Economic Operation of Power Systems

Power System Stability-I

Power System Stability-II

Excitation Systems & Interconnected Power Systems

Voltage Control, stability & Power system security

Introduction to EOPS

In electric power systems, the rst step is to properly assess the load requirement of a given area
where electrical power is to be supplied. This power is to be supplied using the available units such
as thermal, hydroelectric, nuclear, etc. Many factors are required to be considered while choosing a
type of generation such as: kind of fuel available, fuel cost, availability of suitable sites for major
station, nature of load to be supplied, etc.
 

The energy requirement on power system is not constant due to the varying demands at the
di erent times of the day. It is expected to supply reliable and quality power to the consumers.
Power system operators should ensure the continuity of power supply at all times.
 

The use of a single unit to supply the complete load demand is not practical since, it would not be a
reliable one. Alternately, a large number of smaller units can be used to t the load curve as closely
as possible. Again, with a large number of units, the operation and maintenance costs will increase.
Further, the capital cost of large number of units of smaller size is more as compared to a small
number of units of larger size. Thus, there has to be compromise in the selection of size and number
of generating units within a power plant or a station.
 

Electric power generating stations are far away from the load centers. Thus, large and long
transmission lines (grid lines) wheel the generated power to the substations at load centers. Many
electrical equipment are used for proper transmission and distribution of the generated power.

Optimum economic e ciency is achieved when all the generators which are running in parallel are
loaded in such a way that the fuel cost of their power generation is the minimum. The units then
share the load to minimize the overall cost of generation. This economical approach of catering to
the load requirement is called as ‘economic dispatch’. The main factor in economic operation of
power systems is the cost of generating the real power. In any electric power system, the cost has
two components as under:

https://electrical-guru.com/subject.aspx?id=2&code=7EE5A&unitid=19&topicid=78 1/3
7/27/2019 Electrical Guru | Tutorial for electrical/electric engineers or students

The Fixed Costs: Capital investment, interest charged on the money borrowed, tax paid, labour,
salary, etc. which are independent of the load variations.

The Variable Costs: which are dependant on the load on the generating units, the losses, daily load
requirements, purchase or sale of power, etc.
 

Economic operation of power systems is concerned about minimizing the variable costs only.
Further, the factors a ecting the operating cost of the generating units are: generator e ciency,
transmission losses, fuel cost, etc. Of these, the fuel cost is the most important factor. Since a given
power system is a mix of various types of generating units, such as hydel, thermal, nuclear, hydro-
thermal, wind, etc., each type of unit contributes its share for the total operating cost. Since fuel cost
is a predominating factor in thermal (coal red) plants, economic load dispatch (ELD) is considered
usually for a given set of thermal plants in the foregoing discussion.

There are two problem areas of operation strategy to obtain the economic operation of power
systems. They are: problem of economic scheduling and the problem of optimal power ow.
 

A. The problem of economic scheduling: This is again divided into two categories:

1. The unit commitment problem (UCP): Here, the objective is to determine the various generators
to be in operation among the available ones in the system, satisfying the constraints, so that the
total operating cost is the minimum. This problem is solved for speci ed time duration, usually a day
in advance, based on the forecasted load for that time duration.

2. The economic load dispatch (ELD): Here, the objective is to determine the generation (MW power
output) of each presently operating (committed or put on) units to meet the speci ed load demand
(including the losses), such hat the total fuel cost s minimized.

B. The problem of optimal power ow: Here, it deals with delivering the real power to the load
points with minimum loss. For this, the power ow in each line is to be optimized to minimize the
system losses.

ABOUT US
www.electrical-guru.com is an online electrical engineering portal for RTU's students.

  It is started with a motive to provide study materials for electrical engineering student as per the
syllabus of Rajasthan Technical University.

CONTACT INFO
  info@electrical-guru.com
  support@electrical-guru.com

Contact us today (../Contact.aspx) (http://www.simplehitcounter.com)

GET IN TOUCH

W e would love to hear about your thoughts. Please get in touch with us.

Follow us:
https://electrical-guru.com/subject.aspx?id=2&code=7EE5A&unitid=19&topicid=78 2/3
7/27/2019 Electrical Guru | Tutorial for electrical/electric engineers or students

 (https://www.facebook.com/electricalgurucom/)   (https://twitter.com/) 
(http://in.linkedin.com/)  (https://plus.google.com/)

(build/electrical-guru.apk)
While using this site, you agree to have read and accepted our terms of use, cookie and privacy
policy.
© Copyright 2016-2019 by Electrical-Guru.Com. All Rights Reserved.
Powered by Electrical-Guru.Com.

https://electrical-guru.com/subject.aspx?id=2&code=7EE5A&unitid=19&topicid=78 3/3

Potrebbero piacerti anche