Minutes of meeting held between M/s FLS and M/s L&T Kansbahal at

M/s Arghakanchi Cement ,Rupun (Nepal ) on Dt. 26/03/2018

Members present
M/s FLS M/s Arghanchi Cement M/s L&T Kansbahal

Mr. Venktesan Murgan Mr.Yashpal Sharma Mr. Debiprasad Pradhan


Mr. Vinu Vijayan Mr.Virendra Singh
Mr. Umesh Singh

M/s L&T representative Mr. Debiprasad Pradhan reached site on 16/03/2018 in


connection with no load and load commissioning of lime stone circuit. Impactor (APPM-
1615), Apron feeder (Model T-50).

Job carried out

Impactor (APPM 1615)

1. Tightness of all the fasteners were checked and found ok.


2. Alignment of drive and driven pulley of Impactor was checked and found ok.
3. V- belt tension of Impactor was checked and found ok.
4. Alignment of motor shaft to Jack shaft readings are found within limit and same was
checked by FLS representative and readings are attached in protocol no 1.
5. Blow bar pairing of rotor was checked and found ok.

289.3 kg 291.4 kg

285.6 kg 285.4 kg

291.4 kg 289.5 kg

6. The gap settings of impactor was carried out & the following were maintained
a) Gap between blowbar tip to lower grinding path tip - 75 mm
b) Gap between blowbar tip to upper grinding path tip - 170 mm
c) Gap between blowbar tip rear impact arm tip - 150 mm
d) Gap between blowbar tip front impact arm tip - 200 mm

7. Clearance between Apron feeder pan top to bottom face of the skirt board was
checked and found 25 mm both the side.
8. Backlash and tip clearance of the bull gear was checked and found to be 0.67 mm
and 5.2 mm.
9. Alignment of pinion shaft to gear box output shaft of Apron feeder readings are
found within limit and same was checked by FLS representative and readings are
attached in protocol no 1.
10. Pilot gap of apron feeder was checked and found ok .
11. Spring tension of scraper conveyor was checked and found ok.
12. No load trail of all the equipments were checked and found all parameters are
within limit ( i.e. Vibration, temperature & Current ) and readings are attached in
Annexure 1. Vibration reading was not accurate because vibration instrument was
error up to 3 to 4 mm/sec unit.
13. L&T requested to M/s Arghakanchi Cement to take OEM operational spare for
smooth operation of plant and spare part list attached in annexure 2.

L&T Suggestions

1. L&T requested to M/s FLS before load commissioning all the sensors and
interlocking should be on line.
2. Rubber skirt of Apron feeder should be installed before load commissioning.
3. M/s FLS to call L&T engineer for load test of crusher.
PROTOCOL NO -1

Motor Shaft to jack shaft Alignment reading

Axial Axial

0.00 mm 0.00 mm

-0.01 mm 0.04 mm - 0.04 mm - 0.03 mm

- 0.08 mm Radial 0.00 mm

0.00 mm

0.03 mm 0.03 mm

Coupling Gap = 3.32 mm

0.02 mm

Counter shaft to Gear box output shaft alignment reading of Apron Feeder

Radial Axial

0.00 mm 0.00 mm

-0.03 mm -0.02 mm -0.02 mm -0.02 mm

- 0.05 mm - 0.01 mm

Coupling Gap =83 mm


Annexure 1
Bearing Temperature ( in ° C ) During No Load Trail Run of IMPACTOR

Time Impactor Rotor Secondary Rotor

DE NDE DE NDE

11:10 am
32°C 32°C 33°C 33°C
03:20 pm
41°C 43°C 42°C 45 °C
04:10 pm
42 °C 43°C 44°C 49 °C
05:10 pm
40 °C 41°C 42°C 50 °C

06:10 pm
39 °C 38°C 39°C 48 °C

VIBRATION IN LOAD (IMPACTOR)

IMPACTOR ROTOR JACK SHAFT

D/S T/S D/S T/S

HORIZONTAL
H- H- 1 H- 3 H- 2.1
(mm/sec)
VERTICAL
(mm/sec) V- V- 1.1 V- 3.3 V- 2.7

AXIAL
(mm/sec) A- A-0.7 A-6.4 A- 4.1

Current Drawn in No load Run

CURRENT DRAWN IN LOAD


EQUIPMENT Motor in KW
MAX. Amp Amp. Drawn
Impactor 480 54 27
Apron feeder 37 66 37
Scraper conveyor 1.5 3.3 1.3
Belt Conveyor (1400 belt width) 37 66 26
Annexure 2

Sl no Description Qty.
01 Blow bar 3 set

02 Grinding bar 1 set

03 Wear plate for Rotor region 2 set

04 Hydraulic cylinder for Grinding path 2 nos.

05 Impact plate for Rear Impact arm 1 set