Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Supplier Supplier
Part Number: OdM:
Code: Name:
Part Supplier
MY: Vehicle: SQE:
Description: Plant:
PROCESS VERIFICATION (VP) PRE-SERIES (PS) RELEASE TO PROD.(DaP) CURRENT PRODUCTION
Material Req. Date: Material Req. Date: Material Req. Date: Material Req. Date:
PROCESS AUDIT Full Approval
Planning
Build Date / Avail.: Build Date / Avail.: Build Date / Avail.: Build Date / Avail.: READINESS EVALUATION
2 - PROCESS
1 - PART DESIGN 3 - PROCESS CONTROL 4 - PROCESS CONTROL 5 - OPERATIONS 6 - LOGISTICS 7 - VERIFICATION 8 - QUALITY SYSTEMS 9 - FULL APPROVAL
DEVELOPMENT
A
0 0 0 0 0 0 0 0
DA DA DA DA DA DA DA DA DA
Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue
B
0 0 0 0 0 0 0 0
DA DA DA DA DA DA DA DA DA
Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue
Design Model & Release Process FMEA Error & Mistake Proofing Safety & Report Characteristics
Rework & Repair Packaging SQE Audit Lessons Learned Planning of Matchability / Benestare
C
0 0 0 0 0 0 0 0
DA DA DA DA DA DA DA DA DA
Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue
D
0 0 0 0 0 0 0 0
DA DA DA DA DA DA DA DA DA
Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue
DA
0
DA
0
DA
0
DA
0
DA
0
DA
0
DA
0
DA
0 0
Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue Open
Open Issue
Issue
NA - Not Applicable 2 - JOB STOPPER 5 - Implemented SCORING OPEN ISSUE & = Documents
1 - JOB STOPPER Risk 3 - Moderate Risk 4 - Low Risk Activity DEFINITIONS
SCORING
CONTACT LIST OBSERVATION
OPEN ISSUE &
Acceptable
NV - Not Evaluated CONTACT LIST DA
DEFINITIONS OBSERVATION
The drawing / design model shall have all required information for the part,
including but not limited to:
- engineering/technical standards, specifications, and norms (plus any Review the design release date. Ensure it is consistent
deviations from those requirements); with temporary tool availability and with the program Verify the Supplier has the latest design model. Ensure Verify the Supplier has the latest design
- Geometric Dimensioning & Tolerancing (GD&T) / dimensional requirements; * Drawing / Design Model Initial design concept Prior to TKO timing. Ensure the latest mathematics are available the latest mathematics are available and are consistent model. Ensure the latest mathematics are
available and are consistent with the latest
- engineering Build Objectives or Table of Tolerances/Profiles; and are consistent with the latest release. Review the with the latest release. Verify the design status of all release. Verify the final released drawing
- identified special characteristics; proposed datum schemes and ensure they are sub-components. meets all requirements for closure.
- a list of sub-components (with part number, revision, and quantity). consistent with vehicle/part mating points.
Datum schemes shall be agreed upon by the applicable FCA representative and
be consistent with part mating/attachment points.
NV
* Engineering Standards Supplier Distribution
The Supplier shall have access to all FCA standards, through the applicable FCA (ESSD) - NAFTA
systems. The Supplier shall have a procedure that requires regular reviews to * BeStandard (ORANGE) - EMEA / LATAM
ensure they have the most recent released versions of the standards, and
requires communication to their various departments in the event of a revision *customer
Procedure for review of
standards Systemic Review for concurrence to the Requirements
update. If Supplier internal specifications or standards are referenced (e.g., on
the design model, on sub-component drawings, etc.), those standards must be
Design Model & clearly linked to the applicable FCA standard or specification.
1C Release
Verify the Engineer concurs with the latest released Verify the Engineer concurs with the latest released
design. For NAFTA, review the engineering Design design. For NAFTA, review the engineering Design
Acceptance document with the FCA Engineer at Step 2, Acceptance document with the FCA Engineer at Step 2, Ensure all open issues relating to design
Supplier-responsible designs shall be approved by the FCA Engineer prior to * Approved design Step 2 (Vehicle) Step 5 (Vehicle) Step 3, and Step 5 (or MR1, MR2, and PRC for Step 3, and Step 5 (or MR1, MR2, and PRC for and DAC, for NAFTA) are closed and the
release. For NAFTA, the Design Acceptance Checklist (DAC) is required to be * Design Acceptance Checklist MR1 (Powertrain) PRC (Powertrain) Powertrain). Ensure corrective actions or risk Powertrain). Ensure corrective actions or risk FCA Engineer has approved the latest
completed by Steps 2, 3, and 5. (DAC) - NAFTA mitigation activities are in place for any open issues. mitigation activities are in place for any open issues.
Issues that receive a score of 1 (Job Stopper) or 2 (Job Issues that receive a score of 1 (Job Stopper) or 2 (Job design release.
Stopper Risk) should have corrective actions in place Stopper Risk) should have corrective actions in place
before proceeding with Tooling Kickof. before proceeding with Tooling Kickof.
For all fastener joints, the Supplier shall have a defined torque strategy in
place. For M6 and above, the Supplier shall develop a torque plus angle Review torque and angle strategy for all fastener joints, Review latest design model against the torque and
strategy unless explicitly told otherwise by an FCA Engineering representative. Verify torque and angle requirements are
The torque plus angle strategy shall include error or mistake proofing such as * Torque Strategy Technical Review Prior to TKO as required. Review planned error and mistake
proofing. angle strategy. being met on all fastener joints.
lock out features in the event the torque and angle requirements are not met,
etc.
The drawing or design model shall reflect the change level and revision level of Verify Supplier has the latest release. Ensure that as Verify Supplier has the latest release. Ensure that as
the part(s) undergoing the Process Audit. All applicable quality documents * Drawing / Design Model changes occur, appropriate modifications are made to changes occur, appropriate modifications are made to Verify Supplier has the latest release and
(including, but not limited to, the Process Flow Chart, D/PFMEA, Control Plan, * All applicable quality On-going program timing and other deliverables, as required. program timing and other deliverables, as required. that it matches the part undergoing
and all Instructions) shall also reflect the correct change level and revision documents Also verify appropriate risk mitigation activities are Also verify appropriate risk mitigation activities are PA/PDR. Verify all risk mitigation activities
planned when deliverables become late to their planned when deliverables become late to their have been successfully closed.
level. required milestones. required milestones.
The Supplier shall have a procedure for proper change management, including:
- receipt of FCA approval (Change Notice or OdM);
Change - notification to the Customer of any risk or impact on timing, program
1E Management milestones, tooling, or resources;
- updates of all applicable quality documents;
- removal of uncontrolled or out-of-date documents; * Change Management
- quarantine/disposition/obsolescence of out-of-date material (product procedure
produced prior to the engineering change); Systemic Review procedure for concurrence to requirements.
* Authorized engineering
- record or log of the first production shipment and retention of that data for change
traceability; documents
- and communication of changes to all applicable sub-tier suppliers. It is the
Tier 1 Supplier's responsibility to ensure the finished part is at the correct
change and revision level. NOTE: The Supplier shall not make any changes
without DOCUMENTED approval from FCA Engineering (i.e. voicemail, e-mail,
etc. are UNACCEPTABLE).
The Supplier shall have access to the eSupplierConnect portal and support all
required FCA systems (e.g., MaPS, CQMS, SQP, NCT, eCIMS, etc.). They shall
have at least 2 fully trained individuals able to access each system. Contact Systemic Verify Supplier has appropriate resources and access to Customer systems.
information shall be current and updated.
A work station layout or manufacturing floor plan shall be available that details
the following: operation to operation flow, all manufacturing / inspection * Work station layout / Process Audit Process Review work station layout and manufacturing floor Review work station layout and manufacturing floor Verify actual plant and process layout
equipment and tooling used in the process, identified material storage manufacturing floor plan Technical Review Evaluation plan. plan. match the documentation.
locations (for WIP / bufers, nonconforming material / scrap, rework / repair,
and raw material / sub-components).
* Potential Failure Mode & Efects Analysis
manual (4th Edition) AIAG
Initial review of PFMEA. Ensure it was developed taking * ISO/TS-16949 7.3.3.2
into account the Master PFMEA and lessons learned Ensure PFMEA has been updated to latest * Supplier PFMEA Audit Summary form
A Process Failure Mode & Efects Analysis (PFMEA) shall be available for all * Process FMEA from previous programs and action plans exist for design revision level. Review using FIAT * FCA Norm 00271 - EMEA / LATAM
parts. It shall be created using all Customer guidelines and required FMEA * Supplier PFMEA Audit Technical Review Prior to TKO items with the highest risk. Verify items with a Severity Review PFMEA as changes occur to design. Ensure norm 00271 to verify document is
reference manuals. The PFMEA shall be reviewed by the SQE and rated adherence to FIAT norm 00271. acceptable. Verify PFMEA has been
"Green" per the "Supplier PFMEA Audit Summary" form. Summary greater than or equal to 8 (or per FCA requirements, if updated to account for most recent version
more stringent) are adequately error-proofed or of Master PFMEA.
actions are taken to minimize the severity via design.
The Supplier shall have a complete list of all dies/tooling, equipment, and Verify that FCA tooling & equipment (complete or Verify that FCA tooling & equipment (complete or
gages used in the process. This list shall indicate ownership of the tooling, under construction) is consistent with that which was under construction) is consistent with that which was
unique identification numbers, and location of the item. The SQE shall verify determined needed during the sourcing phase. Any determined needed during the sourcing phase. Any
the presence of all tooling (including number of cavities), equipment, and * Supplier Tool Record Issuance of the OTOP modifications (e.g., more tools required, some tools modifications (e.g., more tools required, some tools Verify completed tooling matches FCA
gages identified on the list. Tooling and equipment, when not in use, shall be * List of Tooling and Equipment Contract not needed/built, etc.) with respect to which was not needed/built, etc.) with respect to which was records and Supplier's tooling list.
properly identified and stored to avoid confusion in the flow management of declared during sourcing shall be promptly reported to declared during sourcing shall be promptly reported to
components/products being manufactured. There shall be a Supplier Tool the Buyer. Review the Supplier's plan / procedure for the Buyer. Review the Supplier's plan / procedure for
Record which lists all FCA-owned tooling, with tooling number and location. release of tools and equipment to the production floor. release of tools and equipment to the production floor.
FCA-owned tooling, equipment, and gages shall be identified and marked per
FCA requirements. It shall be used only for the production of FCA products. Tooling Kick-Of Process Audit Process N/A Review requirements for Customer tools with the Verify tools are marked per FGP norm 24.
Tools shall meet the requirements in FGP procedure 24. Evaluation Supplier to ensure they understand.
Sub-Component
2E Development Review preliminary Supply Chain diagram for potential
The Supplier shall have available a Supply Chain diagram. The diagram shall
outline the entire Supply Chain, beginning with raw materials and ending with supply concerns (e.g., long distances, multiple border
the FCA or FCA-designated facility. All secondary processes and/or services * Supply Chain diagram PPR Kick-Of Process Audit Process crossings, etc.). If potential supply issues or risks (e.g., Update Supply Chain diagram and back-up plans / risk Verify final Supply Chain diagram.
Evaluation long distance) exist, ensure that appropriate risk mitigation activities as necessary.
(e.g. plating, heat treating, etc.) shall be shown, including of-site storage and
shipping locations. mitigation activities are in place (e.g., safety stock,
expediting, etc.)
For sub-tier suppliers and sub-components, the supply of sub-components Review preliminary Supply Chain diagram for potential
shall be ensured through backup plans; e.g., safety stock, alternate supply concerns (e.g., long distances, multiple border
transportation, availability of alternate PPAP approved sub-components, etc. Process Audit Process crossings, etc.). If potential supply issues or risks (e.g., Update Supply Chain diagram and back-up plans / risk Verify back-up plans for critical
NOTE: switching sub-tier suppliers requires notification and approval from FCA * Sub-component backup plans PPR Kick-Of Evaluation long distance) exist, ensure that appropriate risk mitigation activities as necessary. components.
(via
A appropriate
Control system
Plan shall or process,
be available for such as the
all parts. Forever
It shall Requirements)
be created using allatFCA
all mitigation activities are in place (e.g., safety stock,
times.
guidelines and the AIAG APQP & Control Plan manual. The SQE shall review the expediting, etc.)
content of the Control Plan and determine acceptability. The Control Plan
shall: * Advanced Product Quality Planning & Control
- include all process stages, from incoming to labelling and shipping; Plan manual (2nd Edition)
- use the Process FMEA in creation of the Control Plan, with emphasis placed * FCA norm 9.01102 - EMEA / LATAM
Regularly review the status and content of the * ISO/TS-16949 7.5.1.1
on special characteristics; Supplier's Control Plan, both for Prototype (if
- ensure numbers and controls match PFMEA and Process Flow Chart; * ISO/TS-16949 App. A
applicable) and Production processes. Verify the Review all phases of the control plan. Ensure it is
- include all special characteristics and corresponding classifications and
symbols; * Control Plan After source selection Process Audit Process linkage between the Process Flow Diagram, PFMEA, updated as changes occur to the part or process, and Verify Control Plan meets all requirements.
- ensure characteristic classification is compliant with the technical Evaluation and Control Plan. Ensure controls are adequate and as changes occur to the Process Flow Chart and
match those described in the Design and Process PFMEA.
specifications and/or preventive analysis performed on the product when FMEAs. Verify that the Control Plan is updated to the
requested (FMEA, DOE, etc.); latest design revision level.
- include all applicable process control parameters;
- include suitable frequencies and sampling sizes;
- be updated to the latest CID/EWO/ODM level;
- ensure updating of the control methods/conditions with the evolution of the
referring documents (e.g., DFMEA, PFMEA, Family PFMEA, etc.); * Advanced Product Quality Planning & Control
The SQEevidence
- show shall verify
thatthat
it isthe Supplier
a “living” is following
document the controls
subject as review.
to regular listed in the Review the Control Plan against the actual Plan manual (2nd Edition)
Control Plan, and that frequency, sample sizes, measurement methods, * Control Plan process. For NAFTA, make sure the Control * FCA norm 9.01102 - EMEA / LATAM
Process Audit Process Audit Process N/A Verify the Supplier is incorporating controls into the * ISO/TS-16949 7.5.1.1
equipment recording, reaction plans, etc. are adequate. For NAFTA, the * Control Plan Process Audit Plan is "Green" per the Control Plan
3A Control Plan Control Plan shall be "Green" per the "Control Plan Process Audit Checklist" Checklist - NAFTA
Readiness Evaluation Evaluation process as it is developed.
Process Audit document. Ensure resources * ISO/TS-16949 App. A
form. dedicated to the controls are adequate.
When inspections are done "per lot", lot size shall not exceed one shift or one
production run, whichever is smaller. This includes incoming inspections on * Control Plan Systemic N/A N/A Verify that any inspections done "per lot"
sub-components, as well as in-process inspections and inspections on final do not exceed one shift or production run.
assemblies.
Ensure Supplier plans for rework / repair parts to go Ensure Supplier plans for rework / repair parts to go Verify rework/repair parts do go through
Repair/rework parts shall pass through controls equal to or exceeding those of Process Audit Process
the primary production line. * Control Plan After source selection Evaluation through controls equivalent to or better than the through controls equivalent to or better than the controls equivalent to or better than the
primary line. primary line. primary line.
* Advanced Product Quality Planning & Control
Plan manual (2nd Edition)
* FCA norm 9.01102 - EMEA / LATAM
The Supplier shall have a plan for Incoming Material Certification / Inspection * ISO/TS-16949 7.5.1.1
for all purchased components and raw materials. Sub-tier suppliers may be * ISO/TS-16949 App. A
placed on Self-Qualification (i.e., "dock-to-stock") if they have quality system Review the Supplier's plan for certification of incoming Verify that all Self-Qualified sub-tier
certification (e.g., ISO/TS-16949, ISO 9001), have acceptable quality
performance, and an approved Process Audit and PDR for that component * Incoming Inspection Plan and outgoing material. Review list of sub-tier suppliers suppliers have Process Audit approved
(see Sub-tier Approval); the Tier 1 Supplier shall have records of all of these (Control Plan) After source selection Process Audit Process who are planned to have Self-Qualification status; Review and update plans for Self-Qualified and non- components and acceptable quality
* Incoming Inspection Results Evaluation verify they have acceptable quality performance and qualified sub-tier suppliers. performance. Verify Tier 1 Supplier is
items. When it is necessary to purchase from non-qualified or unapproved * Self-Qualification procedures appropriate Process Audit activities are planned. following the inspection plan for non-
sub-tier suppliers, efective controls, using an adequate sampling plan, shall be Review plans for non-qualified sub-tier suppliers. qualified sub-tier supplier components.
exercised both in the Incoming Inspection area and the manufacturing process
to prevent/block the use of nonconforming parts or raw material. Inspection
results and records shall be available for review by the customer at all times.
All Verification samples shall be clearly marked, labeled, and controlled to Prior to Process Audit Process Audit Process Ensure adequate storage and handling of Verification Ensure adequate storage and handling of Verification Verify all Verification Samples are properly
prevent mixing with production materials. They shall be stored separate from identified and stored to prevent accidental
WIP or finished product in a clearly marked container or designated area. Readiness Evaluation Evaluation Samples is planned. Samples is planned. mixing with production parts.
Line or station lock out shall be implemented at all process steps to prevent During the Error and Mistake Proofing
failed operations from proceeding to a subsequent station or into finished Review the Error and Mistake Proofing process and Verification Audit, ensure line and station
product. Audible and visual indicators shall notify of the failed operation. plan. Ensure Supplier has planned appropriate lock-outs, as well as audible and visual
Corrective actions shall be implemented prior to restarting the line or station. *contingency
Error and Mistake Proofing
/ backup plans Tooling Kick-Of Process Audit Process line/station lock out and audible/visual indicators. Review and update the Error and Mistake Proofing plan indicators, are working correctly each time
The Supplier shall have a contingency plan in the event the production Mistake Evaluation Ensure the Supplier has an adequate back-up plan in as required. a sample is run. This should be a part of
Proofing is not operable. A visual and/or audible alert shall signify the Mistake the event that applicable Error and Mistake Proofing the Supplier's checklist, as well. Verify the
Proofing is inoperable. The plan shall include notification to FCA via the fails Supplier's backup plan is robust and
applicable system. functioning.
Error and Mistake Proofing software shall be tested for all known failures and Prior to Process Audit Process Audit Process Review the Error and Mistake Proofing process and Review and update the Error and Mistake Proofing plan Verify Error and Mistake Proofing software
during the Error and Mistake Proofing
bypass scenarios. Readiness Evaluation Evaluation plan. as required.
Verification Audit.
3rd party sources used for gage and test equipment calibration shall be * ISO/TS-16949 cl. 7.6 - 7.6.3.2, 8.2.4-8.2.4.2
evaluated by the Supplier and be certified to ISO/IEC 17025. Systemic Identify 3rd Parties used for calibrations and verify ISO/IEC 17025 certification. * ISO/IEC 17025
* PPA Manual
* FCA norm 07171 - EMEA / LATAM
The SQE shall review the Supplier's Safe-Launch Plan (SLP), included on the
Control Plan, for ensuring parts meet specifications during the pilot and launch
phases. This includes inspections and controls over and above those of
standard production (e.g., increased frequencies, sample sizes, etc.) for special,
BSR/NVH, and other required characteristics. The SQE shall also review any Review the Supplier's initial SLP. Ensure all special
data collected for SLP prior to the Process Audit and stations or inspection Job 1 + 90 days characteristics are included. Identify whether the
Safe Launch areas used for the activity. Stations or inspection areas used for SLP activities * Safe-Launch Plan Prior to VP (Vehicle) (Vehicle) standard duration will be followed or if it will be Review initial SLP data. Verify the Supplier
3E Activities shall be considered part of the normal process (i.e., included in the Control * Data from previous SLP Prior to Gamma SoP + 90 days extended. Identify if the part/program will follow Review the Safe-Launch Plan and update as necessary. is following the plan for all shipments
Plan), and have adequate lighting (at least equivalent to that used by the shipments (Powertrain) (Powertrain) launch containment (such as Launch Risk Mitigation). through the specified duration.
Customer's CPA inspection area), inspection instructions, boundary samples, Identify method of identification of parts for SLP.
etc. Duration of SLP is Job 1 plus 90 days (new programs) or first shipment plus
90 days (all other situations). If a defect is discovered, the SLP duration shall be
repeated in full. Parts inspected as part of the Safe-Launch activities shall be
identified per the Customer's requirements.
The Supplier shall have a process for creation, approval, and proper storage
and handling of Boundary Samples or Appearance Manual used for inspection.
Approval shall include Plant Perceived Quality (CPA), plus other appropriate
FCA representatives (SQ, Engineering, Corporate Quality, etc.). This process * Boundary Sample / Appearance Systemic Review Suppliers process for Boundary Samples for conformance to requirements.
shall also include periodic review of Boundary Samples (minimum every 3 Manual procedure
months, or as agreed to by FCA) to ensure acceptability. When requested,
copies of Boundary Samples shall be made available to the FCA facility and
Quality personnel.
* PF-SAFETY - NAFTA
* FCA norm 9.01120 - EMEA / LATAM
For parts with Safety/Report characteristics and/or subject to Homologation,
the Supplier shall have a process to identify, develop, and implement controls
on those characteristics (with results recorded and retained per FCA and Review list of expected Safety/Report characteristics,
regulatory requirements). Controls for safety/report characteristics shall be
identified on the Control Plan (and other quality documents), both on the step * Control Plan Technical Review Process Audit Process along with planned controls. Identify any monitored or
controlled by sub-tier suppliers, along with planned Update list and planned controls as needed.
Verify final list of Safety/Report
characteristics along with controls and data
in which the characteristic is generated and in a special annex that summarizes * Safety/Report records Evaluation controls. Review Supplier's record retention to ensure retention.
these controls. Controls performed by Tier 2 (or lower) Suppliers shall also be data is appropriately retained.
identified and maintain the same level of record management. The Supplier
shall meet all FCA requirements regarding Safety / Report characteristics, as
required (NAFTA: PF-SAFETY / EMEA / LATAM: FCA norm 9.01120).
* PF-SAFETY - NAFTA
Nonconformances on Safety/Report characteristics shall be tracked, with * Supplier Notification of Shipment of
immediate containment of all product. Root Cause Analysis and Corrective Nonconforming Parts process - NAFTA
Action procedures shall be implemented immediately following containment. * Corrective Action procedures Systemic Review Nonconformance and Corrective Action procedures to ensure they meet requirements for Safety/Report characteristics. * FCA norm 9.01120 - EMEA / LATAM
The Supplier shall notify FCA (SQE, Plant Quality, etc.) immediately upon
detecting a potential issue on safety parts.
The Supplier shall have a documented First Piece Approval procedure and
instructions which verify proper set-up at each station and that parts made
meet applicable specifications. The procedure shall include:
- part approval by responsible personnel with specific approval instructions;
- analysis of all special characteristics and process parameters (for
conformance, drift, out-of-control conditions, etc.);
- 'OK to produce' given by responsible personnel after verification of Witness the Supplier performing the First
conformity to specifications of the first parts produced with a steady process; *and First Piece Approval procedure Process Audit Process Audit Process Review the Supplier's First Piece Approval process for Piece Approval process during the PDR.
4D First Piece Approval - requirements for First Piece Approval at the beginning of each shift,
instructions
Readiness Evaluation Evaluation conformance to requirements.
Update First Piece Approval process as required. Ensure the entire process is followed, even
* First Piece Approval results if the PDR is shorter than a normal
production run, and following any changes to the production process; production run or shift.
- retention of the First Piece Approval sample until the end of the production
run/shift and verification of the last piece produced at the end of the shift or
production run against the approved First Piece Approval sample;
- retention of the last piece produced at the end of the shift or production run
until verified against the First Piece sample of the next shift or production run;
- documented evidence of First Piece Approval results
4E Special Processes
* CQI-15 Special Process: Welding System
Assessment (AIAG)
4E Special Processes * FCA US LLC Customer-Specific Requirements
for ISO/TS-16949 cl. 4.12.3 - NAFTA
Suppliers with welding operations and processes shall meet all requirements in * FCA welding norms 9.5017#/## - EMEA /
CQI-15 “Special Process: Welding System Assessment”, including conducting LATAM
regular self-assessments and audits. In addition, they shall meet the following: * Applicable Standards, Certifications, and
- All welding technicians, operators, and inspectors shall be trained and licenses (per FCA, ANSI, AWS, UNI EN, etc.)
certified (to all applicable FCA, ANSI, AWS, UNI EN, etc. standards), with re-
training, re-qualification or re-certification as necessary;
- Include all welding cells in the Suppliers LPA Process Control Audit to ensure
conformance to requirements;
- The Supplier shall have objective evidence of a working weld conformance * Welding Assessment and Audit
system for a period of at least one year demonstrating control and corrective procedures and records
action on a daily basis; Verify parts with welding requirements
- All weld audits, assessments, and Control Plans shall include cut and etch as * Welding training plan, Technical Review Process Audit Process Review Supplier's plan for control of parts with welding Review status of plan and update as necessary. have the required controls and those
well as microscopic inspection; certifications, and records Evaluation requirements. controls are followed by the Supplier.
* LPA Process Control Audit
- The Control Plan cut and etch frequency for each weld shall be determined * Control Plan
by the PPA Team and be adequate to ensure that each lot of material has had
welds validated prior to shipment from the facility (i.e., four-wall containment).
This applies at the Supplier’s facility.
Suppliers with other special processes (e.g., heat treating, plating, painting,
etc.) shall have a process in place that includes the following:
- Operator training and certification;
- Inclusion of the process in the Supplier's LPA program;
- Conducting self-assessments to industry standards (as required);
- Process monitoring and data recording requirements.
Work stations, inspection areas, etc. shall have clear operation, set-up,
changeover, First Piece Approval, Mistake Proofing, rework/repair, gage
operation, inspection, and packaging instructions according to the needs and
method of production. Instructions shall be visible and easily accessed by Verify work instructions are followed while
operators, inspectors, and other necessary personnel. During the planning and * Work Instructions: operation, Review and update work instructions as necessary. the Stage 1 PDR occurs. Ask operators,
development of these instructions, special attention shall be given to set-up, changeover, 1st Piece Ensure they are updated to the latest revision level. inspectors, etc. questions to ensure
Process Audit Review temporary or draft work instructions. Ensure
operations where inspections occur, and all special characteristics identified. Approval, Mistake Proofing, Tooling Kick-Of Readiness Evaluation visual techniques are used wherever possible. Ensure appropriate Supplier personnel approve final understanding and knowledge. Ensure
Instructions shall be clearly identified regarding their usage (e.g. classification, rework/repair, gage, inspection, work instructions prior to the Readiness Evaluation and work instructions are available to all
colors, pictures / sketches / drawings, etc.) to avoid any possible mistake. packaging release to the manufacturing floor. applicable personnel and they know where
Visual management techniques (e.g. displays, pictures, diagrams, etc.) shall be to locate.
used whenever possible. In cases where the facility workforce is multi-lingual,
visual-based work instructions shall be used in place of multiple, translated
copies.
Set-up and changeover instructions shall include acceptable control limits for
process parameters (e.g. temperature, pressure, etc.) and verification of those
parameters during process set-up and/or re-start. They shall detail all required Verify set-up/changeover instructions are
steps, including of-line activities such as gage management. Control limits Review and update work instructions as necessary.
shall be determined using preliminary process analyses (e.g., assembly FMEA, Ensure they are updated to the latest revision level. followed during initial set-up and at least
DOE, knowledge of successive processes, knowledge of how the product is * Set-up, changeover instructions Tooling Kick-Of Process Audit Review temporary or draft work instructions. Ensure Ensure appropriate Supplier personnel approve final one changeover during the PDR (if
Readiness Evaluation visual techniques are used wherever possible. possible). Ensure the instructions are
used, engineering specifications and standards, etc.) and show evidence of work instructions prior to the Readiness Evaluation and accessible to the set-up/changeover
continual improvement. At a minimum, the Supplier shall analyze process release to the manufacturing floor. personnel and they know where to locate.
parameters that afect close tolerances, fit, function, finish, reliability,
durability, or that afect the successive/final process. NOTE: Ensure control
limits are not confused with tolerances.
The Supplier shall ensure that, as tooling and/or equipment approaches the
predetermined end of life cycle, appropriate actions are taken to ensure Systemic Review Supplier's process for "end-of-life" tooling for robustness and conformity to requirements.
conformity to requirements (e.g. increased inspections, enhanced detection
measures or methodologies).
At the Process Audit, all key personnel needed to ensure that the Supplier’s * Personnel plan for support of Process Audit Process Audit Process Review plan for hiring of key personnel, if necessary. Review and update plan for hiring of key personnel, if Verify personnel needed to satisfy launch
process(es) can meet the required volume at launch shall be hired and fully requirements are available, and review
trained, and a plan shall be in place to support full production volume. production Readiness Evaluation Evaluation necessary. plan for supporting full production volume.
EMEA: the Supplier shall have a Fire Prevention License (or equivalent). * Fire Prevention License Systemic Verify Fire Prevention License, if required.
The Supplier shall have a procedure for material handling and in-process
6A Material Handling material re-stock (e.g., Kan-Ban), including details on how material is tracked
and moved from one process to another. Material storage locations shall be
clearly identified and adequate for process requirements. Pallets, shelves, etc. Witness and verify the Supplier's material
shall be clean and well-maintained. Storage areas shall be sufficiently sized to * Material handling and re-stock Systemic Review the Supplier's plan for material handling and in-process re-stock. Ensure adequate space has been handling and re-stock procedures. Review
contain the material, located in a logical way with respect to process flow, and procedures allocated for the program's components and raw materials. Review the process layout for proper flow. storage locations for adequate protection,
adequate to contain and protect the product with easy access and safe organization, and space.
handling. Handling, transport and containing means (forklifts, pallets, etc.)
shall be efficient and operated under proper safety conditions. The SQE shall
verify that material handling procedures are followed during the Process Audit.
All materials used in the process shall be clearly identified and diferentiated
(set-up parts, rework/repair, scrap, Work in Process (WIP), sub-components,
etc.). Identification labels shall be clearly visible on each container, with lot
number, date, quantity, and part number, at a minimum. WIP shall also be Prior to VP MRD Verify materials used in the process are
identified with operator/supervisor, operation number, number of pieces (Vehicle) Review Supplier's plan for identification of materials at Review and update the plan, as necessary. Review appropriately segregated and
entering/exiting the operation, number of pieces reworked/ repaired, number * Material handling procedures After source selection Prior to Gamma MRD all stages of production. internal and external labeling prior to the first pilot
builds. identified/labeled. Ensure identification
Traceability & Part of pieces scrapped, operation number and shift. Identification shall be clear, (Powertrain) meets minimum requirements as listed.
6B Identification even after the partial use of the lot. Parts used for set-up or inspection
purposes shall be clearly identified and stored in a way that prevents
accidental shipment.
Parts shall be identified per FCA requirements, in a manner consistent with the Prior to VP MRD * PS-4480 - NAFTA
risk of the part/process. Product identification/marking shall be written, in (Vehicle) Review Supplier's plan for part ID. Ensure Supplier * FCA norm 9.01106/02 - EMEA / LATAM
Design completion Review FCA standards for part ID requirements. accounts for FCA ID requirements in the tool or process Review part ID against print and
case of assemblies, on all components of the assembly, if they are available Prior to Gamma MRD prior to kick-of, as applicable. specifications.
loose on the spare parts market. (Powertrain)
There shall be a link between packaging labels (for both internal and external
containers) and the product, lot, packing list, quantity, revision level, sub-
components and other relevant information.
The Supplier shall also send to FCA EMEA plants (including Powertrain and IRF
Poles) AVIEXP/ASN (advance shipment notice) for each physical shipment
(telematic and physical shipment at the same time) according to CGA and Prior to VP MRD Review and update the plan, as necessary. Review
following FCA procedure 71092 rules. After source selection (Vehicle) Review intended packaging labels for internal and internal and external labeling prior to the first pilot Verify labels meet the requirements listed.
Not sending (or sending partial) Aviexp/ASN will result in SQP penalization as Prior to Gamma MRD external containers. builds.
written into FCA procedure 08018. AVIEXP/ASN can be sent via EDI connection (Powertrain)
or Web portal (all information can be found on the FCA Logistic Portal at
https://fiat4suppliers.fiat.com/LOGISTICS)
NOTE: AVIEXP transmission is mandatory. AVIEXP provides FCA plant detailed
information about actual deliveries and facilitates material receiving process.
There shall be a link between packaging labels (for both internal and external containers) and the product, lot, packing list, quantity, revision level,
The Supplier shall specify all containers used in the process, both internally Verify Supplier is following packaging
and externally, in the packaging or work instructions. Specific information shall
include container dimensions, material, pieces per container, weight of Prior to VP MRD instructions. Review shipping/receiving and
container (full and empty), containers per pallet, maximum stacking height, * Packaging instructions Technical Review (Vehicle) Review initial packaging plan. Determine responsibility Review and update packaging plan, as necessary.
Complete packaging instructions. Ensure packaging
storage areas / warehouses and verify
packaged parts are adequately protected.
etc. All packaging and labeling for product being shipped to FCA shall conform Prior to Gamma MRD for packaging containers /racks (FCA or Supplier). availability for pilot builds. Verify that internal containers (i.e., for
to all FCA requirements. During receiving, shipping, and storage operations, (Powertrain) Work-in-Process) are adequate and prevent
environmental conditions shall be such as to protect the integrity of the part
and packaging. damage to parts stored within.
The Supplier shall not use FCA-owned and provided containers for internal N/A Emphasize requirement to Supplier. Emphasize requirement to Supplier. Verify FCA-owned packaging is not being
handling or WIP. used improperly.
In the Shipping Area the SQE shall select finished samples from previously * Control Plan
* Inspection / gage instructions
accepted/approved lots that are ready to be shipped and witness the Supplier * FPSC plan or Strengthened Process Audit Process Evaluation N/A N/A
inspect them per the Control Plan and Safe-Launch activities. Control Plan
Nonconformances found while performing the SQE Audit shall have root cause
analyses performed, and corrective actions approved (by the SQE and Supplier * Corrective Actions Process Audit Process Evaluation N/A N/A
Management) and implemented prior to Process Audit approval.
The SQE shall verify the Supplier's ability to maintain traceability on the
finished product. The Supplier shall demonstrate, on one finished assembly,
the traceability back to the raw materials or applicable sub-tier supplier on one Process Audit Process Evaluation N/A N/A
or more sub-components selected by the SQE.
* Production Part Approval Process manual (4th
Sub-components not considered low risk shall have a Process Audit (or Verify all sub-components have been Edition)
equivalent) and Production Demonstration Run led by the Supplier and * PA/PDR results for M/H risk approved for use. Review PPAP packages of
followed with a Level 3 PPAP submission (or equivalent approval) to the sub-components After source selection Process Audit selected sub-components for conformance
Supplier (see 2E). Sub-components considered low risk shall be submitted with *submissions
Sub-component PPAP Readiness Evaluation See 2E See 2E with requirements. Verify there are no
& samples capacity issues with any sub-components
a Level 1 PPAP (or equivalent) to the Supplier, at a minimum. or raw materials.
The Supplier shall have a Corrective Action procedure. This procedure shall
include:
- training and use of appropriate Problem Solving and Root Cause Analysis
tools (e.g. 3 Legged 5 Why, Critical Thinking, LUA/LUR, etc.);
- use of the appropriate FCA tool/system for documentation (GIMS, eCIMS,
SQP, 8-step/8-D);
- identification and containment of nonconformities including inspection of
parts back to the last 'in-control' or acceptable point (at a minimum);
- development of interim and long-term corrective actions with clear target
dates and escalation procedures when target dates are not met;
- verification of corrective action efectiveness; Review Supplier's Corrective Action procedure and tools used for conformance to requirements. Review and approve corrective actions as they become
- ensuring updates of applicable quality documents (PFMEA, Control Plan, * Corrective Action procedures Systemic necessary.
Work Instructions, etc.);
- ensuring the communication of lessons learned, “best practices,” and known
systemic weaknesses throughout the facility (and all other facilities within the
company);
- assignment of the corrective action to an individual, with target and actual
dates;
- tracking the progress of implementation of corrective actions;
- ensuring communication of quality and manufacturing issues across shifts,
departments, and personnel;
Non-Conformance - management involvement in the reporting of quality issues and tracking and
8A Management & approval of corrective actions.
Corrective Actions
Planning of Self-
9A Qualification Tests
Testing failures shall have root cause analysis, implemented corrective actions, and be fully retested; it is unacceptable to simply replace the failed
Have the reliability targets been identified in the product card? Have they been Process Audit Process Review reliability test plan and ensure all requirements are met.
compared to historical data on similar parts / processes? If yes, has the root * Reliability Plan After source selection
cause of any gaps been included in the DFMEA and PFMEA? Evaluation
P
V
T
e
s
t
s
a
m
p
l
e
s
Review the forecasted delivery date of Integrative Tests
s
Have the samples for Integrative Testing been delivered? If not, has a delivery * Integrative Test Plan After source selection Process Audit Process samples to ensure consistency with the timing of Review and update timing plan for Integrative Tests
Project (taking into account also the lead time of FCA and Verify status of Integrative Test samples. h
date been planned? * Reliability Plan Evaluation reliability. a
Labs). Evaluate the risk of a negative result of
Integrative Tests. l
l
:
-
Suppliers shall have a Craftsmanship Quality Procedure for all components with appearance requirements. This procedure shall include team mem
c
Planning of o
9B Integrative Tests m
e
f
r
o
m
a
P
r
o Supplier shall deliver parts to the FCA Assembly Plant per PQP requirements (typically data on 5 parts, plus 2 fully marked-up samples at eac
The
c
e
Review the plan for obtaining Benestare s
Review the plan for obtaining Benestare approval. Review the plan for obtaining Benestare approval. approval. Ensure the forecasted delivery s
Ensure the forecasted delivery date of samples is Ensure the forecasted delivery date of samples is date of samples is consistent with program
Planning of consistent with program timing (taking into account consistent with program timing (taking into account timing (taking into account the lead time of
A
Have the samples for Matchability and Benestare been delivered? If not, has a the lead time of the Plant Lab / Metrology Center). the lead time of the Plant Lab / Metrology Center). the Plant Lab / Metrology Center). Review
9C Matchability / delivery date been planned?
0 VP Build DaP
Review the plan for matchability submission. Is the Review the plan for matchability submission. Is the the plan for matchability submission. Is the u
Benestare availability of samples consistent with the timing of the availability of samples consistent with the timing of the availability of samples consistent with the d
Project? Ensure that there is a timing "safety factor" in Project? Ensure that there is a timing "safety factor" in timing of the Project? Ensure that there is i
the event of reoccurrence of the tests due to failures. the event of reoccurrence of the tests due to failures. a timing "safety factor" in the event of t
reoccurrence of the tests due to failures.
R
e
* www.mdssystem.com a
* Fiat Cap. 9.01102 – Fiat Cap. 9.01108 - EMEA / d
The Supplier shall have a process for Material/Substance Composition LATAM i
reporting via the International Materials Data System (IMDS), and be registered n
at www.mdsystem.com. This process shall include: e
- reference to all FCA requirements for IMDS; s
- communication with sub-tier suppliers regarding sub-component IMDS data,
and retention of sub-tier documentation; Review the Supplier's plan for management of International Materials Data System (IMDS) submission. Ensure they are registered to www.mdssystem.com, s
- communication to FCA of any changes/updates to IMDS data and retention of * IMDS Process Systemic and that they keep copies and records of their submissions. Verify they have appropriate controls in place to manage sub-tier supplier IMDS submissions
any documentation submitted or received; and are aware whenever a sub-tier supplier makes a change that could require a new submission. E
9D IMDS - ensuring traceability of components before and after a material/substance of v
concern change or elimination; a
- updating the IMDS every time a significant variation of total weight of the l
product (>10%) occurs or a variation of the composition of the product u
(including surface treatments) occurs. a
t
i
o
n
w
i
t
h
a
9D IMDS
All parts undergoing the Process Audit shall have an approved IMDS * www.mdssystem.com
Prior to PPAP / Full Review timing for IMDS submission. Ensure Supplier is * Fiat Cap. 9.01102 – Fiat Cap. 9.01108 - EMEA /
submission. The Supplier is responsible for the IMDS data on their parts, as * IMDS Submission Prior to Pilot Builds Approval Review timing for IMDS submission. beginning to collect required information. Verify IMDS submission is complete.
well as sub-tier supplier data for materials/components. LATAM
BACK TO PPA HIDE UNUSED ROWS SHOW ALL
MATRIX
BACK TO PPA
MATRIX HIDE UNUSED ROWS SHOW ALL
BOX SCORE OPEN ISSUE / OBSERVATION CORRECTIVE ACTION RESPONSIBLE DEPARTMENT OPEN DATE TARGET DATE CLOSED DATE STATUS* COMMENTS
#N/A ###
#N/A ###
#N/A ###
#N/A ###
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
#N/A
Supplier Quality Engineer (Name/Date) Engineer (Name/Date) Supplier Quality Manager (Name/Date)
*Status: 25% Identified problem; 50% Action Plan proposed; 75% Action Plan implemented; 100% Solved issue
Process Planning Review Kick-Off Meeting
Attendees
Name Title / Company Name Title / Company
Executive PPR Kick-Off Meeting
One Page Summary
HEADER
Supplier Name:
Supplier Code:
Model Year / Program:
Part Number(s):
Date of Meeting:
TEAM LIST
Supplier
VP of Quality:
Plant Manager:
Quality Manager:
Program/Project Manager:
Sales Manager:
Other:
Other:
Other:
Name Phone
BACKGROUND INFORMATION
QRA Program Risk:
Current Bid List Score:
TPSL / NBH:
Date of Last PA (if app.):
KGROUND INFORMATION
Initial PPR Score (if app.):
SEA Score (if app.):
TPSL / NBH Trend:
Last PA Score (if app.):
ing?
LITY IMPLEMENTATION
COMMENTS / ACTIONS RESP. / DATE
Name:______________________ Name:_______________________
• Very late to required milestone and will cause other required deliverables to
their required milestone/vehicle launch
• Risk Mitigation Plan does not exist
1 JOB STOPPER • Certain to cause delay in milestone/vehicle launch
• Has resulted in critical build/launch issues and certain to cause critical quali
production (yardholds, PRIs, field campaigns, etc.)
• Total lack of quality system or systemic control
IMPLEMENTED
5 Complete and approved
ACTIVITY
nch
certain to cause critical quality spills in
)
failures
ming
• Has resulted in critical quality spills (yardholds, PRIs, field campaigns, etc.)
• Corrective Action Plan does not exist.
• Results in process producing defective material with no adequate controls in place
• Total lack of quality system or systemic control
• Has resulted in moderate quality spills (NCTs, Bills, etc.) or may result in critical quality
spills in the future
• Corrective Action Plan exists but is not acceptable; needs containment action
• Can result in process producing defective material with inadequate controls in place
• Chronic quality system or systemic control failures
• May result in moderate quality spills in the future not impacting critical / safety
characteristics
• Corrective Action Plan exists and is acceptable
• Can result in process becoming unstable (may need additional controls added)
• Non-chronic quality system or systemic control failures
Contact List
Attended
[Y/N] NAME COMPANY TITLE
Contact List
TELEPHONE MOBILE
NUMBER NUMBER
E-MAIL
Date Revision Number
01-Sep-14 1.0
19-Feb-15 1.1
30-Jun-15 1.2
06-Nov-15 2.0
18-Dec-15 2.1
Revision Description
Initial Release
Revised logo to FCA for all sectors
Revised sector names to regional names
Changed Open Issues to only hide rows that have received a "5"
Deactivated QRA Program Risk for EMEA / LATAM, APAC (EMEA / LATAM sourced), and Powertrain
(EMEA)
1D Special Characteristics: added "FPSC" and Strengthened Control Plan" to list of items critical
characteristics need to be included on
2D Tooling: revised requirements for marking tools for FCA US LLC (metal tags now acceptable)
3E Safe-Launch Activities: Added "(at least equivalent to that used by the Customer's CPA inspection
area)" to the first item; added "Data shall be collected by the Supplier and forwarded to the
Customer SQE and Plant."
4A Process Monitoring: added "When requested, copies of Boundary Samples shall be made
available to the Customer facility and quality personnel." in the 4th item.
Fixed 7B where "pages XX & XXX" in reference column is replaced with "Appendix B"
Updated Open Issues to allow selection of Box (allows more than one issue per box)
Updated "Customer" to "FCA"
1A - Commonized by adding MFA to all regions, and specifying SoR for EMEA/LATAM; added
references; revised QRA add providing Sourcing % for Quality First; changed target for completion to
"Prior to Source Selection"
1B - added requirement for DFMEA development procedure to include benchmarking and updating
for yardholds and field campaigns; changed target to start for second paragraph to "Initial design
concept"
1C - minor revision to second paragraph for clarity; third paragraph updated for commonality and
clarity.
1D - removed "Key Product Characteristics" as a designation (only "special" will be used); clarified
definition of special characteristics; revised to remove Part I/S final document; revised for clarity and
current characteristic classification
1E - added "- notification to the Customer of any risk or impact on timing, program milestones,
tooling, or resources;" and "- record or log of the first production shipment and retention of that
data for traceability;" to second item; clarified approval from FCA Engineering is required to make an
engineering change
2A - revised references; clarified deliverables in first paragraph; added requirement for Supplier to
update tooling status every 2 weeks minimum for "Ongoing PPR Activities"; added requirement to
identify TAG individual, when applicable
2B - combined Process Flow Diagram elements into a specific list
2C - updated PFMEA development procedure to match DFMEA development procedure; changed
EMEA/LATAM suggested completion to "Prior to TKO"; matched EMEA/LATAM requirements to
NAFTA requirements
2D - Added clarification to second paragraph that Readiness and Process Evaluation portions of the
Process Audit are required on production tools and process
2E - Removed "critical" from sub-tiers required to have backup plans; added "or process" to fourth
paragraph
3A - clarified in second paragraph that the Control Plan Process Audit checklist is a NAFTA
requirement; removed requirements for Final Part I/S
3B - clarified that a PDR is also required (besides PA) on sub-tier Suppliers for Sel-Qualification
3D - Added "When required by FCA, gages shall be built to reflect the part in actual vehicle position."
to the first paragraph; added "Determine which gages, if any, need to be built to reflect the part in
vehicle position." to "PPR Kick-Of Meeting Activities" in the first line; rewrote paragraph 4 as a
checklist for clarification; added requirements from fourth paragraph into first paragraph and
deleted fourth
3E - Rewritten to commonize as SLP
4A - changed approvals required for Appearance Manual / Boundary samples to read (paragraph 3):
"Approval shall include Plant Perceived Quality (CPA), plus other appropriate Customer
representatives (SQ, Engineering, Corporate Quality, etc.).;
4B - added requirement to adhere to CQI-8 to first paragraph; added clarification statement to thrid
paragraph that the E/M-proofing audit shall be performed prior to the PDR
4E - added "- ESD production areas separated from other areas of the facility, with climate controls
as necessary;" to first paragraph; added "Suppliers with other special processes (e.g., heat treating,
plating, painting, etc.) shall have a process in place that includes the following:
- Operator training and certification;
- Inclusion of the process in the Supplier's LPA program;
- Conducting self-assessments to industry standards (as required);
- Process monitoring and data recording requirements." to second paragraph
5B - added " based on past history, AQR, MPFMEA, PFMEA, etc." to first bullet of the first paragraph
5C - added "- criteria for determination of what parts shall undergo rework/repair (as opposed to
being scrapped);" to first paragraph
5E - deleted second paragraph regarding ISO 14001 (this is still a requirement, but is out of scope for
PPR or PA); clarified that the Fire Prevention License is EMEA requirement
7B - added reference to performance tab
7D - added definition of 3CPR as NAFTA and CSL as EMEA/LATAM; clarified deviation must be
approved by FCA Engineer; clarified CQMS note in last paragraph applies to NAFTA
8A - added "LUA/LUR" to examples of tools, "with clear target dates and escalation procedures when
target dates are not met", and "Work Instructions" to list of quality documents needing to be
updated; added clarification to second paragraph of Customer responsibility; added GIMS and SQP
to list of systems
8B - added FR to list of quality requirements
8D - added clarification that NAFTA Suppliers must meet AIAG CQI-14
8E - changed reference link for SQP to access via eSupplierConnect.com
9A - added second paragraph regarding reliability to EMEA/LATAM users;
Added Performance Requirements chart
Added tab for Executive PPR Kick-Of form
Made "QRA Program Risk" on Matrix viewable for all regions
Added tab for Sample PPR Kick Of agenda
Sheet
All
All
All
Open Issues
PPA Matrix
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Open Issues
Entire document
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Requirements Worksheet
Performance Requirements
Executive PPR KO
PPA Matrix
Sample PPR KO Agenda