DESIGN TEAM SCHEDULE

DAT 8/6/2019
Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18
CURRENT
DISCIPLINE STAGE Notes STATUS 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1
ARCHITECTURE Podium Drawing 15% CONSTRUCTION DRAWING
Podium Specs 15% CONSTRUCTION SPECS
Tower Drawing 0% CONSTRUCTION DRAWING
Tower Specs 0% CONSTRUCTION SPECS
C&S Construction Drawing 0% CONSTRUCTION DRAWING
ID PUBLIC AREA Detailed Design 15% DD
ID GUESTROOM Perspective 50% PERSPECTIVE FOR NON STND ROOMS
ID F&B DD TD
INT LIGHTING Public Area Concept Design 30% CD SD DD
F&B Concept Design 30% CD SD DD
EXT LIGHTING Concept Design TBC with BSLD 50% CD DD
KITCHEN DD complete pending Budget 90% TD
SIGNAGE Concept Design Starts on 50% DD ID 0% CD SD DD TD
LANDSCAPE Schematic Design 80% SD DD
SECURITY SD completed. Comments from HWW SD
IT CD completed. DD next stage. Continue upon 50% DD of ID DD TD
AV CD completed. DD next stage. Continue upon 100% SD of ID DD TD
Completion of specs coordination with
ACOUSTICS CD completed. DD next stage. Arch DD and MEP TD DD

Design Release Date for Tender Legend


BP-08 INTERIOR FIT OUT (ROOMS) 11-May Current Date
BP-10 INTERIOR FIT OUT (FOH) 11-May Concept Design (CD)
BP-11 INTERIOR FIT OUT (F&B) 21-May Schematic Design (SD)
BP-12 LANDSCAPING 17-Sep Detailed Design (DD)
BP-13 KITCHEN 11-May Tender Design (TD)
Approval
Jul-18 Aug-18

2 3 4 1 2 3 4

CONSTRUCTION DRAWING
CONSTRUCTION SPECS