Required conditions:
1 No LC should be pending in the system
2 AOP & JOP should be in service
3 EAST Panel should be ready
4 P & I system and annunciation system should be available
UNIT : DATE :
AOP: A
S.No Description Sensing element Result Remarks
1 AOP: A Manual starting AOP-A ON
2 AOP-A Manual stopping AOP-A OFF
3 SLC AOP-A ON AOP-A ON
AOP-B OFF & Discrepancy
OIL HDR PR 4.8 ksc Simulated MAV 21 CP 011
4 SLC AOP-A ON
AOP-A ON
OIL HDR PR < 4.8 ksc MAV 21 CP 011
5 AOP-A ON AOP-A trips
SLC AOP-A ON SLC AOP-A OFF
Fire-protn 2 channel: 1 & 2 operated
6 SGC OIL SUPPLY ON
MYA 01 FS 001 AOP-A ON
Turbine speed < 2800 rpm
7 SGC OIL SUPPLY ON
turbine speed > 2800 rpm MYA 01 FS 001 AOP-A OFF
OIL HDR PR > 5 ksc MAV 21 CP 010
8 SLC AOP-A OFF
MYA 01 FS 001 SLC AOP NOT ON alarm
Turbine speed < 15 rpm
9 SLC AOP-B OFF
MYA 01 FS 001 SLC AOP NOT ON alarm
Turbine speed < 15 rpm
AOP-B
1 AOP-B manual starting AOP-B ON
2 AOP-B Manual stopping AOP-B OFF
3 SLC AOP-B ON AOP-B ON
AOP-A OFF & Discrepancy
OIL HDR PR 4.8 ksc Simulated MAV 21 CP 012
4 SLC AOP-B ON AOP-B ON
OIL HDR PR < 4.8 ksc MAV 21 CP 012 Control oil pr low alarm
5 AOP-B ON AOP-B trips
SLC AOP-B ON SLC AOP-B OFF
Fire-protn 2 channel: 1 & 2 operated
2 . SLC JOP LOGICS
UNIT : DATE:
JOP A & B
UNIT : DATE :
Required conditions:
1. AOP & JOP should be in service
2. Gen. Seal oil system should be in service
UNIT : DATE :
Required conditions:
1. No LC should be pending in the system
2. All existing protections Boiler Trip, Generator Trip are to be
kept bypassed to reset the Turbine with K 101 & K 102 switched on
3. AOP should be in service
4. Governing rack should be charged
5. P & I system and annunciation system should be available
6. Turbine should be reset to check the protections and to check
the necessary logics