Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Add 0% GST : -
Contract Sum + GST : 298,935.00
SUMMARY
Sub Total Total Amount
219,720.25
8) Add; 0% of GST -
Summary of Breakdowns
A Prepare the existing premix binder course for resurfacing 245 M2 35.00 8,575.00 0% 0% 0% -
including milling and all necessary works
C Prepare and apply one tack coat of approved 245 M2 5.00 1,225.00 0% 0% 0% -
bituminious emulsion spread evenly
E Prepare and apply reflectrised thermoplastic paint for 4 No. 300.00 1,200.00 0% 0% 0% -
straight arrows overall size 500 mm x 1600 mm as
specified all to relevant Authorities aprpoved standard as
per Engineer's Drawing No. AP1134/RD/LO/01
F Ditto for mirror arrows overall size 2000 mm x 2200 mm 1 No. 300.00 300.00 0% 0% 0% -
ditto
2 of 6
PROJECT: EXTERNAL WORKS FOR JATI HOTEL
INTERIM CERTIFICATE OF PAYMENT NO : 6
I Extra over, ditto with 300 mm diameter opening including 20 No. 100.00 2,000.00 0% 0% 0% -
reinforcement at every 6000 mm c/c
J 225 mm Diameter PVC pipe as described scupper drain, 20 No. 100.00 2,000.00 0% 0% 0% -
bedded, jointed and pointed in cement mortar (1:3), laid
in gradients and setting on and including 75 mm mass
concrete surround and all necessary excavations and
formworks at every 6000 mm c/c
A Existing road kerb, road kerb with opening and scupper 18 M 75.00 1,350.00 0% 0% 0% -
drain to be made good, painting, replaced with new or
refurbished where necessary
B Allow for the provision of all necessary permit from the 1 Item 10,000.00 10,000.00 30% 0% 30% 3,000.00
Local Authority including fullfilling all necessary terms
and conditions as imposed by the authorities concerned
Other Works
A Making good and touching up of existing drainage, 92 M 330.00 30,360.00 95% 0% 95% 28,842.00
roadside drain and SGW pipe where necessary as
instructed by SO all to Authority's requirement as per
Engineer's Drawing No. AP1134/RD/LO/01
B Making good, touching up and repainting of existing 62 M 500.00 31,000.00 95% 0% 95% 29,450.00
boundary wall including all necessary works all as
instructed by SO
C Removal of existing grating and replacing with 610mm x 4 No. 1,500.00 6,000.00 50% 0% 50% 3,000.00
450mm heavy duty grating comprising of 20mm
diameter galvanised iron pipe cast into concrete side,
60mm x 60mm x 10mm thick angle bedded in concrete
with fish tail at 300mm centres, 50mm x 10mm thick GI
plate at 40mm centres and 60mmx 10mm thick GI plate
as frame, including all necessary works to receive new
grating and making same level as new premix.
D Allow for cleaning up existing drain from clays, muds, etc 1 Item 5,000.00 5,000.00 50% 0% 50% 2,500.00
and remove all debris to Contractor's own dump prior to
handover of site to the entire satisfaction of the S.O
E Allow for the provision of all necessary permit from the 1 Item 5,000.00 5,000.00 50% 0% 50% 2,500.00
Local Authority including fullfilling all necessary terms
and conditions as imposed by the authorities concerned
Other Works
(i) Removal and reinstall existing hoarding for execution Rate Only M
of works
(ii) Liasion with Authority for handover 1 Item - -
(iii) Prepare As Built Drawing by Licensed Surveyor 1 Item - -
3 of 6
PROJECT: EXTERNAL WORKS FOR JATI HOTEL
INTERIM CERTIFICATE OF PAYMENT NO : 6
Note:
A 150 mm Diameter pipe with overall width 750 mm, 53 M 80.00 4,240.00 95% 0% 95% 4,028.00
starting from ground level, not exceeding 1.50 M deep
C Extra over for 150 mm diameter 2 No 800.00 1,600.00 95% 0% 95% 1,520.00
including extra joints, seal rings and other necessary
fixing
E Approved 150 mm diameter S-bend for crossing box 1 No 7,500.00 7,500.00 95% 0% 95% 7,125.00
culvert drain including excavation, removal and disposal
of excavated material, backfilling, all necessary approved
joint, 45 degree vertical bend, concrete thrust block, air
valve with isolating sluice valve to SYABAS standard
spike guard (where necessary) and all necessary fixing
accessories and works as per Engineer's Drawing No.
AP1134/WR/LO/01 and AP1134/WR/DT/01
A 150 mm Diameter sluice valve 2 No. 3,800.00 7,600.00 95% 0% 95% 7,220.00
B Approved stainless steel meter stand for water meter 1 No 5,000.00 5,000.00 95% 0% 95% 4,750.00
including excavation, removal and disposal of excavated
material, backfilling, all necessary approved joint,
reducer elbows, SS Socket, stopcock/gate valve, meter
coupling , all to SYABAS standard and all necessary
fixing accessories and works as per Engineer's Drawing
No. AP1134/WR/LO/01 and AP1134/WR/DT/01
Sundries
C On completion of installation, sterilize and test the whole 1 Item 5,000.00 5,000.00 95% 0% 95% 4,750.00
works make good defects and leave the whole works in
perfect working order to the entire satisfaction of the
Engineer to the requirement of SYABAS and Local
Authorities
D Allow for the provision of all necessary apparatus for 1 Item 5,000.00 5,000.00 95% 0% 95% 4,750.00
testing as described and cleaning the Water Reticulation
System complete with piping, fittings, specials and valve,
etc. to the requirement of the Local Authorities and make
good all defects and leave in perfect working order to the
satisfaction of the S.O.
E Allow for connection to existing water recticulation (200 1 No. 30,000.00 30,000.00 85% 5% 90% 27,000.00
mm diameter pipe) including all necessary excavation,
4 of 6
PROJECT: EXTERNAL WORKS FOR JATI HOTEL
INTERIM CERTIFICATE OF PAYMENT NO : 6
F Allow for the provision of all necessary permit from the 1 Item 8,000.00 8,000.00 85% 5% 90% 7,200.00
Local Authority for pipe laying work including fulfilling all
necessary terms and conditions as imposed by the
Authorities concerned.
Other Works
5 of 6
PROJECT: EXTERNAL WORKS FOR JATI HOTEL
VARIATION ORDER
VARIATION ORDER
1 V.O NO. 1
Supply general workers for dismantling MS
hoarding, clear scaffolding and debris
2 V.O NO. 2
Hacking existing RC ramp & footing, etc for LS 1 8,500.00 8,500.00 0% - 100% 8,500.00 100% 8,500.00
VCP pipe as per IWK comment.