Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CE 502 – CE51FC1
REINFORCED CONCRETE DESIGN
Submitted by:
to:
on:
MARCH 2019
Table of Contents
CHAPTER 1: PROJECT INTRODUCTION .......................................................................................................... 5
1.1 Introduction ........................................................................................................................................ 5
1.2 Project Location .................................................................................................................................. 6
1.3 The Client ............................................................................................................................................ 6
1.4 Project Objectives ............................................................................................................................... 6
1.4.1 General Objective ........................................................................................................................ 6
1.4.2 Specific Objective ......................................................................................................................... 6
1.5 Scopes and Limitations ....................................................................................................................... 7
1.5.1 Scopes .......................................................................................................................................... 7
1.5.2 Limitations.................................................................................................................................... 7
1.6 Project Development Plan .................................................................................................................. 7
CHAPTER 2: DESIGN INPUTS ......................................................................................................................... 9
2.1 Description of the Project ................................................................................................................... 9
2.2 Data and Statistics............................................................................................................................. 10
2.3 Input Parameters .............................................................................................................................. 11
2.3.1 Load Definition and Parameters ................................................................................................ 11
2.4 Architectural Plans ............................................................................................................................ 14
2.4.1 Vicinity Map ............................................................................................................................... 14
2.4.2 Site Development Plan ............................................................................................................... 15
2.4.3 Ground Floor Plan ...................................................................................................................... 16
2.4.4 Second Floor Plan....................................................................................................................... 17
2.4.5 Third Floor Plan .......................................................................................................................... 18
2.4.6 Fourth Floor Plan........................................................................................................................ 19
2.4.7 Roof Deck Plan ........................................................................................................................... 20
2.4.8 Left Side Elevation ...................................................................................................................... 21
2.4.9 Front Elevation ........................................................................................................................... 22
2.4.10 Right Side Floor ........................................................................................................................ 23
2.4.11 Rear Elevation .......................................................................................................................... 24
2.2.4 Review of Related Literature ......................................................................................................... 25
2.2.5 Bibliography ................................................................................................................................... 26
CHAPTER 3: DESIGN CONSTRAINTS , TRADE OFFS AND DESIGN STANDARDS ........................................... 27
3.1 Design Constraints ............................................................................................................................ 27
3.1 Design Constraints ............................................................................................................................ 27
3.2 Trade-offs .......................................................................................................................................... 28
3.3 Seismic Force-Resisting System ........................................................................................................ 30
3.4. Raw Designer’s Ranking ................................................................................................................... 30
3.4. Tradeoffs Assessment ...................................................................................................................... 31
3.2.5.1 Economic Assessment ............................................................................................................. 31
3.2.5.2 Constructability Assessment ................................................................................................... 31
3.2.5.3 Sustainability Assessment ....................................................................................................... 31
3.2.5.4 Environmental Assessment ..................................................................................................... 31
3.2.6 Initial Cost Estimate ................................................................................................................... 32
3.5. Design Standards ............................................................................................................................. 37
CHAPTER 4: DESIGN OF STRUCTURE ............................................................................................................. 0
4.1.Design Methodology: .......................................................................................................................... 0
4.2 Framing Plans ...................................................................................................................................... 1
4.3 Geometric Plan.................................................................................................................................... 6
4.5 Validation of Multiple Constraints, Tradeoffs and Standards ............................................................ 2
4.5.1 Final Estimates of Tradeoffs .......................................................... Error! Bookmark not defined.
4.6 Influence of Multiple Constraints, Tradeoffs, and Standards in the Final Design .... Error! Bookmark
not defined.
4.6.1 Computation for Final Designer’s Ranking.................................... Error! Bookmark not defined.
CHAPTER 5: FINAL DESIGN ............................................................................................................................ 8
5.1 Design Schedule .................................................................................................................................. 8
Appendix B: Initial Cost Estimate .............................................................. Error! Bookmark not defined.
Appendix C: Manual Computation of Slab using Moment Coefficient Interpolation Method and excel
program .................................................................................................................................................. 21
COMPUTATION OF TWO-WAY SLAB ....................................................................................................... 21
COMPUTATIONS OF ONE WAY SLAB ...................................................................................................... 76
Appendix D: Design of Beams Computation Using Excel Program ......................................................... 79
Appendix E: Design of Columns Computation Using Excel Program ...................................................... 93
Appendix F: Manual Computation of Load Distribution ........................................................................... 0
Table of Figures
Figure 1-1 Project Perspective .......................................................................................................................... 5
Figure 1-2 Google Earth view of the site location of the proposed 4-storey hospital building © Google
Earth .............................................................................................................................................................. 6
Figure 1-3 Project Delopment Plan ............................................................................................................... 7
Figure 2-1 3D Model of Reinforce Concrete ................................................................................................. 9
Figure 2-2 Population Census of Quezon City © Philippine Statistics Authority ........................................ 10
Figure 4-1. Design Stage Process ..................................................................................................................... 0
Figure 4-2. Second Floor Framing Plan ......................................................................................................... 1
Table of tables
1.1 Introduction
Quezon City is a former capital of the Republic of the Philippines, located in Metro Manila and is considered
as the most populated city in the Philippines having a population of 2,936,116 as of 2015. Being highly
urbanized city means that there are many opportunities for its people leading to the increase of basic need
and building of new infrastructure. An urbanized city means higher birth rate, has a high risk on having health
problems and also the existence of many kinds of accidents due to human error and other considered factors.
The problem there is the need of affordable hospitals for people that can provide complete medical services.
The design project is a 4-storey hospital building in accordance to all design codes and standards having a
dimension of 20 meters by 25 meters with a total floor area of 2000 square meters located at the 15th Avenue,
Cubao, Quezon City.
Figure 1-2 Google Earth view of the site location of the proposed 4-storey hospital building © Google Earth
1.5.1 Scopes
The following are the scopes of the project:
1. Design of a 4-storey hospital building in accordance to the NSCP 2010 for structural loadings and
specifications needed.
2. Structural design and analysis of 3 trade-offs.
3. Cost estimate of materials to be used in the design.
1.5.2 Limitations
The following are the limitations of the project:
1. The project does not include cost estimates for electrical, mechanical, and plumbing works.
2. Electrical, mechanical and plumbing plans will not be provided in the project.
1.6 Project Development Plan
CONCEPTUALIZATION
Formulation of
Constraint
Develop
Gathering Develop
of data
Develop
Proceed to
Result Proceed to
Evaluation
Finalize to
Designer s Decisions
Quezon City is divided into 6 districts with 142 barangays and the location of project is located in district 3
and nearly closed to district 4 with a total population of 324,669 although it is not populated district in
Quezon City compared to others it is still considered populous according to 2015 census.
2.3 Input Parameters
Table 2-2: Dead Loads from Table 204-1 (NSCP 2010 Section 204)
Hospitals are one of the most complex of building types. Each hospital is comprised of a wide range of
services and functional units. That services includes a lot such as diagnostic and treatment functions, such
as clinical laboratories, imaging, emergency rooms, and surgery; hospitality functions, such as food service
and housekeeping; and the fundamental inpatient care or bed-related function.
In addition to the wide range of services that must be accommodated, hospitals must serve and support
many different users and stakeholders. Ideally, the design process incorporates direct input from the owner
and from key hospital staff early on in the process. The designer also has to be an advocate for the
patients, visitors, support staff, volunteers, and suppliers who do not generally have direct input into the
design. Good hospital design integrates functional requirements with the human needs of its varied users.
According to the National Institute of Building Sciences there must be a several ideal forms of an
hospital to be considered based on its functions. These Involves bed-related inpatient functions,
outpatient-related functions, diagnostic and treatment functions, administrative functions, service
functions (food, supply), research and teaching functions.
Building Attributes is one of the things that is needed to be considered due to the big aspect that it can
contribute to the function of an hospital. Every Building should have a common attribute specifically an
hospital in a manner that it analyzes the locations of every functional units as well as considerations of
overall sizes and budget that the structure have.
Wind Loads :
In Every structure especially in an higher part of the elevation there is always existence of wind loads in
which it is a external or actual forces that act on a certain part of the structure in any direction. The
materials that undergoes this forces is usually a rigid part which is a concrete or a steel but notice that that
usual designs of the hospital nowadays usually used a material which is a glass on some part of the front
elevation and also to the sides and can replace a big part of the walls in which this material is also
subjected to undergoes the said external forces such as wind loads.
Wind loads are randomly applied dynamic loads. The intensity of the wind pressure on the surface of a
structure depends on wind velocity, air density, orientation of the structure, area of contact surface, and
shape of the structure. Because of the complexity involved in defining both the dynamic wind load and the
behavior of an indeterminate steel structure when subjected to wind loads, the design criteria adopted by
building codes and standards have been based on the application of an equivalent static wind pressure.
Earthquake Loads :
Designs of recent buildings nowadays involves considerations of seismic loads during an earthquake
conditions especially in the Asian country like Philippines, Japan, and china who is usually subjected to this
kind of load conditions. That’s why in Earthquake Engineering it is crucial to analyze and calculate for the
seismic design force and the seismic base shear for a reinforced concrete building.
The seismic loads on the structure during an earthquake result from inertia forces which were created by
ground accelerations. The magnitude of these loads is a function of the following factors: mass of the
building, the dynamic properties of the building, the intensity, duration, and frequency content of the ground
motion, and soil-structure interaction. In recent years, a lot of achievements have been made to incorporate
these influential factors into building codes accurately as well as practically.
According to the Building design and Civil Engineering the basis for IBC 2000 seismic provisions is the
1997 NEHRP ‘‘Recommended Provisions for the Development of Seismic Regulations for New
Buildings and Other Structures’’ (FEMA 302). The National Earthquake Hazard Reduction Program
(NEHRP) is managed by the Federal Emergency Management Agency (FEMA).
In IBC 2000, the seismic loads are on a strength level limit state rather than on a service load level, which
was used in UBC 94 and prior versions.
2.2.5 Bibliography
https://www.engineeringexamples.net/calculating-seismic-design-force-seismic-base-shear-
reinforced-concrete-building-structure/
https://www.wbdg.org/building-types/health-care-facilities/hospital
http://www.civilengineeringx.com/bdac/earthquake-loads/
CHAPTER 3: DESIGN CONSTRAINTS , TRADE OFFS AND DESIGN STANDARDS
1. Economic Constraints: As for Considering the effectiveness of the cost of the structure based on
the budget of the client for the whole project it came up to a several structural techniques. The trade-
offs were designed to be compared whether which of the discussed several designs trade-off is more
economical. The tradeoffs will be assessed by enumerating and classifying the materials needed for
the structure to be constructed and computing the total costs of the structure. The structural design
which will typify a much more lesser amount of structural cost will be more favorable to use and will
be considered as more economical compared with the other materials and trade-offs to be used.
(Php).
2. Constructability: In designing a structure, time is a big constraint to be considered which may affect
the phase and the deadline of which the project is needed to be accomplished. The tradeoffs to be
considered as a replacement or innovation of the materials in Reinforced concrete to be used, will
be compared whether which of these three methods has the easiest time to construct. The Methods
in for structural design are the Building Frame system, Special Moment-Resisting Frame, Dual Frame
System. It will be evaluated based on the equipment’s and number of Man-days needed for the
materials to be constructed. (Days).
3. Environmental: Having Considered the Economic and Constructability Constraints, the stability and
safety of the structure should also be considered. As it is stated in the related Literature the lateral
loads such as gravity, seismic and wind loads that can occur to the structure should be given an
attention and should be analyzed well in the manner that the structure should withstand these kinds
of loads.
4. Sustainability : The spontaneous calamities brought by the Mother Nature are a great factor in
designing the structure. That is why; the designer has considered it as a constraint on the design of
the structure. In the Philippines, there a lot of different unexpected calamities so, we should consider
the lifespan of the building. The three-design trade-off will be evaluated according to it’s prolong
lifespan. The evaluation will be done by comparing the lifespan of the 3 trade-offs. The structural
design which will exhibit to have a longer lifespan will be proved to be more satisfactory to build.
(Years).
In considering design constraints, trade-offs were provided by the designers that have a significant
effect on the structural design of the hospital building. The designers will have to evaluate whether
what type of materials to be used in constructing the hospital structure considering the economic,
constructability, sustainability and environmental constraints.
Overall the designers will choose which materials have much more well efficiency and lesser cost
that will satisfy the demands and needs of the clients and also for the consumers of this matter.
3.2 Trade-offs
After considering the design constraints, the designer came up with the raw rankings on the
conventional slab and filler slab for roofing. The discussion on how the designer came up with the raw
rankings values are shown and computed below.
Criterion’s
Ability to satisfy the criterion
Importance
(on a scale
Decision Criteria (on a scale from 0 to 10)
of 0 to 10)
Building Frame Special Moment Dual Frame
Design Resistant Frame Design
1. Economic 10 10 9 9
2. Constructability 9 9 8 7
3.Environmental 9 9 8 7
4.Sustainability 10 9 9 10
Over-all Rank 352 324 316
Table 3-1: Raw Designer's Ranking
*Reference: Otto, K. N. and Antonsson, E. K., (1991). Trade-off strategies in engineering design. Research
in Engineering Design, volume 3, number 2, pages 87-104.
Retrieved from http://www.design.caltech.edu/Research/Publications/90e.pdf
3.5. Tradeoffs Assessment
The criterion’s importance is subjective and its value will still depend on the mutual decision of the
client and designer. The Constructability and Labor constraint was given an importance value of
Nine(9),because with the less men work number needed but can be done with the short period of time.. While
both the sustainability and Economic constraints were given an importance value of nine (10) because the
structure, while being cheap, but it is very important to consider on how long can it function without affecting
the environment as much as possible.
3.5.1. Economic Assessment
The designer has calculated the initial cost estimate of the three structural designs based on the
typical cost floor area of the structure to determine which of the three designs is more economical over the
other. It turns out that the structural cost of Building Frame system design is most economical compared with
the initial estimate of the structural cost of Special Moment Resisting frame design and Dual System concrete
design.
3.5.2 Constructability Assessment
Based on the initial estimate of the labor works needed for the construction of the three structural
designs, it seems that it takes more time to construct and transport the Dual system concrete design and
Special Moment Resisting Frame design compared to the Building Frame design. The longer duration for the
Moment Resisting Frame Design and Dual Frame design is mainly because of the difficulty in constructing
the connection. In this case, the Building Frame design becomes a more favorable design with respect to the
constructability of the structure. The initial cost is elaborated in the Appendix B.
As for the sustainability constraint, it’s longevity of the structure is something that we consider for
this kind of constraint based on what we estimated Dual Frame design have a much longer lifespan than the
other two tradeoffs. Based on the Building component life expectancy which is the minimum is 81 years of
concrete frame system, the designers came up to an idea of how long each framing system will be sustainable
through the years. For sustainability Dual System Design will govern.
As for the Environmental constraint, Building Frame System is more reliable in terms of less
number of materials that produces carbon dioxide and waste needed to finish the project, however
SMRF has also a grade of about nearer but less than that of Dual System.
3.5.6 Initial Cost Estimate
In the following table, the designer had provided an initial structural estimate for Reinforced Concrete
Design, Design and Concrete Design. With the aid of this estimate that is elaborated in Appendix B, the
designer was able to identify on which engineering design will govern for All constraint.
Estimates
Constraint Special Moment
Building Frame Design Dual Frame Design
Resistant Frame
Php 1,620,015
Economic (Cost) Php 1,678,133
Php 1 525, 574
Constructability 120 days 127 days 145 days
Sustainability 81 years 86 years 91 years
Table 3-2. Summary of Initial Cost Estimate
1,620,015 − 1,525,574
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
1,620,015
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 =0.58=1
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 = 10 − 1 = 9
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 =9
Economic Constraint: Subordinate Rank of Building Frame System in comparison to SMRF Plotted In a
Rank Line
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 =0.55=1
Constructability Constraint: Subordinate Rank of Building Frame System in comparison to SMRF Plotted In
a Rank Line
Sustainability Constraint: Subordinate Rank of Building Frame System in comparison to SMRF Plotted In a
Rank Line
1,678,133 − 1,525,574
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
1,678,133
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 =0.90=1
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 = 10 − 1 = 9
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 =9
Economic Constraint: Subordinate Rank of Building Frame System in comparison to Dual System Plotted
In a Rank Line
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 =1.72=2
Constructability Constraint: Subordinate Rank of Building Frame System in comparison to Dual System
Plotted In a Rank Line
91 − 81
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
91
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 =1.09=1
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 = 10 − 1 = 9
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟗
Sustainability Constraint: Subordinate Rank of Building Frame System in comparison to Dual System
Plotted In a Rank Line
91 − 86
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
91
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 =0.55=1
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 = 10 − 1 = 9
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟗
Sustainability Constraint: Subordinate Rank of SMRF in comparison to Dual System Plotted In a Rank Line
The designer some come up with the design of the hospital building with accordance to the following
codes and standards:
The sections and codes used were specified in design computations included in the Appendices of
this Paper.
CHAPTER 4: DESIGN OF STRUCTURE
4.1.Design Methodology:
The Figure in the Illustration below shows the design methodology of the proposed hospital building.
The tradeoffs ranking will be validated and the presentation final’s designers ranking will be illustrated.
As for the whole project. Reinforcement
Five-Storey for the concrete was used. The design of the flow of the whole
Apartment Building
project system is also presented in this part.
Geometric Modelling
Material Strength
Material Properties
°Compressive Strength
° Bar Grade
Shear Diagrams
Structural Analysis Moment Diagrams
Deflections
The Validation of the tradeoffs is analyzed by the designers in order to confirm the results of
Designer’s Raw Ranking in Chapter 3. The initial estimates done and presented in the chapter 3 will
be compared to the finals cost estimates and will show the results of the validation and certainty of
the assumptions.
As presented in the Chapter 3 based on the raw designer’s ranking, the drafted tradeoffs (particularly,
the Building frame system, SMRF, and Dual system) were compared through initial estimates. The
one that will govern among all the tradeoffs from the results is Building Frame System.
A comparison of the materials between one-way slab and two-way slab is done to prove the costs
savings. The cost estimate for this comparison is presented on the Appendix B of this paper.
Estimate
Constraint
Building Frame SMRF Dual System
Economic (Cost) ₱ 1,806,671 ₱ 1,363,866 ₱ 1,912,282
Constructability 139 days 120 days 146 days
Sustainability 92 years 81 years 87 years
Table 4-2: Final Estimate
4.6 Influence of Multiple Constraints, Tradeoffs, and Standards in the Final Design
For the design of the framing of the four-storey hospital building the engineering standards is
provided and has guided the designers to design a safe and sustainable design. It is crucial to have
an accurate data so the designers conform with the code and assure that the details they have is
aligned in the standards. Through the multiple constraints considerations, the designers have chosen
what type of design from the systems among the tradeoffs they will use. Solving the problems
regarding the interests of client’s expenses is very crucial and significant, so the trade-offs is very
relevant to the process.
4.6.1 Computation for Final Designer’s Ranking
1,806,671 − 1,363,866
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10 = 2.45 ≈ 2
1,806,671
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 = 10 − 2 = 𝟖
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟖
Economic Constraint: Subordinate Rank of Building Frame System in comparison to SMRF Plotted in a
Rank Line
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 9 − 1 = 𝟖
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟖
Constructability Constraint: Subordinate Rank of Building Frame System in comparison to SMRF Plotted In
a Rank Line
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 10 − 1 = 𝟗
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟗
Sustainability Constraint: Subordinate Rank of Building Frame System in comparison to SMRF Plotted In a
Rank Line
1,912,282 − 1,806,671
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10 = 0.55 ≈ 1
1,912,282
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 = 10 − 1 = 9
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟗
Economic Constraint: Subordinate Rank of Building Frame System in comparison to Dual System Plotted in
a Rank Line
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 9 − 1 = 8
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟖
Constructability Constraint: Subordinate Rank of Building Frame System in comparison to Dual System
Plotted In a Rank Line
92 − 87
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10 = 0.54 ≈ 1
92
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 = 10 − 1 = 𝟗
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟗
Sustainability Constraint: Subordinate Rank of Building Frame System in comparison to Dual System
Plotted in a Rank Line
1,912,282 − 1,363,866
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10 = 2.87 ≈ 3
1,912,282
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 = 10 − 3 = 7
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟕
Sustainability Constraint: Subordinate Rank of SMRF in comparison to Dual System Plotted In a Rank Line
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 9 − 2 = 7
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟕
Constructability Constraint: Subordinate Rank of Building Frame System in comparison to SMRF Plotted in
a Rank Line
Computation of ranking for Sustainability Constraint
87 − 81
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10 = 0.69 ≈ 1
87
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 10 − 1 = 𝟗
𝑺𝑼𝑩𝑶𝑹𝑫𝑰𝑵𝑨𝑻𝑬 𝑹𝑨𝑵𝑲 = 𝟗
Sustainability Constraint: Subordinate Rank of Building Frame System in comparison to SMRF Plotted In a
Rank Line
Criterion’s
Ability to satisfy the criterion
Importance
(on a scale
Decision Criteria (on a scale from 0 to 10)
of 0 to 10)
Special Moment Dual Frame
Building Frame
Resistant Frame Design
1. Economic 10 9 10 8
2. Constructability 9 8 9 7
3.Environmental 9 8 9 7
4.Sustainability 10 10 9 9
Over-all Rank 334 352 296
Table 4-3: Final Designer's Ranking
Based on the Designer’s Final Ranking, the trade-off that will govern is the special moment-reisting
frame system compared to the initial raw designer’s ranking. In terms of economic constraints, it got
the rank of 10, considering that its price cost in the market as well as the volume of concrete to be
used is cheaper than in other two systems. As for constructability and sustainability constraints, the
building frame system emerges in terms of duration of its construction and the longevity and
performance of a structure.
CHAPTER 5: FINAL DESIGN
Tradeoff 1:
COST ESTIMATE - TWO WAY
CONCRETE WORKS-Ground Floor
GRAVE
L b t pc V CEMENT SAND L
Member
s
(m) (m) (m) (m3) (bags) (m) (m)
0.2 0.3
B-1 20 5 5 5 8.75 78.75 4.375 8.75
0.2 0.3
B-2 25 5 5 5 10.9375 98.4375 5.46875 10.9375
C-1 3 0.5 0.5 25 18.75 168.75 9.375 18.75
TOTAL 345.9375 19.21875 38.4375
GRAVE
L1 L2 t pc V CEMENT SAND L
Slab
s
(m) (m) (m) (m3) (bags) (m) (m)
7.3 0.1
S-1 8 5 5 4 22.14 199.26 11.07 22.14
5.1 0.1
S-2 2 5 5 4 15.36 138.24 7.68 15.36
6.2 0.1
S-3 5 5 5 4 18.75 168.75 9.375 18.75
6.2 0.1
S-4 5 5 5 5 23.4375 210.9375 11.71875 23.4375
TOTAL 717.1875 39.84375 79.6875
PRICES
ITEM TOTAL per
pc ITEM LABOR
CEMENT 1063.125 Bags 250 265781.3 106312.5 GRAND
SAND 59.0625 m3 50 2953.125 1181.25 TOTAL
GRAVEL 118.125 m3 800 94500 37800
TOTAL PRICE 363234.4 145293.8 508528.1
COST ESTIMATE - TWO WAY
CONCRETE WORKS- Second Floor
GRAVE
L b T pc V CEMENT SAND L
Member
s
(m) (m) (m) (m3) (bags) (m) (m)
0.2 0.3
B-1 20 5 5 5 8.75 78.75 4.375 8.75
0.2 0.3
B-2 25 5 5 5 10.9375 98.4375 5.46875 10.9375
C-1 3 0.5 0.5 25 18.75 168.75 9.375 18.75
TOTAL 345.9375 19.21875 38.4375
GRAVE
L1 L2 T pc V CEMENT SAND L
Slab
s
(m) (m) (m) (m3) (bags) (m) (m)
7.3 0.1
S-1 8 5 5 4 22.14 199.26 11.07 22.14
5.1 0.1
S-2 2 5 5 4 15.36 138.24 7.68 15.36
6.2 0.1
S-3 5 5 5 4 18.75 168.75 9.375 18.75
6.2 0.1
S-4 5 5 5 5 23.4375 210.9375 11.71875 23.4375
TOTAL 717.1875 39.84375 79.6875
PRICES
ITEM TOTAL per
pc ITEM LABOR
CEMENT 1063.125 Bags 250 265781.3 106312.5 GRAND
SAND 59.0625 m3 50 2953.125 1181.25 TOTAL
GRAVEL 118.125 m3 800 94500 37800
TOTAL PRICE 363234.4 145293.8 508523
PRICES
ITEM TOTAL per
pc ITEM LABOR
CEMENT 1063.125 bags 250 265781.3 106312.5 GRAND
SAND 59.0625 m3 50 2953.125 1181.25 TOTAL
GRAVEL 118.125 m3 800 94500 37800
TOTAL PRICE 363234.4 145293.8 508523
PRICES
ITEM TOTAL per
pc ITEM LABOR
CEMENT 1063.125 bags 250 265781.3 106312.5 GRAND
SAND 59.0625 m3 50 2953.125 1181.25 TOTAL
GRAVEL 118.125 m3 800 94500 37800
TOTAL PRICE 363234.4 145293.8 508523
152557
From Ground Floor to Roof Deck the Estimated Cost is equal to: 4 Php
PRICES
ITEM TOTAL per
pc ITEM LABOR
CEMENT 1128.938 bags 250 282234.4 112893.8 GRAND
SAND 62.71875 m3 50 3135.938 1254.375 TOTAL
GRAVEL 125.4375 m3 800 100350 40140
TOTAL PRICE 385720.3 154288.1 540008.4
162001
From Ground Floor to Roof Deck the Estimated Cost is equal to: 5 Php
PRICES
ITEM TOTAL per
pc ITEM LABOR
CEMENT 1169.438 bags 250 292359.4 116943.8 GRAND
SAND 64.96875 m3 50 3248.438 1299.375 TOTAL
GRAVEL 129.9375 m3 800 103950 41580
TOTAL PRICE 399557.8 159823.1 559380.9
167813
From Ground Floor to Roof Deck the Estimated Cost is equal to: 3 Php
Tradeoff 1: Constructability Initial cost:
Assuming that 500% of Total Volume of Concrete Works is equal to Total Man Days,
Adding 200% For Rebar Works and 350% For
Finishing
Assuming that 500% of Total Volume of Concrete Works is equal to Total Man Days,
Adding 200% For Rebar Works and 350% For
Finishing
Quantit
Members b(mm) t(mm) L(m) y Volume
B-1 350 400 20 5 14
B-2 350 400 25 5 17.5
C-1 500 500 3 25 18.75
t s l
S-1 150 5 7.38 4 22.14
S-2 150 5 5.12 4 15.36
S-3 150 5 6.25 4 18.75
S-4 150 5 6.25 4 18.75
TOTAL VOLUME 125.25
Assuming that 500% of Total Volume of Concrete Works is equal to Total Man Days,
Adding 300% For Rebar Works and 350% For
Finishing
I. DESIGN SPECIFICATIONS
Live Loads
Basic Floor 4.8 Kpa
Total 4.8 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 16.7772 Kpa
Ma. Neg. = Ca. neg. Wla2 (Where w= total uniform dead load plus live load)
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
Ca DL = 0.052329
Cb DL = 0.00803762
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.0617681
Cb LL = 0.01005
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
d. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.918946
Cb./Wb. = 0.080376
ρ = ῳfc’/fy
ρ = (0.062826255)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.003468
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.02211)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.00122046
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
V. DESIGN SPECIFICATIONS
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
Ca DL = 0.0334463
Cb DL = 0.00552738
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.051762
Cb LL = 0.01005
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
h. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.903377
Cb./Wb. = 0.095314
ρ = ῳfc’/fy
ρ = (0.062826255)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0017272
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.01664)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.00091856
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
Ca DL = 0.0334463
Cb DL = 0.00552738
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.051762
Cb LL = 0.01005
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
l. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.903377
Cb./Wb. = 0.095314
ρ = ῳfc’/fy
ρ = (0.062826255)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0017272
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.01664)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.00091856
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
Ca DL = 0.06005
Cb DL = 0.015067
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.0591980
Cb LL = 0.0125602
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
p. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.85776
Cb./Wb. = 0.17083
ρ = ῳfc’/fy
ρ = (0.051093)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0028203
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.02388)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.00132
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
Ca DL = 0.01891
Cb DL = 0.01703
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.03782
Cb LL = 0.02604
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
t. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.52285
Cb./Wb. = 0.47590
ρ = ῳfc’/fy
ρ = (0.018995)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0010485
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.02129)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.001175
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
Ca DL = 0.01891
Cb DL = 0.01703
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.03782
Cb LL = 0.02604
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
x. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.52285
Cb./Wb. = 0.47590
ρ = ῳfc’/fy
ρ = (0.018995)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0010485
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.02129)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.001175
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
Ca DL = 0.02091
Cb DL = 0.02204
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.02937
Cb LL = 0.02855
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
bb. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.35256
Cb./Wb. = 0.64608
ρ = ῳfc’/fy
ρ = (0.02398)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.001324
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.02129)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.001175
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Ma. Neg. = Ca. neg. Wla2 (Where w= total uniform dead load plus live load)
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
dd. Coefficients for Dead Load Positive Moments in Slabs (Using Interpolation)
Ca DL = 0.045
Cb DL = 0.015
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.051
Cb LL = 0.019
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
ff. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.86
Cb./Wb. = 0.14
ρ = ῳfc’/fy
ρ = (0.0401635)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.00221702
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.037121)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.00204907
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
hh. Coefficients for Dead Load Positive Moments in Slabs (Using Interpolation)
Ca DL = 0.026
Cb DL = 0.011
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.041
Cb LL = 0.017
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
jj. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.71
Cb./Wb. = 0.29
XXXV. Ma. Along Short Direction = ma. Pos. Dl + ma. Pos. Ll
Ma. Along Short Direction = 4.92765 KN.m + 1.9475 KN.m
Ma.(Total) = 6.87515 KN. m
Mb. Along Long Direction = Mb. Pos. DL + Mb. Pos. LL
Mb. Along Long Direction = 0.81641 KN.m + 2.96133 KN.m
Mb.(Total) = 3.77774 KN. m
XXXVI. CALCULATE THE SPACING OF BARS
ρ = ῳfc’/fy
ρ = (0.02435)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.001344
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.02129)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.001175
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
ll. Coefficients for Dead Load Positive Moments in Slabs (Using Interpolation)
Ca DL = 0.026
Cb DL = 0.011
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.041
Cb LL = 0.017
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
nn. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.71
Cb./Wb. = 0.29
ρ = ῳfc’/fy
ρ = (0.02435)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.001344
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.02129)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.001175
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
pp. Coefficients for Dead Load Positive Moments in Slabs (Using Interpolation)
Ca DL = 0.032
Cb DL = 0.015
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.044
Cb LL = 0.019
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
rr. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.55
Cb./Wb. = 0.45
ρ = ῳfc’/fy
ρ = (0.02435)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0015988
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.02129)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0013173
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
tt. Coefficients for Dead Load Positive Moments in Slabs (Using Interpolation)
Ca DL = 0.029
Cb DL = 0.010
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.042
Cb LL = 0.017
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
vv. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.83
Cb./Wb. = 0.17
ρ = ῳfc’/fy
ρ = (0.026568)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.001467
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.013029)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0007192
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
xx. Coefficients for Dead Load Positive Moments in Slabs (Using Interpolation)
Ca DL = 0.029
Cb DL = 0.010
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.042
Cb LL = 0.017
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
zz. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.83
Cb./Wb. = 0.17
ρ = ῳfc’/fy
ρ = (0.026568)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.001467
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.013029)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0007192
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
Live Loads
Basic Floor 1.9 Kpa
Total 1.9 Kpa
Total Uniform Load = 1.2 (DL) + 1.6 (LL) ~ Based on 2010 NSCP
Total Uniform Load = 12.1372 Kpa
Mb. Neg. = Cb. neg. Wlb2 (Where w= total uniform dead load plus live load)
bbb. Coefficients for Dead Load Positive Moments in Slabs (Using Interpolation)
Ca DL = 0.039
Cb DL = 0.016
Ma. Pos. DL = Ca. DL. Wla2 (Where w= total uniform dead load)
Mb. Pos. DL = Cb. DL. Wlb2 (Where w= total uniform dead load)
Ca LL = 0.048
Cb LL = 0.020
Ma. Pos. LL = Ca. LL. Wla2 (Where w= total uniform live load)
Mb. Pos. LL = Cb. DL. Wlb2 (Where w= total uniform dead load)
ddd. Ratio of Load w in La and Lb Directions for Shear in Slab and Loads on Supports
Ca./Wa. = 0.71
Cb./Wb. = 0.29
ρ = ῳfc’/fy
ρ = (0.026568)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0019024
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
ρ = ῳfc’/fy
ρ = (0.025196)( 20.7 Mpa)/ (375 Mpa)
ρ = 0.0013908
Checking:
ρmax. = (0.75)(0.85)(fc’)( β)(600)
fy (600 + fy )
ρmax. = 0.018407077
ρmin. = 1.4/fy
ρmin. = 0.003733333
As = ρbd
As= (0.003733333)(1000 mm)(124 mm)
As= 462.933292 mm2
GIVEN DATA
Dead Loads (kPa) f'c 20.7 MPa
Weight
of Slab 3.541 fy 375 MPa
Other
Materials 4.04 L 5.12 m
0 t 150 mm
Total 7.581 b 1000 mm
Live Load (kPa) Φbar 12 mm
Basic
Floor
Area 1.9 Φtie 10 mm
d 114 mm
GIVEN DATA
Dead Loads (kPa) f'c 20.7 MPa
Weight of
Slab 3.541 fy 375 MPa
Other
Materials 4.04 L 6.25 m
0 t 150 mm
Total 7.581 b 1000 mm
Live Load (kPa) Φbar 12 mm
Basic Floor
Area 1.9 Φtie 10 mm
d 114 mm
ρ-max = 0.01598
Design of Beam - 2
Design Parameters
Mu 47.3055 kN-m d' 50 mm
fy 415 Mpa d 300 mm
bar
20.7 20
f'c Mpa dia. mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
ρ-max = 0.01598
Design of Beam – 4
Design Parameters
Mu 39.332 kN-m d' 50 mm
fy 415 Mpa d 300 mm
bar
20.7 20
f'c Mpa dia. mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
ρ-max = 0.01598
Design of Beam - 6
Design Parameters
Mu 67.33 kN-m d' 50 mm
fy 415 Mpa d 300 mm
f'c 20.7 Mpa bar dia. 20 mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
ρ-max = 0.01598
2. Mu > Mu.max
As1 = bd
As1 = 1198.31 mm^2
Mu1 = Mumax
Mu2 = Mu - Mmax
Mu2 = 126.59 KN-m - 108.89464 KN-m
Mu2= 17.6954 KN-m or 17695364.5 N-mm
c= a / β
c= 133.005 mm
F's= 600(c-d')/c
F's= 374.444 Mpa
A's= As2
A's= Use step 5
5. F's < Fy, then use F's (compression steel does not yield)
A's= As2(fy/f's)
A's= 210.034 mm^2
N= As/A
A=π/4(D^2)
A= 314.159 mm^2
Design of Beam - 8
Design Parameters
Mu 193.38 kN-m d' 50 mm
fy 415 Mpa d 300 mm
f'c 20.7 Mpa bar dia. 20 mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
2. Mu > Mu.max
As1 = bd
As1 = 1198.31 mm^2
Mu1 = Mumax
Mu2 = Mu - Mmax
Mu2 = 193.38 KN-m - 108.89464 KN-m
Mu2= 84.4854 KN-m or 84485364.5 N-mm
c= a / β
c= 133.005 mm
F's= 600(c-d')/c
F's= 374.444 Mpa
A's= As2
A's= Use step 5
5. F's < Fy, then use F's (compression steel does not yield)
A's= As2(fy/f's)
A's= 1002.79 mm^2
N= As/A
A=π/4(D^2)
A= 314.159 mm^2
Design of Beam - 9
Design Parameters
Mu 72.4 kN-m d' 50 mm
fy 415 Mpa d 300 mm
f'c 20.7 Mpa bar dia. 20 mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
Design of Beam - 10
Design Parameters
Mu 8.06 kN-m d' 50 mm
fy 415 Mpa d 300 mm
f'c 20.7 Mpa bar dia. 20 mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
Mu is less than Mu.max no need to proceed to step 2, instead, design as Doubly with
minimum 4 bars
Design of Beam - 11
Design Parameters
Mu 116.72 kN-m d' 50 mm
fy 415 Mpa d 300 mm
f'c 20.7 Mpa bar dia. 20 mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
Mu is greater than Mu.max therefore design as Doubly Reinforced Beam and proceed
to step 2
2. Mu > Mu.max
As1 = bd
As1 = 1198.31 mm^2
Mu1 = Mumax
Mu2 = Mu - Mmax
Mu2 = 116.72 KN-m - 108.89464 KN-m
Mu2= 7.82536 KN-m or 7825364.502 N-mm
c= a / β
c= 133.005 mm
F's= 600(c-d')/c
F's= 374.444 Mpa
A's= As2
A's= Use step 5
5. F's < Fy, then use F's (compression steel does not yield)
A's= As2(fy/f's)
A's= 92.8827 mm^2
N= As/A
A=π/4(D^2)
A= 314.159 mm^2
Design of Beam - 12
Design Parameters
Mu 79.49 kN-m d' 50 mm
fy 415 Mpa d 300 mm
f'c 20.7 Mpa bar dia. 20 mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
Design of Beam - 11
Design Parameters
Mu 73.78 kN-m d' 50 mm
fy 415 Mpa d 300 mm
f'c 20.7 Mpa bar dia. 20 mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
Design of Beam - 14
Design Parameters
Mu 44.87 kN-m d' 50 mm
fy 415 Mpa d 300 mm
f'c 20.7 Mpa bar dia. 20 mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
Design of Beams
Design Parameters
Mu 5.413 kN-m d' 50 mm
fy 415 Mpa d 300 mm
f'c 20.7 Mpa bar dia. 20 mm
b 250 mm β 0.85
h 350 mm Ø 0.9
ρ-max = 0.01598
ρ-max = 0.01598
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 446.5963641 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Tension Controls
Therefore
480 mm
use =
SPACING
Design of Column - 2
Design Parameters
P 649.06 kN d 440 mm
My 250 kN-m f'c 20.7 MPa
b 500 mm fy 415 MPa
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 385.1724032 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Tension Controls
Therefore
480 mm
use =
SPACING
Design of Column - 3
Design Parameters
P 574.8852 kN d 440 mm
My 250 kN-m f'c 20.7 MPa
b 500 mm fy 415 MPa
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 434.8694313 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Tension Controls
Therefore
480 mm
use =
SPACING
Design of Column – 4
Design Parameters
P 594.24 kN d 440 mm
My 250 kN-m f'c 20.7 MPa
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 420.7054389 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Tension Controls
Therefore
480 mm
use =
SPACING
Design of Column - 5
Design Parameters
P 133.4 kN d 440 mm
My 250 kN-m f'c 20.7 MPa
b 500 mm fy 415 MPa
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 1874.062969 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Tension Controls
Therefore
480 mm
use =
SPACING
Design Parameters
P 1083 kN d 440 mm
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 230.8402585 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Therefore
480 mm
use =
SPACING
Design of Column – 8
Design Parameters
P 1738.84 kN d 440 mm
My 250 kN-m f'c 20.7 MPa
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 143.7740103 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Therefore
480 mm
use =
SPACING
Design of Column - 9
Design Parameters
P 1528.39 kN d 440 mm
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 163.5708163 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Solving for Spacing of Ties
Therefore
480 mm
use =
SPACING
Design of Column - 10
Design Parameters
P 818.2 kN d 440 mm
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 305.5487656 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Therefore
480 mm
use =
SPACING
Design Parameters
P 1824.28 kN d 440 mm
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
ρg= As/Ag = 0.022519 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 137.0403666 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Therefore
480 mm
use =
SPACING
Design Parameters
P 1681.52 kN d 440 mm
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 148.6750083 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 137.0403666 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Therefore use
480 mm
=
SPACING
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve eb:
eb= 330.5580336 mm
ex=My/P
ex = 265.8895601 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Therefore
480 mm
use =
SPACING
Design of Column - 22
Design Parameters
P 943.4 kN d 440 mm
My 250 kN-m f'c 20.7 MPa
b 500 mm fy 415 MPa
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 264.99894 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Therefore
480 mm
use =
SPACING
Design of Column - 23
Design Parameters
P 869.24 kN d 440 mm
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 287.6075652 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Therefore
480 mm
use =
SPACING
Design of Column - 24
Design Parameters
P 943.44 kN d 440 mm
My 250 kN-m f'c 20.7 MPa
b 500 mm fy 415 MPa
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 264.9877046 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Compression Controls
Therefore
480 mm
use =
SPACING
Design of Column - 25
Design Parameters
P 485.6 kN d 440 mm
My 250 kN-m f'c 20.7 MPa
b 500 mm fy 415 MPa
t 500 mm Φbar 32 mm
d' 60 mm Φtie 10 mm
Find Actual ρg
Ag=b*t --------> 250000 mm²
Pb = 0.85*f'c*a*b
Pb = 1944.984236 kN
Pb*(eb+x) = As(actual)*(d-d')+0.85*f'c*a*b*(d-a/2)
Solve
eb:
eb= 330.5580336 mm
ex=My/P
ex = 514.8270181 mm
ex<eb = compression controls ex>eb = tension controls
REMARKS
Tension Controls
Therefore
480 mm
use =
SPACING
Appendix F: Manual Computation of Load Distribution
Concrete unit weight = 23.6 kN/m3
Cross sectional area of beam = (0.25m)(0.35m) = 0.0875m2
Uniform load (kPa) = 12.1372 kPa
Wbeam = (23.6kN/m3)(0.0875m2)(1.2) = 2.478kN/m
Beam 1
β = Ly/Ls
= 7.38/5 = 1.476
Wu = (Uniform load)(Ls/2)[1 – 1/2β]
= (12.1372 kPa)(5m/2)(1 – ½(1.476)) = 20.06420596 kN/m
W(total) = 2.478 + 20.06420596
= 22.542205 kN/m
Beam 2
Wu = (Uniform load)(Ls/3)
= (12.1372 kPa)(5m/3) = 20.228666667 kN/m
W(total) = 2.478 + 20.228666667
= 22.70666667 kN/m
Beam 3
Wu = (Uniform load)(Ls/3)
= (12.1372 kPa)(5m/3) = 20.228666667 kN/m
W(total) = 2.478 + 20.228666667(2)
= 42.93533332 kN/m
Beam 4
β = Ly/Ls
= 5.12/5 = 1.024
Wu = (Uniform load)(Ls/2)[1 – 1/2β]
= (12.1372 kPa)(5m/2)(1 – ½(1.024)) = 15.52708203 kN/m
W(total) = 2.478 + 15.52708203
= 18.00508203 kN/m
Beam 5
β = Ly/Ls
= 6.25/5 = 1.25
Wu = (Uniform load)(Ls/2)[1 – 1/2β]
= (12.1372 kPa)(5m/2)(1 – ½(1.25)) = 18.2058 kN/m
W(total) = 2.478 + 18.2058
= 20.6838 kN/m
Beam 6
β = Ly/Ls
= 5.12/5 = 1.024
Wu = (Uniform load)(Ls/2)[1 – 1/2β]
= (12.1372 kPa)(5m/2)(1 – ½(1.024)) = 15.52708203 kN/m
W(total) = 2.478 + 15.52708203(2)
= 33.53216412 kN/m
Beam 7
β = Ly/Ls
= 6.25/5 = 1.25
Wu = (Uniform load)(Ls/2)[1 – 1/2β]
= (12.1372 kPa)(5m/2)(1 – ½(1.25)) = 18.2058 kN/m
W(total) = 2.478 + 18.2058(2)
= 38.8896 kN/m
Beam 8
β = Ly/Ls
= 7.38/5 = 1.476
Wu = (Uniform load)(Ls/2)[1 – 1/2β]
= (12.1372 kPa)(5m/2)(1 – ½(1.476)) = 20.06420596 kN/m
W(total) = 2.478 + 20.06420596 (2)
= 42.60641192 kN/m
Beam 9
β = Ly/Ls
= 5.12/5 = 1.024
Wu = (Uniform load)(Ls/2)[1 – 1/2β]
= (12.1372 kPa)(5m/2)(1 – ½(1.024)) = 15.52708203 kN/m
W(total) = 2.478 + 15.52708203 + 15.1715
= 33.176582 kN/m
Beam 10
W(total) = 2.478 + 15.1715
= 17.6495 kN/m
Beam 11
β = Ly/Ls
= 6.25/5 = 1.25
Wu = (Uniform load)(Ls/2)[1 – 1/2β]
= (12.1372 kPa)(5m/2)(1 – ½(1.25)) = 18.2058 kN/m
W(total) = 2.478 + 18.2058 + 15.1715
= 35.8553 kN/m
Beam 12
Wu = (Uniform load)(Ls/3)
= (12.1372 kPa)(5m/3) = 20.228666667 kN/m
W(total) = 2.478 + 20.228666667
= 22.70666667 kN/m
Beam 13
Wu = (Uniform load)(Ls/3)
= (12.1372 kPa)(5m/3) = 20.228666667 kN/m
W(total) = 2.478 + 20.228666667
= 22.70666667 kN/m
Beam 14
W(total) = 2.478 kN/m