Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Method Statement
CONTENTS
1. General ................................................................................................................................................. 6
1.1. Contractor’s Organization................................................................................................. 6
1.2. Project Scheduling ............................................................................................................ 8
1.3. Progress Report ................................................................................................................. 8
1.4. Sub-contracting ................................................................................................................. 9
1.5. Construction Mobilization ................................................................................................. 9
1.5.1. Mobilization for Temporary Facilities ............................................................................ 9
1.5.2. Mobilization for Construction Start-Up ......................................................................... 9
1 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
2 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
3 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
METHOD STATEMENT
The following is the METHOD STATEMENT for the design works, construction installation works, and
pre-commissioning, trial operation and training schedules to be carried out by the Contractor (Bidder)
for Kandy City Wastewater Management Project particularly under Contract Package No. 1 – Design
and Construction of Wastewater Treatment Plant, Main Pump Station, Treated Effluent Disposal
System, Sludge Drying Beds and Supply of Operation and Maintenance Equipment.
The Contract will take part from the proceeds of the loan received by the Government of the
Democratic Socialist Republic of Sri Lanka from Japan International Cooperation Agency (JICA). The
Project will be administered by the National Water Supply & Drainage Board (NWSDB) under the
Ministry of Water Supply and Drainage (MWSD).
As provided in the Bid Data Sheet as Annex ITB-1, the Scope of Works to be provided by the
Contractor, are as follows:
Design, execute and complete the Works in accordance with the Contract and remedy any defect in
the Works of Wastewater Treatment Plant (WWTP), Main Pumping Station (MPS), Sludge Drying Bed
(SDB) and Main Force Line in the City of Kandy, Sri Lanka. Such Works comprises the following
Scope of Work:
a. Wastewater Treatment Plant
b. Main Pumping Station
c. Sludge Drying Bed
d. Force Main
e. Treated Effluent Line with Discharge Structure to Mahaweli River
f. Building Works
(i) Septage Preliminary Treatment Building at WWTP
(ii) Sludge Pump Building at WWTP
(iii) Disinfection Building at WWTP
(iv) Sludge Treatment Building at WWTP
(v) Administration Building at WWTP
(vi) Workshop & Garage at WWTP
(vii) Guard Post at WWTP
(viii) Main Pump Station Building at MPS
4 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
This Method Statement establishes the execution program in the construction implementation. Work
procedures for all important activities planned to be carried out during the Construction Phase as
outlined here will be validated considering actual site conditions based on the verifications, tests and
surveys to be conducted during the Design Phase. In such case, adjustments or revisions will be made
if necessary.
Detailed method statements shall be prepared for specific tasks of the construction activities for which
as required shall be submitted at least 10 working days prior to commencement of relevant activity.
5 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
(1) ”EMPLOYER” means National Water Supply and Drainage Board for Kandy City
Wastewater Management Project
(2) “JFE” means JFE Engineering Corporation of Japan as the Main Contractor
(3) “WORK” means Contract Package No. 1 – Design and Construction of Wastewater
Treatment Plant, Main Pump Station, Sludge Drying Bed and Main Force Line in the City
of Kandy in Sri Lanka.
(4) “WWTP” means inside the battery limit of the Wastewater Treatment Plant of the WORK.
(5) “MPS” means inside the battery limit of the Main Pumping Station of the WORK.
(6) “SDB” means inside the battery limit of the Sludge Drying Bed of the WORK.
(7) “OSBL” means outside of battery limit of WWTP, MPS and SDB.
(8) “JOBSITE” means construction jobsite for the WORK.
1. General
The Project Organization Chart with the Bio Data of Key Personnel is included in this Tender
submission that which forms part of the Contractor’s qualification.
In the execution of the WORK, the project site staff will be classified into functional teams.
6 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The Project Director (stationed in Japan Head Office) will be the leader of all teams and assisted
by the Project Manager and Assistant Project Managers to form the Management Team. The main
function of this team is to fully manage and control the WORK in all aspects. This is also the center
of decision making. All project site staff shall be fully accountable to this management team. And
one of their important is to closely coordinate with the Employer and the Engineer’s representative.
Discussions and meetings for problem tackling in regards with any important project matters will be
arranged with the Employer and Engineer’s Representative.
The Design Team will be handled by the Contractor’s Design Coordinator together with the
Engineers, Designers and experienced personnel. Design consultant firm particularly for Civil
Building and Structural Works will be employed to carry out the design activities though the Main
Process Designs including its Electro-Mechanical components will be an in-house participation. All
temporary and permanent works and their relevant details will be handled by this team.
The design will be produced in accordance with the submitted Time Programme. An important role
of this team is to coordinate with the design team of the Employer and the Engineer’s
Representative to ensure that the designs are matching each other and fully integrated.
The Control Team is formulated covering the Quality Assurance/Quality Control, Health, Safety &
Environmental and Project Control. This team is directly responsible to the Management Team and
to plan, implement and monitor the project in accordance to their respective special functions
assigned by the Management Team. Quality Assurance/Quality Control or QA/QC is responsible
for all the quality aspects including the material control, quality control and including drawing
control. Health, Safety & Environmental is responsible for the planning, training, implementation
and monitoring of all the health, safety and environmental aspects within the project. And the
Project Control is responsible for the planning and scheduling, cost control, quantity surveying and
contractual aspects.
The Construction & Installation Team is the frontline personnel to carry out the daily
construction and installation activities. This team is headed by the Construction Manager and his
Superintendents. They will coordinate and monitor the installation works as well as be responsible
for the daily coordination with the Employer and Engineer’s Representative on the site construction
issues. Being on the frontline, this team will be the prime mover of the project and they will be fully
responsible for a close and timely coordination all aspects of the WORK.
7 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The Services Team is assigned to assist the different teams in the project organization, especially
the Construction & Installation Team. This team is composed by the Engineering/Technical Section
under the Engineering Manager and the Commercial Section under the Administration Manager.
The Engineering/Technical Section will be responsible for the material & samples submission,
temporary works design & as-built drawings production and design coordination. While the
Commercial Section will be responsible in handling procurement, accounting, human resources
and administration issues within the project site.
The Overall Project (Master) Schedule will be submitted and discussed with the Employer for
finalization prior to implementation. Please see the proposed “Time Programme of Design and
Construction” under Attachment 7: Technical Proposal.
A Critical Path Method schedule shall be used to control the work of this Contract. Using Microsoft
Project software facilities, a project scheduling and monitoring shall be developed in the project
management of all phases of the WORK encompassing, but not limited to, general designs, site
surveys and investigations, detailed engineering, establishment of temporary works, periods of
manufacture, delivery, erection, construction, installation, setting of work, commissioning and site
testing of all works required including plant and civil works, pipelines and services.
The Time for Completion allowed for this Contract is 45 months reckoned from the Effective Date
from which the Contractor received the Notice to Proceed. It covers the 10 months of Design Stage
for the detailed design and engineering for which approvals should be obtained for the Preliminary
Design Report, Mobilization Report, Project Organization, Key Personnel and other preliminaries.
The Construction Phase follows covering the 29 months of construction and installation activities
and completed with the pre-commissioning tests in 3 months for a total of 32 months. The project
will be made final and complete with a 3 months of Trial Operation or Performance Test.
The Contractor will monitor progress of each activity on a daily and weekly basis, and this will be
summarized and submitted as a Monthly Progress Reports to the Employer throughout the entirety
of the design and construction of the project.
8 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The Monthly Progress Reports shall be submitted during the Project Meetings. This is to validate
the contents to the reports and to give the Contractor chance to bring about Project Issues and
Concerns. Coordination meetings, other regular meetings and even ad-hoc meetings will be taken
into consideration to support the progress monitoring of the project.
1.4. Sub-contracting
The Contractor might use Local Contractors in Sri Lanka shown in “Attachment 6 the list of
Subcontractor and Vendor List”, to perform all of the Civil Works, as well as part or whole of
specific items if necessary. These contractors will be under the supervision of the Contractor to
ensure safe, quality and prompt delivery. Installation Work will be done by the Contractor.
As provided in the Bid Documents Volume I – Instruction to Bidders and Conditions of Contracts
under Annex C, Sub-Clause 2.1, it states that the ‘Time for Access is 150 days after the
commencement date.’ This is approximately 5 months after the commencement into the Design
Phase.
Mobilization of resources will follow the required Time for Access. Preliminary works such as
topographic surveys, geotechnical investigations, test pits and other necessary preliminary studies
will be commenced at this stage. Results of these preliminary works will be used to validate the
preliminary designs and make final the detailed project designs.
Likewise, mobilization for temporary works such as setting up of Contractor’s Field Office,
Engineer’s Field Office, site construction access, site construction utilities, and other temporary
facilities will be initiated. Manpower and equipment mobilization will follow the planned Overall
Construction Program to be presented in the Pre-Construction Conference.
The construction phase begins after the 10-month Design Phase for which the project design has
been approved and the construction permits have been obtained.
9 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The mobilization period within the construction phase shall be for the purpose of attending to the
following tasks and obtaining the required approvals, and also for making required preliminary
work for the efficient construction program.
(1) Obtaining approval of the detailed design report
(2) Obtaining approval for project organization structure of the Contractor and supervisory
arrangements
(3) Obtaining approval for Bio data of key personnel to be deployed
(4) Obtaining approval for local or foreign sub-Contractors if any
(5) Organizing required insurance, agreements with local agencies etc.
(6) Confirmation of work schedules
(7) Establishing mechanisms for liaison with external agencies (Kandy Municipal Council,
Mahaweli Authority of Sri Lanka, Roads Development Authority, Sri Lanka Telecom Ltd,
Ceylon Electricity Board, Local Authorities and Central Environmental Authority, etc.)
(8) Obtaining EMPLOYER’s assurance and commitments for land acquisition, power supply,
road approvals, source, environmental clearances, etc.
(9) Preparation and submission of a Mobilization Report including necessary documents,
agreements, method statements, etc. for review and approval of the ENGINEER
(10) Construction Officers for the Engineer’s Representatives and Employer’s Project
Management Unit
(11) Providing Transportation for PMU and Consultant’s Staff
After award of the contract, all provided survey data, soil investigation reports and technical reports
shall be verified and further investigation and topographic survey will be carried out as necessary
during the 10-month Design Phase. The layout plans received with the tender documentation
have indicated the setting out plan for structures and pipe lines. These data have been used for
the preparation of the bidder’s proposals and it shall be the responsibility of the Contractor to verify
them for any inaccuracies, errors or omissions in the information provided.
10 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
A new topographical survey, based on nodal points taken from the concept hydraulic designs, will
be conducted purely to verify the data provided and to correct the location and elevation of
structures that are to be considered for preliminary designs. The proposed topographic survey will
cover the entire project sites of WWTP, MPS and SDB.
This survey will also establish the Temporary Bench Marks (TBMs) for the construction and
installation teams and will provide relevant details of existing structures such as bridges located
along the trace of the proposed gravity and force sewers. Slight adjustments of the force main pipe
trace will have to be made to suite site conditions and for the setting out of pipe trace and new
structures.
The geotechnical investigation report will be studied along with the topographic information and
where necessary further investigation shall be carried out to acquire soil characteristics for
foundation designs of treatment plant, lifting station and other structures.
A provisional sum has been allocated in Bill of Quantities, Bill #1-Preliminaries, Item 20, for further
investigation and additional topographical survey work such as this.
After the review of preliminary design and prior to the commencement of detailed designs, the
Contractor will submit a report to the Engineer on the outcome of review and data verifications.
Detailed Design
Detailed design shall be carried out in consideration with conforming to the agreed design criteria
and its requirements and specifications, specifying the durability of structures, pipes, plant and
equipment, taking into account for energy-efficient equipment and conforming to engineering best
practices for energy conservation in the design of the treatment plant, pumping station and building
systems. During the Design Phase, the General Design Informationwill be prepared and shall be
submitted to the Engineer for review.
Involvement and participation of the wastewater O&M staff shall likewise be arranged during this
phase to obtain valuable inputs and feedbacks on the design of the facilities.
11 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Civil, building and structural designs will be carried out hand in hand with mechanical and electrical
designs of pump house, treatment plant and its facilities, sludge drying beds, pipelines, outfall
structures, as well as development plans for access road, river protection and others. The
engineering design shall comply with the design criteria and design standards given in section 4 of
the general requirements. Sewer system design shall also comply with Design Manual D7 and the
design criteria. All civil structures shall comply with the relevant sections of BS 8110, BS 8007
and BS 8005.
Sub-structures within groundwater shall be protected from buoyancy and designed to withstand
buoyancy effects and static loads. During construction, the uplift due to buoyancy is to be
neutralized by introducing balancing loads with sand or soil bags.
A minimum period of six weeks is required after approval of the design of structures and its
respective drawings and schedules prior to commencement of construction. This arrangement
shall accommodate within overall construction period and has no impacts on construction
programs.
The civil designs for pumping station shall comply with the requirement given in Section 5.0 of
Particular Specifications. Wet well type sewage lifting station will be constructed using concrete
made with sulphate resisting cement. The size of wet well is determined according to the number
of stops. It is recommended that 10 stops per hour be allowed for, for submersible pumps.
This pumping station will be equipped with an automatic grit removal system and a manual
screenings removal system. The total head of the pumping system is less than 15m in the pumping
station.
12 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The preliminary design shall comply with requirements given in Section 5.0 of the particular
specifications. DI [PN16] pipes are proposed for the pumping mains. Tyton joint will be adopted
for the system connections and where specified, expansion joints shall be provided. Thrust blocks,
specials, and valve details are all given on drawings. All pipes above ground shall be DI flanged
type.
The force main pipeline design will provide a design for surge pressures using appropriate surge
analysis computer software and the necessary control measures. Hydraulic design calculations
including hydraulic profile study will likewise be included in the detailed design of the force main
pipeline.
Mechanical and electrical detailed designs will be reviewed and submitted hand-in-hand with the
civil design. The components are designed to BS or equivalent standards acceptable to the
Engineer to consider all aspects in the installation, testing and commissioning of all mechanical
and electrical equipment and all other items necessary for a complete and functional installation fit
for the intended purposes at each site – wastewater treatment facilities, main pump station, sludge
drying, and all buildings/quarters.
On completion of the first part of the design, it will be submitted to the Engineer for approval.
Necessary revisions to the design, to suit site conditions, shall be carried out during the
construction period.
Design activities that will be carried out, but are not limited to, are:
13 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
EMPLOYER
Attention :
Address :
Phone No. :
FAX No. :
e-mail :
Phone No. :
FAX No. :
e-mail :
The Engineer, within a reasonable time after receipt of any document or drawings for approval
from the Contractor, will either return the document or drawing to the Contractor with the
Engineer’s Approval or will notify the Contractor in writing of his disapproval and the reasons
behind the disapproval. No work will proceed without the written approval of the Engineer.
14 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Also, it can be used as document transmittal sheet when drawings and/or documents should
be sent.
For the purpose of notification of submission, first page of the letter shall be sent by facsimile
and/or e-mail in advance.
The Contractor shall monitor the submission status of LETTER or TRANSMITTAL using log
sheet as appropriate.
15 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Example
② Kinds of document
D : Shop Drawing
S : Sample
M : Manual
I : Information
〇-〇〇〇〇〇-〇〇-△
⑥ Revision No.
The first issued document is “A”.
⑤ Serial Number (01-99)
④ Section Number
The Contractor will submit the coordination of procedure immediately after receiving notice to
proceed. Technical drawing and document will be monitored/ controlled by DRAWING &
DOCUMENT LIST to be provided later.
16 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
(2) Title Block of Technical Drawing - Following figure is example of typical title block.
3. Material Procurement
Material procurement will be made from suppliers, manufacturers, and subcontractors who offer
reliable goods and work performance. Qualification and selection is done based on the criteria of
the Contractor. Conformity to required specifications is required prior to placing of purchase
orders.
17 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The Procurement principle applies to procurement and its related works for such as overseas and
inland transportation required equipment, materials and its spare parts to the storage area of the
JOBSITE.
The information of Vendors and/or suppliers and submitted by the prospective bidders listed in
“BID C 8.Proposed Subcontractors for Major Item of Plant and Installation Service”.
Sufficient qualified personnel shall be assigned to plan, manage, document, monitor, and report
procurement activities. Equipment and material shall meet or exceed the project requirements for
quality. Deliveries shall meet the construction schedule.
Important formalities (Laws, regulations and instructions of the government) if applicable, for
equipment and materials, shall be observed.
1) Procurement Organization
All procurement activities, to be executed at the ContractorHead Office, are managed by the
Purchasing & Logistic Manager (PLM) independently. PLM is supported by staffs in
Procurement Department. Project QA/QC manager (QA/QCM) will also support PLM in the
coordination of required Inspectors to be carried out on Materials and Equipment.
2) Procurement Process
Inquiry to Vendor and/or Suppliers
The Contractor shall issue Request for Quotations (RFQ) to nominated vendors and/or
suppliers, which consists of the following documents.
18 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
While it is mandatory that equipment and materials quoted by vendors and/or suppliers are of
good quality, conform to the Project technical requirements and meet the requested delivery
time, the following points are also confirmed and considered in Contractor’s evaluation;
(1) Dimension and weight of equipment with regard to transportation, layout and installation
(2) Ease of installation, operation and maintenance
(3) Vendor’s and/or supplier’s experience/historical record on supply of similar equipment
and materials
(4) Lessons learned with vendors and/or suppliers and for similar equipment/materials
(5) Vendor’s and/or supplier’s Quality Assurance and Quality Control System/Organization
(6) Quality/Capacity/Inventory of vendor’s and/or supplier’s fabrication facility and equipment
including annual production capacity, work space (indoor/outdoor), and manpower
information (design, shop, QA/QC, field etc.)
(7) Current and future shop load & backlog of vendors and/or suppliers
(8) Vendor’s and/or supplier’s after sales support/service system/organization
(9) Acceptability of deviations/exceptions proposed by vendors and/or suppliers from the
project commercial terms and conditions, particularly on the warranty, liabilities and
indemnification
(10) Source of suborder materials and/or name of sub vendors and/or suppliers
(11) Payment terms and conditions proposed by vendors and/or suppliers
(12) Vendor’s and/or supplier’s financial stability
(13) Vendor’s and/or supplier’s proposed conditions for field technical service, if applicable
(14) Spare parts for construction, commissioning, start-up and operation, and special Tools
(15) Requirements for the Contractor’s resident personnel (engineer, expediters, inspectors)
during design and fabrication
After evaluation, the Contractor will choose recommended suppliers for review and approval by
the Engineer.
19 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
If changes in the specification, the quantity, delivery date arising from Contractor’s/vendor’s
and/or suppliers reason and so on occur after placement of the original purchase order, the
Contractor settles cost and schedule impact with the vendor and/or supplier and issues a
supplemental purchase order to them accordingly.
Any changes to the original Purchase Order arising from other stakeholder’s (e.g. EMPLOYER,
AUTHORITY) reason shall be covered by change orders to reflect the change to both technical
and commercial.
And also for critical and/or major equipment, the Contractor will hold Pre-Inspection Meeting
with the vendor at the vendor’s shop, at which time the requirements and procedures for
inspection/testing are confirmed in detail.
The Contractor shall be solely responsible for the expediting of deliverables from vendors
and/or suppliers to Contractor and for their return to vendors and/or suppliers in a timely
manner. The Contractor shall also be solely responsible for expedition suppliers so that
materials are delivered in accordance with purchase order requirements and project schedule.
20 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Inspection and Test for procured equipment and materials are carried out by Quality Control &
Quality Assurance Section and approved Inspection Agencies in accordance with designated
Inspection Level defined in the relevant requisition control of QC/QAM.
The vendor is not allowed to fabricate till the Contractor reviews the vendor’s Inspection and
Test Plan (I&TP), Test Procedures, WPS/PQR, General Assembly drawings.
In accordance with the reviewed I&TP, the Contractor proceeds with the inspection activities
such as:
(1) To obtain the inspection applications and monthly inspection schedule from the vendor
(2) To review inspection and test records obtained from the vendor
(3) To witness the vendor’s inspection and testing and to report the result to all concerned
parties
(4) To issues inspection release notices to the vendor before the equipment and materials
are to be packed for shipping
The Contractor will submit a Comprehensive Material and Equipment Delivery Schedule to the
Engineer. Monitoring of which will be done regularly. Test and Inspection of Materials and
Equipment will be done before delivery, according to the criteria of the Contractor. Copies of Mill
Certificates, Test Certificates, and Inspection Checklist will be submitted by the Contractor to the
Engineer for reference and record. All activities here will be performed according to ISO9001
Standard (Quality) Manual and Project Specifications.
The Contractor will be responsible for organizing, coordinating and performing all arrangements
for the transportation of goods procured to the storage area provided. The Contractor will
produce individual shipping manuals/ procedures for the transport of critical equipment, if
necessary. The Contractor will arrange all appropriate transportation for the cargoes through the
nominated international freight forwarder.
21 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
1) Export Packing
The Contractor will request the supplier or international freight forwarder for export boxing
and ensure that all packing for materials and equipment is suitable for transport from
Supplier’s Warehouse up to arrival at the site. Packing should be adequate to withstand the
adverse effects of rough handling at the ports of embarkation and destination and during sea/
airfreight. Any goods received damaged will be repaired or replaced by the Contractor.
2) Shipping
The Contractor will request the Supplier or international freight forwarder for preparation of
shipping documents for import customs clearance. These documents will be prepared in
strict compliance with the Contractor’s instructions. The consignee shall be the EMPLOYER.
Subject to construction schedule constraint, consolidated shipment of multiple cargoes from
various vendors will be considered for the following reasons:
(1) To avoid loss of small cargoes in transit,
(2) To avoid minimum inducement charge which the shipping company in case the actual
shipping volume per vessel was less than the agreed minimum volume, and
(3) To secure enough storage space on the vessel for the cargoes.
Pre-shipping advice upon booking on the vessel and final shipping advice after
departures of the vessels will be issued by the Contractor’s international freight forwarder
to all concerned parties. The international freight forwarder distributes the shipping
documents for import customs clearance to all concerned parties as well.
3) Customs Clearance
The Contractor will ensure that all shipping invoices include the Brussels Tariff Nomenclature
Number (BTN), Harmonized Tariff Schedule or equivalent. The Contractor will bear full
responsibility of all shipping documents. After arrival of the vessel on international Vietnam’s
port, the local freight forwarder will arrange unloading the goods from the vessel, and arrange
for the customs clearance.
22 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
4. Quality Control
The Contractor is responsible to control the quality of work and complete the work in accordance
with the Contract. The Contractor will provide all labour, materials, and equipment necessary to
achieve this. The Contractor will have and maintain a Quality Control System that complies with
ISO9001 or an equivalent Quality Management System that is acceptable to the Employer and to
the Engineer. Although registration for ISO9001 is not required, a Quality Management System
will be implemented. The Contractor will submit documentary evidence of compliance with all
Contract Requirements ensuring that all activities related to Quality Control are being applied.
Design and Engineering will be performed by Qualified Engineers having sufficient knowledge
and experience with similar plants and projects. Designs and documents prepared by these
engineers will be further reviewed by other specialists of the Contractor during the Design Review
Meeting to further enhance it and prevent the possibility of error and to eliminate the risks
involved because of this inaccuracy. A Complete Set of Design and Engineering Documents will
be submitted by the Contractor to the Engineer for approval before any construction,
manufacture, and procurement will commence.
23 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
All equipment designed by the Contractor will be manufactured by qualified suppliers selected
under specific qualification criteria. These suppliers should have previous experience in providing
equipment to the Contractor. On the other hand, simple equipment will be supplied by local
suppliers in Sri Lanka. Inspectors will be appointed by the Contractor and dispatched to every
manufacturing plant to check the quality and ensure that the required specifications are being
met.
The Contractor will assign a Quality Control & Quality Assurance Manager who will be
responsible for overseeing the overall Quality Control Plan of the Contract.
The Contractor will assign Lead Inspectors for each shift for each location where work is being
performed. Each Lead Inspector will be chosen based on his qualification, training, and
experience in all construction activities being conducted at his assigned location of work.
The Contractor will notify the Employer and the Engineer in writing of all inspection and testing
activities. All materials, equipment, and works will be inspected and tested in accordance with the
Quality Control Planto verify that they follow the Method Statement, Work Specification, and
Construction Drawings. Documentary records and evidences will be maintained of all inspections
and tests conducted.
The Contractor will keep document, collect, and preserve records of all activities performed for
the Contract. Documents will be prepared in forms acceptable to the Engineer. Quality Records
will be provided and maintained in accordance with the Quality Control Plan. The Contractor’s
Quality Control & Quality Assurance Manager will provide, as part of the Monthly Progress
24 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Report, a monthly written certification that the Quality Control Plan and all of its measures and
procedures are functioning properly and being complied with.
5. Progress Control
Initial and all subsequent programs will be in such forms that the critical element of construction
can be readily identified. The application of computer techniques is considered essential. The
program will be based on the application of established programming procedure such as Critical
Path Analysis (CPA) and Program Evaluation and Review Technique (PERT). All programs will
show the expected cash flow both monthly and cumulatively.
The Contractor will submit a Monthly Report showing the Actual Progress against Scheduled,
Actual Ordering and Delivery Dates of Materials and Equipment versus Anticipated, Information
required by the Contractor from the Employer and the Engineer, and Plant, Labour, and Materials
on Site at the end of the month. Monthly progress will be marked on sets of Construction
Drawings kept specifically for this purpose. Important dates and the like will also be recorded on
these drawings.
The Contractor will provide the Engineer technically perfect coloured photographs of the Works
taken in such manner and time as the Engineer directs.
Regular weekly meetings, the time and day as agreed upon by both Contractor and Engineer or
his representative, will be held to examine actual progress against agreed program.
25 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The Contractor will progressively prepare As-built Drawings covering all of the works based on
the Construction Drawing and a Final Report.
OVERALL
PROGRESS
1) Engineering Progress
(1) Measurement Unit and Identification
Engineering progress is measured in integration of key progress documents expressed in
the DRAWING AND DOCUMENT LIST.
26 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Ex.)
Ex.)
2) Procurement Progress
(1) Measurement Unit and Identification
Procurement progress is measured in integration of principal equipment (and materials)
for WWTP.
27 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Ex.)
EQUIPMENT AND MATERIALS Weight %
Overall Each
Equipment ---
Machinery (e.g. Pump) ---
Local Fabricate Equipment ---
Electrical ---
Power receiving Unit ---
Panel ---
Instrument ---
Monitoring, Control and ---
Automation System
Field Instrument ---
Pipe with components ---
Embedded Piping w/Fitting ---
Piping w/Fitting ---
Valve and components ---
Cables
TOTAL 100% 100%
Ex.)
Requisition L/I and/or P/O Witness Ex-Works*2 or Arrival at
issue Inspection arrival at Sri JOBSITE
to Vendors Ex-Works*1 Lanka Port
10% 20% 50% 10% 10%
Cumulative Cumulative Cumulative Cumulative Cumulative
20% 30% 80% 90% 100%
NOTE : 1. Ex-Works*1 will be applied for items that have no witness inspection.
2. Ex-Works*2 will be applied for items fabricated at Sri Lanka.
28 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
3) Construction Progress
(1) Measurement Unit and Identification
Construction progress is measured in integration of major construction progress for STP.
Ex.)
Wastewater Treatment Plant Pumping Station
Civil Works AR ME E&I CW Others
SW ST Others
29 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Where:
SW – Site Works
ST – Structural Works
AR – Architectural Works
ME – Mechanical Works
E&I – Electrical and Instrumentation Works
Having regarded with an utmost priority, safety and risk management for the construction works
will be implemented in compliance with the Contractor’s Project Health, Safety and Environmental
Management Plan (as provided in Section 7 of this Method Statement) in accordance with all the
relevant Sri Lankan health, safety and environmental regulations.
Where necessary and as outlined in the Project Health, Safety and Environmental Management
Plan, Safety Job Analysis and Risk Assessment are provided for those elements of the each
critical construction activity identified as being a risk factor. Impact of risk is assessed and
quantified in terms of project cost, construction schedule and work quality. Treatment of these
risks is mainly to provide control by avoidance and impact reduction. Outlined here but not
necessarily limited as listed below are some of major areas for which safety and risk assessments
will be taken as part of the implementation of the Work.
The Project Construction Sites – the Wastewater Treatment Plant Area, the Main Pump Station
Area in Getambe, the Sludge Drying Bed Area, the New Operations Building and the several Staff
Quarters – are to be kept clean at all times. Regular cleaning schedule will be setup with the
implementation of standard housekeeping requirements such as garbage disposal, construction
waste management, and sanitation maintenance program.
Work personnel will be monitored to maintain good hygiene standards with regards to their camp
accommodation, mess areas, latrines, shower/wash areas, and the required personal protective
equipment such as uniforms, hard hats, safety shoes, body harness, goggles, era plugs, dust
masks, gloves, and others.
30 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
In the erection of scaffoldings and construction work staging platforms, safety regulations and
standards are to be followed. Only qualified scaffolders or erectors are to be allowed to conduct
such work.
Erected scaffolding and construction work staging platforms shall be checked by the qualified
scaffold checker and safety officer prior to its use. It shall be erected complete with hand rails,
protected work platforms, toe boards, life lines and protection netting, where necessary.
All ladders shall be ensured to be firmly secured at the foot and at the top and should have stiff
members to avoid swinging. Ladders exceeding 4 meters in height shall be secured at midpoint.
And ladders should be on a clear area and within easy reach of the workplace.
Working on confined spaces such as deep tanks, manholes or the likes shall require a full body
safety harness to be worn at all times. Workers inside the confined spaces shall be roped to the
exit point at all times using life line attached to their safety harness. Fresh air circulation using air
blowers and exhausts shall be ensured inside the confined spaces or chambers to avoid
suffocation.
In the event of an incident that rescue is necessary, only qualified rescue crew shall be allowed to
conduct rescue operation. Use of breathing apparatus, retriever (crane or tripod and winch), gas
detection equipment and other safety tools shall be used as may be required.
31 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
b. Non-intrinsically safe laboratory analytical instrument will not be used unless prior
approval has been obtained in the form of a work permit.
(2) Engine Driven Equipment
a. All engine driven equipment whether installed on vehicles or not, such as auxiliary
machinery, pumps, welding machines, compressors, etc., shall be fitted with spark
arresters when used in areas with potential hazard of flammable gases, vapours, or
fumes. Prior approval shall be obtained before using them.
2) Electrical Equipment
(1) Any electrical equipment which does not form part of the fixed installation of the plant is
considered as portable, transportable, or mobile equipment, will be of the approved
types:
a. Hand amps
b. Welding sets
c. Mobile generators
d. Portable tools
e. Flexible cables
f. Temporary switchboards
g. Motorized tools or equipment
h. Battery and battery operated tools
i. Hand phones
j. Transceiver sets
k. Etc.
(2) All electrical equipment will be checked by the Electrical Section before they can be used.
(3) All electrical works shall be conducted in accordance to statutory requirements.
(4) Only trained and experienced electricians will perform electrical works.
(5) No one will change, alter, or modify any electrical equipment, tools, or instruments except
authorized electricians.
(6) The user shall also conduct visual inspection of his electrical equipment tools and
instruments each time before use.
(7) All hand tools and hand amps are to be checked and tested by competent electricians
before they can be used.
(8) All hand torches used in areas with potential hazards must be of the intrinsically safe
construction type.
32 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
(9) All live parts of temporary electrical installations and equipment shall be effectively
guarded.
(10) Electrical plugs and sockets must be of distinctive type to ensure that no connections can
be affected by sudden change in voltage. They must conform to the local electrical
standards.
(11) Warning signs or posters, such as “DANGER, HIGH VOLTAGE”, “NO ENTRY – EXCEPT
AUTHORIZED PERSONS ONLY”, etc., shall be displayed as and when necessary during
work and at dangerous areas such as substations, switchboxes, overhead or
underground cables, etc.
(12) Periodic inspection and maintenance of electrical installations and distribution systems
will be carried out at least once a month by a competent person or licensed electrician.
(13) All portable equipment, tools, and instruments will be used with ELCB to protect workers
from electrical shocks or electrocution.
(14) All electrical used in site will be maintained in good working conditions at all times.
(15) Equipment that causes arcing or sparking will not be used until it is properly repaired by
authorized electricians.
(16) All electrical hand tools using AC current supply will fulfil one of the following
requirements:
a. Voltage 50V to 110V single phase – must be fed from a dual winding transformer with
midpoint of secondary earthed.
b. Voltage 230V and above single phase – must be of the approved type with double
insulated construction.
(17) Do not use test lamps or other electrically operated instruments unless they are of an
approved type. Makeshift testers and long bare metal prods are dangerous to gas plant
operation.
(18) All electrical tools must be switched off and made inoperative before moving the
connecting plug.
(19) When work is performed on electrically powered equipment and associated circuits, the
Electrical Tag Out (ETO) Permit will be applied prior to work commencement. The ETO
Permit will not apply to:
a. Lighting circuit for the purpose of re lamping.
b. Window or package air-conditioning units and outgoing circuits from distribution
panel for lighting and socket outlets.
33 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
c. Circuits of less than 230V and circuits which must remained energized. In such
cases, the method of work must be established and the Electrical/ Safety Section
duly notified.
3) Welding Machines
(1) All AC supplied welding machines will be fitted with Low Voltage Shock Presenters and
will be tested every day before work commencement.
(2) All subcontractors will attach a tag on the welding machine their company names and the
name of the person responsible.
(3) All welding cable will be of proper insulation having a dielectric strength of not less than
the rated voltage of 600V.
(4) All welding machines will be provided with proper earth cable connected with brass or
steel bolts and nuts.
34 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
(10) Do not use them on hard brittle material or into steel of greater hardness than the
fastener being used.
(11) All personnel must be cleared to do the area behind and on indirect line of the possible
flight line of fixing. Consideration must also be given to the possibility of ricochet.
(12) The operator shall use ear protector when the tool is used in confined space.
5) Portable Hand Tools
(1) Special attention shall be paid to hand tools that can cause sparks when struck on
concrete or metal. The sparks can ignite flammable gases and cause fire and explosion.
Use non-sparking tools in hazardous areas or on vessels containing flammable gases. If
this is not practical do not start work, consult your immediate supervisor.
Note: Tools made of beryllium bronze can also produce sparks on frictional impact with
aluminium-painted iron or steel surface.
(2) Always use the right tools for the right job.
(3) Ensure all portable tool shall be defects free and before the first use check that they are in
good working conditions, it in doubt refer to your immediate supervisor or Tool Store for
advice.
(4) Tools must not be thrown to another person.
(5) Use proper tool bag to carry tools that are required for work at height in order to prevent
them from dropping off.
1) Permit to Work
(1) Excavation work shall be defined as any digging work on the ground (earth or concrete)
either by manual or mechanical means and shall require an Excavation Permit. The work
shall include miscellaneous work, such as tree planting, installation of road signs or flag
posts, etc., and piling work which may affect the adjacent plants or underground facilities.
2) Hazards Identification
Special attention shall be paid to those trenches being dug within process plant area or any
place where there are possible sources of flammable or toxic gas emission. Such emission
sources may be from the nearby equipment or the pipes underneath the trenches. Therefore
any trench that exceeds 1.5m in depth may require atmosphere testing before any person is
allowed to enter.
35 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Considering the need for the use of crane in the lifting operation of heavy loads – construction
materials and equipment, cranes will be hired from a reputable local source. Equipment
suppliers and operators will required to provide the necessary documents and certificates
including equipment certification, equipment maintenance record, operator’s license, rigger
certificates, checklist on lifting shackles, straps, slings, and others, that may be used during the
lifting operation.
A Cranage Coordinator shall be appointed to conduct monitoring on the setup and to supervise
lifting operation, so as avoid lifting of unsafe loads. He will ensure that the lifting equipment or
crane is suitable for the purpose and also to notify the schedule of lifting operation to others in
the area of operation.
Prior to the commencement of any piling works, the stability of the adjacent structure shall be
surveyed and determined. The piling equipment shall be thoroughly examined by an approved
person once in every 6 months.
1) Procedure
All pile driving equipment before coming to the work site shall be thoroughly examined by an
approved person.
36 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
2) Preparation
(1) All works involving the use of pile driving equipment shall be properly planed, organized
and coordinated to ensure that all necessary safety precautions are taken.
(2) Check and confirm with the Engineer to ensure that the area for piling is free from
underground cables, pipes or structures.
(3) Ensure all preparation work for the piles is conducted at a safe distance from the driving
operation.
(4) During the hoisting of the pile all persons not actually engaged in operating the
equipment and handling the piles shall be kept out of the area.
(5) Every day before work commencement the piling equipment shall be inspected, and any
defects found shall be rectified.
(6) Provision shall be made to protect the operator from falling objects, steam, cinders and
water.
(7) When the pile driver is not in use the hammer shall be choked or blocked in the leads or
lowered to the ground.
(8) A ladder extending from the bottom of the leads to the overhead sheaves shall be
permanently attached to the structure supporting to the leads.
(9) Where a structure supports the leads, a suitable working platform of adequate strength
shall be provided on the level of the leads at which it is necessary for men to work.
(10) The working platform shall be provided with safety railings and the boards on all sides,
except on the hammer, or lead side of the platform.
(11) Where such platform cannot be provided, full body harness or safety belts shall be used.
(12) Before placing or advancing a pile driver, the ground shall be inspected and where
necessary for firm or level footing, timber shall be placed. After placing or advancing a
pile driver, inspection and correction of the footing if necessary shall be made to maintain
stability.
3) Operation
(1) The Supervisor-in-charge shall prior to work commencement provide clear instructions to
the operator regarding safe work operation.
(2) The operator shall be provided with the necessary personal protective equipment such as
safety helmet, safety shoes, ear protectors, etc. to protect him from personal injury and
health damage.
37 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
7. Safety Plan
Please see Attachment 7: Technical Proposal - HSE Plan in this Bid Proposal
Please see Attachment 7: Technical Proposal – HSE Plan in this Bid Proposal
9. Division of Works
The Construction and Installation Works will be broken down into the following categories:
38 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
2) Piping Installation
(1) Force Main (DI Pipe)
(2) General Piping (Stainless Steel, PVC, etc.)
3) Electrical Work
(1) Power Distribution
(2) Low Tension Power Distribution System
(3) Lighting
(4) Street Lighting
(5) Generator
8) Painting
a. Steel Structures
b. Supports and Framings
c. Others
39 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
1) Mobilization
2) Construction Camp Yard
3) Temporary Road
4) Temporary Workshop and Warehouse
5) Transportation Materials
6) Design (Mechanical and Electrical Plant Structures)
7) Site Office
8) Reclamation
9) Soil Improvement
10) WWTP Area
(1) Flow Meter
(2) Grit Chamber
(3) Oxidation Ditch
(4) Sedimentation Tank
(5) Disinfection Building
(6) Sludge Pumping Station
(7) Sludge Treatment Building
40 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
11) Building
(1) Administration Building/Control Room
(2) Liquid Process Control Building
(3) Blower Room
(4) Generator Room
(5) Guard Post
12) Site Development Works
(1) Landscaping
(2) Pavement
(3) Fence and Noise Barrier
(4) Storm Drainage System
(5) Plant Utilities
1) Operation
2) Preventive Maintenance
3) Analysis
4) Monthly Report
Method of working for major items of Mechanical & Electrical Portion in this project will be
generally as follows:
1) General
(1) Scope
This specification covers the requirements for the installation of equipment that will be
used in the plant.
(2) Codes
The applicable codes and standards shall be indicated in Specific Job Requirements.
41 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
(3) Units
Unless otherwise specified, metric units shall be used as the measurement system for the
drawings and documents to be submitted.
3) General Requirements
(1) Work Execution
All works shall be implemented carefully and without delay.When required, the works
shall be supervised and performed by qualified personnel or technicians as
recommended by the manufacturer.
(2) Precautions for Installation
When the equipment is lifted by using ropes, protection pads shall be placed in between
the rope and equipment body to prevent dents and scratches.
The operator of the winch or crane shall be careful and always be attentive, when lifting
or unloading the equipment. Construction equipment, machines, tools and measuring
instruments to be used in the works shall be checked thoroughly before using.
When sling is used in lifting or lowering the equipment, the center of gravity shall be
properly considered in order to avoid damage on the equipment. Lifting hooks when
available shall be used.
If winch is used for loading or transferring of equipment, the path of the equipment should
be properly cleared to avoid injuries to the workers.
42 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The ground at the unloading point, if it is not firm, shall be thoroughly reinforced in order
to prevent the equipment from overturning, etc.
Prior to unloading, the orientation and position of the equipment after unloading shall be
confirmed in relation to the direction of installation.
(2) Transportation
For transportation of the heavy equipment after unloading, transportation method shall be
determined by investigating the following items and transportation plan shall be made out
prior to the works.
a.) Size, weight and shape of the equipment.
b.) Maximum allowable loads for the roads and bridges in the transport routes.
c.) Width and conditions of the road on the transport route.
d.) Building, aerial wirings, overhead girders, electric posts, underground facilities in the
transport route.
Where highway is passed over, detailed investigations shall be made regarding the
restrictions of time, size, weight, traffic, etc.
In the field, the equipment shall be temporarily placed at the points shown in the
transportation plan. Skids for transporting and temporary placement of equipment shall
be made properly equipment to avoid damages.
43 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
5) Custody of Equipment
(1) Unpacking
Upon arrival of the equipment in the field, the number and external appearance of the
package shall be checked based on the packing list.
After unpacking, the specification of the equipment such as dimensions, weight and
quantity shall be checked based on the packing list, purchase order and / or invoice.
Anything that is defective such as appearance of rust, defect or distortion shall be
checked.
Centering marks, orientation marks, markings of center of gravity and sling point shall be
checked according to the drawings.
(2) Safekeeping
The place and method of safekeeping until installation shall be determined taking the
following items into consideration:
a.) Type of the equipment, parts, accessories and spare parts, if any.
b.) Property of material used and finished surface.
c.) Period of stocking and weather condition.
d.) Environmental condition, such as whether or dust, sand or soil, corrosive gas, etc.
exists.
6) Lifting Method
(1) General
The following shall be considered for the selection of the lifting method and the erection of
lifting equipment.
a.) Size, weight and shape of the equipment to be installed, and the slinging points.
b.) Space of the location of installation.
c.) Space and ground condition at the place of erecting the lifting equipment.
d.) Buildings, structures, equipment, etc. existing nearby and whether or not those can
be utilized.
44 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
e.) Buried objects such as underground piping and cables and open trenches existing at
the place where lifting equipment is erected.
f.) Condition of roads as to whether it can be used or not.
g.) Space for dismantling or taking out the lifting equipment.
For heavy weight equipment, installation procedures including specification of the lifting
equipment, routing and method for hauling of the equipment from the temporary location,
the direction and sequence of installation, etc. shall be made, before starting the works.
In general, the chocker hitch sling shall not be used for heavy weight equipment. If use of
such sling is inevitable, strength of the equipment shall be determined and
countermeasures against slipping off, impact, etc. shall be made prior to lifting works.
The following design criteria shall be used for the strength calculations:
a.) Coefficient of dynamic load : 1.25
b.) Stay wire bracing angle : 30 degrees or less
45 degrees maximum,
if unavoidable
45 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
a.) Dead man shall be duly installed at proper positions based on the installation manual.
b.) Assembly of the gin poles shall be done on flat ground and any misalignment of bolt
holes shall be completely corrected.
c.) Bolts at joints shall not be over tightened.
d.) Erection of the gin poles shall be carried out by the use of truck crane or auxiliary gin
poles.
e.) Equalizer beam shall be mounted after the gin poles have been erected and the stay
wires firmly braced.
f.) Bracing of the stay wires shall be checked again after the equalizer beam has been
mounted.
g.) Markings shall be made at fastening wire clip of the stay wire tail end for checking
any slip of the stay wire after adjustment.
h.) Winches (for lifting, drawing-in, etc.) shall be set at the locations specified in the
installation manual, and tied with dead man using wire ropes. Slipping off or upward
moving of the winches shall be avoided by all means.
46 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Outriggers shall be fully extended and thus the crane shall be firmly fixed. The ground at
which the outriggers are set should be reinforced in order to prevent the crane from
overturning, etc.
Lifting angles (the angle between the sling wire and perpendicular axis at the hook of the
crane) shall generally be less than 30 degrees or if unavoidable case, 45 degrees
maximum.
Where the equipment is installed under pipe rack or in the building where the truck crane
cannot be used, the equipment shall generally be rolled into its point of installation and
shall be installed with chain block, etc.
(3) Treatment of the surface of the foundation, such as chipping and fitting, shall be carried
out as follows:
a.) Remove foreign matters completely.
b.) Chip the portions which come in contact with liners and fit them in line with liners.
47 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
c.) If grouting is made after centering, chip the surface so as to give good adherence and
avoid cracking, peeling-off, etc. of grouting mortar.
(4) Liners
Liners to be used shall be, in general, made of carbon. In case of corrosive environment,
liners made of non-corrosive material shall be used.
Liners shall be so arranged that the load of the equipment is uniformly and exactly
distributed to the foundation within allowable load. The liners shall be placed as near as
possible to both sides of each anchor bolts.
In case where only flat liners are used for alignment, these flat liners shall be piled in 3
layers or less.
In case where wedge liners are used for alignment, gradient of the wedge liners shall be
1/30 – 1/60, and two wedge liners shall be put together in back to back manner so as to
have their top and bottom faces in parallel. And as base liner, flat liners having about 2
times the thickness of the wedge liners, shall be put under the wedge liners.
Dimension, gradient and surface roughness of liners shall be as shown in the attached
Table 2, Standards of Liners.
(5) Equipment
Prior to the installation, the following checking for the equipment shall be made:
a.) Appearance of equipment, such as absence of damage and rust.
b.) The quantity and appearance of auxiliaries.
c.) Size of the anchor bolts, and absence of damage and rust on the threaded parts, if
anchor box is applied.
d.) Orientation marking.
e.) Marking of the center of gravity.
f.) Sling points.
Oil and other foreign matters stuck on the surface of legs, bed, frame, etc., which will
contact the grouting mortar shall be entirely removed.
48 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
11) Installation
(1) Setting
Setting of the equipment on the foundation shall be, as a rule, performed as shown in the
attached Table 1 - Standards of Setting.
In case of anchor box type, fixing of the anchor bolts shall be carried out as follows:
a.) Anchor bolts shall be set so that a few screw threads come out from the nut.
b.) When mortar is being poured into the anchor boxes, thoroughly check if it’s free from
foreign matters before the mortar shall be poured. Cover the threaded part of the
bolts to prevent splashes of mortar getting stuck.
c.) Mixing ratio of the mortar shall be specified in attached Table 3. Standard in Mixing
Ratio of Mortar.
d.) All anchor bolts shall be tightened completely and uniformly after sufficient curing of
the mortar has been attained.
(2) Grouting
Grouting of the base of the equipment shall be carried out as follows:
a.) The grouting shall be done by damping the surface after cleaning.
b.) When the grouting mortar is being poured into the gap between the bed of the
equipment and the foundation, it shall be done continuously and should be
monolithic.
49 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
12) Inspection
Inspection required in the works shall conform to the Engineering Specification corresponding
to individual equipment installation works.
1) General Notes
(1) Scope
This specification covers the requirements for fabrication, assembly, erection, inspection and
testing and other field works of all piping.
When conflicts exist between the aforementioned documents, this specification shall govern
except when code requirements will apply.
(3) Codes
Unless otherwise specified, the fabrication of piping shall be in accordance with the Code for
Chemical Plant and Petroleum Refinery Piping, ANSI B31.3, latest edition.
(4) Reference Documents
On piping works, the following latest documents shall be referred to as a part of this
specification:
a. Isometric Drawings __
b. Piping Arrangement Drawings __
c. Fabrication Drawings for Pipe Supports __
d. Pipe Sleeve Drawings __
e. Specification of Welding of Steel Piping __
50 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
2) Materials
i. Material Identification
Pre-fabricated piping sections shall be marked with their specific spool number.Piping
materials to be used are indicated on the material list on the applicable isometric
drawings by Code Number or Tag Number.
Irrespective of the weight and/ or volume, the following materials shall be stored indoors:
a.) Check, Ball, Butterfly and Special Valves with actuator.
b.) Sight glasses, expansion joints, flexible tubes and other piping accessories.
c.) Chemicals and consumables
d.) Spare parts
All materials shall be stored with proper identification based on types (color codes),
sizes and Tag No., in order to facilitate issuance and inventory of materials.
51 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
When materials are delivered, warehouse keepers shall properly record material
balance in such a way that;
a.) When stored, quantities are kept on record with reference to a packing list.
b.) When being delivered, quantities are registered by reference to Code No. or Tab
No. indicated on a material list of applicable reference drawings.
3) Fabrication
(1) General
Threaded Connections - Threads shall conform to JIS B0203: PT or ISO 7/1 Tapered
Pipe Threads, unless otherwise specified.
Socket Welding -Care shall be taken to ensure that a clearance of approximately 1.6
mm remains between the male and female ends at the bottom of the socket.
Longitudinal seams in adjoining lengths of welded pipe shall be staggered and located
so as to provide openings between external attachments and weld lines as shown in the
figure below.
Figure 1: Location of Longitudinal Seams
L3
Lo
L2
Min Lo = four (4) times the nominal wall thickness or 25 mm, w/e is greater
Min L1 = five (5) times the nominal wall thickness
52 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
When pipe works are prefabricated, the contractor shall reflect the adjustments points
on the Isometric Drawings according to actual field conditions.
Prior to fabrication work, shop–applied rust preventive coating shall be removed from all
piping material surfaces by solvent cleaning.
Gas cutting, arc cutting for stainless steel shall be used for rough cutting only. In this
case, the cut part shall be made smooth by grinding. But these procedures are not
necessary for carbon steel and low alloy steel.
Cutter blade of abrasive cutting machine for cutting austenitic stainless steels shall not
be confused with that used for cutting carbon steel.
End preparation for welds shall be done by mechanical means when practicable or
grinding. Flame-cut surfaces shall be ground properly.
(3) Welding
All welding works shall conform to the requirements described in the following
specification:“Specification for Welding of Steel Piping “
Approval of the welding procedures to be used and of the performance of welders will be
required and shall comply with the requirements of Section IX of the ASME Code.
53 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Welding processes shall be determined by the welding abilities of the welders, within the
limitations described in Welding Specification.
However, the welding processes for butt circular welding are required. Insert rings and
backing rings shall not be acceptable.
Tack welds shall be done by a qualified welder and procedure based on the final welding.
Electrodes used for tack welds in the root pass shall be of the same type as that one
being used for the first pass.
All welds on pressure containing parts shall be accomplished with a qualified procedure
and by qualified welders. If seal welds for threaded joints are required, all exposed
threads shall be covered by the seal weld and must be done by qualified welders.
(4) Bending
When welded pipe is bent, the longitudinal weld shall be located between 10” and 15”
away from the neutral axis.As a rule, the bending radius shall not be less than 5 times
the nominal pipe diameter.
Bends in carbon steel piping may be made in hot or cold condition by any procedure
which will not cause wrinkling, excessive thinning or scaling of the pipe wall or flattening.
Bends in austenitic stainless steel piping must be made in cold condition by a procedure
which will not cause wrinkling, excessive thinning or scaling of the pipe wall or flattening.
If the above condition is not feasible, the bends may be made by high-frequency
induction heating. The maximum decrease of wall thickness shall not exceed 10% of the
maximum wall thickness. This minimum wall thickness is 87.5% of the nominal wall
thickness.
The maximum flattening, as measured by the difference between the maximum and
minimum diameter at any cross section, shall not exceed 8% and 3% of the nominal
outside diameter for internal and external pressure respectively.
54 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The reinforcing pad, if required, shall be provided with a 1/8” in. PT hole telltale hole.
Orifice runs shall not contain welds except at the flanges. Pipe ends and bevels at orifice
flanges shall be machine cut and shall be perpendicular to the axis of the pipe. Welds at
orifice flanges shall be ground smooth and flushed inside. Pipe tap connections on slip
on orifice flanges and directly on the pipe, if specified, shall be drilled through the pipe
wall. And it shall be finished smooth and flushed and cleaned inside.
55 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Surface defects shall be completely removed by grinding. The ground out area shall be
repaired by welding if the defect removal results in reduction of pipe wall thickness
below minimum. The repaired area shall be ground smoothly.
(10) Cleaning
All fabricated piping assemblies shall be cleaned by air or water to remove scales and oil
on the inner surface and shall be dried out with air blow.
If water is used in cleaning stainless steel piping assemblies, it shall not contain more
than 50 ppm of chloride.
56 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
When flanged joints are assembled, the gaskets and flanges shall be bolted with
relatively uniform bolt stress consistent with the type of gasket used. Connection of steel
and cast iron flanges shall be bolted with care so as not to damage the cast iron flange.
Threads of bolting shall be coated with a suitable compound before installation to
prevent damage on the threads.
Gasket paste shall not be applied to the gasket unless otherwise specified.
l
f a - normal engagement by hand
a f - usable threads length
l - effective threads length
Checking of Threads - Check the threads for pipe fittings based on the following
procedures:
a.) Checking of external threads
a.1) When stain or foreign materials stick on the threads, clean with steel brush
along the screw threads.
57 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
a.2) Check that insertion can be done smoothly by inserting the ring gauge or the
opposite fitting.
a.3) Check that the length of complete threads portion is not less than the value
as indicated in Table 2.
When piping accessories are installed with flanges in piping system, such as valves,
strainers or expansion joints, the requirements specified in Section 4.2 for flanged
joints shall be equally observed.
1.) Valves
a.) Valves shall be installed in piping system on closed position.
b.) Globe, check and control valves shall be installed considering the fluid flow mark.
58 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
2.) Instruments
a.) Instruments mounted in-line may be installed to establish the actual dimensions of
final piping systems.
However, the instruments shall be removed during cleaning of the internal part of
the piping system
b.) All restrictions such as orifice plates or flow nozzles shall not be installed until the
completion of pressure tests and line cleaning operations.
3.) Supports
Pipe supports shall be installed prior to assembly and erection of piping system. This
will be necessary for piping alignment.
Temporary supports, if needed, may be used.
Records of pipe flange misalignment (with the piping free and unrestrained), and
showing the effect of the piping connections on the machinery shaft alignment shall be
prepared and ready for request of representative.
59 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
vi. Miscellaneous
Unless otherwise specified, all equipment, piping and valves which are of a temporary
nature shall be designed and prepared by the contractor in a safe and sound manner.
These shall include such lines as temporary vents for air blowing, piping required for
pressure tests and all other piping that are required for the successful completion of
the permanent piping systems.
The temporary piping shall be removed before starting the final leak test.
Assembly and erection work of piping shall carefully be performed without any
damage to equipment, piping and instruments which have been installed.
All joints including welded joints shall be left unpainted and uninsulated until
completion of field pressure testing.
Piping on Pipe Rack - For piping run on pipe rack, precaution shall be observed so
that the field weld point will not coincide with rack beam.
60 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
When any doubt exists as to the quality of materials, the materials shall be assured
by verification of certifications, records or other evidence that they are of the specified
grades and ratings, and that they have received required heat treatment, examination
and testing.
Fit up Inspection
Before welding, all welding joint parts shall be checked on the following items.
a.) Bevelled part shall be fully cleaned so that there is no rust, oil, paint, and
moisture.
b.) End Penetration
End penetration for butt-welding shall be in accordance with “Specification for
Welding of Steel Piping.
c.) Misalignment
Misalignment at butt-welding shall in accordance with “Specification for Welding
of Steel Piping”
(5) Cleanliness
In order to prevent the damage to machine and aid in the trouble-free start of the
units, cleanliness of all piping should be inspected by the following stage:
a.) Before transport from the shop, cleanliness for prefabricated piping is inspected
in accordance with Par. 3.10.
b.) When prefabricated piping are assembled and erected, cleanliness for
prefabricated piping is inspected in accordance with Par. 4.1.
61 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
c.) After completion of pressure testing and when flushing the piping systems,
system cleaning is performed in accordance with Clause 7 and the cleanliness
is evaluated by dirt being included in the fluid which is discharged from ends of
piping systems, or by dirt being left behind on the temporary strainers which are
inserted into the piping system, in accordance with Clause 7.
d.) After water circulation operation, the final cleanliness is checked by dirt being
left in the strainers.
6) Pressure Tests
(1) General
Test fluid and pressure shall be applied to each piping systems as specified in Pipe
Line Schedule, or other reference drawings.
Unless otherwise specified herein, the requirements specified in ANSI B31.3 Par. 337
shall govern.
62 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
7) Cleaning
(1) Standard Cleaning of Piping System
After completion of pressure testing, all piping systems shall be flushed until they are
thoroughly cleaned of loosed scale, debris and other foreign materials by suitable
means using air or water.
Prior to final leak test, the following points shall be carefully checked for all piping
systems.
a.) Re-confirmation of removal of temporary items;
• Temporary piping
• Blanks
• Temporary strainers
b.) Restoration of permanent items;
• Orifice plates
• Spacer rings instead of temporary strainers
(2) A final leak test shall be carried out to verify the tightness of threaded joints, bolted
joints, packing glands and shaft seals.
For this purpose, the following joints are to be confirmed to be tight and not leaking.
a.) Joints of items removed during pressure testing and cleaning, such as in-line
instruments, piping, accessories and short pieces.
b.) Joints at which a blackout was used as isolation at pressure testing.
c.) Manhole flanges of equipment which were opened at cleaning.
d.) Joints to which a temporary piping was connected during testing and cleaning.
e.) Other joints at which tightness could not be verified at pressure testing.
63 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
64 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
This manual is explained about cold- setting joining (TS joining method) and
hot-setting joining (Sleeve joining method), as follows:
a.) TS Joining
In this case, TS joining are used and cold adhesion is adopted. The inside
surfaces are tapered.
a.1) PVC pipe cutting
The pipe shall be scraped to the given size and shall be cut by a saw in the
rectangular direction to the pipe axis.
Oily and extraneous matter will decrease the bonding strength so it must
be completely removed.
65 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
66 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
As the adhesive will progressively cure, it is difficult to pull out the pipe
after; re-adhesion shall be carried out as rapidly as possible. (Within 0
to 30 sec.)
TS sleeve joining
Two step sleeve joining
Zero sleeve joining
67 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Procedure on works:
Pipe cutting
Bevelling of the pipe edge
Cleaning of joining part
The mentioned above shall be carried out just the same as TS joining.
Marking of the insertion length
The insertion dimension of the female pipe shall be previously
determined and marked with colored pen or based on the following
Table 4.
Application of lubricating oil
Grease shall be uniformly applied as lubricant on the insertion point of
the male pipe’s outer surface for easy insertion and pulling out.
Heat softening of the female pipe
The female pipe shall be heated to the point slightly longer (30-60 mm)
than the insertion length with a propane burner or oil bath.
In case of propane burner, the pipe shall be uniformly heated as
rotating. Then the female pipe shall be immersed and heated in
polyethylene glycol bath in which the temperature should be controlled
in the range of 130- 5o C.
Insertion of the male pipe
When the female pipe is softened, the male pipe shall be inserted to
the prescribed length chartered above into the female pipe.
At this moment, the insertion shall be carried out carefully so that both
axes of the male and female pipes are aligned with each other.
Cooling of the Joined parts
After the insertion and joining operation, the male and female pipes
shall be cooled by water and cured.
Marking of the mating mark
After completion of cooling and curing, the fitting mark and numbers
shall be marked on both pipes.
Detaching of the female and female pipes
After the marking, they shall be pulled out by using a drawing jig.
When no jig is present, the edge of the female sleeve portion shall be
slightly hammered to detach the male pipe.
68 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Cementing
Grease, oil, dust, etc shall be removed with cloth from inner surface of
the female pipe sleeve and outer surface of the male pipe.
Then, after cleaning with cloth soaked with acetone, adhesive should
be applied to the pipe and inserted into the female pipe.
At this moment, it shall be confirmed that the male pipe is perfectly
inserted to the sleeve length with the fitting marks getting aligned.
69 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
1) GENERAL
(1) Scope
This specification covers the requirements for the installation of pumps that will be
used in the plant.
This specification may be applied to the installation of blower and other similar
machinery in general use. The general requirements which are common to the
installation works are covered by General Specification for Equipment Installation.
(2) Codes
The applicable codes and standards shall be indicated in Specific Job Requirements.
(3) Units
Unless otherwise specified, metric units shall be used as the measurement system for
the drawings and documents to be submitted.
2) EXECUTION OF WORK
(1) Manufacturer’s Installation Specifications
In general, Paragraph 2.2 through 2.4 in this specification shall apply to the works.
However, the manufacturer’s installation manual as approved by the Bidder/Employer
shall be used instead, if applicable.
70 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
a.5) Fix the anchor bolts by pouring mortar into the anchor bolts.
a.6) Tighten provisionally the anchor bolts after mortar hardens.
a.7) Place the pump (frame, casing or the complete unit) in the base plate, align
the pump and tighten the anchor bolts.
a.8) Grout the base plates.
a.9) Re-check the alignment of the pump and couple the shafts after connection
with piping system.
b.) Preparation of the foundation surface, setting the liners, installation of the base
plate and pump, tightening of the anchor bolts and grouting of the base plate shall
conform to General Specification for Equipment Installation.
c.) Installation of the base plate and pump shall be carried out within the tolerances of
elevation, position, level and perpendicular alignment of the pump.
d.) Levelling shall be carried out at least on four corners of the base plate.
e.) The alignment of the pump shall be carried out based on the finished surfaces
which are nearest to the center of the shaft.
f.) When adjustment between shaft and coupling is required, the adjustment shall be
carried out on the coupling side, not on the shaft.
g.) The alignment of the pump shall be carried out until complete alignment of driving
and driven shafts is attained. On the alignment of the pump, deflection and face
deviation of the driving and driven shafts shall individually measure and it shall be
confirmed that values are within the tolerances specified and these data shall be
recorded properly.
h.) As a rule, the complete alignment of the driving and driven shafts shall be carried
out in accordance with the following procedures:
h.1) Measure the deflection of the shaft at the finished surface on the side of the
coupling with dial gage by rotating the shaft. Measure the face deviation
with feeler gage or dial gage for parallel alignment of both coupling faces.
h.2) Measure the deflection and face deviation at more than four equally
divided points on periphery of the coupling and confirm that measured
values are within the tolerances specified in the manufacturer’s standard.
h.3) Set the clearance between the couplings to the dimension specified in the
drawing. For connection with motor having plain metal bearing, align the
motor shaft to the magnetic center and adjust the clearance between the
two couplings.
71 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
i.) Where dial gage is fixed with magnet base, the following cautions shall be taken
for minimizing errors caused by instability of measuring points:
i.1) Fix firmly.
i.2) Shorten the arm length as much as possible.
i.3) Use small type dial gage.
i.4) Put the measuring point of the dial gage right angle to the shaft surface,
pointing to the center of the shaft.
j.) After completion of alignment, confirm that the shaft can be rotated smoothly.
k.) After connection with piping system, make sure that the pump was connected
without counter force and recheck the alignment of the pump again. If the
alignment was affected by connecting the piping system, realignment shall be
made.
l.) After confirming the direction of rotation, the shafts shall be coupled.
(5) Inspection
Inspection required in the works shall conform to manufacturer’s standard; inspection
shall comply with manufacturer’s inspection manual as approved by Bidder/Employer.
1) General
(1) Scope
This specification covers the requirements for the installation of submersible pumps
that will be used in the plant.
(2) Codes
The applicable codes and standards shall be indicated in Specific Job Requirements.
72 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
(3) Units
Unless otherwise specified, metric units shall be used as the measurement system for
the drawings and documents to be submitted.
2) Execution of Work
(1) Manufacturer’s Installation Specifications
In general, Paragraph 2.2 through 2.4 in this specification shall apply to the works.
However, the manufacturer’s installation manual as approved by the Owner shall be
used instead, if applicable.
Determine the correct anchorage position of the discharge elbow, so the guide rails
when installed, will run parallel and plumb.
The construction of the concrete should be of sufficient strength to ensure a safe and
functional installation. The concrete foundation must have set before installing the
discharge elbow. The surface must be level and even.
Also take into account the upper guide rail brackets. Dimensions and space
requirements are based from the equipment standard dimensions table. Fix the upper
guide rail bracket by means of stainless steel anchor bolts at the edge of the sump
opening. Never fasten the brackets directly to a curved sump wall.
73 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Safely guided by 2 vertical guide rails, the pump slides into the sump or tank and
attaches itself automatically to the discharge elbow fixed at the bottom. Sealing
between the pump and discharge elbow is achieved by the weight of the pump. A
profile gasket between the pump and discharge elbow assures a water tight
leak-proof connection. There is no need to enter the sump for maintenance and
inspection of the pump.
b.) Installation of Guide Claw
Fit the guide claw to the discharge nozzle of the pump. Do not forget to place the
washers under the hex nuts. Nuts must be evenly tightened according to
instructions and to the required tightening torque.
c.) Installation of Mounting bracket / Discharge Elbow/ Bottom Guide Rail Bracket
Construction of the concrete foundation has to be of sufficient strength to ensure
safe and functional fixing of the guide rail system and the discharge elbow. Level
and anchor the discharge elbow. The guide rail must be installed absolutely
parallel and plumb.
Mount the bottom guide rail brackets on the discharge elbow in such a way that
standard dimension between the guide rails centerlines and the centerline of the
discharge elbow is complied with. Fix each bottom guide rail bracket the proper
tightening torque as required.
The installation of the bottom guide rails bracket is completed after tightening the
anchor bolts for the discharge elbow. Continue with the installation and fitting of
the discharge pipe to the discharge elbow.
Install the guide rails onto the bottom guide rails brackets at the discharge elbow.
Cut and fit the guide rails to required lengths. Make sure the guide rails are
absolutely plumb; it is important for the suspension and guidance of the pump
during installation. In case of deeper installations the scope of supply may include
intermediate brackets that will function as spacers between the guide rails. It
depends on the construction whether a support at the discharge pipe or sump wall
becomes necessary.
d.) Installation of Lifting Chain, Lifting Cable or Rope on Motor Housing
The chain of required sizes is attached to the top of the motor casing toward the
back and opposite the discharge nozzle using a shackle. Depending on the
motor and hydraulic combination, the pump will be suspended from this point with
an inclination of approx. 5-10 degrees.
74 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
This guarantees a problem – free lowering of the pump, provided that the
suspension point of the lifting equipment is directly above the pump.
(5) Inspection
Inspection required for the works shall conform to manufacturer’s standard; inspection
shall comply with manufacturer’s inspection manual as approved by the Employer.
1) General
(1) Scope
This specification covers the requirements for field welding work on carbon steel pipes
and stainless steel pipes.
(2) Codes
Unless otherwise specified, the welding and other criteria covered by this specification
shall be in accordance with the Code for Chemical Plant and Petroleum Refinery
piping, ANSI B31.3, latest edition.
75 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
2) Welding Method
(1) Welding Method
Welding method shall be qualified in accordance with ASME SEC. IX, and the
following are generally accepted for welding of pipes;
a.) Shielded metal Arc (SMA) Welding
b.) Gas Tungsten Arc (GTA) Welding
Butt circular welding shall be done in accordance with the Table I, attached;
The Shielded Metal-Arc Welding (SMAW) process shall be used for fillet welding.
(3) Welder
a.) Qualification
The welder and welding operator shall be qualified by in accordance with ASME
Section IX. Each qualified welder and welding operator shall have assigned
identification numbers, letters, or symbol, which shall be used to identify the work.
Records of Performance Qualification shall be prepared and maintained and shall
be available when requested for verification by the inspector or customer
representative.
76 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Temperature
Welding Material Hour
( ْ C)
77 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
1.6 to 2mm
60 +/- 0 to 10 deg.
t=1.6 +/-
t
0.8mm
2.0 to 3.6mm
78 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Misalignment (x)
= 1.5 mm or ¼ the wall thickness, whichever is less
79 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Maximum allowable projections of weld metal into the pipe bore at welded
butt joints are as follows:
Projections shall not exceed 3.0 mm.
Imperfections exceeding these limitations are considered defects.
c.) Slip–on Flange Welding
In principle, fillet welding on both sides shall be made in accordance with Figure 3.
d.) Socket Welding
In socket welding, proper clearance (approximately 1.6 mm) shall be provided at
the end of the pipe.
80 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
For such defects under the surface of welding such as blow hole, slag inclusion,
etc., the defects shall be removed completely by means of grinder, arc air gausing
or chisel and re-welding shall be applied.
If cracks were found in the weld zone, the defect shall be removed by means of
grinder. After checking that the defect has been removed completely, re-welding
will be applied.
(10) Finishing
Inside the circumferential weld bead shall not have any burr or fragment of welding rod
and all adhering substances shall be removed as far as possible.
Spatter, slag, etc. of welded part shall be thoroughly removed from the metal surface.
Record including the following information shall be prepared for each welding joint of
Inspection Class A and B Piping.
a.) Name of welder
b.) Kind of welding rod used
81 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
(11) Tables
a.) Table 1 – Application of Welding
82 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
WEL
Stainles SUS 304TP 18Cr-8Ni E308 WIPWELD308
308
s Steel
Pipes SUS 16Cr-12Ni-2M E316 WEL
WIPWELD316
316LTP o Low Carbon L 316L
SGP-B, E
SGP-B(G) E WIPWELD110
Carbon
STPG38-E, 6011 0
Steel
S E
Pipes WIPWELD130
STPT38-S 6013
0
STPY41
1) General
Design and construction of electrical equipment and system is performed basically
according to project standard specified by the Employer and the local standard or
regulations in Sri Lanka. Manufacturing of electrical system will be done in Sri Lanka as
much as possible by the qualified subcontractors having sufficient experiences and skill.
83 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
All the instrument equipment will be supplied from the countries outside Sri Lanka to
construction site except the standard instrument equipment and construction materials.
Custody of special electrical and instrument equipment shall be made at air-conditioned
storage house in order to avoid any deterioration of electrical and electronic parts.
Cable rack and ducts are installed with the supporting pitch of 2 meters or smaller.Conduit
pipes are used for connection of cables to motors and equipment.
3) Instrumentation
Instruments to be assembled with the pipe lines are installed at a time of piping work by
piping people and those to be installed onto the equipment will be set by the instrument
engineers from subcontractor under the supervision by the Contractor’s instrument
engineer.
Control cables for instrumentation are laid separately from the power cables.
GENERAL
Installation of low voltage switch gear, motor control centers, instrumentation panels, cable
tray/ladder, etc. will be basically made after the civil and foundation work has completed
and shall be carried out in accordance with the approved drawings and erection manual.
A crane or forklift will be needed to lift up all the electrical equipment to set in to a desired
location and purpose. Proper handling of the equipment should apply to avoid damaging
the equipment and the components itself.
84 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Receiving
Before and after unloading the electrical equipment, inspect its section and unit exterior for
evidence of damage that may have been incurred during shipment. If there is any indication
has been mishandled or shipped on its back or side, remove the draw out units and make a
complete inspection of the internal structure, bus bars, insulators and unit components for
possible hidden damage. Report any damage found to the carrier at once.
Handling
Handle the electrical equipment with care to avoid damage to components and to the
enclosure or its paint finish.
Keep the electrical equipment in an upright position.
Insure that the moving means has the capacity to handle the weight of the electrical
equipment.
The electrical equipment should remain secured to the shipping skid until it is in final
location.
Exercise care during any movement and placement operations to prevent falling or
unintentional rolling or tripping.
Lifting angles for handling by overhead crane are bolted to the top of each shipping section.
Handling by overhead crane is preferable but when crane facilities are not available,
the electrical equipment can be positioned with a fork-lift truck or by using rollers under
the shipping skid.
Fork-lift Truck
Electrical equipment’s are normally top and front heavy. Balance the load carefully and
steady, as necessary, while moving. Always use a safety strap when handling with a
fork-lift.
Storage
When electrical equipment cannot be installed and place into operation immediately upon
receipt, take steps to prevent damaged by condensation or harsh environmental conditions.
If the equipment cannot be installed in its final location, store it in a clean, dry, ventilated
building, heated to prevent condensation, and protected from dirt, dust, water, and
mechanical damaged.
85 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
86 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Piping
Install conduit in such a manner as to prevent water from entering and accumulating in the
conduit or into the enclosure. Eliminate sags in conduit. Have the conduit enter the
equipment in the areas designated for conduit entry on the plan views.
Wiring
Please be guided with the wiring diagram, termination diagram and single line diagram this
is to avoid incorrect wiring.
Use conductor with a rating of 75°C or higher, but regardless of the insulation temperature
rating select the wire size on the basis of 75°C wire ampacity. Using a higher
temperature wire ampacity table often results in a smaller cross section of copper
available for carrying heat away from the terminals.
Install insulated wire and cable at a temperature sufficiently warm to prevent the insulation
from splitting.
When more than one conduit is run from a common source or to a common load, be sure to
have each phase and the same number of conductors per phase. If the phase
conductors are not distributed uniformly, eddy currents will be generated in the steel
between the conduits.
Locate the equipment to avoid physical damage and to avoid overheating. Secure
incoming power lines in a manner adequate to withstand the forces which will act to
separate the conductors under short-circuit conditions. Use the cable ties furnished in
both horizontal and vertical wire ways to support the load and interconnection wire.
Use a shielded communication cable to protect very low signals transmitted to or from
a computer or programmable controller.
Verify the compatibility of wire size, type, and stranding with the lugs furnished. Where they
are not compatible, the wire or lugs accordingly. If crimp lugs are used, crimp with the
tools recommended by the manufacturer.
All fields wiring to control units should be made in accordance with the wiring drawings that
are furnished with the equipment. Load and control wiring can be wired trough lower
horizontal wire ways.
87 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
GENERAL
Cable tray/ladder system shall comply with IEC 61537, manufactured from not less than
2mm thick perforated hot dipped galvanized steel material.
The following tools are commonly used for installation of cable tray:
• Metal cutting saw
• Touch-up material
• Screwdriver
• Drill with bits
• File
• Open end wrench
• Nylon cord or laser
• Sealant for cut edges
• Leveling device
• Tape measure
• Torque wrench
• Ratchet wrench
• Appropriate safety equipment
Do not cut or drill structural member like beams, columns and steel trusses.
In order to install cable tray supports like threaded rods, first find the require elevation from
the floor to the bottom of the cable tray and established a level line with a laser or a nylon
string.
88 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Support fabrication.
The support will be prefabricated on the workshop of approved supplier using appropriate
approved material cut according to the length show on the drawings and after that, the
bracket will be fixed with anchor bolt to the channel.
89 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
CONDUIT INSTALLATION
GENERAL
Approved conduit system shall comply with IEC 614. That all steel conduit and fittings shall
be hot dipped galvanized. Use steel conduit if exposed installation and PVC conduit if
embedded in concrete walls and slab.
Installation must be performed in a neat and workman like manner and shall be inspected
by engineer’s representative and approved before any cable is drawn.
Messenger wire minimum of 1.2mm shall be inserted into spare conduit.
90 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Conduit bushing shall not be used to secure threaded steel conduit to a box or enclosure. A
locknut shall always be assembled between a conduit bushing and inside of the box or
enclosure.
Where locknut is provided with fittings at the means of securement to a box or enclosure,
the locknut is to be secure by hand-tightening to the enclosure plus ¼ turn using an
appropriate tool.
Do not rely upon locknut to penetrate nonconductive coatings on enclosure. Coating shall
remove in the locknut contact area prior to raceway assembly to assure a continuous
ground path is achieved. Touch up bare area as needed after installation.
For outdoor type installation weatherproof boxes and accessories shall be use as agreed
on site by the Engineer as per also indicated in the specification or on the approved
drawing.
VERIFICATION OF INSTALLATION
After the raceway is fully installed and supported, and prior to installing conductors in a
raceway, all fittings and locknut shall be re-examined for secureness.
91 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
SIZE INTERVAL
20 mm Ø 1.2 m
25 mm Ø 2.0 m
32 mm Ø 2.5 m
SUPPORTING
Follow all code requirements for spacing of supports and frequency of securing steel
conduit. The requirement to securely fasten raceways within the specified distance from
each termination point includes, but it is not limited to, outlet and junction boxes, device
boxes, cabinets, and conduit bodies. Each raceway shall be so secured. Do not omit any
supports.
92 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
COROSSION PROTECTION
Steel conduits are typically galvanized to provide excellent corrosion protection.
Sometimes supplementary corrosion protection is required if the installation is in a severe
corrosive environment.
INSTALLED IN A SOIL
Where installed in contact with soil, steel conduit and associated fittings require
supplementary corrosion protection if soil resistivity of less than 2000 ohm-centimeter and
has confirmed that the soil is extremely corrosive.
Also, warning sign or warning tape shall be provided on the ground to indicate that there is
a buried conduit.
PULL BOXES
Pull boxes and fittings shall be plated by melting zinc or coated with-preventive paint and
shall be sized correctly to accommodate the connected conduit and all required conductors
run through.
GENERAL
All cable routes must be authorized by the supervising officer for the project.
All cable installed must comply with the BS standard. All power / control cable shall be
600/1000V rating.
93 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
All wiring/cabling shall be done after the roughing-inns and cable tray installation and it
must follow the wiring schedule and termination diagram.
Wiring and Cabling of Power, control and instrumentation will be done via cable tray/ladder
and conduits in a workman like manner and separator will be provided to cable tray to
separate power cable to control and instrument cable.
INSTALLATION
Bending of the cable shall keep to an absolute minimum.
Consider the minimum bending radius of the cable at any point, with zero stretching stress,
following installation.
Cables should not be stressed by over-tight cable ties. Ties should be used to segregate the
cables and managed them, not to flatten or change the geometry.
Cable ties should only be used in such circumstances to loosely bundle the cable runs for
ease segregation and identification and identification to various works areas.
When cables pass through holes in walls or floors precautions must be taken to remove the
sharp edges, which will damage cable beyond repair.
Where possible, to minimize the effect of power cables on data cable when installed in three
compartment trunking, it is recommended that the power cables occupy one of the
outer sections and other data cables.
Cable rack and ducts are installed with the supporting pitch of 2 meter or smaller.
Cables are not cast directly into concrete. It should have conduit or suitable raceways.
Conduit pipes are used for connection of cables to motors and equipment.
Cabling works in the cable pit shall be arrange suitable separator and support to separate
cable route between power cable, control cable, and instrumentation cable.
Where cable pass through fire rated walls of floors a fire barrier or fire rated sealing
compound shall be used.
94 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
INSTRUMENT INSTALLATION
SCOPE
This specification describes the practices that shall be employed and the standards of
workmanship that shall be required for the installation of instrumentation.
CODE
The applicable codes and standards shall be indicated in specific job requirements.
GENERAL REQUIREMENTS
Quality assurance, Inspection and testing shall be undertaken in accordance with
installation CONTRACTOR’S Quality Assurance System/ Quality Plan, requirements of the
project specification and reference International Codes and Standards.
95 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
grade, the supports shall be grouted such that any water is shed.
Instrument located outdoor, and subject to severe ambient temperature including moisture
and corrosion shall be protected by installation in a weatherproof housing or IP 68
similar protective enclosure.
INSTRUMENT ACCESSIBILITY
All instruments shall be accessible for servicing from floor level, walkways, permanent
ladder or platforms. Above 2m instrument shall be provided with permanent access.
PIPING OF INSTRUMENT
One or two single pipes or tubes may be supported by dedicated heavy duty channel
section if other support is not available.
Tubing shall be fastened to support at regular intervals with non-corrosive fixing to prevent
sagging, or misalignment.
INSTRUMENT CABLING
GENERAL
Instrument cable shall be installed in such a manner that the design requirements for the
contract in terms of safety, reliability, access, etc. are realized. The main points of the
design philosophy are given below and all installation method shall take account of this
philosophy.
DESIGN PHILOSOPHY
All outdoor cable shall be armoured. All cables shall be supplied as specified in agreed
cable specification.
Multicore cable shall be sized such that they contain a minimum of 20% spare conductors
at the completion of contract design.
Intrinsically safe circuit and non-intrinsically safe circuit shall not be contained within the
same cable or marshaled in the same junction box.
96 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
All equipment containing an electrical signal or power supply shall be earthed for personnel
safety reasons and for minimizing electrical interference. This includes enclosures, cables,
cable tray and conduit.
All cabling shall be protected against mechanical damage, chemicals and heat. In general,
underground cabling and cabling run on ladder rack and tray will meet this requirement if
installed in accordance with the contract drawing and provided attention is paid in detail
routing.
CABLE SEPARATION
Control cables for instrumentation are laid separately from the power cables.
Instrument cables carrying more than10 amps shall be treated as power cables.
CABLE INSTALLATION
All cables from control buildings to junction boxes, from junction boxes to individual
instruments, and other cables, shall be supported by a suitable cable support system.
Routes which cross walkways shall provide minimum headroom of 2.5m. Routes which cross
roads or areas requiring vehicular access shall provide minimum headroom of 5.5m.
Where routes pass through the floor of a structure, mechanical protection in the form of a
metal sleeve shall be provided.
Cables within control rooms shall be routed under floor. Where cables are routed above the
floor they shall be trunking or conduit.
Under floor cables shall be installed on ladder rack and cable tray. The general requirements
for above ground installations in the field are applicable.
97 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Cables connected to instruments shall be installed with loop of cable to provide sufficient
slack for re-making the cable connection if the instrument is removed and to allow for
removing the instrument without electrical disconnection.
CABLE GLANDING
All cables in the field shall have gland with correctly certified cable glands in accordance with
hazardous area classification.
Cable glands are not normally required for cables in equipment rooms of buildings, but may
be required at required at other locations within the buildings.
All gland installation shall maintain the IP rating of the associated equipment.
WIRING TERMINATIONS
All terminals shall be screw clamp terminal clamp type where the screw is not direct contact
with the wire. Terminal may incorporate test sockets if necessary. Power supply
terminals and all terminals shall be fitted with protective covers and warning labels.
Power supply terminals shall be fitted with partitions between adjacent terminals.
Normally only one conductor shall be terminated in each terminal. Common connections
shall be made as far as possible using the terminal manufacturer’s standard bridging
arrangement. Where connection of 2 wires into one terminal unavoidable, two
flat-bladed crimps shall be pin type crimps shall not be screwed into one terminal.
Sufficient slack wire shall be left looped at terminals to allow for re-making of terminations.
All spare cores in multi-core cable shall be terminated. Sufficient terminals shall be fitted in all
equipment to facilitate this.
Conductors shall be ferruled with the number of the terminal to which they are connected.
98 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
LABELS
Every item of instrument equipment for which an identification reference is allocated shall be
provided with engraved label. This label shall be in addition to any manufacturer’s
wired-on tags or nameplates.
Labels shall normally be engraved plastics. Dimensions, sizes, colours, engraving details
and method of fixing shall be as determined by the contract drawings or as agreed with
the site engineer.
Labels for individual instrument shall be fitted adjacent to the instrument such that the label
remains in place if the instrument is removed. Labels for other equipment shall
normally be fitted on the equipment.
GROUNDING SYSTEM
GENERAL
All exposed metal frames of all electrical system, apparatus and equipment that are part of
the electric circuits, neutral of transformer, etc., shall be grounded to ensure the public and
personal safety.
Refer to approved drawings and consult Engineer for the final location and installation of
grounding rods.
99 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
MATERIAL REQUIREMENT
Steel rod use shall meet the requirement of copper clad steel rod, 16 mm Ø, and 1.5 m
length.
The leading edge of the ground rod shall be provided with sharpened point, and the other
shall be beveled.
The ground rod shall be free from badly formed, cracked or other defective structure.
A grounding plate shall be 90 cm, 1.5 thickness copper plate.
Annealed stranded copper conductor type shall be used as a grounding conductor.
GROUNDING WORKS
Locate the grounding pit. This is where the ground rod to be installed.
Drive ground rod into the ground pit until the coupler is just above ground.
Measure the ground resistance of the ground rod before connecting the grounding conductor.
A minimum system grounding resistance of 5ohm shall be maintained.
Connect the ground conductor into the ground rod by means of compression type connector
or by exothermic welding if necessary.
Soil excavation and backfilling works shall be executed by a civil works.
Lightning protection and instrument grounding shall be done by a separate common
grounding.
Grounding for transformer neutrals and lightning arrester, grounding rod shall be installed
for interconnections with grounding mesh
FIELD TEST
A notification will give in advance to carrying out any tests of the electrical equipment and field wiring so
that the company representative is able to witness equipment and cable support mounted within the
panel/in the field, but not wired. Fully wired and ready to test.
Prior to starting any test it is required to double check the installation, electrical devices and
instrumentation are strictly in accordance with the manufacturer’s specification, electrical
and instrumentation drawing.
100 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Individual test
• Visual inspection
• Insulation resistance for all equipment and wiring/cable
• Withstand voltage test of insulation oil
• Circuit continuity test
• Relay checking
• Polarity test
• Phase rotation test
Completion test
• Visual inspection
• Insulation resistance for all equipment and wiring/cable
• Withstand voltage test of insulation oil
• Circuit continuity test
• Relay checking
• Polarity test
• Phase rotation test
• Operation test of each equipment
• Interlock sequence test
• Indication test
• Fault alarm test
Installation of SCADA
1) GENERAL
The SCADA system takes over, is produced, and delivered to the procedure for of this chapter.
2) Workflow
The work flow of the SCADA making is composed of the following item.
• Basic Engineering
• System Engineering
• Detail Engineering
• Documentation
• Erection (Supervision)
• Commissioning and Training.
101 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
3) Engineering
The following document is submitted at the first stage.
• Overall DCS concept system configuration with network topology, operator place
definition,
• MHI concept (Machine Human Interface System) operation and monitoring concept,
hierarchy of mimic
• Diagrams, data archiving and retrieval, report functions, access control, graphic
layout concepts,
• Colors and symbols, etc.
• Concepts for power supply, shielding, earthing and lightning protection
• Wiring concept
We will submit the detailed drawing and the document at the final documentation.
102 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
5) Erection
After the equipment is carried, the following work is executed in the site.
• Connection of the power supply cables to the process control cubicles
• Connection of the earthing to our cubicles
• Installation/connection of our cubicles
• Installation/connection of control room equipment (HMI, printers, etc.)
• Installation/connection of the engineering systems
• Cabling and connection of the field equipment
• Handing over to the commissioning
6) Commissioning
The commissioning includes system commissioning, cold commissioning and hot
commissioning according to the detailed
• System Commissioning
System commissioning consists of the setting up of the delivered system components.
• Cold Commissioning
During the cold commissioning all process components, connected to the DCS will be set up
for remote operation on drive control level via the operator stations. For this a non-recurring
test of all measurement and control circuits will be executed.
• Hot commissioning and optimization
Precondition for the hot commissioning is the readiness of the mechanical process systems to
dispose their different operation conditions. All tests will be executed on basis of the approved
documentation of the basic engineering. During startup and shut-down procedures, typical
operation and disturbance conditions as well as load variations the function of SCADA will be
verified.
7) Training
Training for Employer’s operator will be conducted by the Contractor’s engineer either during
commissioning or test run (process proving) period, depending on the actual situation and
Employer’s demand.
103 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Pre-commissioning
As soon as the construction work has been mechanically completed, waste water, utilities
and chemicals required for the pre-commissioning are supplied to the plant site.
Commissioning
After the pre-commissioning is completed, the plant is ready for commissioning and is
regarded that the Mechanical Completion has affected. Readiness of the plant for
commissioning shall be confirmed by the Contractor under the consultation with the
Employer.
Commissioning of the plant shall be conducted according to the manner and schedule that
will be submitted to and agreed by the Employer before commissioning.
Commissioning engineers shall be dispatched to plant site from the Contractor. The
Employer shall also assign his operators, maintenance crew and supervisors and position
them to working shift for the plant commissioning.
Following the confirmation of the above, each machine shall be tested individually by the 24
hour running test at the presence of Employer’s engineer to check the following.
• Functioning of equipment and machinery
• No fluid leak
• Bearing temperature
104 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Test run
Immediately after the plant is confirmed by the Employer and the Contractor to be
available for the continuous and normal operation, test run of the plant will be
conducted at the presence of the Employer’s engineers for a minimum period of 30
days to check and confirm the plant performances as guaranteed by the Contractor.
Test run manners and procedures as well as acceptance criteria shall be mutually
agreed by the Contractor and the Employer beforehand.
As soon as the plant performances have been confirmed as a result of the test run, the
acceptance certificate shall be issued by the Employer for the successful completion
and acceptance of the plant.
Training for Employer’s operator will be conducted by the Contractor’s engineer either
during commissioning or test run (process proving) period, depending on the actual
situation and Employer’s demand. This is to train and educate the operator in proper
operation and maintenance the moment the project is turn-over to the end user.
1) Pre-commissioning
As soon as the construction work has been mechanically completed, waste water, utilities
and chemicals required for the pre-commissioning are supplied to the plant site.
105 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
(performance test) and is regarded that the Time for Completion has reached.
Readiness of the plant for trial operation shall be confirmed by the Contractor under the
consultation with the Employer and the Engineer.
Trial Operation of the plant shall be conducted according to the manner and schedule that
will be submitted to and agreed by the Employer before operation. Operation engineers
shall be dispatched to plant site from the Contractor. The Contractor shall also assign his
operators, maintenance crew and supervisors and position them to working shift for the
plant operation.
Following the confirmation of the above, each machine shall be tested individually by the
24 hour running test at the presence of Employer’s engineer to check the following:
a.) Functioning of equipment and machinery
b.) No fluid leak
c.) Bearing temperature
d.) Vibration and noise
e.) Availability for continuous operation of the plant
3) Performance Test
During the Trial Operation, the Contractor willconduct the Performance Test to ascertain
whether the Facilities attain the functional guarantee considering:
a.) Wastewater Flow
b.) Influent Quality (BOD, SS, T-N, T-P)
c.) Effluent Quality (BOD, SS, T-N, T-P)
d.) Maximum Moisture Content of Dewatered Sludge
e.) Air Emissions Limits
The Contractor assumes that the functional guarantees have been achieved during the
trial operation period. The Contractor will ask third parties of analysis to analyze the
functional guarantee items.
106 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
107 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
This method statement for the pipeline works methodology covers all requirements of trench
excavation, excavation protection works, rock excavation, pipe jacking system for roads and
railway crossing, excavation in the vicinity of existing utility services, pipe laying procedures,
pipe laying in the existing service duct of bridge, pipeline supports, backfilling, removal of
temporary supports and reinstatement work.
A preliminary study of the work execution shall be conducted to understand existing conditions of
the work area. Surveys will be conducted to establish reference levels, pipeline profile, and data
of existing utility services – Telephone, Electricity and Water/Sewer.
A joint inspection along the pipe route shall be coordinated with the following authorities prior to
start of work:
a. NWSDB
b. Road/Provincial Road Development Authority
c. Sri Lanka Telecom
d. Ceylon Electricity Board
e. Sri Lanka Railways
f. Sri Lanka Police
g. Agriculture Department
h. Institutions/Residents in the Vicinity
i. And other Local Authorities
108 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Before the start of pipe laying and construction works, particularly in the main road, a Public
Notice Board will be set up indicating date of commencement and expected date of completion
of works.
Setting-Out Works
Setting-out or ground marking works shall be done by a competent person with appropriate
survey equipment. Based on approved construction drawings, correct coordinates and levels
shall be validated referring to the survey bench marks established along the pipe route.
After completing this pipeline tracing, trial or test pits investigations and other sub-surface
studies shall be carried out to assess existing conditions. Final setting-out work will be done as
approved by the Engineer.
(1) Test pits will be conducted at proposed pipe route especially at each street intersection to
determine possible obstruction.
(2) Test pit volume = L x W x depth (invert elevation of proposed line)
(3) Provision of safety requirements such asinformation boards, barricades, safety cones,
warning signals, and lighting facilities of work areas during night time.
(4) Traffic management and control such as stationing of traffic aides will be provided. In the
event of traffic disturbance such as road closure, prior approval of the road maintenance
authority and police department shall be taken.
(5) No open excavation will be left at the end of each working day, if not possible, provision of
steel plates.
(6) All waste excavated materials will be disposed outright at approve disposal areas.
(7) Temporary restoration work will be done. Permanent restoration will only commence after all
the required tests (for Force Main – Pressure Line Test and for Gravity Lines - Infiltration/
Exfiltration Test and Ball Mirror Test) have been satisfactory conducted.
(8) Construction of manholes, where required, will start as soon as pipe laying reaches each
proposed locations.
(9) Manholes will also be tested for Infiltration and Exfiltration Tests.
109 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
(10) Other than soil materials for backfilling, all materials shall be stored as per manufacturers’
recommendation and in a suitable stock yards such that HDPE pipes shall be protected from
direct sunlight, pipes shall be supported with wooden blocks to prevent surface damage, and
loose materials will be placed on crates. Materials will be stored separately in the WWTP
Area, MPS Area and SDB Area. The storage shall be divided into sections such that any
pipe type and material class will be stored in its particular section for easy identification and
retrieval when needed.
(11) Particular attention will be taken on the handling of all materials as for delivery, storage and
transport. Use of appropriate equipment is necessary. Materials shall be suitably covered
and properly supported.
(12) Suitable equipment shall be prepared for the implementation of work. As a minimum, a set of
survey instruments, crane and lifting devices, excavators, delivery trucks and trailers, dump
trucks, water pumps, power generator sets, plate and roller-type compacting equipment, and
other tools will be generally provided.
(1) Cutting of pavement (where required) after determination of pipe route based on the test pit
results.
Asphalt or pavement cutter shall be used to cut the pavement surface.
Trench minimum width as required in the Standard Trench Excavations provided in the Bid
Drawings KCWMP/G/C/TS/ 01 and 02.
(2) Breaking of pavement. Use of backhoe breakers
(3) Trench excavation shall be carried out using mechanical excavators such backhoes or
mini-backhoes or manually depending on the site condition of the excavation line.
Trench protection, use of trench box or sheet piles depending on trench depths
Pipe Cover shall be 900mm unless otherwise specifically decided. Trench depths are
dependent on the pipe material, pipe diameter and existing ground condition.
(4) Manual trimming to grade.
(5) Checking of elevation.
(6) Putting bedding material (granular material, minimum 100mm thick).
(7) Checking of elevation.
(8) Installing Pipe Supports (where required)
(9) Pipe laying
(10) Checking of elevation.
110 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
111 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Prior to commencing the pipe laying, it is necessary to dewater the pipe trench for which the
pipe will be laid. Well point system with filter shall be provided.
Sump pumping at the end of the trench is not recommended considering instability of the
excavation wall/formation arises.
Surface runoff will be controlled by diverting surface runoff water by dike or temporary canal
system to prevent entry or collection of water to the excavation pit.
Dewatering shall be used until the final backfilling has been laid and compacted as required.
112 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Depending on the situation, the use of trench protection has to be strictly studied and
implemented to address risk of excavation wall collapse. In some adversely difficult
situations, such as the 4-meter trench excavation for the Gravity Effluent Line or the Entry
and Exit Pits for the Pipe Jacking System, driving vertical supports such as H-beams at
designed intervals or using sheet piles if so needed, will be required. A further study of the
ground condition prior to this work section implementation will be conducted to assess the
required excavation protection.
(3) Pipe Cleaning before Laying (particularly for D.I. Pipes to be used for Force Main)
D.I. Pipe cutting to its required length shall be done using the appropriate pipe cutter.
Cutting edge of the pipe will be tapered by using grinders.
Placing the D.I. Pipe into the trench shall be by use of suitable lifting equipment such as a
Crane Boom Truck. The spigot socket is cleaned and shaped to ensure that there is no any
sharpen edge. The rubber ring should be wiped, cleaned and placed in the groove of the
socket. A thin film of lubricant is to be applied to the inside surface of the rubber ring which
will be in contact with the entering spigot.
The outside of the pipe spigot is cleaned and the portion is filed until rough edges is
removed and will also be applied a thin film of lubricant.
To assemble the joints, use of either a ratchet or excavator bucket is provided to suit site
condition. In laying the force mains, according to the final completed pipe profile, a washout
or blow-off valve has to be provided to the lowest point and an air-relief valve will be
installed in the highest point. Depending on the pipeline profile, in some cases several
blow-off valve and air-relief valve will be required.
In case of flanged-joint, it should be coated including all bolts and nuts with Denso paste
and primer, Denso mastic, Denso tape and PVC or Polyethylene outer wrapping.
And accordingly, concrete thrust blocks shall be provided at all pipe bends against thrust
force.
113 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
From the MPS, the Force Main will cross the William Gopallawa Mawatha Road. It is
proposed that the alternative pipe route be placed inside the Getambe Ground, an open
grounds parallel to the railway/road. The road crossing will have to be done using a pipe
jacking system.
The pipe route will then cross the Peradeniya Road near the Getambe Roundabout for
which another pipe jacking system will be used. From this point, it will cross the Mahewali
River along the service duct at the right side of the Gannoruwa Bridge.
And it will then cross the Gannoruwa Road by pipe jacking system entering the service road
going to the WWTP site.
Pipe Jacking is a specialist tunneling method used to avoid a major surface disruption on
the traffic of the railway and roads to be crossed by the pipe laying.
Pipe jacking system is a general technique of the installation of pipes with a tunneling shield
or pipe casing in front and the pipes are jacked from a jacking entry pit to a receiving pit.
Excavation is carried out in a shield forward of the leading pipe as the pipeline is pushed
out of the jacking pit and the process repeated. Excavation can be by hand or machine,
depending upon the conditions. But nevertheless, safety will be of utmost concern since
this involves working condition on a very much confined space.
Soil investigation of the jacking and its pits locations is a major factor. It influences the
excavation method of the entry and receiving pits, the required temporary works, jacking
length, pipe casing design and, if so needed, ground stabilization.
114 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Differing soil profile needs to be assessed as appropriate. Water table has to be checked.
Records have to be prepared on a regular basis. Data monitoring is a must on main survey
checks, line and level, pipe casing position, pipe rolling, main jacking load, inter-jack load,
casing load, total load, and surface checks.
The pipe length to be pressure tested will be based on the locations of the jacking points in
segments such as (i) MPS to the first jacking receiving pit inside the Getambe Ground, (ii)
from the first jacking receiving pit to the second jacking receiving across the Peradeniya
Road, (iii) from the second jacking receiving pit to the third jacking receiving pit across the
Gannoruwa Road, and (iv) from the third jacking receiving pit to the inlet tank of the
preliminary process tank in the WWTP. After all the interconnections have been completed,
a final pressure testing of the total 1,032-meter line shall be tested.
The both ends of the segment to be tested will be blocked and supported by a concrete
thrust blocks. The lowest end of the segment shall be prepared for water filling while the
other end will be prepared for air releasing. Water to be used is clean, potable water from a
natural water source and to be transported to site using water tankers.
The water should be slowly filled at the lowest end using booster pump until a 10-bar
pressure can be attained. This pressure shall be kept for 24 hours and regularly checked
for pressure drop. A pressure drop signals a leakage on the tested line. The minimum
allowable leakage is calculated using the requirements and formula to be specified by the
Engineer.
115 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Only after the successful completion the pressure testing that the final reinstatement of the
ground surface shall be started.
The Project comprises of three (3) major areas for the Wastewater Treatment Plant (WWTP) and
its Facilities, Main Pump Station (MPS) Building and Sludge Drying Bed (SDB) Facility, and
seven (7) locations for the New Operations Building and several Staff Quarters.
WWTP and its Facilities includes Preliminary Process Building (Screen and Grit Chamber),
Oxidation Ditches (4 units), Sedimentation Tanks (4 units), Disinfection Building and its
Disinfection Tank, Sludge Pump Building, Sludge Treatment Building including the Electrical and
Power Generator Room, Administration and Control/Monitoring Building, Work Shop and
Garage, and other facilities such as Flow Meter Chambers, CEB Substation, and Guard Post.
WWTP covers about 26,000 square meters of development providing essential facilities and
services for its operation. This includes clearing and grubbing the total area, land improvements,
slope protections along Mahaweli River, fences, noise barriers and gate, road networks, and
other access requirements.
116 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
It will also be provided with Effluent Disposal System of sewer pipeline crossing the Gannoruwa
Road to the Discharge Structure or Effluent Outfall to be constructed downstream.
MPS is to be located also in Getambe along the William Gopallawa Mawatha Road on an 880
square meter lot. The 3-level building will house the intake structure with coarse and fine
screenings, grit chambers and the wet well pump pit at about 8 meters underground, the Staff
Office, Tool Room and Toilets, Grit Classifier Facility and Generator Room at the first level, and
the Electrical Room and Deodorization Room at the second level.
The MPS Facility will also be provided with its Loading Bay Area, its own Sub-Station, receiving
manholes for the Inflow Pipe, and as well as an Overflow Pipe directed to Discharge Structure in
the Meda Ela.
SDB is to be located inside the Tekawatta Mixed Garden Municipal Property adjacent to the
Mahaweli River. Covering about 4,100 square meters of land, SDB Facility includes 5 units of
sludge drying bed buildings with its corresponding land developments of paved road network,
fence and gate, storm drainage system connected to a discharge facility having an outlet in the
Mahaweli River, and a Staff Office Building.
117 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Where necessary, the demolition contractor will be requested to prepare a demolition plan.
Any such demolition plan shall be submitted to the engineer and all those affected or
concerned shall be kept informed about the activity.
Heavy machinery will not be used for demolition unless absolutely necessary. The
development of defects on existing structures will be monitored during demolition. Small
machinery and an appropriate technique, as approved by the Engineer, will be used and
methods that control pollution and environment impacts will be adopted.
Remaining demolition materials will be transported off-site, to a designated dumping site. The
Engineer’s assistance is required in arranging suitable dumping sites.
118 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Where appropriate, the contractor may opt for thrust boring, to make road crossings. This
system could reduce open out excavation across roads. Trial pits and detectors shall be used
to locate existing services. For open cut trench excavations in self-supporting ground, the
mechanical excavators or backhoe machines will be used in open cut. All excavations deeper
than 1.5m will have suitable support, whether it would be timber planking, drag-boxes,
sheet-piles or steel shoring.
With extreme precaution the free split type control blasting technology [delay detonating] shall
be utilized for rock excavations. Handling of explosives will be supervised by a blasting
foreman with a minimum 10 years of experience in controlled blasting. Percussion type
silencer fitted drilling. Per blast advance is limited to 1.5m and before blasting the rock surface
shall be fully covered with a suitable bunker, such as tires connected with chain link mesh.
The relevant blasting permits, storage of blasting materials, transport to site and loading shall
all be in accordance with the blasting standards and the regulations of the GOSL. Detailed
arrangements will be notified later.
Granular material bedding and backfilling of trenches with imported materials shall be in
accordance with the specifications and details shown on the drawings. A combination of
pneumatic compactors, plate compactors and drum rollers will be used for compaction, in
layers not exceeding 200mm.
119 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
4) Foundation Work
The basic concept for the foundation work is taken from the recommendations given in the
geotechnical investigation report, provided with tender documents. Taking into account the
geotechnical investigation carried out on the proposed sites and on the assumption that sound
rock could be encountered at average depth of 5m below ground, no piling is required. A
granular material sub-base cushion will be placed and compacted below the foundation.
Ground water is anticipated at 1 – 2m below and lowering the water level under foundation will
be carried out with drainage pipe and a pump sump system or well points if necessary. The
drain pipes will collect ground water and take it to a pumping shaft outside the structure.
In cases where the remaining ground water affects the foundation works, perforated drain pipe
in near horizontal filter layer below the base, will be installed.
120 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The majority of concrete placed will be carried out using mobile concrete pump, crane &
skips, chutes or tremmies. Compacting will be done using concrete vibrating pokers of a
suitable diameter. Additional equipment for successful placement and compaction of
concrete will be sourced as necessary. Curing will be carried out using water and the
structures will be covered in jute/hessian sacking or similar, keeping the fresh concrete
wet. Concrete testing will be in accordance with the specifications.
Some per-cast item such as manhole rings, cover slabs etc.., will be sourced from locally
reputed manufacturers, while a small per-cast yard will also be established adjacent to the
batching plant site, for all small and special types of per-cast items. (Concrete interceptor
units for house connections, being one such special item)
The on-site batching plant will manufacture all the concrete required for the sewerage
project.
iii. Reinforcement
Reinforcement will be stored in accordance with the manufacturer’s recommendations and
shall comply with the standard technical specifications. Correct installation and layout of
reinforcement shall be maintained by the use of cement mortar spacer blocks and/or
plastic spacers.
The Oxidation Ditch is the biggest structure in this Wastewater Treatment Plant Project. For
this project, it requires four (4) units of oxidation ditches with each having internal
measurements of 76 meters in length, 12.30 meters in width and with a depth of 5.70 meters.
With its huge volume of construction work, this can be considered as one of the critical
scopes of the project.
121 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Based on the Hydraulic Profile, the wastewater will be coming out from outlet chamber of the
Distribution Chamber at a Mean Water Level (MWL) +472.994 with a high of HWL +473.291
and a low of LWL +472.900. In the Oxidation Ditch, the water level will be maintained at a
Mean Water Level (MWL) 472.972 with a high of HWL +473.057 and a low of LWL +472.900.
These level have been referenced to the design Finish Ground Level of +473.00 based on
the maximum protection level (to protect the facilities from flood) of +472.40 MSL.
Considering the projected depth of excavation of about 5 meters and the existing soil
conditions to be generally soft soil, extreme care must be taken in the excavation works with
necessary protections and suitable work sequence.
1) Site Clearing
Appropriate equipment such as excavators will be used for clearing the site area. Big
trees will be cut manually, after receiving required approvals. Cut trees will be handed
over to relevant authorities as per the request of Water Board. Temporary access road
will be constructed to facilitate to take the machineries inside the site. All rubbished and
top soil will be removed from site to the pre-approved designated dumping yard.
3) Excavation Works
Excavations will be done using mechanical excavators.
Excavated material which will not be suitable for back filling works will be removed from
site. Dump trucks and tractors will be used to transport the unsuitable materials to
dumping areas.
Minor excavation such as trench excavation and vertical slope excavations shall be done
manually. All the excavations shall be done according to the lines and levels indicated in
drawings. Special attention will be paid to avoid the over excavation.
122 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
4) Screed Concrete
Grade – 15 concrete that shall be produced and transported to site by truck mixers and
placed as screed concrete.
Reinforcements will be placed and tied as per the reinforcing steel bars drawings.
Cover blocks will be placed to maintain the required cover and necessary box outs will be
kept as detailed in drawing to place pipes etc. After receiving approval for reinforcing
steel bars fixing, concreting will be commenced.
Grade – 35A ready mix concrete produced at batching plant will be used for all the
concreting works. Skilled workers will place the concrete by the help of skip bucket hang
on crane or alternatively pumped in place using adequate concrete pumping equipment.
Concrete will be handled in such a way to avoid segregation of material inside the
concrete during transporting, placing and compacting.
Construction joints will be cleaned for loose particles and dust and approved bonding
agent will be applied.
123 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
7) Man Power
9) Quality Control
(2) Construction Materials - All the construction materials will be unloaded to site
after checking by our staff.
124 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
(4) Concrete
Slump and temperature of each truck load will be checked before placing. Test
cubes will be cast as per the requirements of specifications. Skip buckets or
pumping will be used to place concrete and it will avoid segregation of material
inside the concrete. Special attention will be paid not to create cold joints
during concreting. Concrete vibrators will be used to compact the concrete
and skilled operators will operate vibrators.
Curing will be done for at least 7 days after placing the concrete. Continuously
wetted gunny bags will be used for curing. Soundness of all the machines
and equipment will be checked by Mechanical Foreman before starting
concreting. All the workers will be instructed to maintain the quality.
125 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Another critical scope of the project is the Sedimentation Tank. This circular structure is designed
to be of 23 meters diameter and tank depth of 7.20 meters at its center.
To be constructed adjacent to the Oxidation Ditches, the excavation could be as much as 8 meters.
And with its bottom slab designed to be sloping to its center, construction has to be strictly checked
considering required levels.
The wastewater supply pipe from the oxidation ditch will be entering to its bottom. Water level is to
be maintaining a Mean Water Level (MWL) at +472.469 with a high level of HWL +472.481 and a
low level of LWL +472.450.
2) Steel Reinforcement
After receiving the approvals for the bar schedules or shop drawings, bar bending will be
started according to approved bar schedules. Polyethylene sheet of 6 mils of gauge 600
will be laid over the screed concrete as damp proofer. Fixing of reinforcements will be
commenced according to the reinforcing steel bar drawings by skilled workers under the
supervision of a Bar Bending Foreman and Supervisor.
3) Base Concreting
Grade 35 A ready mix concrete, which will be produced at the batching plant will be used
for base concreting. Two truck mixers will be used for transporting concrete and ‘U’
shaped chutes and skip buckets hanged on cranes or alternatively adequate concrete
pumping equipment will be used for placing of concrete.
126 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Before mixing of concrete starts, Mechanical Foreman will inspect the soundness of
batching plant, track mixers and vibrators. Batching Plant Supervisor will check the
moisture content and other parameters of aggregates.
Carpentry Foreman will check the formwork while Bar Bending Foreman checks
reinforcement. All the equipment that will be used to transport and place concrete will be
cleaned thoroughly.
Slump and temperature of each load of Ready Mix Concrete Truck load will be checked
before placing and test cubes will be cast as per the requirement of the Water Board and
the Consultant.
Base slab of Sedimentation Tank will be divided into an appropriate number of parts for
concreting.
All vertical walls of the tank will be cast monolithically with base slab.
Thereafter, concreting will be done as group wise for, say six individual days. Special
care will be taken to avoid segregation of aggregates during placing and concrete will be
discharged completely from mixer and mixer will be cleaned before it is recharged. The
elapsed time between mixing and placing will be kept to a minimum and concreting will be
done methodically to avoid the cold joints.
In construction joints, dirt, dust and loose particle of previously done concrete will be
removed by using chisels, drills and compressor. Approved bonding agent will be
applied on construction joints before starting the next portion of the base.
If the temperature of concrete increases above 32C0 while pouring, then iced water will be
used for concrete mixing and aggregate stocks will be kept in cover to prevent the
absorption of heat.
127 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
When concreting the walls and center column, openings will be kept where the locations
of pipes are indicated in drawings. These openings will be covered by approved non
–shrink grout after placing pipes.
Construction joints of previous concrete will be cleaned and loose concrete particles will
be removed. Approved bonding agent will be applied before concreting next lift. Curing
will be done by covering continuous wetted gunny bags on walls and columns.
a. Project Engineer - 01
b. Engineering Assistant - 01
c. Concrete Foreman - 01
e. Carpentry Foreman - 01
g. Laboratory Technician - 01
h. Equipment Mechanic - 01
128 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
i. Site Electrician - 01
j. Skilled Workers - 04
k. Unskilled Workers/Labors - 14
7) Equipment Schedule
e. Concrete Vibrators
2” - 02 Nos.
i. ½ “ - 02 Nos.
f. Generator Set 60 KVA - 01 Nos.
The Main Pumping Station (MPS) will consist of a collection sump and provision for 4 units’ sewer
pumps that will be installed approximately 10meters below the ground level. The facilities required for
the operation of the MPS are overhead crane, coarse screens, fine screens, grit removal facility
including grit classifier and grit pumps, dewatering pumps, access stairs, ventilators, and odor removal
facility that will be designed to suit the requirements.
This structure will be designed for severe exposure conditions and the construction materials will be
selected to ensure durability conditions.
The construction of the MPS is critical considering depth of excavation about 7 meters for which its
rear portion is adjacent to a creek. The required excavation protections will be provided and containing
the perimeter with construction of retaining wall will be made priority.
129 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
1) Method of Excavation
a.) The first step is to secure the rear portion adjacent to the creek by providing
excavation protection. Dewatering operation all through the excavation work shall be
commissioned to keep the excavation pit free of water.
b.) Wall excavation protection shall continue simultaneously with the excavation
procedure.
c.) Supports will be secured and a strict monitoring of soil movements around the site
shall be checked.
d.) Using mechanical excavator, the lower portion the pit will be excavated up to bottom of
the base slab. It will followed by manual excavation to trim the pit to its desired level
and dimensions.
e.) Then a screed or lean concrete of 50mm thick is placed at the bottom of the pit.
Dewatering provisions for pumping of water will still continue until the total basement
walls have been raised.
130 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
a. The excavation protection walls are designed to resist the loads due to ground water
and earth pressure as well as the loads acting from the super-structure.
b. The base slab will be designed to resist the vertical loads acting on the base and the
up lift pressures.
c. The cross beams, slabs and ring beams will be designed to withstand the loads
acting on them from secant pile walls and vertical dead and imposed loads as per
BS 6399.
d. The concrete will be grade 35 and grade 35A. Grade 35A concrete will be
produced to suit the specifications given for the concrete, for example, the maximum
cement content will be 400 kg/m 3 and max. Water/Cement ratio will be 0.50. The
slump of the concrete will be set to suit a mix which can be pumped or equal to
180mm.
e. Minimum cover to reinforcement will be 50mm for structures below the ground and
25mm for the members above the ground.
f. The type of steel will be in accordance with BS 4449. High yield steel with
minimum yield strength of 460 N/m2 will be used.
131 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
5) Wet Well
The wet well will be located below ground level and is sized to provide adequate storage of
sewage between pump starts.
Wet well sizes are calculated based on the minimum cycle time of pumps is 10 minutes or
6 starts per hour for peak flow condition. The area of the wet well is sized to adequately
accommodate all the pumps on duty and on standby as per the manufacturer
requirements.
The pumping station is designed to minimize the need for operator entry to confined
spaces. Therefore, gantry cranes are provided to allow convenient removal of pumps
should they require servicing. However, should there be a need to access the wet well,
aluminum ladders located on the ground floor will provide access to the wet well from the
ground level.
In the unlikely event of a total station failure, a by-pass pipeline will direct excess sewage
to a nearby creek to prevent flooding of the pumping station control room and surrounding
residential dwellings. The overflow pipe inlet will be equipped with a check valve and
insect screen and located below the critical basement elevation of surrounding properties.
However, back-up and alarm systems are integrated into the design to minimize the
chance of total failure.
6) Pumps
Wet well Submersible pumps were selected for the pumping station because they require
small installation footprint, no cooling requirement and reduced overall construction costs.
The numbers of duty pumps have been sized to meet a peak flow condition at a total
dynamic head. An additional identical pump (minimum 50% of duty pumps) is to be
made available as standby in the event that one (1) pump fails or is taken out of service.
During normal operating conditions, it is expected that only one or two duty pumps will be
required. During peak flow conditions, other duty pumps will run in parallel to meet peak
flow.
132 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
7) Station Piping
The station piping and force main header will use steel pipes as required by the employee.
Gate valves will be provided to control the flow of sewage from the pumps and check
valves will be used to prevent backflow in each pipe header. Air release valves will also
be installed to remove entrapped air and a surge relief valve will provide adequate
buffering against pressure surges by draining sewage back into the wet well if gauge
pressure exceeds a threshold units.
8) Inlet Screening
A manually cleaned coarse bar screen will be installed at the inlet channel sewer entering
the wet well of pumping station. A portable trash receptacle at grade will be used remove
accumulated solids. The equipment will be fabricated from stainless steel and the bar
spacing will be approximately 50mm dictated by the passage size of the duty pumps.
For Getambe pumping station, 2 manual bar (coarse) screens (50mm), two electrically
driven fine screens (10mm), vortex type grit trap with grit classifier will be installed for each
of the 2 trains of wastewater entering. All the above equipment will be fabricated in
stainless steel.
The Effluent Line will be constructed along the Access Road coming from the treatment plant. It is also
on this road that the Force Main Influent Line will be constructed going to the treatment plant.
Considering this, work programming will be the main concern so as to avoid or limit construction
constraints due to movability and access.
From the treatment plant going to the outfall structure area, level reference will be set up. Since the
effluent line is a gravity line, level is highly critical. A level check during construction is important.
The work involves 825 meters of pipeline. The use of sheet piles for excavation protection is planned.
This is considering that for gravity lines excavation gets deeper as it extends. A micro-tunneling is also
planned crossing the road junction. From Katugastota Road going to the Outfall Structure is a rather
steep slope. A drop manhole is initially designed to address this concern.
133 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The Outfall Structure will be constructed along the river bank of Mahaweli River. The structure, a
reinforced concrete, will be protected with gabions to its sides to avoid damage and river bank
scouring.
The existing access road to be used during the construction of the treatment is also the same road
where the Force Main Influent Line and Gravity Effluent Line will be constructed. In connection to this
work programming will be the essential aspect for the Access Road construction.
In the General Work Program, the construction of treatment plant will be started ahead of the influent
and effluent pipelines. During this period the maintenance of the Access Road will be observed and
implemented.
After the completion of the pipeline works running through this Access Road, the road will be restored
and improved.
The sludge drying bed facility is to be located in Gohagoda next to the sanitary landfill site. The
construction is planned to provide five (5) sludge drying beds. Dewatered sludge cake from the
treatment plant shall be delivered to this facility by 10-ton dump trucks and will be dried before final
disposal.
Main concern for construction is the access to site due to narrow existing road. Heavy equipment for
site area clearing and leveling will pass here including dump trucks that will be used to dispose of
surplus materials. This access road will be subject for development or widening where necessary and
for maintenance. Site clearing and leveling would be a major scope of work to include a general area
clearing covering more than 4,000.00 square meters and a soil cut and fill for about 6,000.00 cubic
meters of soil.
The facility is designed to accommodate truck movements for easy maneuverability in the unloading of
sludge cakes to the drying beds as well loading of dried sludge for disposal. This internal road network
is to aid in developing a fully functional facility.
134 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The drying beds shall be a monolithic reinforced concrete slab. Knee walls 1.2m high will be provided
to avoid spillage. A transparent roofing is to be used and with full open sides to promote drying.
Filtrate from these drying beds will be collected to a sump/manhole for which will be emptied using
vacuum tanker to be brought to the treatment plant.
Development works will be providing storm drainage system directed to an outfall in the river bank of
Mahaweli River and perimeter fence and area lighting for security.
Potential impacts of construction activities on the environment (construction dust, odor, noise,
sediment and any potential contaminated soil) must be mitigated throughout the implementation period.
The best construction management practices will be followed to minimize the adverse effects on the
surrounding environment. The following controls will be implemented to provide monitoring
throughout the construction phase.
The mitigation measures to prevent environmental degradation due to construction activities will be
adopted as indicated in the following table and the measures identified during the construction will be
adopted. The Construction Environmental Mitigation Plan (CEMP) will be prepared on mobilization to
cover all the aspect for approval of the NWSDB before commencing any of the works.
Prior approval will be necessary for certain work items to be implemented. These procedures will be
agreed upon the initial planning phase of the construction activities.
Such Environmental Aspects and its corresponding Mitigating Measures are as follows:
135 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Traffic warning signs and construction speed limits will set around construction areas,
trained personnel will be used to control access to work sites and where lane closures are
required;
Equipment and Materials storage to occur on existing cleared land or land which will be
occupied by proposed works and which will therefore be cleared to permit construction.
This is to include construction of Wastewater Treatment Plant, Main Pump Station and
Adequate notification will be given to affected residences or businesses at least four weeks
prior to construction, identifying the anticipated length of the disruption, specific impacts to
individual properties and the strategy for providing alternative arrangements for such
properties;
Dedicated parking and / or alternative access will be provided to clubs and services;
Coordination to consolidate the transport of equipment and materials to sites that would be
required for construction of pipelines and pumping stations in the event that these occur
Where required, temporary access to properties over trenches will be provided by use of
Trained construction staff to control access and exist movements of construction machinery
If lane closures along pipe line routes .are required at some locations, stop/go traffic
controls to be provided;
2) Land Use
The NWSDB is required to provide all the possession of site with the approvals from the
UDA, CEA, and LA for the pipe laying sites from MPS.
Construction team will investigate the most suitable mechanism to achieve long-term
136 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
NWSDB is requested to provide a surveyed description of the land required for the site in
RDA roads,
Steering Committee of the project will to be consulted at all relevant phases of project
NWSDB or its Project Director to liaise with landholders well in advance of construction
required;
Construction at force main will be undertaken outside peak holiday periods, if possible;
At least four weeks notification will be given to affected residences or businesses prior to
construction;
Provision of alternative access ways and detours to be made around construction areas
Noise monitoring to be carried out during the earthworks stage to ensure compliance with
Structures are not to be located closer than 20meters to the nearest residence;
Earthmoving equipment to be fitted with high efficiency mufflers and noise suppression kits;
Where vibratory rollers are used they must be no closer than 12m from dwellings and a
137 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The total number of vehicles and plant operating at any one location and at any one time
will be minimized;
4.00pm Mondays to Friday, and 8.00 am to 1.00pm Saturdays, when within 100meters of
any residence;
Residents within 300meters of any construction work will be advised of impending activity
Noise Consultant appointed by the contractor to assess whether allowable noise levels are
In the event that noise complaints are received from nearby land users, each complaint to
be investigated and where noise emissions are established as exceeding the set limits,
Where potential vibration impacts exist, construction contractors are to monitor ground
vibration close to the nearest residence until satisfactory vibration levels, have been
demonstrated.
4) Air Quality
Dust Control Plan to be included within the Construction EMP. This is to include measures
to control dust from construction (for example, water sprays, ceasing work in high wind
Use of water sprays during hot, dry windy days to manage dust from construction. Spray to
be applied to exposed surfaces or potentially dust generating areas, for example, unsealed
construction;
138 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Soil exposure to be limited by vegetation clearance and confining work areas to as small an
area as possible;
Access to site to be controlled and all machinery kept to designated tracks whenever
possible;
A designated hardstand area to be provided, where possible, for parking and emergency
appropriate facilities;
Run-off generated outside of the work area to be diverted around the construction site;
Run-off generated internally to be intercepted and treated through the use of sediment
Topsoil and leaf litter on areas to be disturbed to be collected prior to any construction
mulching or hydro-mulching;
Discrete layers of soil material to be stockpiled separately for sequential replacement after
materials. Silt barriers to be provided around all stockpiles to prevent the loss of material;
Any noxious weeds to be removed by specialist bush generators prior to construction works
commencing;
139 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Working areas in the vicinity of wetlands and banks of creeks and waterways to be
6) Water Issues
Storm water flows to be diverted around construction sites;
Erosion control devices to be installed before site stripping commences and regularly
construction;
Containment basins, pump-out etc. to be used to contain slurries used for thrust boring and
The time that soil is exposed to be minimized and other mitigatory measures identified for
in areas away from receiving waters and bounded to contain any spills;
Any in-stream works are to be referred to KMC and LA for comment should be done three
Water quality protection measures, such as use of silt curtains and scheduling of
construction works during low flow periods, to be implemented for open-trenched waterway
crossings;
140 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The effective design and construction of temporary catch ponds to contain run-off and allow
sedimentation of waters on sites where construction may occur for four weeks or longer;
Suitable material removed from site to be returned to the site during final landscaping;
Grassed swales to be used along all drainage lines at construction sites and excess soil
sites transport form and along pipeline routes to reduce run-off velocities and collect
sediment.
Diversion structures to be provided upslope of the construction sites to divert water running
Re-vegetating or hydro mulching of any steep slopes to be carried out as soon as possible
following construction;
Storm water to be pumped out and tinkered from site and disposed of appropriately where it
cannot be demonstrated that it can meet acceptable criteria for pollutants of concern (for
example, suspended solids, BOD5, fecal coli forms, phosphorus and nitrogen).
7) Ground Water
Ground water encountered or produced during excavation will be diverted appropriately so
that the capacity of the drainage paths is not obstructed. Sedimentation will be done as
the storm water system or tinkered from site and disposed of appropriately.
8) Visual Impacts
Measures to minimize visual impacts and improve the aesthetics of scheme infrastructure
are to be assessed and adopted in detailed design for the proposed scheme;
residences;
141 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
Access to public use areas to be provided around construction sites where possible;
water retention methods, as identified in the Erosion and Sedimentation Control Plans;
around structures and surrounds to improve the visual character of the area.
persons in control of the workplace must ensure adherence to all Occupational Health and
storm water drainage system. If appropriate levels cannot be obtained, such waters to be
advise four weeks in advance of the timing, location and potential impacts of the pipeline
possible;
disruption to land users along the pipeline routes and at pumping station sites;
Works to be scheduled such that, as far as possible, they do not coincide with major holiday
142 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
A community inquiry hotline to be established and the existing NWSDB customer contact
Careful facility design, site management and public education to be implemented for
10.4.1. General
Commissioning test period follows right after the pre-commissioning test and has two (2) major
activities, the wet run test and startup. The objective of Commissioning is to prove that the treatment
facilities will operate as designed.
Standard Operating Procedures will be developed to ensure continued facility operation. The
Contractor will keep commissioning test records and forward copies to the Engineer immediately on
request. As Operation and Maintenance manual will be modified in accordance with actual operation
condition experienced during commissioning, all copies of the records will be incorporated in the
Operation and Maintenance Manual to be submitted to the Engineer.
The Contractor will make available all necessary certified instruments, gauges or any other equipment
necessary for checking the installation.
During the course of the test, the Employer, the Engineer and his representatives will have full access
for inspecting the progress of works and checking the accuracy as may be required. The Contractor’s
commissioning team, including contract vendors for equipment and instrument, will have full
coordination with the Employer, the Engineer and his representatives.
The party specifically entrusted with the task of carrying out the test varies with the particular form of
condition of contract involved. These specified persons not limited to the Contractor’s party contract
143 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
obligation must be in coordination for the whole duration of commissioning test. These include: (1) the
Contractor’s commissioning team as the main/general contractor including Engineers,
electro-mechanical and instrument technicians, and (2) the Contractor’s contracted vendors for
equipment and instrument.
The Contractor and his contracted vendors for equipment and instrument will carry out the entire
preliminary tests accordingly and both parties should agree upon the principal issues pertaining to the
contract. This will be disclosed in submitted methodology by the Contractor to the Employer before the
commissioning test to be implemented, namely:
7) Identifies the particular of the testers, the recorder of the results/readings, relevant personnel,
and the interpretations of the results/readings;
8) Any other relevant matter or detail.
All necessary tests will be carried out and actual commissioning test will be started only once defect
has been eliminated. The Contractor will issue a letter to the Employer upon successful preliminary
test and once the plant is ready on the actual commissioning test performing the two (2) major
activities.
144 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
The Contractor and his vendors for equipment and instruments will be responsible for the operation
and maintenance of the treatment plant during the required commissioning period during the wet run
test and startup activities. The Contractor’s commissioning team together with his operators and
maintenance technicians and equipment and instrument vendors will perform the operation and
monitoring of the treatment process based on the prepared draft of Standard Operating Procedures.
The Contractor’s commissioning team will demonstrate efficient operation and maintenance of the
wastewater treatment plant during the commissioning period in compliance with the project
performance standards subject to following tasks:
The objective of the services proposed hereof is Operation& Maintenance Works in accordance with
Bid requirement. The Contractor will assign 6 staffs including the Plant Manager who works for the
Contractor as representative at site, and the Plant Manager will stay at site during work time for
operation management. Under the Plant Manager, Operation Group and Maintenance Group will be
organized and total 8 operators (3 shift 4 teams) and staffs will be assigned at site.
The Maintenance Group will implement regular and routing servicing, maintenance services and
inspections. Operations and Maintenance Program will be submitted later.
145 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
10.5.2 Spare Parts and Special Tools for Operation and Maintenance
1) Spare Parts
Anticipated spare parts list will be submitted later.
This list is for 5 years of Operation & Maintenance.
146 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
2) Special Tools
The Contractor provides special tools listed below preliminarily.
No. Item Capacity Size Qty.
1 Mobile floor crane manual type Capacity 200kg 1unit
2 Hand Truck (trolley) Capacity 200kg 1unit
3 Tool Cabinet Capacity 15kg 1set
4 Grease Gun 85cc 1set
5 Water hose reel 30m 1set
6 Wire Brush 50mm 1set
7 Safety Goggle - 3 sets
8 Sound Level Meter 130dB 1set
9 Volt-ampere tester AC/DC - 1set
10 Electrical Code reel 30m 1set
11 Mechanical Tool Set 1set
1) Tool Box - 1set
Double ended open jaw
2) 20 to 36mm 1box
wrenches
3) Combination wrenches 16 to 28mm 1set
4) Double ended ring 24 to 36mm 1set
5) Hexagonal socket screw 1.5 to 12mm 1set
6) Socket set 10 to 34mm 1set
7) Rubber hammer 2 Ibs 1set
8) Universal Pliers 1set
9) Cutting Pliers 1set
10) Locking Pliers-Chain Clamp 1set
11) Wire Stripper 1set
12) Electronic Pliers 1set
13) Pipe Wrench 1set
14) Adjustable Wrench 1set
15) Screw Driver Plus 1set
16) Screw Driver Minus 1set
17) Hexagon key set 1set
18) Hacksaw 1set
19) Tapes 5m length 1set
147 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
1) Classroom Training
The Classroom Training period will be for 5 work days over a one week period. These sessions will
cover the treatment facility as the main area and also cover inlet gates and other controlled devices
on the interceptor delivering wastewater to the treatment plant. The topics to be taught are as
follows;
148 / 149
JFE Engineering Corporation National Water Supply and Drainage Board
Contractor Employer Engineer’s Representative
Method Statement
2) On-the-Job Training
On-the-Job training (hereinafter called OJT) will be conducted for the whole trial operation period.
OJT will be for 24 hours per day for the duration. During OJT, the Contractor will operate the
facilities in the presence of the long-term operations personnel as provided by the Employer. At the
end of this period, the long term operations personnel are able to take operation tasks under the
Contractor’s observations.
The OJT will proceed without undue interruption. Minor interruptions which are attended promptly
by the Contractor will be acceptable. In the case of major interruption the period of OJT will be
extended to make up for the loss in time due to rectification work at no additional cost to the
Employer.
Before end of the Operation & Maintenance period, the Exit Test shall be carried out by the
Contractor. The Exit Test shall be conducted same as the Performance Test.
The Employer and the Contractor will select an independent, technically qualified engineering or
consulting firm to conduct a complete plant audit for the purpose of determining the condition of
each and every part of the Facilities. An estimated cost for repair, renewal or replacement, even if it
is judged to be deficient in upkeep and maintenance, shall be borne by the Employer except the
cost of items which affect the performance of the functional guarantee.
149 / 149