Kind Attn: SAMI A.

AL-SUGHAIYER

Daily Site Progress Report


Report # D-34R1

Projects Department - East Date: 8 June 2016


Wednesday
Civil & Electro-Mechanical```` Projects Division- Temp 42°C
East Weather: Sunny and
Windy

Construction of Dhahran Home Ownership 115/13.8 kV Substation


Project Title
#2
Contractor Name Grupo Maessa Saudi Arabia Ltd.
Contract No. 4400006083
DUST FREE BLDG.: 31 OCT 2016 POWER TRANSFORMER: 15 OCT 2016 TCC: 31 JULY 2017
A. ACTIVITIES (CIVIL WORKS)
% Completion
Location Activities Status *Target
Today Total
S. S Bldg. Backfilling and Compaction – Aggregate Sub-Base 1st
Area
On-going 12-6-2016 10% 35%
layer below Building Area
Lean Concrete for Foundation Work - 13-6-2016 - -
S.S Yard Backfilling and Compaction – General fill 1st layer
Area
On-going 28-8-2016 1% 7%
Yard Area outside Building Area

Miscellaneous Activities
Fabrication of Project Sign Board No-Activity 6-6-2016 5% 95%
Offset of Aramco Fence On-going 12-06-2016 5% 50%
Housekeeping On-going
B. FORECAST ACTIVITY
Location Activities *Target Remarks
S. S Bldg. Backfilling and Compaction – Aggregate Sub-Base 1st layer
12-6-2016
Area below Building Area
Lean Concrete for Foundation Work 13-6-2016
S.S Yard Backfilling and Compaction – General fill 1st layer Yard Area
28-8-2016
Area outside Building Area

Note: indicate target date above


C. INSPECTION (RFI by PD-E/CEMPD & SI by CSD)
Inspection
Description of RFI / SI Remarks
(Date/Time)
1 Routine

D. ISSUES/CONCERNS which requires Action and Action taken:


1.

E. MANPOWER & EQUIPMENT


Manpower / Equipment of Main Contractor & Subcontractor & Specify SEC witnessing persons
Sl Job Category No Job Category No Machineries/Equipt. Remark
1.0 Direct Manpower Tools:
Civil Engineers 2 Labor 2
Surveyor 1 Electrician 2
Safety Officer 1 Mason/Painter 5
Office Boy 1 Guards 2
Civil foreman 1 Grader Operator 1
Carpenter 6 Roller Compactor Operator 1
Steel Fixer/welder 3 Loader Operator 1
Electrical Foreman Backhoe Operator 1
Driver 1

TOTAL: 31
2.0 Direct Manpower (GMSA) Equipment:
Site Engineer - Civil 1 Safety Engineer 1
QA/QC Engineer – Civil 1 Loader 1
QA/QC Engineer – Electrical 1 Welding Machine 1
Service Car 2
TOTAL: 4 Cutter 1
In-Direct Manpower (ESS Diesel Generator 1
& GMSA)
Project Managers 2 Roller Compactor 1
Grader 1
Backhoe 1

TOTAL: 2 9
F. PROGRESS PHOTO

Back Filling and Compaction- Below Building Area ( 1st Layer Sub-Base Course)
Back Filling and Compaction- Yard Area ( 1st Layer General Fill)

Offset of Aramco Fence