Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
AL-SUGHAIYER
Miscellaneous Activities
Fabrication of Project Sign Board No-Activity 6-6-2016 5% 95%
Offset of Aramco Fence On-going 12-06-2016 5% 50%
Housekeeping On-going
B. FORECAST ACTIVITY
Location Activities *Target Remarks
S. S Bldg. Backfilling and Compaction – Aggregate Sub-Base 1st layer
12-6-2016
Area below Building Area
Lean Concrete for Foundation Work 13-6-2016
S.S Yard Backfilling and Compaction – General fill 1st layer Yard Area
28-8-2016
Area outside Building Area
TOTAL: 31
2.0 Direct Manpower (GMSA) Equipment:
Site Engineer - Civil 1 Safety Engineer 1
QA/QC Engineer – Civil 1 Loader 1
QA/QC Engineer – Electrical 1 Welding Machine 1
Service Car 2
TOTAL: 4 Cutter 1
In-Direct Manpower (ESS Diesel Generator 1
& GMSA)
Project Managers 2 Roller Compactor 1
Grader 1
Backhoe 1
TOTAL: 2 9
F. PROGRESS PHOTO
Back Filling and Compaction- Below Building Area ( 1st Layer Sub-Base Course)
Back Filling and Compaction- Yard Area ( 1st Layer General Fill)