Sei sulla pagina 1di 6

A Study on Construction Management Contract for Construction Project

in Japan

Takashi GOSO* Shunji KUSAYANAGI**

*Research Center for Social Management, Kochi University of Technology, Japan


**Department of Infrastructure and Engineering systems, Kochi University of Technology, Japan

Abstract Construction projects based on Construction Management Contract (CM Contract)


have been spread out in Japanese public works. Under the project based on CM contract,
“Process control” is necessary. By “Process control”, transparency of project implementation is
expected to be improving. This matter contributes to recover nation’s confidence in improving
transparency in the construction industry.
Japanese construction contract is based on two-party system- Owner and Contractor. To
implement CM contract in Japan, suitable environment to integrate the function of the
Construction Manager (CMR) as third party is necessary. This research reviewed and revised
“Standard Form of Construction Management Agreement between Owner and Construction
Manager” and “Standard Form of Contract for Public Construction Works” based on three-party
system established in previous study. Furthermore, “Standard Form of Design Agreement
between Owner and Designer” based on CM contract was tried to established in this study.

Key Words : Construction Manager, CM Contract, Claim Document, FIDIC

1. Introduction “Standard form of Contract for Public


Construction Works in Japan” is based on two-party
Construction projects based on Construction system. To spread out CM Contract, making basis
Management Contract (CM Contract) have been for the participation of the Construction Manager
spread out in Japanese public works. Ministry of (CMR) as third party is necessary. As a concrete
Land Infrastructure and Transportation (MLIT) aims measure, Construction Management Contract based
to develop transparency, to secure quality and to on three-party system should be established.
reduce cost by introducing CM Contract. Project By previous research by this research group,
execution based on CM contract needs “Process “Standard Form of Construction Management
Control” to keep transparency. Agreement between Owner and Construction
Examples of public works based on CM Contract Manager” and “Standard Form of Contract for
are Moriyoshizan-Dam and Isawa-Dam construction Public Construction Works” based on three-party
projects executed by Tohoku Regional Bureau, system were established, referred to many Standard
MLIT. These projects have been monitored form of agreements in Japan and other countries.
continuously from viewpoint of effect and problem This research is based on our previous research as
of CM Contract. Many suggestions to spread out mentioned above. Main propose of this research is
CM Contract in Japan can be found out from these to revise Standard Form of Contract of previous
monitoring. research to apply for civil works especially dam
<1.Review and revising of Construction Management
Agreement between Owner and Construction Manager> Contract
z Actual two dam projects
Control
z Establised in previous research

Owner <3.Establishing Design Agreement based


on three-party system>
<2.Rwview and revising of Standard Form of
z Present standard form of agreement
Contract for Public Construction Works > CMR
based on two-party system
z Actual two dam projects
Designer
z Established in previous research

Contractor A Contractor B Contractor C Contractor D

Figure 1: Subjects of this study


construction works. industry should change their system that they
In this study, hearing on persons concerned to show not only “result” but also “process” of
Moriyoshizan-Dam and Isawa-Dam construction construction projects.
projects done by Japan Dam Engineering Center z From viewpoint of transparency, it is difficult
(JDEC) was referred. Objection by persons to execute public construction project only by
concerned were referred to find out problem and two-party (Owner and Contractor).
study measures for previous Standard Form of Construction project essentially have
Contract of previous research from. Moreover, cooperation with owner and contractor based
“Standard Form of Design Agreement between on contract in every stage of project. It has
Owner and Designer” based on CM contract was possibility that fair cooperation for concerned
tried to established in this study. This study is joint with the project thought to be cozy relationship
research project between JDEC and our research by outsider.
groups. Figure 1 shows subjects of this study. By above states, from changing economical
condition, citizens have started to require
2. Purpose to introduce CM contract transparency of construction industry. But two-party
system have limit to ensure enough transparency.
Purpose to introduce CM contract was reviewed There is the case that taking part in public project by
in this study. Previous study of this research group, third party who has enough knowledge is profitable
MLIT and other research groups has taken to get citizen’s understanding.
“developing transparency”, “keep quality” and “cost Second problem of transparency is the
reduction” as purpose of introducing CM contract. “transparency of each concerned of project”.
Each purpose is restructured in this study. Principal objective of present Japanese public
“Developing transparency” was the core to construction project execution system is “result
restructuring control” which control complete date, final amount
First problem of transparency is the of money and quality. Fundamental measure to
“transparency of construction industry from ensure transparency is changing principal form
citizens’ viewpoint”. Previous study express “result control” to “process control”. Changing to
following about transparency of construction “process control” makes realize developing
industry. construction site management and engineering
z Japanese two-party system is the “Public sector competitiveness of concerned (technical proposal
lead private companies” style. In this style, and discussion of each other). Based on above
relationship of owner and contractor has been condition, “keep quality” and “cost reduction” will
complicated. This relationship makes rapid be achieved.
reconstruction of Japanese infrastructure. Introducing CM contract is the one of the
z Two-party system adjusted market before 1st oil
<Present Condition>
shock (1973). In those days, construction Citizens
investment in Japan is increasing 15% per year. 1. Transparency of Construction
Construction Industry
In such condition, construction industry need Industry
not market analyzing and getting citizen’s (Citizen’s needs have been strong) Control
Owner Contractor
needs. Two-party system has made good
2. Transparency of each concerned
performance by using its characteristics in such
(It become difficult to keep transparency)
market condition.
z Construction investment has not increasing <CM Contract System>
from 1978 (year of 2nd oil shock). A period Citizens
1. Transparency of Construction
from 1978 to start bubble economy in Japan Industry Construction Industry
(1986) called “Ice age of construction industry”. (From “2. Transparency of each
This period is thought to be that Japanese concerned”, owner have basis to Owner CMR
infrastructure has been almost prepared. Japan explain to citizens) Control
thought to be a developed country form at that Contractor
time. ・Establishing “Process Control” to show outsider

z Changing from high economic growth society 3. Realizing “keep quality” and ・Developing management by taking part in CMR
・Promotion of engineering competitiveness
to low economic growth society means “cost reduction”
changing of quantity and quality by citizen’s 2. Transparency of each concerned
needs. Construction industry should develop (“Process control” by CMR is monitored by owner)
infrastructure based on citizen’s opinion in such
condition. At the same time, construction
Figure 2: Purpose to introduce CM contract
Table 1: Difference of contact documents for Japanese public works and
measures for realizing “process control”. Taking international project based on FIDIC contract
part by a third party who has enough knowledge of Contract Japanese Public Works International Construction Project based
engineering and management is expected to make Document on FIDIC
developing construction site management and Condition of ●Applicable contents for usual project ●Part I (General Conditions) states
Contract are stated in“Standard Form of Contract applicable contents for usual project
engineering competitiveness of concerned. In this
for Public Construction Works” ●Part II (Particular Conditions) states
system, owner changes from executer to procurer, ●Applicable contents for each project are revised matter from Part I to apply each
he monitors construction work done by contractor not stated. Generally, Condition of project.
Contract is not changed for each project ●Part I and Part II are unified to make
and construction management by CMR. Based on from “Standard Form of Contract for Condition of Contract to stipulate right
above developing “transparency in the activities of Public Construction Works” and duty of stakeholders
each concerned of project”, “transparency of Specification ● General Specification ●Specification
construction industry from citizens” will be realized. ● Special Specification
Figure 2 shows above story. Priority of ●Special Specification have high priority ●Priority of ducuments are stipulated as
contract than General Specification followings
documents ●Order of priority between Condition of ①The Contract Agreement (if
3. Problem of Tender-Contract system and Contract and Special Specification are not completed)
Standard form of contract in Japanese public stipulated. Reason is thought to be that ②The Letter of Acceptance;
concrete contents are stated in Special ③The Tender;
works specification; same kind matters are not ④Part II of these Conditions;
stated in Condition of Contract. In actual ⑤Part I of these Conditions; and
In this study, each clause of contract is revised. But business, Condition of Contract has high ⑥Any other document forming part of
priority than Special Specification. the Contract.
before revising clauses, problem of tender-contract
system and Standard form of contract in Japan Handling Special information of each project is Condition of Contract has high priority
should be reviewed. This chapter takes problem of situations of stated in Special Specification. Condition than Specification. Condition of Contract
Condition of of Contract does not state actual states special information of each
tender-contract system and Standard form of Contract in procedure to solve problem. So, Condition project. Moreover, Condition of Contract
contract, and makes basic policy to revise each actual of Contract does not referred in actual states actual procedure to solve problem.
clause of contract. business business. So, Condition of Contract should referred
frequently in actual business.

(1)Problems of tender-contract system in Japanese Works” says “The BOQ and Work Program shall
public works not be binding on the Owner and Contractor”. In
a) Actual cost control is not necessary for present this condition, important significance of existence of
tender-contract system CMR has possibly to be lost.
As Bill of Quantity (BOQ) and other contact Existence of CMR itself can not ensure
documents become detail, transparency of public transparency and not reduce public work’s cost. In
works is developed. Changing of cost and schedule present trial two dam projects, above clause are kept
from unexpected event are estimated based on unchanged. Moreover, construction management
agreed BOQ and contract documents. Transparency agreement between owner and contractor in these
is ensured by these records. projects doesn’t require CMR to control project cost.
In the case of tender of international construction As a result, effect of introducing CM contract
project, bidders are required to apply contact thought to be limited, for example cost reduction
documents, BOQ, schedule, statement of works. from VE proposal by CMR. In hearing for
These documents are reached about 1,000 pages. concerned of two dam project, owner said that
Owner checks these documents, and about top 3 “from view point of cost control, change is not
companies are clarified as candidates for bidding. In found out from previous two-party system”. Based
clarification stage, based on clarification for unclear on above Condition of Contract, owner’s above
point of tender document, estimation for alternatives opinion thought to be correct.
by bidders, and studying on validity of BOQ, etc,
successful bidder is decided. To analyze problem b) Changing of Tender-Contract system and Clause
and to manage cost and schedule based on such of Standard form of contract
detail agreed matters, suitable level of engineering Public works can be defied as “Execution of
knowledge is necessary. Significance of existence of annual budget”. Based on this character, cost control
CMR is for this point. Based on such tender- of Japanese public works place importance on final
contract system, CMR works from starting stage of total project cost. Purpose of such kind control is to
project, transparency of project are realized. finish project within lump sum cost. View point on
The other hand, bidder submits only total cost in this control is total cost. This is different from
almost case of tender of Japanese public works. In general meaning of “Cost control” which monitors
almost case, successful bidder is decided from cost, each cost of BOQ item.
and contract will be concluded. Moreover, Symbol of this matter is bidding without BOQ. It
“Standard Form of Contract for Public Construction is difficult to manage project cost without detail
BOQ. Suitable estimation to each bid cannot be In this situation, level of specification may become
done without a detail BOQ. different by each project.
Cost control require understanding of Therefore, important and normal matters of
disbursements of each cost item; disbursements of specification should be moved to Condition of
each cost item are compared with BOQ or budget; Contract; and Condition of Contract should be
cost items which is larger or smaller than budget are separated to part I (General Condition) and Part II
picked up; reasons and measures for such condition (Conditions of Particular Application).
are found out and execution of measures. These data Condition of Contract made in this study is
is applicable to next project. Cost control is defined corresponded to Part I.
as above cycle. Moreover, Condition of Contract should not be
In Japanese public works, such kind cost control written by abstract word but be made from actual
is contractor’s inside jobs. Owner doesn’t concern procedure to solve problems (ex. Submission
such kind of cost control. deadline and party). Condition of Contract for
To realize developing transparency and cost Works of Civil Engineering Construction by FIDIC
reduction, CMR should have function of cost (Federation Internationale Des Ingenieurs Conseils)
control. In previous study, function of cost control is a good reference of this matter.
was taken to CMR’s duty in “Standard Form of “Standard Form of Contract for Public
Construction Management Agreement between Construction Works in Japan (Japanese standard
Owner and Construction Manager”. Moreover, to contract)” and “Condition of Contract for Works of
perform this function, “The BOQ and Work Civil Engineering Construction by FIDIC (FIDIC
Program are a part of Contract Documents” was put contract)” are compared. FIDIC contract states
on “Standard Form of Contract for Public actual procedure to solve problem in construction
Construction Works”. site, more than Japanese standard contact.
In the future, to realize developing transparency For example, in “Extension of Time for
and cost reduction, these clauses have important Completion” clauses, Japanese standard contact
meaning. basically says “Any adjustment of the
Moreover, to select appropriate contractor from Construction Period shall be through consultations
viewpoint of cost and quality, submitting detail between Owner and Contractor”. Foreseeable
tender documents (e.g. BOQ, schedule, and reasons, negotiation procedure and schedule to
statement of construction method) and clarification change schedule are not stated in Japanese standard
procedure are necessary. contact .The other hand, FIDIC contract says states
5 items of foreseeable reasons to change schedule.
(2)Handling of contract documents and specification Moreover, actual procedures are stated in FIDIC
in Japan contract. Other clauses are also in same situation.
BOQ, Schedule and Statement of method for Difference of contact documents for Japanese
project execution should be a part of contract public works and international project based on
documents and binding to both the parties. FIDIC contract are compared in Table 1.
Moreover, state of Specification in Japanese public Condition of Contract does not clearly state actual
project should be changed. From view point of procedure to solve problem in Japanese public
transparency, contents of Condition of Contract works. So, execution staff can implement their work
should be referred and used in daily work. But without referring Condition of Contract. They
“Scope of works”, “Documents to be submitted”, almost can implement their work only with referring
“Procedure for change of works” and other contents Special Specification. This condition is same as
are written in specification of almost Japanese Design Agreement between owner and designer.
public works. Most of above contents should be The other hand, Condition of Contract of
written in Conditions of Contract or other contract International Construction Project states actual
documents. In this condition, Conditions of Contract procedure to solve problem.
and other contract documents except specification Based on detail procedure stated in Condition of
are not used in actual work. Specifications of some Contract, documents are exchanged between owner
project are made by execution level staff of project and contractor though The Engineer as third party.
execution section. This situation can rapidly solve This condition leave on record of project; and
problems from negotiation of execution level staff transparency will be developed.
of each organization. The other hand, in this Introduction of CM system aims to developing
situation, essence of contents of contract can be transparency. To realize this purpose, actual
understood by execution level staff of each procedure to solve problem should be stated in not
organization. Transparency of project becomes low. Special Specification but in Condition of Contract.
So, Standard procedures to solve problems in projects. Condition of Contract and Specification for
construction site which are stated in specification CMR of two dam project does not state procedure
level documents in Japan are stated in new about evaluation procedure of contractor’s claim.
Condition of Contract revised in this study. Such kind of procedure should state in Condition of
Contract to dispel contractor’s doubt.
4. Review and revising of Construction Basic policy of claim evaluation procedure is
Management Agreement between Owner and “CMR evaluates Contractor’s claim. Decision
Construction Manager Making is done by owner”

Management Agreement between Owner and 5. Review and revising of Contract for Public
Construction Manager of actual two dam projects Construction Works between Owner and
established in previous research are reviewed and Contractor
revised in this study. Hearing on persons concerned
to two dam project done by JDEC was referred to (1) Fee for cost reduction from VE proposal
find out problems. CMR are expected to make many VE proposals by
Main points are followings. Owner side. Owner expects that VE proposal form
CMR accelerates technical competitiveness between
(1) Cost control CMR and Contractor. However, consultant says that
One engineer belongs to owner says that he “Contractor may have negative image for VE
cannot find out effect of introducing CMR from proposal by CMR. Because total cost will be
viewpoint of cost control. Condition of Contract and reduced”. Present Specification of two dam projects
Specification for Construction Management does state no incentive for contractor by VE proposal of
not state about cost control by CMR. In such CMR. To encourage VE from CMR, Contractor
condition, above opinion by owner side is thought to should get suitable fee to realize cost reduction idea
be properly. from other party.
First purpose of introducing CM system is to
develop transparency. To realize this matter, CMR (2) Dispute resolution between each Contractor
should have function of cost control. Dispute between each Contractor should be solved
by negotiation between concerned with such event.
(2) Fee for cost reduction from Value Engineering However, to keep transparency, detail of event and
(VE) proposal resolution procedure should be reported to Owner
CMR sometimes realize owner’s idea. Such case is though CMR.
difficult to share cost reduction between owner and
CMR. Generally, CMR should get suitable fee to (3) Claim evaluation
realize cost reduction idea from other party. To dispel contractor’s doubt about evaluation
procedure, claim evaluation procedure should state
(3) Evaluation procedure for VE proposal in Condition of Contract for Construction works.
Condition of Contract and Specification of two Moreover, duty of CMR in claim evaluation
dam project does not state about evaluator. Actually, procedure should be stated.
owner estimate VE proposal. To develop
transparency, third party should evaluate VE 6. Establishing Design Agreement based on
proposal. “Standard Form of Construction three-party system
Management Agreement between Owner and
Construction Manager” established in previous Based on present “Standard Form of Design
study does not include procedure of VE evaluation. Agreement between Owner and Designer”, new
In this study, procedure of evaluation of VE Design Agreement on three-party system is
proposal is stated in revised Agreement. established in this study.
Functions of CMR are incorporated to present
(4) Claim evaluation agreement.
One engineer belongs to contractor says that he
cannot find out notification procedure of their claim. (1) Policy of reviewing in establishing
Under present contract, if owner received claim Agreement
document from contractor, owner decides “design a)State Scope of Works in Design Agreement
change” by oneself based on negotiation and Present Agreement does not state Scope of Works.
investigation. CMR evaluates such kind of claim Reason of such condition thought to be that such
documents under control of owner in two dam Agreement can use any type of works. However, an
Agreement is formally treated only to a particular construction stage is same as expected procedure.
condition. Such condition does not have enough Such joint control based on information exchange
transparency. So, general design works are stated in makes develop quality and Designer’s ability.
new Design Agreement based on present “Special Present system in Japan does not have such process.
Specifications of some Design works” This study has tried to make such process in Design
Agreement. Figure 3 shows difference of Design
b) Advising for Designer and inspection of Design Works between present system and proposed system.
Document by CMR in design stage CMR makes Designer to take part in construction
Main duty of CMR in design stage is to advise the stage. So, duties of CMR are stated in new Design
Designer. Followings two cases are prepared in Agreement. Fee for Designer in construction stage is
new Design Agreement considered to be cost plus fee.
Case A: Advising by CMR for Designer are
pontificated though Owner. CMR does not 7. Conclusion
advise to Designer directly.
Case B: Based on discussion between Designer Project execution system based on Contracts
and CMR, CMR notifies result of established in this study makes “Process control”.
discussion to Owner. Realizing Change form “Result control” to “Process control”
amendment should be agreed by Owner. realizes developing transparency. Construction
Case B is more practical and effective advice. In this Industry in Japan will get confidence of citizens
research, Case A and Case B are placed as based on “Process control”
selectable options.
<Reference>
(2) Joint Control of Designer and CMR in 1)Study on Standard form of Construction
construction stage Management Agreement in Japan, Japan Dam
Generally, Design works in Japan by Designer are Engineering Center and Kochi University of
usually limited in design stage. Designer usually Technology, Mar 2004
does not take part in construction stage. 2)Study Report on Standard form of Contracts based
However, to keep quality, information of design on CM Cotract, Japan Dam Engineering Center,
stage should be notified to Owner and CMR. Kochi University of Technology and Research
Contrary, Designer should have information about Center for Infrastructure System Kochi, Mar 2006
construction stage; and confirm whether
<General Duty of Designer in Japan>
Designer’s duty is completed in delivering design documents

Planning Basic Design Detail Design Construction Stage


Design for construction

Designer’s Duty

Building:On site drawing by contractor


Civil Works:Consultant or Contractor without charge

<Designer’s Duty of Established Contract in this research> Designer duty is completed in

Delivering design documents finishing construction stage

Planning Basic Design Detail Design Construction Stage


Design for construction

Designer’s Duty

Delivering information about design, understanding of site information


and confirming safety and quality

Figure 3: Difference of Design Works between present system and proposed system

Potrebbero piacerti anche