Cladding Studs
1. Top Chord = 4 Lengths W6 x 15 a. Front Frame L =2.618 x (4 studs x 2)
L= 4.60m x 4sets, use 1L - W6 x 15# L=0.445 m L= 2.618 x 8
= 4 lengths W6 x 15 @ 6m Qty = 29 L= 20.944 m / 6 = 3.49
L = 29 x 0.445 Total = 4L - 50 x 150 x 1.5 mm C-Purlins
2. Web = 1 lengths W6 x 15. L= 12.91m
L = 1.98 m x 4 sets I. Cladding Railing:
= # of 1.98 per 6m = 3pcs. b. Back Frame LC-1.5 x 50 x150 mm
= 2 lengths W6 x 15. L=0.378 m L =8.740 x 5 Rails
Qty = 29 L= 43.70 / 6 = 7.28 --- say, 8
3. Bottom Chord = 4 lengths W6 x 15. L = 29 x 0.378 Total = 8L - 50 x 150 x 1.5mm C-Purlins
L = 4.54 m x 4 sets, use 1L w6 x 15 L= 10.96 m
= 4 lengths W6 x 15. J. Side Roofing Panel: 0.60 mm PPGL
Total = 12.91 + 10.96 =23.87 / 6 = 3.98 --- say 4 Spandek Roofing Panel
Total = 4 + 2 + 4 = 10 lengths W6 x 15 @ 6m = 4 length - 25 x 25 x 3 mm Angle Bar A = Computation by AutoCad
A = 2.22 sq. m
B. PURLINS 4. Horizontal Frame ( L - 25 x 25 x 3 mm)
1.Longitudinal a. Front Frame K. Top Flashing: Plain G.I. Sheet
L= get longest length = 8.69 m L=0.30 m L = 8.740 m
= 8.69 m x 9 (quantity) = 78.21m Qty = 30 L = 8.740 / 2.40
= 13 lengths - 50 x 150 x 1.5 mm C-Purlins = 30 x 0.30 = 9 L = 3.64-----say 4
L = 9 / 6 = 1.50 ----say 2 Total = 4 pcs.
2. Transverse Total = 2L - 25 x 25 x 3mm Angle Bar
L = 3.035 m x 2 (quantity) = 6.07m L. Side Flashing: 0.40 mm Painted
= 1length - 50 x 150 x 1.5 mm C-Purlins D. 12 mm ∅ Deformed RSB Sag Rods @ Plain G.I. Sheet
Spacing = 1.20m L = 3.30 m
Total = 13 + 1 = 14 lengths -50 x 150 x 1.5mm C-Purlins Qty = 8.556 /1.20 = 7.13---say, 8 units L = (3.30 x 2 sides) / 2.40
= 8 x 3.033 m = 24.264 / 6 = 4.04 L = 2.75-----say, 3
C. GUTTER TRAY Total = 5L - 12mm Ø Sag Rod Total = 3 pcs.
1. Main Chord (L - 40 x 40 x 3 mm)
L = 8.556 + 0.225 E. Main Roofing Panel: 0.60 mm M. Gutter : 0.60 mm Painted
L = 8.78 x 4 chords PPGL Spandek Roofing Panel Plain G.I. Sheet
L = 35.12 / 6 = 5.85 A= L x W L = 8.556 m
Total = 6 lengths - 40 x 40 x 3 mm Angle Bar A = 8.556 m x 3.079 m L = 8.556 m / 2.40 m
A= 26.332 sq. m L = 3.565 ------say, 4
2. Vertical Web (L - 25 x 25 x 3 mm) Total = 4 pcs.
a. Front Frame F. Fascia: 0.40 mm Plain
L = 0.40 m Painted G.I. Sheet N.EXTRA SIDE FRAMING
Qty = 8.56 / 0.30 + 1 = 29.53 ---say, 30 L = 8.556 + 0.225 + 0.225 = 9.00m L = use longest length of
L = 30 x 0.40 L = 9.00/ 2.40 3.00 x 3 stacks
L = 12.00 m L= 3.75-----say, 4 L = 3.00 x 3 = 9.00 m
Total = 4 pcs. = 9.00 / 6 = 1.50 ----say 2
b. Back Frame Total = 2L - 50 X 150 X 1.5mm C-Purlins
L = 0.30 m G. Cladding:
Qty = 8.56 / 0.30 + 1 = 29.53 ---say, 30 0.60 mm PPGL Spandek Roofing Panel
L = 30 x 0.30 A=LXW
L = 9.00 m A =8.740 x 2.448
A= 21.40 sq. m
Total = 12 + 9 = 21 / 6= 3.50 ---say, 4
= 4 length - 25 x 25 x 3mm Angle Bar
CANOPY ESTIMATE - MASONRY ADDITIVE
STIFFENER COLUMN
DESCRIPTION LENGTH (m) WIDTH (m) HEIGHT (m) QUANITY AREA (m²) VOLUME (m³)
(FORMWORKS)
2.650 8 23.32 1.27
SC-4 0.40 0.15
2.365 6 15.61 0.85
TOTAL 38.93 2.12
STIFFENER BEAM
DESCRIPTION LENGTH WIDTH HEIGHT QTY AREA(m²) VOLUME
(FORMWORKS)
SB1 1.815 0.15 0.30 2 3.27 0.16
SB2 2.471 0.15 0.30 1 2.22 0.11
SB3 2.335 0.15 0.30 7 14.71 0.74
SB4 1.960 0.15 0.30 1 1.76 0.09
SB5 2.579 0.15 0.30 1 2.32 0.12
TOTAL LENGTH 11.160 TOTAL 24.29 1.21
CHB
DESCRIPTION LENGTH HEIGHT QTY AREA(m²) PCS. (Ax12.5)
WALL 1 1.815 2.350 2 8.53 106.63
WALL 2 2.471 2.350 1 5.81 72.59
WALL 3 2.335 2.350 3 16.46 205.77
WALL 4 2.335 2.065 4 19.29 241.09
WALL 5 2.579 2.065 1 5.33 66.57
TOTAL LENGTH 11.54 TOTAL 55.41 694
REBARS
10mm Ø 12mmØ 16mm Ø kg./m TOTAL
DESCRIPTION
6.00 m 6.00 m 6.00m 9.00m WEIGHT
STIFFENER V-RSB 14 1.5792 198.98
COLUMN (14) TIES 16 0.6162 59.16
STIFFENER L-RSB 12 1.5792 113.70
BEAM STIRRUPS 12 0.6162 44.37
V-RSB 33 0.8883 175.88
CHB
H-RSB 24 0.8883 127.92
TOTAL 28 57 12 14 720.00
SUMMARY
DESCRIPTION VOLUME FORMWORKS AREA OF CHB CHB (pcs) REBARS WEIGHT UNIT
STIFFENER COLUMN 2.12 38.93 10mm Ø 103.52 kg.
STIFFENER BEAM 1.21 24.29 12mm Ø 303.80 kg.
CHB 55.41 694 16mm Ø 312.68 kg.
TOTAL 3.34 63.22 55.41 694 TOTAL 720.0018 kg.
COMPUTATIONS OF REBA
A. STIFFERNER COLUMN
a.
b.
B. STIFFENER BEAM
a.
b.
C. CHB
a.
COMPUTATIONS OF REBARS
C. CHB
VERTICAL BARS (by direct counting)
Length of V-Bar 1 = 2.425m
Quantity of V-Bar 1 = 35pcs.
b. Diagonal Support
Length = 1.07m
Quantity = 61 pcs per side x 2 sides = 122
# of 1.07m bar per 6m L = 5pcs
Order = 122/5 = 25L - 50x50x3mm Angle Bar