METRADOS GENERALES

PROYECTO CONSTRUCCION DE TROCHA CARROZABLE CANTA GALLO


DISTRITO CIUDAD CONSTITUCION
PROVINCIA CIUDAD CONSTITUCION
DEPART.: PASCO

ITEM DESCRIPCION UND CANT VECES LARGO ANCHO ALTO PARCIAL TOTAL
01 TRABAJOS PRELIMINARES
01.01 CARTEL DE OBRA UND 1.00 1.00 1.00 1.00 1.00
01.02 CAMPAMENTO PROVICIONAL GLB 1.00 1.00 1.00 1.00 1.00
01.03 MOVILIZACION DE MAQUINARIA GLB 1.00 1.00 1.00 1.00 1.00
02 OBRAS PRELIMINARES
02.01 TRAZO, NIVELES Y REPLANTEO KM 1.00 1.00 5.50 5.50 5.50
02.02 TRAZO DURANTE LA EJECUCION DE OBRA MES 1.00 1.00 6.00 6.00 6.00
02.03 LIMPIEZA Y DEFORESTACION M2 1.00 1.00 4,500.00 8.00 36,000.00 36,000.00
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE MATERIAL SUELTO M3 18,316.00
carretera 1.00 1.00 4,500.00 4.50 0.40 8,100.00
cerro 1.00 1.00 2,500.00 2.00 2.00 10,000.00
plazoleta de cruze 1.00 9.00 15.00 4.00 0.40 216.00
3.02 RELLENO CON MATERIAL PROPIO M3 1.00 1.00 2,788.25 2,788.25 2,788.25
3.03 PERFILADO Y COMPACTADO DE SUB RASANTE M2 1.00 1.00 4,500.00 4.50 20,250.00 20,250.00
04 PAVIMENTOS
04.01 PRESTAMO DE CANTERA M3 1.00 1.00 4,635.00 4.50 0.40 8,343.00 8,343.00
04.02 CARGIO M3 1.00 1.00 4,635.00 4.50 0.40 8,343.00 8,343.00
04.03 TRANSPORTE A LA OBRA M3 1.00 1.00 4,635.00 4.50 0.40 8,343.00 8,343.00
04.04 AFIRMADO e=0.20 M M2 1.00 1.00 4,635.00 4.50 0.20 4,171.50 4,171.50
05 CUNETAS
05.01 EXCAVACION DE CUNETAS EN MATERIAL COMUN M3 1.00 2.00 4,500.00 0.50 0.30 1,350.00 1,350.00
06 ALCANTARILLA TMC Ø=48"
06.01 EXCAVACION PARA ESTRUCTURAS - ALCANTARILLA 313.87
cabezal de entrada M3 7.00 1.00 1.80 2.60 2.55 83.54
cabezal de salida M3 7.00 1.00 4.10 1.50 2.40 103.32
Para la alcantarilla M3 7.00 1.00 4.80 1.80 2.10 127.01
METRADOS GENERALES
PROYECTO CONSTRUCCION DE TROCHA CARROZABLE CANTA GALLO
DISTRITO CIUDAD CONSTITUCION
PROVINCIA CIUDAD CONSTITUCION
DEPART.: PASCO

ITEM DESCRIPCION UND CANT VECES LARGO ANCHO ALTO PARCIAL TOTAL
06.02 COLOCADO Y ARMADO ALACANTARILLA TMC Ø=48" M 7.00 1.00 5.60 39.20 39.20
06.03 RELLENADO COMPACTADO CON MATERIAL SELECCIONADO 160.89
Para la alcantarilla M3 7.00 1.00 5.20 1.80 1.90 124.49
Descuento de la tuberia diametro de 48" M3 7.00 1.00 5.20 area=1.13 36.40
06.04 CONCRETO ARMADO f'=175 Kg/cm2 51.41
Cabezal de entrada, Base M3 7.00 1.00 2.60 1.80 0.30 9.83
Cabezal de entrada, Parapeto M3 7.00 1.00 2.20 0.20 0.40 1.23
Cabezal de entrada, Muros M3 7.00 1.00 5.60 0.20 1.95 15.29
Cabezal de salida, Base M3 7.00 1.00 7.00 0.60 0.30 8.82
Cabezal de salida, Parapeto M3 7.00 1.00 2.20 0.20 0.50 1.54
Cabezal de salida, Muros M3 7.00 1.00 5.00 0.20 2.10 14.70
06.05 ENCOFRADO Y DESENCOFRADO 260.26
Cabezal de entrada, Parapeto M2 7.00 1.00 4.80 0.40 13.44
Cabezal de entrada, Muros interior M2 7.00 1.00 5.60 1.95 76.44
Cabezal de entrada, Muros exterior M2 7.00 1.00 6.40 1.95 87.36
Cabezal de salida, Parapeto M2 7.00 1.00 3.20 0.50 11.20
Cabezal de salida, Muros M2 7.00 1.00 5.40 1.90 71.82
06.07 ACERO DE REFUERZO f'c = 4200 Kg/Cm2 2,013.90
Cabezal de entrada, Base KG 7.00 1.00 17.00 1.80 peso=056 Kg 214.20
7.00 1.00 12.00 2.60 peso=056 Kg 218.40
Cabezal de entrada, Muros KG 7.00 1.00 30.00 1.90 peso=056 Kg 399.00
7.00 1.00 6.00 1.90 peso=056 Kg 79.80
Cabezal de salida, Base KG 7.00 1.00 33.00 0.60 peso=056 Kg 138.60
7.00 1.00 3.00 5.00 peso=056 Kg 105.00
Cabezal de salida, Muros KG 7.00 1.00 33.00 1.90 peso=056 Kg 438.90
7.00 1.00 12.00 5.00 peso=056 Kg 420.00
06.08 TARRAJEO MUROS DE CONCRETO 30.24
METRADOS GENERALES
PROYECTO CONSTRUCCION DE TROCHA CARROZABLE CANTA GALLO
DISTRITO CIUDAD CONSTITUCION
PROVINCIA CIUDAD CONSTITUCION
DEPART.: PASCO

ITEM DESCRIPCION UND CANT VECES LARGO ANCHO ALTO PARCIAL TOTAL
Cabezal de entrada, parapeto M2 7.00 1.00 4.80 0.40 13.44
Cabezal de salida, Parapeto M2 7.00 1.00 4.80 0.50 16.80
06.09 MAMPOSTERIA DE PIEDRA CON CONCRETO 9.28
Cabezal de salida, Base M3 7.00 1.00 2.60 1.70 0.30 9.28
07 PONTOM 10.00 M (02 UNIDADES)
07.01 OBRAS PRELIMINARES
07.01.01 TRAZO Y REPLANTEO M2 2.00 1.00 16.00 20.00 640.00 640.00
07.01.02 TRAZO, NIVEL Y REPLANTEO DURANTE M2 2.00 1.00 16.00 20.00 640.00 640.00
07.01.03 ENCAUZAMIENTO DE CURSO DE RIO M3 2.00 1.00 30.00 3.00 1.00 180.00 180.00
07.02 MOVIMIENTO DE TIERRAS
07.02.01 EXCAVACION EN SECO M3 2.00 2.00 Area = 38.00 2.80 425.60 425.60
07.02.02 EXCAVACION BAJO AGUA M3 2.00 2.00 Area = 38.00 2.50 380.00 380.00
07.02.03 RELLENOS EN SECO M3 2.00 2.00 Area = 18.00 2.50 180.00 180.00
07.02.04 RELLENO BAJO AGUA M3 2.00 2.00 Area = 16.00 2.50 160.00 160.00
07.02.05 ELIMINACION DE MATERIAL EXCEDENTE M3 2.00 1.00 402.80 805.60 805.60
07.03 FALSA ZAPATA
07.03.01 FALSA ZAPATA O SOLADO f'c=100 kg/cm2 M3 2.00 2.00 Area = 38.00 0.30 45.60 45.60
07.04 LOSA DE ACCESO
07.04.01 CONCRETO f'c=210 kg/cm2 PARA LOSA M3 2.00 2.00 2.40 5.60 0.20 10.75 10.75
07.04.02 ENCOFRADO Y DESENCOF. DE LOSA DE ACCESO M2 2.00 2.00 2.40 5.60 53.76 53.76
07.05 OBRAS DE CONCRETO CICLOPEO
07.05.01 ESTRIBOS
07.05.01.01 CONCRETO f'c = 210 kg/cm2 + 30% P.G. 8" PARA ESTRIBO M3 2.00 2.00 Metrado en sistema CAD 31.23 124.92 124.92
07.05.01.02 ENCOFRADO Y DESENCOFRADO DE ESTRIBOS M2 2.00 2.00 8.68 3.46 120.13 120.13
07.05.02 ALEROS
07.05.02.01 CONCRETO f'c = 210 kg/cm2 + 30% P.G. 8" M3 2.00 4.00 Area = 5.40 3.10 133.92 133.92
07.05.02.02 ENCOFRADO Y DESENCOFRADO DE ALEROS M2 2.00 4.00 4.00 4.00 128.00 128.00
METRADOS GENERALES
PROYECTO CONSTRUCCION DE TROCHA CARROZABLE CANTA GALLO
DISTRITO CIUDAD CONSTITUCION
PROVINCIA CIUDAD CONSTITUCION
DEPART.: PASCO

ITEM DESCRIPCION UND CANT VECES LARGO ANCHO ALTO PARCIAL TOTAL
07.05.03 ZAPATA
07.05.03.01 CONCRETO f'c = 210 kg/cm2 + 30% P.G. 8" M3 2.00 2.00 Area = 33.66 0.75 100.98 100.98
07.05.03.02 ENCOFRADO Y DESENCOFRADO DE ZAPATAS M2 2.00 2.00 31.80 0.75 95.40 95.40
07.06 OBRAS DE CONCRETO ARMADO
07.06.01 LOSA MACIZA
07.06.01.01 CONCRETO f'c=210 kg/cm2 PARA LOSA MACIZA M3 2.00 1.00 8.50 3.60 0.50 30.60 30.60
07.06.01.02 ENCOFRADO Y DESENCOF. EN LOSA MACIZA M2 2.00 1.00 8.50 3.60 61.20 61.20
07.06.01.03 ACERO DE REFUERZO EN LOSA MACIZA KG 2.00 1.00 1,409.70 2,819.40 2,819.40
07.06.02 VEREDAS
07.06.02.01 CONCRETO f'c=210 kg/cm2 PARA VEREDAS M3 2.00 2.00 13.30 0.70 0.20 7.45 7.45
07.06.02.02 ENCOFRADO Y DESENCOFRADO EN VEREDAS M2 2.00 2.00 13.30 0.70 37.24 37.24
07.06.02.03 ACERO DE REFUERZO EN VEREDAS KG 2.00 1.00 598.90 1,197.80 1,197.80
07.06.03 CAJUELA
07.06.03.01 CONCRETO f'c=210 kg/cm2 PARA CAJUELAS M3 2.00 2.00 Area = 0.45 6.45 11.61 11.61
07.06.03.02 ENCOFRADO Y DESENCOFRADO EN CAJUELAS M2 2.00 2.00 6.45 1.33 34.19 34.19
07.06.03.03 ACERO DE REFUERZO EN CAJUELAS KG 2.00 1.00 455.20 910.40 910.40
07.07 TARRAJEOS
07.07.01 TARRAJEO DE VEREDAS M2 2.00 2.00 13.30 1.40 74.48 74.48
07.07.02 TARRAJEO DE SUPERFICIE DE RODAMIENTO 1:3 M2 2.00 1.00 8.50 3.60 61.20 61.20
07.08 OBRA FALSA
07.08.01 FALSO PUENTE M2 2.00 1.00 8.00 5.60 89.60 89.60
07.09 PINTURA
07.09.01 PINTURA EN BARANDAS METALICA M 2.00 2.00 8.50 34.00 34.00
07.09.02 PINTURA DE SEGURIDAD EN VEREDAS M2 2.00 2.00 13.30 0.20 10.64 10.64
07.09.03 PINTURA EN ESTRIBOS M2 2.00 2.00 14.20 3.71 210.73 210.73
07.10 VARIOS
07.10.01 BARANDA METALICA EN VEREDAS M 2.00 2.00 8.50 34.00 34.00
METRADOS GENERALES
PROYECTO CONSTRUCCION DE TROCHA CARROZABLE CANTA GALLO
DISTRITO CIUDAD CONSTITUCION
PROVINCIA CIUDAD CONSTITUCION
DEPART.: PASCO

ITEM DESCRIPCION UND CANT VECES LARGO ANCHO ALTO PARCIAL TOTAL
07.10.02 TUBERIA PVC SAP 3" M 2.00 6.00 0.55 6.60 6.60
07.10.03 APOYO MOVIL UND 2.00 2.00 4.00 4.00
07.10.04 APOYO FIJO UND 2.00 2.00 4.00 4.00
07.10.05 JUNTA DE DILATACION M 2.00 2.00 3.60 14.40 14.40
08 BADEN DE CONCRETO
08.01 EXCAVACION MANUAL PARA ESTRUCTURAS 198.00
Cimiento M3 6.00 1.00 11.00 5.00 0.30 99.00
Baden M3 6.00 1.00 11.00 5.00 0.30 99.00
08.02 CIMIENTO CORRIDO 1:10 + 30% PG M3 6.00 1.00 11.00 5.00 0.30 99.00 99.00
08.03 ENCOFRADO Y DESENCOFRADO 176.08
Baden M2 6.00 1.00 3.67 4.00 88.00
Para juntas de Dilatación M2 6.00 1.00 3.67 4.00 88.08
08.04 CONCRETO CICLOPEO + 50% PM 99.00
Baden M3 6.00 1.00 11.00 5.00 0.30 99.00
08.05 JUNTAS DE DILATACION ML 6.00 1.00 3.67 22.00 22.00
09 SEÑALIZACION Y SEGURIDAD VIAL
09.01 EXCAVACION Y COLOCACION U 1.00 31.00 31.00 31.00
09.02 SEÑALIZACION VIAL U 1.00 31.00 31.00 31.00
09.03 POSTE KILOMETRICOS U 1.00 5.00 5.00 5.00
10 PROTECCION AMBIENTAL
10.01 DEPOSITO DE DESECHOS M3 1.00 100.00 25.00 0.50 1,250.00 1,250.00
10.02 READECUACION DE CAMPAMENTO M2 1.00 100.00 25.00 2,500.00 2,500.00
10.03 RECONFORMACION DE CANTERAS U 1.00 4.00 4.00 4.00
11 FLETE
11.01 FLETE TERRESTRE GLB 1.00 1.00 1.00 1.00
11.02 PAGO POR SERVIDUMBRE GLB 1.00 1.00 1.00 1.00