Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
INDEX
Flow No.of
Pump H.P. Make Lubrication
(lpm) Stages
1ND06A 220 550 Sulzer 10 Oiler lubrication
The reject line provides the facility to reject water from primary
system to either radwaste system or to main condenser. The reject flow is
controlled by manually operating the reject valve FCV-1ND22. The reject
CV closes automatically if there is high pressure in reject line towards
radwaste or if there is high vacuum in reject line towards condenser.
DRG 130A
Biological Shield Cooling Water System
The system is initially filled by demin. water through the surge tank.
During operation, any losses of water from system are made up by filling the
surge tank whenever the low level alarm comes. The chemical feeders are
provided to feed a potassium dichromate and caustic soda.
The water from pool, cavity and equipment storage pool overflows to
fuel pool surge tank through skimmers. The pool skimmer serves as the level
control and overflow weir from pool to surge tank. The normal overflow
level is adjusted to 199 ft. elevation.
ii) Provides sufficient capacity for evaporation losses for one week
operation.
Two full capacity pumps, each rated for 30 lps. (500 gpm) flow
are provided for recirculating the water through filters and plate type heat
exchangers. The pumps can take suction from surge tank, reactor cavity or
equipment storage pool and deliver to cavity or fuel pool depending on
specific mode of operation.
Both the plate type heat exchangers (NUO3A, B) are normally
kept in service with one pump running. Two pressure pre-coat type filters
are provided to maintain water clarity and quality. Each filter is rated for 19
lps (300 gpm) flow and normally both filters are in service. The system
operates at reduced capacity when one filter is being back washed and pre-
coated. Different pre-coat materials like Powdex , Ecodex resins and Solca-
floc are used to pre-coat fuel pool filters. Solca-floc (Fine Cellulose Powder)
removes only insoluble impurities. While Powdex and Ecodex resins remove
soluble impurities and maintain the fuel pool water quality.
Each logic channel consists of two logic sub channels. Each logic sub
channel consists of set of relays and relay contacts. The logic sub channels
are not totally independent as they share common power supply and
protective channels. Tripping of either logic sub channel results in tripping
of corresponding logic channel. The trip logic of sub channels is described
as one out of two.
Apart from automatic scram signals listed above, the reactor scram
takes place due to following:
DRG 141C
DRG 141D
DRG 141E
Auto-Blow Down System
When all the four signals coincide, all the three relief valves will open
automatically after a time delay of 120 seconds and depressurize the reactor
by venting steam to suppression pool. The time delay of 120 seconds is
provided for operators action to bring up the reactor water level. The auto-
blow down system can be reset manually, if the reactor water level can be
brought up within this 120 seconds period.
Core Spray and Post Incident System
Among the features which differentiate the nuclear reactor from
conventional boiler are the radioactivity and the decay heat. The heat
liberation from irradiated nuclear fuel continues indefinitely due to decay of
fission products even after the reactor is shutdown. If no means are provided
for removal of this decay heat, fuel failure and damage to the fuel cladding
can occur due to overheating of cladding. Once the cladding fails, the
radioactive fission products get released from fuel to primary system and
even may get released to environment.
Each core spray loop has a spray ring header located inside the
reactor vessel above the reactor core. Each header has 120 nozzles designed
to spray water in fine droplets directly over the fuel bundles. The system has
built in facility to test the freeness of nozzles by admitting good quality
water from condensate service system to the spray headers. Strainers
provided on suction lines from drywells and suppression pools trap the
particles which could cause blocking of spray nozzles.
Four lines branch off from the common discharge header of the
Core spray pumps as given below. Each line is provided with two MOV’s.
The post incident system is designed to spray the cool water into the
drywell and common chamber to condense the steam arising from incident
such as break in primary system inside the dry well and transfer the heat to
RBCW system outside the drywell.
Six lines branch off from common outlet header of the heat
exchangers as given below. Each branch line has a motor operated valve.
Inside each drywell there are two full capacity spray headers. Each
spray header has 120 nozzles for spraying water uniformly in the drywell. A
selector switch is provided to select one of the headers for operation and the
other header remains on standby. During incident condition the MOV on
selected header will open automatically and the MOV in standby header
will open only if the selected header is not giving required flow. The MOVs
on spray headers to common chamber open irrespective of incident on any
unit. The strainer provided on suction lines from drywells and suppression
pools trap the particles which could cause blocking of nozzles. The nozzles
of drywell spray headers are tested periodically by admitting compressed
air to spray headers.
The suction MOVs to the post incident cooling pumps change over
from suppression pool of respective unit to the outlet from the drywell of
that unit, as soon as the water level in the drywell reaches particular preset
valve.
During refueling shutdown Core spray spargers of both the loops are
tested for nozzles through ness test by actually admitting water through the
spargers. Post incident spray header nozzles in drywell are also tested for
through ness by admitting service air in to the nozzles.
DRG 147A
Shutdown Cooling and Head Spray System
There are two shutdown cooling pumps for unit #1 1NU0-2A/B are of
75 lps (1200 gpm) each capacity at 55 M (180 ft.) TDH driven by 75 HP
motor. For unit #2 2NU0-2A/B are of 75 lps. each (1200 gpm) capacity at
55 M TDH driven by 100 HP motor. Unit No.1 pumps are supplied from
Class IV power supply where as Unit No.2 pumps are supplied from class III
power supply. The pumps have mechanical seals. RBCW is provided as
cooling water to seal coolers. The pumps are protected against low suction
pressure, low discharge flow and high temperature. The pumps suction
header is connected to reactor recirc. loop B by MOVs and the discharge
header is connected to recirc loop A by MOVs. The pumps take water from
reactor annulus and pump it back to reactor core through heat exchangers.
Usually, it is sufficient to run one pump. The pumps are located at lower
elevation to ensure sufficient NPSH.
There are three shutdown cooling heat exchangers (1NU01, NU01 and
2NU01). RBCW system provides the cooling water. Reactor water flows
through tube side and RBCW flows through Shell side of the heat
exchanger. Each heat exchanger has heat duty of 1.32 MWt (4.5 x 106
Btu/hr.). Tube side of heat exchanger is designed for 1250 psi. (85 Kg/cm2)
at 350oF (176oC) and the shell side is designed for 150 psi. The heat
exchanger 1NU01 serves for unit#1 and 2NU01serves for unit#2 shutdown
cooling system and NU01 is a spare heat exchanger for both units.
Interlock (i) Prevents any possible loss of reactor water from shutdown
cooling system during conditions of low level.
Interlocks (ii) Prevents inadvertent valving of shutdown system during
running unit.
The reactor vessel head spray system is provided to spray water and
cool the upper portion of reactor vessel and vessel head at a rate matching
with the rest of the vessel, when shutdown cooling system in service. The
system receives cool water supply from CRD hydraulic system. The spray
nozzles are provided at the top center of reactor vessel head. The head spray
flow is controlled manually by a remotely operated pneumatic throttling
valve. The head spray is started little before the shutdown system is taken in
service. An MOV is provided on head spray line which can be opened only
when the reactor mode switch is in other than “RUN” mode position.
DRG 149A
Containment and Containment Isolation
The containment is the last and most important barrier that prevents
the uncontrolled release of fission products to the environment. The
functions of containment are to,
Vacuum Breakers:
After the incident, the steam in the drywell is condensed and also the
suppression pool water is cooled by operation of core spray and containment
spray systems. The containment system can be subjected to vacuum under
such conditions. It is protected against excessive vacuum by providing three
sets of vacuum breakers as described below:
As V1/V2 decreases :
TAPS
Identical power supply systems are provided for the safety and
control systems of each reactor. Each system consists of two motor
generator sets with fly wheels and associated switchgear.
Operating Philosophy:
2) Instrument AC Supply:
Operating Philosophy:
DRG 158B
Station Transformers and
Electrical Distribution at TAPS
The low voltage winding is rated for 3.3KV line to line and its neutral
is grounding with resistance to limit the fault current during fault time. The
low voltage line terminals are connected to the 3 phase non-segregated phase
bus duct. The low voltage winding has sixteen 0.625% taps each above and
below rated voltage. The low voltage automatic tap changer can be
controlled both locally and from the main control room while delivering its
full KVA rating. Local and remote (main control room) tap position
indicators are provided.
There are two Nos. of start-up transformer in TAPS. The station start-
up auxiliary transformers for Unit #1 and Unit #2 are designated as XO3A
and XO3B respectively. However, any of the above two transformers can be
used for both units or each transformer (XO3A and XO3B) can be used for
individual units.
One set is used for transformer over-current relaying. The other set is
not presently used.
Normally XO3A will be feeding AO2 and XO3B will be feeding AO3
with bus coupler breaker open. AO1 and AO4 are supplied by respective
unit’s auxiliary transformer. But following conditions can also be achieved:
a) XO3A feeding AO2 and AO3 with bus coupler close AO1 and
AO4 on respective unit auxiliary transformers.
b) XO3B feeding AO3 and AO2 with bus coupler close AO1 and
AO4 on respective unit auxiliary transformers.
c) XO3A feeding both AO1/AO2 and XO3B feeding AO3/AO4
with bus coupler breaker open.
Transformer Protections
(240Volts. 1phase.)
The air circuit breakers are of the vertical lift draw out type and of the
“stored energy” trip free design. The circuit breakers have an interrupting
rating of 37,500 Amps. asymmetrical at 3.3 KV. The switch gear buses are
capable of withstanding a momentary fault current of 60,000 Amps. Control
supply voltage for the circuit breakers is 250V DC. All breakers units are
having like rating and are physically and electrically interchangeable. Each
breaker is provided with mechanical emergency manual trip device,
mechanical “closed” and “open” indication and mechanical breaker
operation counter.
The low voltage switch gear consist of seven double ended and three
single ended 415 volts load center buses for use in the auxiliary power
system of the two generating units. The buses are designated as BO1 to B10.
Each of the ten load center buses are supplied with an integrated 750 KVA,
3.3KV/415V, 3ph, 50 cycle open dry type transformers. Delta connected
high voltage windings are connected to the low resistance grounded 3.3KV
system. The “wye” connected low voltage winding are solidly grounded.
The high voltage winding of each transformer has two 2 ½% full capacity
no-load taps each above and below rated voltage. The transformers are
capable of continuous operation at rated capacity over a frequency range at
47.5 c/s to 51.00 c/s and current rating of 1040 amps.
The air circuit breaker elements for the incoming lines and bus ties
between double ended load center buses have a continuous current rating of
1,600 Amps. and interrupting capability of 60,000 Amps. asymmetrical at
480 volts. Current transformers for phase and ground over current protective
relaying are provided for the incoming circuit breaker trips. One single
phase ammeter is provided for each load center bus. Motor and feeder
circuits have air circuit breaker rated at 600 amps depending on the load
requirements. Circuit protection is provided by micro versa trip devices.
All circuit breakers are of “Stored Energy”, trip free design. All
breakers are electrically operated from 250V DC Control source and suitable
for operation from either a maintained or a momentary contact type initiating
device.
Purpose:
Description:
Design Basis:
The 48V DC batteries are sized to furnish for a period of four hours
the normal load requirements of the neutron monitoring instruments in the
event of loss of power to the chargers.
Mode of Operation:
Battery banks are taken out of service on monthly basis for boost
charging with external chargers. When one of the battery bank is taken out
for maintenance the affected panel D16 or D17 is tied with the other in-
service battery bank .This prevents power failure to NMS as one battery
bank is capable of supplying both the panels in case of charger failure.
DRG 170A
250V DC System
Purpose:
General Description:
The static type battery chargers are provided for each of the two
systems to maintain a float or equalizing charge of the station battery bank.
Unit #1 battery chargers are located at 118’ Cable spreading room Division
#1 and Unit# 2 battery chargers are located at 133 elev. in service building.
The main DC Distribution Panel for Unit#1 is located in cable
spreading room Division #1.Panel is divided into three sections
(D10A/B/C). Section D-10C is supplied from the battery bank No-1 and
sections D-10A/B are supplied from D-10C. The battery chargers G-4A/B
are connected to panels D-10A/B respectively. The main DC Distribution
Panel for Unit#2 is located in cable spreading room Division #2.
Under normal operation the tie breakers between all the three sections
are kept closed thus all the three sections effectively operate as a single bus.
Normally one of the two chargers is kept in service and the other one is kept
as standby. In the event of driving power failure to the running chargers, it is
automatically disconnected from the DC bus.
The control switches and voltage adjustment push buttons for Unit #1
Static battery chargers, metering instruments for the Station battery bank
No.1 and ground fault detector unit are located on Battery Charger and DC
distribution panels at Cable spreading room Division #1.
The Battery chargers and control switches of chargers for Unit #2 are
located at 133’ Service building, While D-20A/B/C panels are located at
Cable spreading room Division #2. There is a permanent link arrangement to
tie both the battery banks while taking out one of the battery bank for
maintenance. Battery banks are taken out for monthly boost charging by
external chargers. During this period other units battery bank is tied with
250V DC Bus.
When loss of power to the station (TLOP) occurs both the supplying
battery chargers trip and the respective units battery bank supplies the
essential loads. When EDG comes in service and class-III power becomes
available one of the battery chargers is taken in service and battery bank
voltage is brought up to the rated voltage. Other battery charger is kept on
standby.
DRG 173A
220 KV and 33 KV Switchyard
1) General :
5. Thermal stability.
a) Local electrically.
b) Remote electrically.
SPECIFICATIONS
3 No. of Poles 3
These are devices to isolate the circuit after the opening of the
circuit breakers to carry out maintenance of Circuit breakers and
line/line equipments maintenance as well as to give complete isolation
on any equipment/feeder. Normal current carrying capacity is 1250
Amps except for Bus Sectionalizer#1 isolators which are having 2000
Amps capacity. The isolators are operated manually.
One core is used for metering, second for feeder protection (i.e.
distance protection and back up earth fault protection) and third for
220KV bus differential protection. Three core CTs are also provided
on either side of bus-sectionalizer breaker. One core is used for
220KV bus differential protection and others are spare.
One set of CVT is provided for TAPS 1&2 –TAPS 3&4 tie line
for voltage indication purpose.
This is a parallel tuned circuit which blocks the flow of the high
frequency currents into the bus and equipment, thus
These are provided on all phases of the four feeders at the take
off from the TAPS switchyard. They safeguard the equipment in
switchyard by absorbing dangerous voltage surges due to lightning
stroke, on the way of the transmission line. Surge counters are
provided one for each arrestor to record the number of times the
arrestor has operated to absorb the traveling wayes.
3. Saline Pollution:
3.1) The proximity of the Tarapur 220KV switchyard to sea presents the
acute problem of insulator contamination due to saline deposits.
When the insulator is dry and the pollutant is also dry there is no
problem. Let us see what happens when the surface becomes wet.
The surface conductivity of the porcelain insulator increases. The
leakage current increases, thus heating the pollutant and drying it up.
Since the surface deposit is never uniform, the wetting and consequent
drying of the portion of the insulator surface is not uniform.
3) Auto Reclosure :
For earth faults, the back-up protection is given by a separate relay i.e. 3 step
directional earth fault protection.
To clear end zone faults of the line without time delay a carrier signal is
sent from the end (where the first zone element of the distance protection acts to
clear faults) to the other end to trip the breaker at the other end.
As line length is only 800 meters the distance protection relay can not be
used hence pilot wire differential protection is used for tie line. This relay
is used at both ends and interconnected with CT and inter trip circuit pilot
wires between TAPS 1&2 to TAPS 3&4. This relay will operate only for
the faults in between the line. After sensing the fault the tripping
command will be sent to the remote end breaker through pilot wire. For
through faults this relay will not operate.
To take care of tie line through faults three phase directional back up over
current and earth fault protection are provided at both the ends.
A bus bar protection is a device which protects bus bars short-circuits and
earth-faults. A 220KV bus fault can be highly disastrous as it involves heavy fault
MVAs. Such fault can be highly dangerous to the personnel and it can damage
equipment and lead to network instability, pole slip of nearby generators and even
total system collapse.
For bus bar protection applications, it is extremely important to have good
security since an unwanted operation of bus differential relay will have the similar
effect from operational point of view as simultaneous faults on all power system
elements connected to the bus. On the other hand, relay has to be dependable as
well. Failure to operate or even slow operation of the differential relay, in case of
actual internal fault, can have serious consequences. Human injuries, power
system blackout, transient instability or considerable damage to the surrounding
substation equipment and close-by generators are some of the possible outcomes.
Very fast clearance of the bus fault and complete stability for through
faults is achieved by low impedance numerical bus bar differential protection
relay REB 670.The relay operates in 20 msecs. and isolates the faulty zone.
When a bus fault occurs, the balance between incoming and outgoing
currents of that zone gets disturbed and differential current flows through the low
impedance relay and actuates it to trip all the breakers in the zone to isolate the
fault.
High speed tripping for internal faults. Typical operating time 20 milli seconds.
Complete stability for through faults, with heavy CT saturation.
Low CT requirement, only 2 ms to sense CT saturation.
Intelligent detection for open or shorted CT secondary circuits and configurable
blocking of differential protection zone.
Built in data communication modules.
On screen display of all measured bay currents and all calculated differential
currents.
Versatile local human machine interface.
Extreme self supervision with internal event recorder.
Status monitoring of individual switch gear devices.
7) Pole discrepancy:
DRG 187A
DRG 187B
DRG 187C
DRG 187D
DRG 187E
DRG 187F
Emergency Diesel Generators
The system consists of three identical diesel generator sets G2A, G2B
and G2C connected independently with three 415V emergency buses BO4,
BO5 and BO9 respectively. The system also includes control circuits for
auto starting, load shedding, auto synchronizing, automatic loading etc. The
diesel generator sets are capable of quick starting and loading. The system is
made fully automatic to minimize the off time of essential services. One
diesel generator is sufficient to cater all the essential loads including CSPI
during TLOP incident if other two EDGs becomes unavailable.
The diesel oil bulk storage tank T12A is having a capacity of 76,000
liters. The low level alarm appears in the main control room when the
quantity of diesel oil in the tank falls below 40,000 liters which is well above
the requirement of one diesel to run at rated load continuously for seven
days.
The second diesel oil bulk storage tank T12B is having a capacity of
55,000 liters. The low level alarm appears in the main control room when
the quantity of diesel oil in the tank falls below 40,000 liters.
Each tank is provided with a level indicator and a level switch with
alarms at high and low level. Manual starting of one of the two-diesel oil
transfer pumps P-20A or P-20B does filling of the day tanks. Starting of
diesel oil transfer pumps from the respective DG day tank instrument panel
can fill the day tanks. In case of high level in any one of the three day tanks,
the diesel oil transfer pump shall stop automatically.
Modes of Operation
i) Manual
ii) Automatic
Normally, the emergency diesel generators are left in the automatic mode of
operation. The manual mode of operation is used for testing or running the
diesel generators other than loss of power situation. As such if a diesel
generator fails to start automatically during total loss of station power, it can
be started manually
i) Engine start/stop
ii) Raise/neutral/lower speed control switch.
iii) Raise/neutral/lower voltage control switch.
iv) Engine emergency stop switch.
v) Auto/manual HS with voltage IN/DEC push buttons for battery
charger.
vi) ON/OFF push buttons for Fuel transfer pumps.
vii) Local /Remote selector switch for remote and local voltage
adjustment
viii) Auto/manual selector switch for DG set.
ix) DG test /reset push button.
x) Synch. switch and synch. check relay.
Out of these buses BO4, BO5 and BO9 are designated as the
emergency buses. Following a complete loss of station power, the EMTR
will initiate (sensing the respective emergency bus under voltage) bus
isolation, load shedding and starting of respective DG sets. Normal source
breakers or tie breaker connecting emergency buses shall also be tripped
automatically by EMTR for achieving bus isolation. However, the
emergency lights, the poison injection pumps (MCC B41 & 52) and Core
spray/Post-incident system MOVs (MCC B-43, B-53 & B91) remain
connected.
Once the diesel generator attains rated voltage and frequency, it shall
automatically close it’s output breaker to the respective emergency bus
provided that the bus is healthy and isolated from the other supply sources.
All the three buses shall operate independently with it’s own DG connected
to it and pick up the loads on the respective emergency bus. If a DG system
is either on maintenance or fails to start, an automatic bus tie breaker closure
command shall be initiated by the PLC based EMTR to restore supply to the
bus from the adjacent energized emergency bus.
Each DG has been located in dedicated room and the cables for the
DG are segregated from the other DG. Any one of the three diesel generators
is capable to meet the load demand during total loss of power to the station
together with the demand of core spray and post incident system. Two of the
three DG sets serve as 2 x100 percent capacity DG sets, thus providing
100% redundancy. Third DG set is treated as maintenance stand by. The
maximum load during total loss of power with CS / PI system in operation is
listed in the table given below. This also meet the requirement of one DG
under maintenance and one of the remaining two DG sets fails to start. The
same relays which initiated the isolation, interconnection and load shedding
of buses BO4, BO5 and BO9 also automatically start all the emergency
diesel generators.
The first diesel generator which reaches normal voltage and frequency
closes its output breaker automatically and energizes the emergency bus and
picks up the loads as per the EMTR loading sequence.
Buses BO4, BO5 and BO9 load shedding, bus isolation, starting of DG, acceleration,
0-15
remote breaker closure and energisation of the essential loads connected to the bus.
40-44 Starts salt service water pump P11B if P11A fails to starts
Time in
Event description
seconds
Buses BO4, BO5 and BO9 shed load, isolate, DG starts, accelerates, remote breaker
0-15
closure and assumes the essential load connected to the bus.
15-20 Suppression pool outlet motor operated valves open (MO1288, MO1289)
Starts core spray pump P25A (or P25C or P25B or P25D if P25A or P25C orP25B
20-24
fails)
Opens core spray sparger MOVs if reactor pressure is less than 200 psig (14 kg/cm2)
24-28
(MO 1312 and MO 1313 or MO 1605)
28-32 Starts core spray pump P-25B (or P25C if P25B fails)
32-42 Starts post incident pump P80-A (or P80C if P80A fails)
42-52 Starts post incident pump P80-B (or P80D if P80C started)
52-54 Opens drywell sparger MOVs (MOV 1295 or MOV 1296)
52-54 Opens post incident heat exchanger cooling water MOV-1311
52-54 Opens common chamber spray water inlet MOVs-1750 & 2750
54-64 Starts RBCW pump P13A
64-68 Starts emergency clean up fan V-25A
68-72 Starts salt service water pump P11A
72-76 Starts RBCW pump P13B if P13A fails to starts
76-80 Starts emergency clean up fan V-25B if V–25A fails to starts
80-84 Starts salt service water pump P11B if P11A fails to starts
84-86 Energizes MCC B42
86-88 Closes dry well RBCW MOV 1342
88-90 Closes dry well RBCW MOV 1343
90-92 Energizes MCC B51
92-94 Closes dry well RBCW MOV 2342
94-96 Closes dry well RBCW MOV 2343
EMTR:
PLC based Emergency Transfer (EMTR) Scheme is provided to
restore class-III power to emergency buses B04, B05 and B09 automatically
when class-IV power to these buses is lost. EMTR performs automatic
functions such as the starting of EDGs, load shedding, emergency bus
isolation, connecting the running DG to emergency buses and sequential
starting of emergency loads. There are two identical EMTR’s provided
which are located in Cable spreading room .EMTR #1 is located in Division
1 of Cable spreading room while EMTR #2 is located in Division 2 of Cable
spreading room.
2. Power supplies, inputs and outputs are provided such that availability
of any one of the systems shall ensure desired functioning of EMTR
scheme.
CPU Module
The CPU module includes logic solver and memory. The ladder
circuits are stored in the memory and solved according to the input
data sent from a local Input/Output driver. The results are output to
the local Input/Output driver. The U84 is capable of dealing with
discrete inputs/outputs up to 2048 points and up to 256 register
inputs/outputs.
Communication Module
Receiving the reference from the CPU module, the local Input/Output
driver transfers input data from the input module to the CPU module
and output data from the CPU module to the output module for local
Input/Output.
Input/Output Modules:
Programming Unit:
(i) To start respective EDG during individual bus under voltage or total
loss of power.
(ii) To provide anticipatory start to all the three diesel generators in case
of
a) Unit-1 or Unit-2 Reactor water low-level scram
b) Start up transformers X-O3A or X-O3B lock out
The existing emergency DGs G2A, G2B and G2C provide power
supply to the emergency buses BO4, BO5 and BO9 respectively during total
loss of power. These DGs come on line automatically and pick up loads as
per the loading sequence. In the event of all the three EDGs becoming
unavailable, i.e. Simultaneous failure of "Class-IV" and "Class-III" power
supply leads to the Station Blackout Condition (S.B.O. condition).
The SBO DG is provided with two mode switches SW2 and SW3.
The mode switch SW2 has four positions namely MANUAL/ AUTO/TEST/
OFF.
This switch will always be kept in MANUAL mode. Another mode
switch SW3 has two position LOCAL/REMOTE.
1. Automatic starting on bus BO9 under voltage (by the action of under
voltage relay 27Y95).
2. Remote manual starting from the control room.
The SBO DG has got a local breaker (ACB-52) in the control panel
(C-102) in the SBO DG room. This breaker is normally kept closed. It can
be closed or tripped from the local control panel only. The breaker trips
automatically on engine and generator protections.
When the SBO DG control switch is in the center position, the master
start relay can be energized by closing of contacts on the BO9 bus under
voltage relay.
A cooling tower is provided for the cooling water supply for the
engine. The power supply for the cooling tower fan and cooling water pump
is provided from the SBO DG bus.
Once the SBO DG starts on bus BO9 under voltage the closing of its
load center breaker 52-916 requires manual action. This manual action
depends on the availability of the Emergency Diesel Generators G2A, G2B
and G2C to cater to the emergency load requirement. For this, the SBO DG
breaker 52-916 has to be closed from the main control room and
subsequently the emergency loads have to be started one by one manually.
The SBO DG is provided with a 990 liters capacity fuel tank. The tank
is provided with a level indicator and switch, which will annunciate an alarm
on local panel whenever the oil level in the tank reaches low level. The oil
supply to the fuel tank is from the diesel oil storage tank.
Vacuum Pumps:
Parameters:
OR
3) Rotative speed.
4) Compressor shaft power (H.P.)
1) Reciprocating
2) Rotary
Dynamic Compressors are divided into:
1) Centrifugal
2) Axial
Reciprocating Compressor:
As rotor rotates gas is trapped in the space between vanes and conducted
from suction to discharge nozzle to be then discharged.
Centrifugal Compressors:
Energy from the shaft is transferred to the gas flow through a impeller. The
gas is rotated about centre at angular velocity. The resulting centrifugal
forces move the gas towards the periphery and throw it into the passages
surrounding the impeller. Thus its kinetic energy is converted into potential
energy through diffusion vanes.
Reciprocating Compressors:
Indicator diagram:
Capacity Controls:
a) Speed Regulation
b) Suction throttling
c) Holding the inlet valve open
d) Clearance variation
Construction:
Asbestos
1) Lubrication system.
2) Crank compressor by hand until all parts get lubricated.
3) Tighten all nuts and bolts.
4) Check for all cooling water leaks and circulation.
5) Check for any discharge line blockage or closed valve or check valve
and safety valve.
6) Pump the motor and let it come to rest.
7) If no abnormality is found run the compressor atleast two hours at no
load and then gradually apply load and minimum period repaired for
full load should be taken as 4 hrs.
Oil Quality:
Oil should be low carbon and sulpher content and contain an oxidation
inhibitor.
A good rule is to hold the outlet temp. of water between 120 and 130oF.
This range will allow for good cooling and lubrication and also keep
condensate in the cylinder to a minimum.
Note: When valve disc or plate wears to less than ½ its original thickness
it should be replaced.
Problems And Checks:
5) Water in cylinder:
8) Knocking Sound :
a) Foreign material
b) Dirty or in-sufficient air cleaning
c) Lack of lubrication
d) Too much end too cold cooling water causing excessive
condensate due to which excessive corrosion or washing out of
lubricant
e) Excessive heat
f) Plugged water jacket cooling line
Electron Theory:
Electric Current:
6) The electrons in the outermost orbit of an atom are usually not surely bound to the nucleus and
therefore may fly off that atom and move into an outer orbit of another atom. These relatively free
electrons normally move at random in all directions.
8) E.M.F.:- In the electric circuit the generator does not create electricity;
the generator merely produces an electrical pressure that causes
electricity to flow. If there is no electrical pressure no current will
flow. This pressure is called Electro Motive Force (EMF).
10) The Ampere: - The ampere is the unit of electric current. We can
express how much electricity is flowing in a wire by saying it in
Amps say 25 amps.
11) Resistance: - The electricity can travel with less difficulty through
some metals than through others. It travels easily through copper,
therefore copper wire is widely used. Copper is therefore called a
good conductor. Any substance that offers little resistance to the flow
of electricity is called a “good conductor”. Hence resistance is the
opposition offered by any substance to the flow of electricity. A “Poor
conductor” is the one which offers high resistance to the flow of
current; whereas an insulator is a “bad conductor”, which practically
does not allow any current to flow through it. Hence, this is used as a
covering for electrical conductors, so that, the current will not flow
away from its path. In an electric conductor, the resistance a
conductor offers to the flow of current will depend on its length and
its thickness or diameter. If the wire is very long, more friction must
be overcome than if it is short; if it is also of small cross section, it
will take still more effort to crowd the current through the wire.
Ohm’s Law
13) From the foregoing, it is clear that resistance will reduce the amount
of current that will flow. The number of amperes that will flow in a
circuit will therefore not be determined wholly by the voltage or
pressure which causes the current to flow but, also by the amount of
friction or resistance in the wires. Thus, with a given voltage the
greater the resistance of a circuit, the smaller the current will be that
flows, and the smaller the resistance, the greater the current will be.
This general relation between voltage, current and resistance is
commonly called “Ohm’s Law”. It is a law because it has been found
to hold in every case. It is written thus :
Resistance Ohms
Or Ohms = Volts
Amp.
The law as stated above applies only to direct current circuits, that is,
a circuit in which the current continuously flows in one direction in the wire.
Electric Power:
14) Power is the rate of doing work. The amount of power delivered by an
electric circuit to an electric load (say motor) depend upon the number
of amperes flowing and the number of volts of pressure. The greater
the current the greater will be the amount of power developed by it,
and the greater the pressure the more effect will be current have, the
actual value of power in a direct current circuit (not true for an
alternating current circuit) is equal to the product of volts times
amperes, thus
16) To measure the current in a circuit, the ammeter is used, the ammeter
Electric Energy:
17) The electric energy depends upon power and time. In order that
electricity may do useful work, it must act for a period of time. The
power expressed in watts tells how much electricity is working, and
the hours express the time during which it acts.
The product of these two factors gives the amount of work done.
Thus
18) Assignment:
Kind of circuits:
19) Series :-
20) Parallel :
Another arrangement is the so-called parallel or multiple connection.
Instead of all the lamps being connected onto each other and then on
to the battery, each lamp is individually connected across the battery.
The lamps are now said to be in parallel with each other. If any given
lamp burns out in such an arrangement, the remaining lamps will
continue to burn, as the path for the current through each of them is
still closed.
22) When two or more resistances are connected in series, the equivalent resistance of the combination
is equal to the sum of the resistances of the individual resistors or
R = r1 + r2 + r3 + .................
The equivalent resistance R of a parallel combination of resistors is determined from the relation
1 + 1 + 1 + 1 + ...........
R r1 r2 r3
R = r1 r2
r1 + r1
23) Series Parallel Circuit :
Some of the resistances are in series, some in parallel, and it is required to find the equivalent
resistance between A and B, the problem is solved step by step, by combining the resistances in
series and adding them with other series resistances. Begin by combining the resistance V2 and
V3 into one. Then find the combined resistance of r4 and the above resistance. Then add upto r1,
which gives the total resistance.
24) Assignment :
b) Find the equivalent resistance across A & B and find the total current taken by the system.
25) (a) An electromotive force is generated in a circuit when there is a change of magnetic flow threading
or linked with the circuit.
(b) The magnitude of the induced emf is equal to the rate of change of flux N.
i.e. emf = - dN
dt
The direction of induced current in a circuit is such as to oppose the cause producing it.
Kirchoff’s Law:
27) (a) The algebraic sum of the current toward any junction point is zero.
i.e. The current going towards a junction must be equal to the current going away from the junction.
(b) The algebraic sum of the voltages around any closed path in the net work zero.
i.e. The sum of the product of current and resistance must be equal to the applied voltage in a closed
circuit.
Joule’s Law:
28) The heat produced in a conductor is proportional to the square of the current passing through the conductor,
the resistance of the conductor and the time for which the current is passing.
i.e. H α I2 Rt.
If r is the resistance between two points of a conductor carrying current i.e. the p.d. between them
and t seconds the time for which the current flows, the work done is given by
W = JH = Eit x 107
Where J is the mechanical equivalent of heat. Substituting
J = 4.2 x 107 ergs/caloris, we have
H = EIT = I2 Rt/4.2
29) The practical unit of electrical energy is one Joule. Thus 1 joule = 1 volt x coulamb. One coulamb is the
quantity of electricity passed through a conductor when 1 amp. Flows for a second.
30) (a) The mass of any substance liberated is proportional to the product of current and the time for which
it passes, that is, to the total quantity of electricity which has passed.
(b) The masses of different substances liberated by the passage of the same quantity of electricity are
proportional to their chemical equivalents (atomic weight divided by valency)
M α I t (first law)
M α n (second law)
M = kn I t = Z I t.
Where m is the mass liberated, I current, t the time n the chemical equivalent, k a constant and Z the electro
chemical equivalent.
Portable Fire Extinguishers
1) Take off the acid jar, stir the solution of water and soda bicarb with a
clean stick, put it in a clean bucket and see if the lead lining is alright
and that no rust is there, refill it if satisfied, to be inspected every
month. See that vent holes & discharge nozzles are kept clean and
unobstructed.
Inspection at station level has to be done the following way; Stir up the outer
container with a clean stick and put the stick down stir up the inner container
with another stick and put down the stick on the other, watch the reaction of
formation of the foam. Then empty both the containers carefully into two
separate buckets, check the lining inside. If everything is satisfactory
assemble the extinguisher carefully and correctly and put it back to service
again. Extinguisher showing signs of corrosion and damage must be
condemned and replaced but not to be repaired or soldered in any case. Vent
holes in the cap, nozzles etc. should also be checked to keep clear of dust
metal polish etc.
Discharge Test:
It is a colourless gas which is one and half time heavier than air and is
charged within the extinguisher in the form of liquid, by application of
pressure and maintaining a temperature of 60oF. The liquid boils off to form
gas again, at a temperature much lower than normal, and this gas mixing
with the atmosphere surrounding the fire in a proportion of 19% to 29% of
air volume, inhibits the fire i.e. it extinguishes the fire by replacing some of
the oxygen in the air as it does not support combustion.
The high velocity with which the gas is released and the sudden cooling
effect may in some instances play a part in the extinguishment, though
primarily it is considered to extinguish fires by blanketing effect. It is non-
conductor of electricity.
Charge:
Charge consists of CO2 in liquid form and can only be recharged by the
manufacturers and not at station level.
Caution :
Its main disadvantages are (a) Comparative heavy weight (b) no visible
check of contents (c) short range (d) unsuitable for use in the open.
Standard Test:
Dry powder is very effective for fires that mostly react with water and CO2.
Charge:
The charge constitutes of dry powder with a sodium bicarbonate base poured
in outer container. A CO2 cartridge is placed inside the inner container
which is screwed on to the inner side of the cap assembly with the sealing
disc. The interior shape of the extinguisher is so designed that CO2 expels
practically 98% of the contents. It is to be kept on the ground, and the
discharge tube held by the hand. When the fire has been extinguished, the
cylinder to be turned upside down, so that only CO2 gas goes out.
Operation:
It is important not to stand too close to the fire as the efficiency of this
extinguisher is then reduced.
Recommendations:
OR
The extinguishers may be used for class `B’ and `C’ fires and in premises
where these risks are present. It is an exclusive recommendation for the fires
involving metals.
Caution:
Since the extinguisher has no cooling effect, on the contrary the initial effect
will be to raise the temperature, specific care should be taken to use it at
fires where life is involves in confinement. This extinguisher for the same
reason of non-cooling effect is not safe for applying to fires of Class `A’.
Standard Test:
System consists of Jocky fire pump installed on raw water storage tank (T-5)
which is a vertical single stage pump with 50 gpm (190 LPM) flow and developing
100 psig. (6.8 Kg/cm2) pressure. The system is designed to give minimum flow of
50 gpm (190 LPM) at 12 psig. (0.81 Kg/cm2) at the highest point of supply. If this
demand is more than 50 gpm (190 LPM) then the selected sea water, screen wash
pump will start and supply the required water supply for the fire system.
The jockey fire pump discharges raw water from storage tank (T-5) (6,00000
gallon capacity) into the fire water system through the accumulator which permits
intermittent operation of the jockey fire pump (P-19). The accumulator (T-10) is
filled with water pumped from raw water storage tank by jockey fire pump to ¾ to
full and then compressed air is admitted to the accumulator (T-10) to keep the fire
system pipe line under constant pressure. This avoids the jockey fire pump
running continuously.
Fire hydrants and hose compartments, each containing two length of 50 ft.
(15.38 M) of 2 ½” (6.35 cms) dia. fabric reinforced, rubber lined woven jacketed
hose and accessories, are located around the building areas and spaced 150’ to 200
feet apart (50 to 70 M apart). Inside the building, five hose cabinets are provided,
containing 75 ft. (23 M) long, 1 ½” dia (6.35 cms) with isolation valve, water
nozzle etc. at different strategic locations where water is best suited as the medium
for fire extinguishing.
The transformer area (viz. X01/X04, X02/X05.X03A/X03B) is protected by
means of a “Deluge Valve” sprinkler system which gets actuated by Heat Actuated
Devices (HAD) which are situated around the periphery of the transformers, which
in event of a fire resulting in a rapid rise of heat would send an automatic release
signal to the control mechanism, thereby operating the “Deluge Valve” allowing
water to flow in the sprinkler loop. Two instrument vaults of each units (1A/1B
and 2A/2B) are protected by the wet sprinkler system which utilizes a number of
fusible sprinkles with a temperature rating of 165o F (75 o C). In event of fire in the
instrument vaults, the fusible inserts in the sprinkles will melt away, allowing the
water to be spread on the fire. During refueling outage or transformer outage
Sprinkler test is carried out to check the throughness of spray nozzles for
transformers.
The liquid fire protection system with raw water is also connected to sea
water as a alternate source of water supply through plant screen wash system.
There are two screen wash pump ( P-10B and P-10C) selected as a electric fire
pump by a selector switch on the local control pannel (C-34), with selected screen
wash pump on “Auto” position and second screen wash pump is on standby
position. In event of the jockey fire pump is not able to come up with the demand
of water requirement, the system header pressure will drop down from normal 90
psig. (6.12 Kg/cm2) pressure to 80 psig. (5.78 Kg/cm2) which will trip the pressure
switch PS-257 and there by give signal to start the designated electric fire pump
to start.
In addition to this signal, PS-257 tripping will isolate raw water section by
closing control valve CV-686 to prevent the flow of sea water in to hydro
pneumatic fresh water system. A non return valve is also provided as a positive
isolation. Also PS-257 tripping will give annunciation on the local panel (C-34) as
well as in the main control room. Running of electric fire pump will also be
annunciated in the main control room. Thirdly, tripping of PS-257 will isolate
screen wash system by closing control valve CV-257A and opening control valve
CV-257B for fire protection system. P-10A pump is supplied from 1MVA
Substation and it can be used during station blackout condition also.P-10A pump is
not having auto start facility as a fire pump however it can be started manually.
In the event the electric fire pump does not start due to loss of AC power
supply and the fire system header pressure drops down further to 75 psig. (5.1
2
Kg/cm ) Diesel fire pump (1000 gpm/3785 lpm) will automatically start due to
tripping of PS-282 and supply sea water to fire protection system.
As the fire protection system is a critical from the stand point of plant and
personnel safety, monthly auto starting test of jocky fire pump is done by suitably
draining hydro pneumatic tank. Jockey fire pump ON and OFF time is also
monitored to asses the leak in the fire system piping. Diesel fire pump is tested
weekly. Quarterly functional checks are done for electric fire pump P-10B/C, PS-
257 actuation and auto actions, CV-257A/B and CV-686 operation.
Portable fire extinguishers of various types are provided throughout the plant
at suitable points. Carbon dioxide gas cylinders, soda acid water, foam type gas
cylinders, dry chemical powder fire extinguishers are provided at various locations
as per the fire load.
DRG 233A
Carbon Dioxide Fire Protection
CARDOX System
Purpose:
Carbon dioxide (CO2) fire protection system provides automatic control of fire for
the following areas/equipments.
i) Tanks: Clean lube oil storage tank T-32, Dirty lube oil storage tank T-
33, turbine lube oil reservoir 1T-29 & 2T-29, lube oil conditioner S-
2.
ii) Local application nozzles on the lube oil reservoir top, protecting
pumps, filter and top of reservoir.
iii) Local application nozzles on lube oil filter pump and lube oil transfer
pump.
The system consists of two cylinder banks. One main bank and another
reserve bank. Each bank consists of 7 nos. of bank cylinders and 2 nos. of pilot
cylinders each of 75 lbs capacity. System is having one common control cylinder
with PRV. PRV down stream pressure is maintained at 300 psig. System is
common for both the recirc pumps.
Control cylinder CO2 is pressurized upto solenoid valves. There are two
temperature switches for detection of fire for each pump which actuates at a
temp. of 225o F (107.2oC). The system is located in valve penetration room
adjacent to RK01/RK11. Actuation of a temperature switch causes solenoid valve
to energise and release CO2 gas for opening of shuttle valves and pilot selector
valves. Pilot cylinders are having actuator heads on the cylinders. These cylinders
are fired by the control CO2 and the gas from pilot cylinder is discharged in main
header. This pressure helps to fire cylinders connected to the main header. The gas
discharged by all the nine cylinders is directed through selector pilot valves
towards the affected pump for extinguishing fire. CO2 control header is provided
with one pressure switch which gives alarm in control room as well as sounds
header inside and outside drywell at 125 R.B. There is a selection switch for
selecting main or reserve bank for each pump. System control power supply is
from 250V DC. Two minutes of time delay is provided for the people to vacate the
area. The system is having three modes of actuation.
When gas enters control header it actuates pressure switch which gives
alarm in control room. The PS trips running makeup area supply and exhaust from
V4 A/B and V5A/B. The PS also trips 1K5, K5 & 2K5 vapour extractors. It will
also sound hooters in lube oil and make up demin. area.
2. Remote manual actuation: When fire is detected & confirmed in the area &
if system did not activate is auto it can be activated from manual activation
station in lube oil area.
3. Manual actuation: The system is having provision for actuating even in case
of loss of Control Power Supply. Confirm first which is the selected bank.
Open the directional valve by its hand wheel and open
manual by-pass valve of pneumatic discharge delay. Open the ball valve in
the discharge of auxiliary N2 cylinder valve and operate auxiliary N2
cylinder valve. This will cause actuation of selected bank cylinders. Both the
Cardox Systems are tested during refueling shutdown. Temperature switches
are actually heated upto required
temp. and system is actuated with one cylinder connected to a bank. This test
is called puff test.
EDG CORDOX System
The system is common for EDG G2A, G2B and G2C. The manifold is
equipped with normally closed directional valves, which are actuated
pneumatically. For operation of directional valves separate N2 pilot cylinders are
provided. In between N2 pilot cylinder and directional valve Solenoid valve is
provided to achieve proper activation of directional valve for the hazard under fire.
The directional valve valve when opened will release CO2 gas into the protected
area. In addition to that directional valve can be opened manually.
In cylinder bank those cylinder which are provided with release unit which
comprises of Electric actuating device and manual override is termed as Master
cylinder. Other remaining cylinders, which are not fitted with electric and manual
actuators, are termed as slave cylinders. The system is capable of electric and
manual activation and can be released by one or more of the following methods.
AUTOMATIC RELEASE
As soon as fire is detected from both the detectors (i.e. one Ionization smoke
detector and Photo electric smoke detector), signal is sent to the Fire alarm and
CO2 release panel.
In the unlikely event of power failure, the system can be actuated manually.
One N2 auxiliary cylinder is provided with additional valve to actuate master
cylinder and slave cylinders of both the banks by actuating N2 auxiliary cylinder
and opening discharge valve the system can be actuated. Required directional
Control valve shall be opened manually.
DETECTION OF FIRE
Each of the areas covered under CO2 Protection system is divided into two
fire detection zones. Each of the detection zones will have any one type of smoke
detectors (ISD or PSD) and one UV detector in the loop. In the event of fire in any
of the three areas the Ionization /Photoelectric/ Ultraviolet detector in its vicinity
will sense it and give signal to the fire alarm cum CO2 Control panel. If the panel
receives signal from both the zones in an area (i.e. if cross zoning of signal takes
place), the panel treats it as a certain “Fire” condition, gives alarm and actuates fire
protection system. In case CO2 flooding is required to be stopped before it is
initiated, the same can be done by pressing the Abort switch, installed at the
entrance of DG room.
DRG 233B
DRG 233C
DRG 233D
Protective Coating & Colour Codes
Pumps - do –
Transformers - do –
Machine Tools - do –
Gantry Cranes - do –
Conveyors - do –
Identification
Piping Description of System Overall Colour
System Band colour & No.
553 Primary feed water Sky blue (101) Single band of white
554 Secondary feed water Sky blue (101) Double band of white
564 Turbine gland seal piping Aluminium Single band of red (538)
571 Salt Service Water Oriental blue (174) Single band of white
Discharge piping from Colour code and bands same as the process piping
576
Misc. Relief Valves on which the Relief Valves are located
584 Reactor recirc. water French blue (166) Single band of crismon (540)
587 Reactor Cleanup French blue (166) Double band of crimson (540)
588 Reactor shutdown French blue (166) Single band of light bronze
green (222)
Emergency condenser
597 Salmon Pink (443) No bands
shell vent to roof
Note: The Specification numbers indicated against each colour stated above
refers to the colour numbers given in Indian Standards Institution
Publication No. IS 5-1961.
During a refueling outage, there are more than 1000 separate activities that
may be necessary to be carried out by different sections. In Mechanical
Maintenance Turbine Group may be attending to 300 jobs and Reactor Group to
200 jobs. Electrical Maintenance may be attending to 250 activities and Instrument
Maintenance to 150, Operation, Technical Services and Civil Maintenance to 200.
These numbers are only an order of magnitude but they clearly illustrate that a
large number of important operations are involved. An efficient and safe refueling
depends upon proper planning, preparation and execution.
Planning:
Months before each refueling outage, specific tasks are designated for each
section and a detailed schedule is made indicating critical path jobs, and activities
of each section and number of days required for each activity are also shown. With
each outage; as experience is gained, job sequences are refined to provide the
safest and most efficient method of performing the function. Planning also includes
pre-refueling equipment inspection and periodic checks of equipment during
operation. For example, refueling grapple is thoroughly checked before using it for
handling fuel bundles etc. and is checked periodically during its use.
Preparation:
Cutting down refueling outage is necessary, but speed alone is not the
primary objective. Safety is the first consideration as a single accident could result
in loss of considerable amount of time and man-rem. Efficient and safe operation
depends upon careful preparation before the start of the operation to be performed.
Execution:
Equipment operator is responsible for a safety and speed more than any
other single factor. He is trained and made thoroughly familiar with equipment, its
proper use, function and its limitations. Jobs are performed in a specified order and
with specified duties by organised teams of men with a leader.
Work is stopped and inspection performed when equipment operators notice
any indication of malfunction. This is particularly important for equipment with
motor drives and hoists, such as CRD removal and installation tool or refueling
grapple. Operations are carried out in a planned way and in the specified sequence.
Refueling Works:
When above cavity works are in progress IRM detectors are removed and
TIP tubes are disconnected. SRMs are connected in non-coincident mode scram.
Initial Core inspection is carried out after clarity improves and In-core
sipping is done to identify the failed fuel assemblies. The sipper head which
positions over the fuel cell isolate the four fuel bundles from the rest of core.
Continuous air flow in the sipper establishes and air pocket above the fuel that
blocks flow out of the channels and prevents water sample contamination and
cross-mixing from surrounding fuel channels. After 20 minutes of soaking time to
allow for fission products build up, water sample is withdrawn from each of the
fuel bundles and samples are analyzed in Chemical Lab. Samples from failed fuel
bundles will show higher activity.
Fuel pool gates are removed after completing In-core sipping. Out of core
sipping is done for fuel bundles which due to any reason could not be sipped in the
core or suspect fuel bundles.
Orifices are inspected and the displaced ones are seated properly or new
ones are installed. Now a days all fuel bundles are coming with welded loose
orifices. The peripheral fuel bundles locations are having adopter orifice as a
substitute for tight orifice.
New fuel bundles, after inspections are channeled with either new channels
or with irradiated channels with new channel fasteners. Approximately 100 nos. of
fresh fuel bundles are loaded in the core to take care of 18 months of refueling
cycle. The irradiated channels are inspected for any bulging out before using for
channeling a new bundle. Reshuffling of fuel bundles and loading of the core with
new fuel bundles is done using refueling grapple. All core work is done under
water standing on the refueling bridge.
Refueling Platform
Over Reactor No. 1
Refueling Platform
Over Reactor No. 2
A “Slack Cable” interlock has also been provided on the fuel hoist.
After fully constituting the new core, core verification in the presence of
IAEA representatives by CCTV camera is done. Final works in the cavity are done
for installation of dryer separator, vessel head, drywell head and pit plugs etc. Then
the unit is started as per guidelines given by Reactor Physics .All the mandatory
tests are conducted and unit is synchronized to the grid. Further power raise is done
as per the guide lines given by Pre-Conditioning Interim Operation Management
Review recommendations up to full power.
Two units outage is availed and total loss of power test is conducted to
check the performance of diesel generators and associated switch gears as well as
the performance of EMTR’s and performance of Core spray and Post incident
system equipments is also done. Checks and inspection cum repairs of common
systems such as SSW, RBCW, TBCW etc. are done.
Surveillance checks such as ISI of primary system piping, welding integrity
checks of critical equipment are done during refueling outage. Functional checks
such as manual scram push button, emergency condenser pipe way high
temperature switches, main steam line high temperature switches, poison system
squib valve firing and liquid poison sparger through ness, drywell cardox puff test,
core spray sparger through ness, drywell spray nozzles through ness tests, and
drywell sump pump performance checks etc. are also performed.
Acid and Caustic System
There are two storage tanks one for acid (T-34) and one for caustic (T-35)
each of about 22,100 liters capacity, located in front of Mechanical Workshop.
Concentrated Sulphuric acid (98% concentration) and concentrated caustic as
Sodium hydroxide (NaOH) (48% concentration) is received separately from the
outside suppliers in tanker and these tankers are unloaded in the respective storage
tanks. Received acid/caustic tanker samples are first analyzed and then only
tankers are unloaded in acid /caustic tanks.
On the acid storage tank acid transfer pumps (P-23A and P-23B) and on
caustic storage tank caustic transfer pumps (P-22A and P-22B) are provided. The
pumps are having selector switches near the pump. The pumps can be tested by
local push buttons provided near the pump. There are bubbler type level indicators
provided which indicate the level in centimeters. On the acid tank the vent line is
provided with silica gel breather to avoid ingress of moisture where as on caustic
line only vent line is provided. The pump capacity is 20 gpm. These pumps are
provided with minimum recirculation line for pump protection. On the discharge of
the acid and caustic pumps a filter is provided and down stream of the filter acid
and caustic is supplied at three places. A separate acid line is provided for Make up
demin. and regeneration facility from outside the building.
The selector switches for acid/caustic pumps are provided near pumps. The
pumps control switches are provided on regeneration facility control panel, Make-
up demin. control panel and radwaste control panel. The selected pump can be
started from Make-up demin. panel only if CV for makeup demin. system is open.
Similarly selected pump can be started from radwaste panel if CV for radwaste
system is open. There is no interlock for starting pump from regeneration facility
panel.
Acid and Caustic storage tank low level alarms are provided on regeneration
facility panel. Safety showers and eye washers are provided at acid/caustic storage
tanks area, Make demin. system area, radwaste system area and regeneration
facility area.
One separate pump is provided each for acid and caustic tanker unloading.
The tanker unloading is done by using these pumps only. While unloading tanker
sample is analyzed by chemist. All the safety precautions are taken while
unloading acid and caustic tanker.
DRG 246A
Radioactive Waste Disposal
Purpose:
Three types of radioactive wastes i.e. Solid, Liquid and Gaseous wastes are
generated as a part of normal operation of the plant. The purpose of the radwaste
system is to collect process and dispose off the radioactive waste in an efficient
manner without limiting station operation and without exceeding prescribed limits
on release of radioactivity to environs.
Description:
The solid waste generated consists of filter sludge, spent resins and assorted
waste. Filter sludge is received in sludge tanks in the form of slurry. The
slurry is processed by centrifuge to separate solids from liquid. The
separated solids collect in a 200 liters drum and the liquid is returned to
liquid radwaste system. Remote operated hoists and conveyor system is
provided to handle the drums containing radioactive solid waste. After a
drum gets full, it is capped remotely and then transferred to concrete cask for
transportion to burial ground. At burial ground the drums are disposed off in
underground concrete trenches.
Spent resin: Now-a-days spent resins are not processed but it is transferred
to large underground storage tank known as SPERT for temporary storage.
However, the facility of processing spent resins using centrifuge exists.
Assorted waste: Assorted waste arises from cotton rags, used filter
elements, used insulation, used pipes, active scrap and other miscellaneous
items. The assorted waste is straight way transferred to burial ground after
proper packing. A hydraulic press is provided to compress the bulky
assorted waste as required.
2) Liquid Waste:
The liquid radwaste arises from system leaks, isolation and draining of
equipments for maintenance jobs, equipment drains, regenerants of
demineralisers, decontamination centre and laundry drains etc. The liquid
wastes are classified depending on their chemical purity. The classification
of waste is shown below:
Liquid Radwaste
CRW: All clean radwaste coming to CRW sumps at various locations in the plant
is pumped out to waste collector tank (T-38). The sump pumps are automatically
controlled by sump level switches.
The waste collector tank has been provided with a cooling coil to cool the water so
that it does not damage ion exchange resins while processing through
demineralizer.
The CRW is first passed through filter (F-4) to remove insoluble impurities and
then through demineralizer (T-51) to remove soluble impurities. The water thus
processed is collected in waste sample tank (T-50). After processing the water is
analyzed and transferred to condensate storage tanks for reuse.
DRW:
All floor drains coming to DRW sumps at various locations in the plant is
pumped out to floor drain collector tank (T-46). The sump pumps are
automatically controlled by sump level switches.
After processing of a batch is over the sample tank water is analyzed for
pH, radioactivity and is then transferred to TRAP (Tarapur Radwaste
Augmentation Plant) for further activity reduction by chemical processing
and decay. After providing maximum possible decay the water is discharged
to sea after analyzing the water through TAPS discharge line.
The waste from (T-48A/B) is then passed through filter (F-5) to one of the
floor drain sample tanks (T-49A/B).After the processing of the batch is over
the tank is analyzed for radioactivity and transferred to TRAP. At TRAP, the
waste is processed using chemicals to remove long lived radioactive
nuclides. After providing maximum possible decay the water is discharged
to sea after analyzing the water through TAPS discharge line.
c) The Laundry Waste is discharged to sea without any processing.
Gaseous Waste:
The basic source of the radioactive gases is the reactor. In the reactor, certain
gaseous activation products are continuously formed due to radiolysis of reactor
water. Also the reactor water undergoes some decomposition to form gaseous
hydrogen and oxygen. Some fission gases are also released in the reactor from
leaky fuel assemblies. The systems which handle gaseous waste are Air ejector off
gas system and gland seal system.
The non-condensible gases from the reactor pass through the steam lines to
the turbine and then to main condenser. A small fraction of gases leave the turbine
via gland seal system.
The air ejector off gas system consists of hold up line of sufficient volume to
provide 30 minutes decay time between the air ejector and the plant stack.
A high efficiency particulate filter has been provided at the end of hold up
line to remove particulate decay products of fission gases. The particulate removal
efficiency of filter is 99.97% for 0.5 micron and larger size particulate. Two Off
Gas radiation monitors are provided to monitor the discharged gases. The Off gas
line is also designed for automatic isolation in case of high activity release.
The non condensible gases coming to turbine gland seal system are extracted
by gland seal exhauster, passed through a 1.75 min. hold up line and then released
to atmosphere through stack.
Gases: The annual average release rate of radioactivity from station stack shall not
exceed 65 mci/sec.
DRG 251A
DRG 251B
DRG 251C
DRG 251D
DRG 251E
Diesel Oil System
The purpose of this system is to store and supply sufficient diesel oil to meet
the requirements of three Emergency Diesel Generators, One Station Black Out
Diesel Generator and One Diesel Fire Pump. The diesel oil system consists of the
diesel oil storage tanks, diesel oil transfer pumps, three over head day tanks
associated with each emergency diesel generator, over head day tank for Station
Black out Diesel Generator, under ground day tank for diesel fire pump and the
necessary valves and instrumentation.
The diesel oil bulk storage tank T12A is having a capacity of 76,000 liters.
The low level alarm appears in the main control room when the quantity of diesel
oil in the tank falls below 40,000 liters which is well above the requirement of one
diesel to run at rated load continuously for seven days.
The second diesel oil bulk storage tank T12B is having a capacity of 55,000
liters. The low level alarm appears in the main control room when the quantity of
diesel oil in the tank falls below 40,000 liters.
Each tank is provided with a level indicator and a level switch with alarms at
high and low level. Manual starting of one of the two-diesel oil transfer pumps P-
20A or P-20B does filling of the day tanks. Starting of diesel oil transfer pumps
from the respective DG day tank instrument panel can fill the day tanks. In case of
high level in any one of the three day tanks, the diesel oil transfer pump shall stop
automatically.
One motor operated discharge valve has been provided for diesel oil transfer
pump P20A. The valve opens automatically, when the pump is started and closes
when the pump is stopped.
P20A & B has got control on EDG MCC and two local areas i.e. at the
Storage tank areas. There is a high level trip for the pump from the individual over
ground day tanks level switches which is effective only when the pump is started
from the corresponding local switch.
Diesel transfer pump P20A takes suction from diesel oil bulk storage tank
T12A and pump P20B takes suction from diesel oil bulk storage tank T12B. Power
supply to the diesel transfer pumps P20A and P20B is derived from G2A and G2B
local MCC panel respectively. Pump control switches are provided on each DG
local MCC panel and near the day tanks. The switches near day tanks override the
high level pump interlock. It is possible to transfer the oil from diesel oil bulk
storage tank to day tanks by gravity. The operability of diesel oil transfer pump is
checked once in a week.
DRG 253A
Neutron Monitoring System
These three (i.e. SRM, IRM and PRM) have enough overlap (See
Fig.61) for reliable reactor protection. One channel of each of the three can be
bypassed for maintenance. In addition to the protection instrumentation there are
other two neutron monitoring systems namely “Local Power Range Monitors”
(LPRM) and Traversing In core Probe (TIP) system. LPRMs do not play as
important in reactor protection, but, are very important to reactor operator. LPRMs
indicate the effect of Control Rod Drive (CRD) movement immediately and helps
the operator to visualize the axial and radial neutron flux/heat flux distribution. TIP
system is used for calibration of LPRM monitors.
Source Range Monitors (SRM):
When reactor goes to heating power the detectors are moved down from (out
of) the active core (i.e. retracted) to increase detectors life as IRM’s and PRM’s get
picked up.
There are four IRMs like they too have retractable detectors located inside
reactor. These detectors are miniature fission chambers similar to those of SRMs
but the principle used for computation of flux is different. It is observed that mean
of the squares of the a.c. ripple of voltage of the fission chamber output is
proportional to the thermal neutron flux in the reactor core. This observation is
used to compute the neutron flux or reactor power. It is not logarithmic device
hence flux is monitored in the working range by making use of range switches.
The signal is received at the monitor after getting amplified at the pre-
amplifier. It is also observed that the frequency of output signal ripple changes
from about 8 kc/s to 16 kc/s band at lower flux to about 300 kc/s 600 kc/s band at
higher reactor flux. This change over is achieved through diode logic after
particular position of the range switch. This monitor gives “On Scale” control rod
withdraw interlock, Rx. high flux alarm and Rx. high flux “SCRAM”. When the
reactor power exceeds 10% the detectors are retracted below the active core to
avoid detectors from getting burnt up.
This system is used to monitor neutron flux at a fixed point location inside
the reactor core. This gives an idea of axial and radial neutron flux distribution
pattern inside core and helps in indicating heat generation pattern and in avoiding
hot spots on fuel bundles.
Control Rods are used in TAPS to control the reactor power. It is necessary
to know the positions of control rod blades (the neutron absorber) with respect to
the fuel bundles. Drive assembly is a hydraulically operated position piston device.
CRD position indication of each drive is transmitted to control room with the help
of a position indication probe housed inside the drive.
Radiation Monitor:
All the instruments described above were directly monitoring the primary
process i.e. the Nuclear Reaction. System here after will be of
secondary nature i.e. monitoring the effects of the reactor operation. This part of
discussion explains important instrumentation which monitors integrity of the
primary systems, aspects affecting plant personnel and the population at large.
These systems are treated under each sub-heading.
These systems monitor the process fluids and gases coming out of reactor or
reactor auxiliary systems. This indicates about system integrity and radioactivity
releases either qualitatively or quantitatively. They are:
1) Radwaste Demin. Effluent 9)Cleanup demin. effluent
2) Drywell purge discharge 10)RBCW cooling water
3) Reactor Bldg. Ventilation Disch. 11)Service Water Disch.
4) Emergency condenser Disch. 12)Circulating water Disch.
5) Emergency cleanup fan Disch. 13)Sample tanks to Disch.
6) Condensate DM Influent 14)Stack gas monitor
7) Condensate DM effluent 15)Primary steam line
8) Off gas radiation monitors radiation monitors.
Five of these are logarithmic gamma monitors are using sodium iodide
scintillates along with photo multiplier tubes. All the monitors are inter-changeable
with some modifications. As in other systems, the monitors are mounted on panels
in the control room whereas the detectors are mounted in field.
In stack gas monitoring system the part of the total gaseous discharge is
drawn as a sample at a constant flow rate through an iso- kinetic probe. It is made
to pass through iodine and particulate filters. Sodium Iodine crystal detector feeds
signals to two monitors. One is the gross count rate activity monitor (Channel “B”)
and the other is a single channel (Channel “A”) analyzer counting all gamma
emitting radio nucleons above 400 Kev contribution by Cs, Co, Noble radioactive
gases etc.
Primary steam line and off gas monitors use ion chamber detectors.
Detectors for the former mounted on the steam lines between reactor and turbine
and initiate primary steam isolation valve closure and SCRAM when preset value
of activity is exceeded. The latter monitors effluents from condenser i.e. non
condensable gases discharged by air ejector after a delay of about 2 minutes.
This monitor initiates closure of off gas discharge valves after a time delay if
pre set value of radiation level is exceeded. This system set point is calculated by
collecting grab sample of “Off-gases” counting it in laboratory and calculating the
values of activity release.
Three gamma detectors are located at a radius of 1 km. from the plant to
monitor and record the effect of plant operation on the environs.
For the purpose of initiating and maintaining long term core cooling
additional control points are identified from where some of the pumps and motor
operated valves can be operated. These are basically motor control centers and
circuit breaker panels and are termed as Supplementary Control Points.
In the Supplementary Control Room provisions has been made for following
controls/indications
II. Initiating Shutdown cooling for long term residual heat removal
DRG 262A
Chillers and CTPH
Purpose:
Chillers are used to provide continuous supply of low temperature cooling water of
@ 8°C to various air conditionings and other equipments for cooling various
zones.
General Description:
The chilled water system provides circulating coolant which is used in conjunction
with the plant ventilation system to remove heat from certain areas in the service
building, reactor building, containment cooling building, administration building
and also provide chilled air to drywell.
Demineralized, inhibited water is circulated within a closed loop by one of two full
capacity pumps. This passes through the cooler section of two chillers. (During
normal operation two chillers are in operation and one in standby condition).
It is important that the chilled water system remain in operation at all times to
prevent overheating of electrical equipment through the plant. This is not required
as an emergency system however.
The Kirloskar Mcquay Ltd., Pune make 280 tons centrifugal chiller is a complete,
self contained, automatically controlled water chilling unit. The chiller consists of
a compressor connected to a condenser and a evaporator. The chiller uses R-134a
refrigerant gas (CH2FCF3-Tetrafluoroethane) at a positive pressure over the entire
range of operation, which reduces size and weight of the chiller package, compared
to negative pressure refrigerant chillers. Thus problem of air ingress and purging
has been eliminated as encountered in previous carrier chillers which operate under
negative pressure in evaporator.
The compressor is single stage, made of high strength aluminum alloy (cast)
and is 254 mm in diameter. The capacity of compressor is 280 Tons of
Refrigeration at design condition. Compressor is rotated at 24,846 RPM.
Compressor outlet discharge pressure is 9.4 Kg/cm². Total five bearings are
provided in the compressor.
One in the rear end of high speed assembly and two in the front end of high
speed assembly of compressor.
One on the motor end and one on the compressor end of low speed shaft.
Lubricating oil under pressure is fed to the bearings for cooling bearings. For
this a separately mounted oil pump and a plate type heat exchanger is used.
2 no. of 250W, 115V AC crank case heaters are provided. These heaters get
switched “ON” whenever Chiller is in stopped condition. This is to reduce
the absorption of refrigerant in the oil.
(b) CONDENSER:
Condenser is a horizontal, double pass, shell and tube type, heat exchanger.
Hot refrigerant flows on shell side and raw water flows on the tube side. The
tubes are 19mm dia copper material and shell is MS as per IS2002 Gr-2. The
design raw water inlet & outlet temperatures are 31°C & 38.0°C. The design
cooling water flow rate is 155 m³/hr (680 gpm – 25 % flow). The design raw
water pressure drop across condenser tubes is 9.2 FT of WG.
The refrigerant discharged by the compressor condenses on the outside of
the condenser tubes, when the latent heat is removed from the refrigerant
vapors by condenser raw water cooling water. The liquid refrigerant
condition at outlet of condenser is 35.9°C & 9.4 Kg/cm². The refrigerant in
liquid form will be fed to evaporator through the pilot thermal expansion
valve. The condenser has two relief valve separated by a three way shut off
valve. This valve allows any one of the relief valve to be isolated (in case of
RV is leaking). Both RV’s can not be isolated at the same time.
EVAPORATOR:
Evaporator is of horizontal two pass shell and tube type heat exchanger.
Evaporator has 19 mm dia copper tubes. Chilled water flows on tube side and
refrigerant flows on the shell side of evaporator.
The design chilled water temperature at evaporator inlet & outlet are 13. 3°C
& 6.6°C respectively for a chilled water flow rate of 128 m³/hr (560 gpm - 61%
flow). The design chilled water pressure drop across evaporator tubes is 9.2 FT of
WG. The evaporated gas at the outlet of evaporator goes to suction of centrifugal
compressor, at a pressure of 2.5 Kg/cm² and temperature of 4.4°C.
Expansion Device:
The oil system provides lubrication and heat removal for compressor
bearings and internal parts. In addition to above, the system provides oil under
pressure to hydraulically operate the loading and unloading piston, for positioning
the compressor inlet guide vane, for achieving the desired chiller capacity control.
The oil system consists of motor, pump, oil heater, oil cooler and oil
reservoir. Oil reservoir has 30 liters oil capacity. The oil pump is driven by a 2 HP
(1.5 KW), 3000 RPM, 115V AC single phase motor.
The oil pump develops a maximum pressure of 14 Kg/cm² and a continuous
flow rate of 16 US gpm. The oil is pumped through a oil filter in to a plate type
heat exchanger. Oil is cooled by chilled water taken from the chilled water inlet
line to evaporator and oil cooler outlet is connected to chilled water circulating
pump suction header.
One SV is provided in the chilled water inlet line to oil cooler, which opens
on chiller starting. The oil temperature is maintained between 32°C -38°C (90-
100°F) during normal operation by chilled water flow control through a
thermostatic valve at the cooler outlet line. The chilled water to oil cooler also has
isolating valve and a 40 mesh strainer. During lube oil pump power supply failure
condition, lube oil requirement during coast down of chiller is accomplished by a
spring loaded piston. When the oil pump is started, the piston is forced back by the
oil pressure. This compresses the spring and filling the piston cavity with oil.
When oil pump stops, the spring pressure on the piston, forces the oil out to the
bearings, hence ensuring lube oil during chiller coast down period.
The oil reservoir has two numbers of 250 watts (each) electric heaters for
maintaining the oil temperature. These heaters get switched ON when the chiller is
not running. Out of this one of the heater remains continuously ON and the other
cuts in and cuts out to maintain oil reservoir temperature. Oil temperature is
maintained to reduce the absorption of refrigerant in the oil.
VANE OPERATIONS:
The hydraulic system for the inlet guide vane operation consists of a 4-way
normally open SV. Oil under pressure is directed by the 4-way valve to either or
both sides of the piston, depending on whether the control signal is to load, unload
or hold the load on chiller.
To open the vanes (load the compressor) solenoid SA is de-energized and
solenoid SB is energised, allowing oil flow from port SA to one side of piston then
drain through port SB.
When both SA & SB solenoid valves are de-energized, full oil pressure is
directed to both sides of the piston through port SA & SB, thus the vanes are held
in that position. Also both SVs can not be energised simultaneously. The speed at
which the capacity control vanes are opened or closed can be adjusted to suit
system operating requirements. Adjustable needle valve in the oil drain lines are
used to control the rate of bleed-off and consequently the “vane speed”. The needle
valves are part of the 4-way SV assembly located in the compressor lube box.
The hot gas bypass system used to feed discharge gas directly into the evaporator
when the system load falls below a predetermined minimum compressor capacity.
Unit Controller – controls unit function and communicates with all other
controllers. It is the secondary location for set point input if the OITS is
inoperative.
It is the primary device by which commands and entries into the control system are
made. It displays all controller data and information on a series of graphic screens.
The side of the OITS contains a floppy disc drive that can be used for loading
information to and from the control system. The screen is reactivated by touching
it anywhere.
Unit Controller:
The unit controller primary function is processing data to the entire chiller unit
operation as compared to data relating to the compressor operation. The unit
controller processes information and sends data to other controllers and devices
and relays information to the OITS for graphic display. It has a 4*20 LCD display
and keys for accessing data and changing set points. The LCD can display most of
the same information as the OITS and can operate the chiller independently if the
OITS is not available. The Unit and Compressor ON/OFF switches are mounted
inside the Unit controller.
Compressor Controller:
• Operator can log chiller operating conditions from a single key pad / display
instead of reading gauges, thermometers, pots etc.
• Auto logging feature will log chiller functions at the time of peak load. The
controller will store and display up to six weeks of accumulated data.
• Three levels security protection against unauthorized changing of set points and
other control parameters.
• Complete warning and fault diagnostics (along with date and time) to inform
operator of any abnormality. In addition the operating conditions that exist
prior to shut down can be recalled to aid in identifying the cause of problem.
• Twenty-five previous faults and related operating conditions are available for
display.
Remote input signals for chilled water reset, demand limiting, unit enable.
• History trend feature will constantly log chiller functions and set points. The
controller will store and display all accumulated data for recall in a graphic
format on the screen.
Chiller-PH-063M has two control panels. They are Micro-Tech panel and local
starter panel.
(1) Micro-Tech panel has STOP/AUTO toggle switch, 18 pressure sensitive key
pads and display unit.
(2) Starter panel has breaker healthy indication, motor current and emergency
trip PB.
(1) Lub oil heater is always kept ON (through logic) when chiller is not running.
The oil sump temperature shall maintain between 50-54°C (125-130°F).
This is to avoid mixing of refrigerant into lub oil.
(2) Chilled water outlet temperature should not be lower than 5°C, to avoid
chiller tripping and not greater than 15°C to prevent area heating.
(3) Lub oil level in the oil reservoir shall be maintained at around 50% during
chiller startup, chiller operation and after chiller trip.
(4) Whenever chiller trips, ensure the control supply to Micro-Tech panel is in
energized condition by checking MCB-1 / MCB-2/ MCB-3 and MCB-4
inside local Starter panel is ON. This is to ensure that oil heater is ON
When the chiller is under shut down, the status of system will be as follows,
(1) Chilled water flow to chiller evaporator is stopped by closure of its isolating
valves
(2) Raw water flow to chiller condenser is stopped by closure of its isolating
valves.
These TRIPS/FAULTS must be cleared manually to restart the unit Chiller will be
shutdown by Micro-Tech panel in response to any of the following TRIP/FAULT
condition.
SL
DESCRIPTION OF TRIP PARAMETER
NO
1. Low Evaporator Pressure
2. Low oil Delta Pressure
3. Low Oil Feed Temperature
4. High Oil Feed Temperature
5. Low Motor Current
6. Motor Protection Trip
7. High Discharge Line Temperature
8. High Condenser Pressure
9. Refrigerant high pressure at compressor outlet line
10. High Motor Temperature
11. High Suction Super Heat
12. Low Chilled Water Flow
13. Low Raw water Flow
14. Evaporator Outlet Temperature Sensor Fail
15. Evaporator Pressure Sensor Fail
16. Condenser Inlet Water Temperature Fail
17. Compressor Suction Temperature Sensor Fail
18. Compressor Discharge Temperature Sensor Fail
19. Condenser Pressure Sensor Fail
20. Oil Feed Temperature Sensor Fail
21. Oil Sump Temperature Sensor Fail
Cooling Tower Pump House
Purpose of the cooling tower pump house is to cool the return water from
chiller condenser by giving its heat to the environment so the cool water can be re
used for chiller condenser cooling. CTPH is of cross flow induced draft type.
CTPH is divided in to two separate compartments. Each compartment is having a
fan. Return water from Chiller condenser is broken in to fine particles (atomized)
by spray nozzles while traveling downwards in cooling tower. The air flow which
enters cross flow and travels upwards cool the fine water particles and picks up the
heat from the water.
The heat transfer takes place by latent heat transfer method. The hot air
which has picked up the heat is discharged to the environment by the running fans.
The cool water is collected in the sump which is divided in to two parts. Pumps P-
104 A/B/C takes suction from the sump and discharges in to common discharge
header. The pumps are protected by Y strainer in the suction. Normally two pumps
are running while third remains standby. During normal operation one
compartment can be isolated and cleaned.
AFR is designed to store the irradiated fuel bundles which have been cooled
in TAPS fuel pool for at least 10 years. Irradiated fuel bundles from TAPS fuel
pool are transported to AFR fuel pool in approved dry transportation fuel cask.
(a) To remove the decay heat generated by stored spent fuels. The expected
generation of heat is at the rate of 0.1 KW per bundle. The fuel pool water
temperature should be maintained less than equal to 42oC. In no case the
temperature should increase more than 60oC.
General Description:
1. Fuel Pool:
The size of the pool is 9M x 13M x 13M depth and is lined with SS -304 L 6
mm thick up to 5 meters from bottom, then onwards it is 3 mm. Cask
handling area with 25 mm thick SS plates is also provided. The pool is
designed to store 2000 TAPS fuel bundles or equivalent with a provision to
augment for storage of 3312 bundles. Total water volume in the pool is 1376
M3 .
2. Heat Exchangers:
For normal operation two plate type heat exchanger are used to maintain the
pool water temperature less than equal to 42oC. Primary and secondary
cooling water flow rates are 30 M3/ hr.
3. Pumps:
Two full capacity centrifugal pumps are provided for circulating pool water.
Pump discharge pressure is 9.0 Kg/cm2.
4. Filters:
Two full capacity cartridge filters of efficiency up to 10 microns are used for
removal of accumulated crud in the fuel pool released during fuel handling.
One full capacity bed of resins volume 1.8 M3 is used to trap radio Cs
isotopes.
6. Mixed Bed:
One full capacity bed of anion to cation resins in the ratio of 3:2 is used to
maintain the pool water quality.
Mixed bed outlet water quality: Silica < 0.02 ppm and conductivity < 1.0
micro mho/cm.
7. Cooling Tower:
Total heat load is 190 x 10 3 Kcal/ hr. Heat extracted from circulating water
(i.e. fuel pool water) in the heat exchanger by raw water which is cooled by
cooling tower to atmosphere.
Two full capacity pump of discharge pressure 3.5 Kg/cm2 is used for
circulating cooling water from cooling tower to heat exchanger and back to
cooling tower.
AFR facility is provided power supply with two different sources. Normal
415 V power supply required for AFR equipments is supplied by a 3.3 KV/415V
transformer of capacity 630 KVA. The transformer is getting power supply from
TAPS Zone-III 33 KV feeder No.5.
The feeder supplies via a 33KV/3.3KV transformer of 2 MVA capacity
through underground cable. The AFR transformer feeds to both the 415 V MCC’s
namely MC1 and MC2. An alternate power supply is provided to MC2 for
essential equipments through TRAP. 1MVA substation provides power supply to
TRAP. The change over from normal to alternate power supply takes place
automatically.
UPS System is provided by IAEA for reliable power supply to the lights in the fuel
pool area. There are two UPSs i.e. UPS#1 and UPS#2 having capacity 1.5 KW
each. The UPS System supplies four nos. of tube lights of rating 14 Watts each.
Each UPS is supplying to two diagonally opposite tube lights. Four spare lights are
also available on the fixture, which can be connected if any one fails. The UPS can
provide power supply to the tube lights for two days even if the AC supply fails.
The maintenance of the UPS and the tube lights will be done by IAEA only. Hence
if the UPS or any tube light fails, it should be informed to IAEA at the earliest.
AC Supply to the UPS is from MC-2 (LM panel breaker 14 -Y). In addition to the
UPS, this also provides supply to the three nos. of IAEA cameras. A voltmeter is
provided in the Control room to monitor this AC voltage. Also, if the AC supply
fails, under voltage alarm will appear on control room alarm panel. Even if the AC
supply fails, the cameras will have power supply from their built in batteries for 6
days. If the AC supply fails, it should be rectified within 24 hrs. Any failure of the
AC supply has to be informed to the IAEA at the earliest.
At least, once in 4 hrs. the AFR operator should monitor that all the 4 tube lights
are glowing. He should also ensure that AC supply to the UPS and cameras is
available. If failure of AC supply, UPS, or any tube light is noticed it should be
informed to SCE/ASCE at the earliest. There are 3 nos. of IAEA emergency lamps
kept at the fuel pool area. Every month E/M and operation should check their
healthiness.
DRG 276A