DAILY ACCOMPLISHMENT REPORT

DAY 1 2 3 4 5 6 DATE: MAY 20, 2019

ACTIVITIES STATUS REMARKS/RECOMMENDATIONS

COMPLETED STARTED BUT NOT YET NOT DONE


COMPLETED

Opening Program /
Trimming of tall mango trees / Done by parents, Marines and SI
Kabagis
Sweeping, cleaning and clearing the school / Done by the volunteer parents
yard (front)
Cleaning, weeding the yard of the HE Building / Done by the volunteer parents of
incoming Grade 5
Cleaning the roofs, gutter of the Grade 6 and / Done by the volunteers, parents of
kindergarten room incoming Grade 6 and Kindergarten
Trimming of malunggay trees / Done by the volunteer PTCA parents
Cleaning , Pulling of weeds of the school garden / Some parts are done to be continued
tomorrow
Renovation of volleyball court / To be continued tomorrow

Prepared by:

EDWIN D. TARIGA
Head Teacher III
Calayab Elementary School
# 37 Calayab, Laoag City
School Year 2019-2020

BRIGADA ESKWELA
DAILY ACCOMPLISHMENT REPORT

DAY 1 2 3 4 5 6 DATE: MAY 21, 2019

\
ACTIVITIES STATUS REMARKS/RECOMMENDATIONS
COMPLETED STARTED BUT NOT YET NOT DONE
COMPLETED
Cleaning , Pulling of weeds of the school garden / Done by the volunteer PTCA
members
Cleaning of rooms-rooms are vacated / Ready for cleaning, dusting
Sorting of chairs for repairs / Ready for repair
Cleaning of rooms, removing of cobwebs, / Some rooms are partially done by
clutters and old decors PTCA volunteers
Clearing and cleaning of walls / Some parts are done to be continued
tomorrow
5S (Sorting, Setting, Shining, / To be continued tomorrow
Standardizing,
Sustaining)
Renovation of volleyball court / Done by the volunteers from Double
M Company

Prepared by:

EDWIN D. TARIGA
Head Teacher III
Calayab Elementary School
# 37 Calayab, Laoag City
School Year 2019-2020

BRIGADA ESKWELA
DAILY ACCOMPLISHMENT REPORT

DAY 1 2 3 4 5 6 DATE: MAY 22, 2019

ACTIVITIES STATUS REMARKS/RECOMMENDATIONS

COMPLETED STARTED BUT NOT YET NOT DONE


COMPLETED

5S (Sorting, Setting, Shining, /


Standardizing,
Sustaining)
Cleaning of rooms, removing of cobwebs, / Done by the volunteers
clutters and old decors
Clearing and cleaning of walls / Continuation of yesterday’s work
Repairs /painting of chairs of chair / Time constraint
Cleaning and clearing of old clinic / Done by the volunteers/parents
Construction of drainage / Done by volunteers and from Double
M Company

Prepared by:

EDWIN D. TARIGA
Head Teacher III
Calayab Elementary School
# 37 Calayab, Laoag City
School Year 2019-2020

BRIGADA ESKWELA
DAILY ACCOMPLISHMENT REPORT

DAY 1 2 3 4 5 6 DATE: MAY 23, 2019

ACTIVITIES STATUS REMARKS/RECOMMENDATIONS


COMPLETED STARTED BUT NOT YET NOT DONE
COMPLETED
Clearing and cleaning of walls / Done by the volunteers
Repairs /painting of chairs of chair / Time constraint
Repainting of classrooms walls, ceiling / To be continued the next day
Repairing of cabinets / To be continued the next day

Prepared by:

EDWIN D. TARIGA
Head Teacher III
Calayab Elementary School
# 37 Calayab, Laoag City
School Year 2019-2020

BRIGADA ESKWELA
DAILY ACCOMPLISHMENT REPORT

DAY 1 2 3 4 5 6 DATE: MAY 24, 2019

ACTIVITIES STATUS REMARKS/RECOMMENDATIONS


COMPLETED STARTED BUT NOT YET NOT DONE
COMPLETED
Repairs /painting of chairs of chair / Done by the volunteers/parents
Repainting of classrooms walls, ceiling / To be continued next day
Repairing of cabinets / Done by the volunteers
Repairing of water facilities, drainage system / To be continued the next day
Restructuring of bulletin boards and other / To be continued next day
learning materials

Prepared by:

EDWIN D. TARIGA
Head Teacher III
Calayab Elementary School
# 37 Calayab, Laoag City
School Year 2019-2020

BRIGADA ESKWELA
DAILY ACCOMPLISHMENT REPORT

DAY 1 2 3 4 5 6 DATE: MAY 25, 2019

ACTIVITIES STATUS REMARKS/RECOMMENDATIONS


COMPLETED STARTED BUT NOT YET NOT DONE
COMPLETED
Distribution of School Supplies / Done
Restructuring of bulletin boards and other / Done
learning materials
Repairing of water facilities, drainage system / Done by the laborers
Clearing and cleaning of canteen / Done
Cleaning of the office / Done
Cleaning of comfort rooms / Done
Replacement of fluorescent bulbs / Done
Pruning of trees / Done by the DPWH
Construction of the roof of the wash facility / To be continued