Sei sulla pagina 1di 6

Configuration Checklist For SAP PP

The following give you an overview of the configuration


checklist for SAP PP and their IMG Path.

SPRO

1) Define Distribution Keys

IMG -> Production Planning for Process Industries -> Master


Data -> Material List -> Item Data -> Item Data from related
areas -> Define Distribution Keys

2) Determine Person responsible for Resource

IMG -> Production Planning for Process Industries -> Master


Data -> Resource -> General Data -> Determine Person
responsible

3) Define Planner Group

IMG -> Production Planning for Process Industries -> Master


Data -> Master Recipe -> Define Capacity Planner

4) Define Capacity Planner

IMG -> Production Planning for Process Industries -> Master


Data -> Resource -> Capacity Requirement Planning ->
Determine Capacity Planner

5) Determine Standard Value Parameter

IMG -> Production Planning for Process Industries -> Master


Data -> Resource -> General Data -> Standard Value ->
Define Parameter

6) Define Setup Groups and Setup Group Categories

IMG -> Production Planning for Process Industries -> Master


Data -> Master Recipe -> Data for operations and phases ->
Define set up groups and set up group categories
7) Define copy setting between plants-Process

IMG -> Production Planning for Process Industries -> Process


Management -> Tools -> Define copy setting between plants

8) Define Set Up Control Recipe destination

IMG -> Production Planning for Process Industries -> Process


Management -> Control Recipe/PI sheet -> Set up control
recipe destination

9) Define MRP controller

IMG -> Material Management -> Consumption based Planning


-> Master Data -> Define MRP controller

10) Special Procurement

IMG -> Material Management -> Consumption based Planning


-> Master Data -> Define Special procurement types

11) Define Floats (Scheduled Margin Key)

IMG -> Material Management -> Consumption based Planning


-> Planning -> Define Floats (Scheduled Margin Key)

12) Define Splitting of Forecast requirements for MRP-

IMG -> Material Management -> Consumption based Planning


-> Evaluation -> Forecast -> Define Splitting of forecast
requirements of MRP

13) Maintain Correction Factors for Forecast

IMG -> Material Management -> Consumption based Planning


-> Planning -> Procurement -> Maintain Correction factors for
forecast

14) Carry Out Overall Maintenance of Plant Parameters

Maintaining plant parameters in MRP

IMG -> Material Management -> Consumption based Planning


-> Plant Parameters -> Carry out overall maintenance of plant
parameters

15) Define Planning Horizon

IMG -> Material Management -> Consumption based Planning


-> Planning -> MRP calculation -> Define Planning Horizon

16) Activate Requirement Planning

IMG -> Material Management -> Consumption based Planning


-> Planning -> Activate Requirement Planning

17) Define Range of Coverage Profiles (Dynamic Safety


Stock)

IMG -> Material Management -> Consumption based Planning


-> Planning -> MRP calculation -> Define range of coverage
profile (Dynamic Safety Stock)

18) Define Stock in Transfer and Blocked Stock Availability

IMG -> Material Management -> Consumption based Planning


-> Planning -> MRP calculation -> Stocks -> Define Stock in
transfer and blocked stock

19) Define MRP Areas

IMG -> Material Management -> Consumption based Planning


-> Master Data -> MRP areas -> Define MRP areas

20) Carry out maintenance of MRP groups

IMG -> Material Management -> Consumption based Planning


-> MRP groups-> Carry out maintenance of MRP groups

21) Define Scope of total Planning - MRP

IMG -> Material Management -> Consumption based Planning


-> Planning -> Define Scope of total Planning

22) Define Order Types


IMG -> Production Planning for Process Industries -> Process
Order -> Master Data -> Order -> Define Order Type

23) Define Order Type Dependent parameters

IMG -> Production Planning for Process Industries -> Process


Order -> Master Data -> Order -> Define Order Type
Dependent parameters

24) Define Production Scheduler

IMG -> Production Planning for Process Industries -> Process


Order -> Master Data -> Bill of Material -> Define Production
Scheduler

25) Define Checking Control - Process Order

Define Availability Check Define Checking Control

IMG -> Production Planning for Process Industries -> Process


Order -> Operations -> Availability Check -> Define Checking
Control

26) Define Checking Rule for backorder processing

IMG -> Production Planning for Process Industries -> Process


Order -> Operations -> Availability Check -> Define Checking
rule for back order processing

27) Define Stock and batch determination for good movement

IMG -> Production Planning for Process Industries -> Process


Order -> Operations -> Define Stock and batch determination
for good movement

28) Specify Scheduling Parameters

IMG -> Production Planning for Process Industries -> Process


Order -> Operations -> Scheduling -> Specify Scheduling
Parameters
29) Define Reduction Strategies

IMG -> Production Planning for Process Industries -> Process


Order -> Operations -> Scheduling -> Resource data -> Define
Reduction Strategy

30) Define Confirmation Parameters

Define Order Confirmation

IMG -> Production Planning for Process Industries -> Process


Order -> Operations ->

Confirmation -> Define Confirmation Parameters

31) Define Valuation of Goods Received

IMG -> Production Planning for Process Industries -> Process


Order -> Integration -> Define Valuation of goods received

32) MRP creation indicator

IMG -> Material Management -> Consumption based Planning


-> Planning -> Define creation indicator

33) Define safety stock

IMG -> Material Management -> Consumption based Planning


-> Planning -> MRP calculation -> Stocks -> Define Safety
Stocks

34) Define alternative determination of Production

IMG -> Production Planning for Process Industries -> Process


Order -> Operations -> BOM selection -> Define alternate
determination of production

35) Define no. ranges

IMG -> Production Planning for Process Industries -> Process


Order -> Master data -> Order -> Number Ranges -> Define
number ranges for orders
36) Define no. ranges

Following Number ranges you need to define :

In OPPQ you need to define Number Ranges for :

Planned Orders

Reservations / Dependent Requirements

Purchase Requisitions

MRP Lists

Simulative Dependent Requirements

Similarly you need to define Number Range for :

Production Order in CO82

Confirmations in CO80

Reservations in CO83

Operations in CO81

Capacity Requirements in CO84

Same way you need to maintain all other number ranges in


Production Server manually. However first you need to
transfer Number range object through Transport Request.