition
engineer’s decisions were final on was to warn the installer to follow of the scope of work referenced the
the relevant issues. the contract requirements.48 “details of the shop drawings.”51
The court rejected the city’s posi- However, if shop drawing review
is required, the approval may affect VI. Timeliness of Review
tion and held the contract did not
provide the city with the absolute the scope of work. In Ozark Moun- and the Creation of Liability
right to reject all submittals for any tain Granite & Tile, Co. v. Dewitt As- A delay in the review process can
reason.42 The city’s judgments were sociates, Inc.,49 the general contrac- impact claims for extended costs or
to be guided by whether the submit- tor contracted with Missouri State the assessment of liquidated damages.
tal indicated Nova’s work would University for a scope and, in turn,
In Gillioz v. Missouri State Highway
comply with the contract.43 The city subcontracted with Ozark Mountain
Commission,52 a contractor was as-
had to exercise discretion consistent for the fabrication and installation of
sessed liquidated damages. The con-
with the contract’s requirements.44 granite. Ozark Mountain prepared
tractor claimed it was delayed due to
The city’s actions, among others, shop drawings. Ozark Mountain
the conduct of Missouri State High-
highlighted the architectural draw-
showing a lack of good faith includ- way Commission. The contractor
ing to indicate where it intended to
ed demanding all submittals be ap- claimed the state’s failure to approve
install granite and submitted those
proved before Nova could begin any shop drawings within a reasonable
as its shop drawings. Ozark Moun-
work contrary to industry practice time after submission delayed its
tain cut, fabricated, and installed the
and the contract and the city’s rejec- completion.
granite in accord with the highlight-
tion of the initial submittal for one rea- ing on the shop drawings. A misunderstanding between the
son and then rejecting the resubmittal owner’s engineer and the contractor
A dispute arose between the gen-
for new and different reasons.45 regarding the review process result-
eral contractor and Ozark Moun-
tain over Ozark Mountain’s scope ed in at least a three week delay be-
V. Impacts on the Scope of fore shop drawings were processed
of work. The general contractor
Work when normally, the court noted, the
argued there was work within the
Arguments can arise over whether scope of Ozark Mountain’s contract time frame was four or five days.
shop drawings can alter or impact the not shown on the shop drawings. The Missouri Supreme Court con-
scope of work. An unsuccessful effort The court of appeals found in favor cluded there was sufficient evidence
to rely on shop drawings to change of Ozark Mountain.50 to show that a substantial part of
the scope of work can be found in The appellate court noted that the completion delay was caused
United States v. Henke Const. Co.46 A the shop drawings were submit- by state’s untimely review of shop
contractor sought recovery for the ted on more than one occasion and drawings, which supported allow-
cost of additional labor and material they highlighted the areas to receive ing the issue to go to the jury.53
as the result of the government-own- granite. The submissions were re-
er’s refusal to “consider, approve or quired by contract. Ozark Moun- VII. Liability to Third Parties
act upon” certain shop drawings. tain fabricated and installed every and the Scope of Review
In Henke, shop drawings were pre- piece of granite highlighted on its
pared with input from the tile install- Third parties, who believe they
er. The general contractor submitted
the shop drawings to the govern- 41. Id. at 8.
ment-owner, but the shop drawings 42. Id. at 9.
were returned without action and
43. Id.
with the notation that no shop draw-
ings were required for “this work.” 44. Id. at 10.
The tile installer, plaintiff in the 45. Id. at 11-12.
lawsuit, argued failing to approve 46. 157 F.2d 13 (8th Cir. 1946).
or disapprove the shop drawings
caused it damage because its installa- 47. Id. at 22.
tion reflected the work shown in the 48. Id.
shop drawings and included work 49. 372 S.W.3d 556 (Mo. Ct. App. 2012).
over and above what was called for
by the contract. 50. Id. at 562.

The court found against plaintiff. 51. Id.


The court held the fallacy in plain- 52. 169 S.W.2d 901 (Mo. 1943).
tiff’s argument was the assumption
53. Id. at 905.

14 THE ST. LOUIS BAR JOURNAL/ FALL 2017


have been damaged, may try to base “for conformance with the design finding for the structural engineering
liability on the review of the shop concept . . . and with the information subconsultant to the architect.63
drawings. This commonly relates to given in the Contract Documents.”57 Similar arguments were addressed
job site safety measures. The court concluded it was the in a suit by an injured plaintiffs relat-
Approval of shop drawings that duty of the contractor - not the archi- ed to the absence of temporary barri-
did not include temporary bracing tect - to see that the shop drawings ers or handrails during construction
or temporary connections was ar- included temporary connections, with the same essential outcome in
gued to be negligence by the design which is encompassed in the field National Foundation Company v. Post,
professional in Waggoner v. W & W construction criteria and construc- Buckley, Schuh, & Jernigan.64 The de-
Steel Company,54 when two workers tion means, methods, techniques, sign and placement of the handrails
died after a gust of wind caused an sequences, and procedures.58 The and barricades were found to be tem-
unsecured and unbraced piece of architect could not be held liable for porary in work site area and a safety
steel to collapse. The event result- the injuries sustained because of an measure, not an inherent design
ed from a failed connection, which unsafe construction procedure.59 requirement. The duty for worker
lacked a temporary device to keep The holding in Waggoner is in line safety was placed on the contractor
the connection from failing during with other opinions. For example, who exercises control and supervi-
construction. By the time of trial the the Illinois Court of Appeals adopted sory responsibly on the job site.65
sole remaining defendant was the the same essential positon in Block v. If the approved shop drawings do
architect for whom the trial court di- Lohan Associates, Inc.,60 when a work- not conform to the design, the courts
rected a verdict.55 er sustained severe head injuries in a may reach a different conclusion. In
The suit reached the Oklahoma fall while erecting the precast panels Jaeger v. Henningson, Durham, & Rich-
Supreme Court, which looked to the during construction of a new build- ardson, Inc.,66 the design professional,
contract documents to determine ing. The injured worker’s represen- Henningson, Durham, & Richardson,
the review process and purpose of tative argued the design professional Inc. (HDR) contracted to provide ar-
shop drawings. The court noted the who agreed to review shop draw- chitectural services for a South Dako-
contract documents provided shop ings and submissions approved the ta office building. Two workers were
drawings were to be first submitted submissions without requiring an injured during steel erection.
to the contractor for review and veri- erection procedures be included.
fication of “all field measurements, A shop drawing had erroneously
The court found that the contract
field construction criteria, materi- called for 14 gauge steel for a land-
documents uniformly and clearly
als, catalog numbers, and similar ing pan contrary to the specifications
limit the architect –lead designer’s
data.” The contractor’s approval is a which required 10-gauge steel. HDR
responsibility regarding shop draw-
representation it checked each shop failed to notice the discrepancy in
ings to a determination of design
drawing against the requirements gauge and approved the shop draw-
conformance and not worker safety.61
of the contact. The documents were ing. The steel was fabricated in ac-
The design professional did not have
clear that the contractor is “solely re- cord with the approved shop draw-
control or charge of the construc-
sponsible for all construction means, ing and later found to the cause of
tion means, methods, techniques,
methods, techniques, sequences, and the injuries.
sequences, procedures or for safety
procedures.”56 On the other hand, precautions in the construction.62 The court concluded that HDR had
the architect was obligated to review The court made essentially the same negligently failed to “supervise the
shop drawings” under the contract
and the proximate cause of the acci-
54. 657 P.2 147 (Ok. Ct. App. 1983). dent.67 The contract in this suit does
55. Id. at 149. not seem to have the AIA language
requiring a written notice and ap-
56. Id. at 151.
proval for deviations.
57. Id.
58. Id.
VIII. Delegation of Design
59. Id. The design process can delegate
design for certain aspects of the proj-
60. 645 N.E.2d 207 (Ill. Ct. App. 1993).
ect. The contract documents will
61. Id. at 222. delegate the design to a supplier,
62. Id. vendor, or contractor with more spe-
cialized knowledge. However, the
63. Id. at 224.
delegation and shared responsibility
64. 465 S.E.2d 726 (Ga. Ct. App. 1995). can cause complications in the sub-
65. Id. at 730. mittal review process and the assess-
ment of responsibility.
66. 714 F.2d 773 (8th Cir. 1983).
The court in Great American Insur-
67. Id. at 776.

THE ST. LOUIS BAR JOURNAL/ FALL 2017 15


ance Company v. North Austin Munici- is followed, which did not occur.72
pal Utility District No. 168 had to sort The engineer’s stamp disclaimed re-
through responsibility for a construc- sponsibility saying, “This review is
tion defect in part of a project involv- for determining general conformity
ing a design delegated to a contractor. with the contract plans and speci-
The dispute involved the design of a fications and shall not relieve the
dry well, which was part of a waste contractor of responsibility for devi-
water system. Almost a year after ations from the drawings and speci-
completion of the wastewater system, fications, or for errors of any sort in
the utility-owner discovered a struc- the shop drawings or schedules.”73
tural deformity in the shell of the dry
IX. Conclusion
well as one side was collapsing. The
collapse occurred because the sides of To have a successful project of any
the underground dry well were not complexity, the submittal process
sufficiently thick given the depth un- must be followed and managed.
derground at which it placed. Though not part of the “Work” as
The utility owner first demanded defined by the contract documents,
the general contractor correct the the shop drawings assure the owner
defect, but the general contractor re- is delivered what it wants, the de-
fused. The utility-owner then turned signer’s design is brought to frui-
to Great American Insurance, who tion, and contractor complied with
had issued the maintenance bond. the contract’s obligations. When the
Great American argued the failure process runs off of the tracks, it can
was a structural defect due to design create issues for all involved.
and it was not liable under the bond.69 Careful attention to the contractual
A subcontractor who worked on the obligations related to the process and
dry well had prepared and submitted attention to details in the submis-
shop drawings to the engineer. They sion and review process will provide
showed how it proposed to refurbish smooth project delivery without sur-
the lift station. However, the shop prises, finger-pointing, or additional
drawings did not indicate thickness expenses.
the sides of the dry well. Regardless,
the engineer approved the subcon- qqq
tractor’s shop drawings.
Great American argued it could
not be liable because the engineer’s
negligence relieved the general con-
tractor of liability. The engineer’s
design required the “thickness of the
sides [of the dry well] shall be de-
termined by the structural require-
ments for the depth of burial.” The
contract documents did not specify a
thickness for the wall; however, the
documents did identify the standard
for determining the thickness of
the sides of the dry well. The court
found such a design sufficient.70
Though Great American argued it
was relieved from liability because
the engineer approved the shop
drawings, but the court disagreed.71 68. 902 S.W.2d 488 (Tex. Ct. App. 1995).
The contract said, “ENGINEER’s 69. Id. at 495.
review and approval of the Shop
Drawings or samples shall not re- 70. Id. at 496.
lieve CONTRACTOR from respon- 71. Id.
sibility for any variation from the
requirements of the Contract Docu- 72. Id.
ments” unless a particular procedure 73. Id.

16 THE ST. LOUIS BAR JOURNAL/ FALL 2017

Potrebbero piacerti anche