Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1. Cast in-situ Bored Pile of Large diameters by track mounted rotary rigs. Bored cast-in-situ concrete
piles are constructed by auguring, drilling, placing reinforcement and then pouring concrete into the
hole. These are structural piles which are constructed for the purpose of carrying the load of buildings.
Contiguous Bored Piles are closely spaced bored piles that are used to build a retaining wall, when we
construct a deep basement or a tunnel. Usually the contiguous bored piles are constructed adjacent &
touching each other piles.
These are constructed with intersections in one pile on another(Primary & Secondary) and using
alternative piles along the line of the wall leaving a clear space in between for embankment
stabilization.
It is important to carry out toe-grouting for large diameter(1500mmand above) piles to increase the
load bearing capacity significantly.
4. Installation of Plunge-in- Columns for top down construction (King Post installation)
When it comes to the top down construction where we have to construct downwards towards the
basement, we need to install plunge-in columns. We at D.P Jayasinghe Pillars complete the task easily
with the man force and the technology we have.
Shoring has to be done where excavation is more than 1.5m or if the soil is loose and collapsing.
Hacking shall be conducted in a fast and latest method to hand over to the clent.
The Static Load Test is conducted on the pile in discrete increments and checking the resulting pile
movement. This method is normally considered as one the most suitable and reliable, methods
though its time consuming in the process of determining the carrying capacity of a certain pile.
This test is most commonly used for pile testing to predict the static soil resistance and the settlement
behaviour. It is widely believed that the further developed analytical models of the pile interaction
can provide prediction of the load/ settlement performance of the tested pile.
When a pile or a shaft is cracked, damaged, necked, bulged or contains voids, The Pile Integrity
Testing is carried out to check it for further testings or repairing.
Through the CSL Test, the soundness of the pile is tested within the drilled shaft. Usually before the
rebar cage is placed in the hole, it is the CSL access tubes that are attached to the interior of the rebar
cage, which is later, used for CSL testing.
Inconveniences
Noise and vibrations are generated when the casing is driven in and extracted from the ground by the
vibro-hammer. Noise is also generated during the augering process. We will therefore try our best to
schedule the work such that it creates minimal disruption to the public.