Sei sulla pagina 1di 7

BRIDGE ENGINEERING: LAUNCHING TECHNIQUES

Trends and Recent Advancements in Bridge


Launching Techniques

Vivek Abhyankar
Senior Manager (Design)
AFCONS Infrastructure Limited, India

Abstract: In complex Bridge construction projects, selection of As all the branches of engineering started growing, it was
correct method of construction / launching of superstructure observed that the growth was rapid, but not parallel! As far as
plays a vital role, towards overall success of the project. The bridge engineering is concerned this fact resulted into a wide
construction / launching method has a direct impact on cost, gap between imagination (i.e. conceptual planning and design)
time and safety of the project. Inexperienced clients often deploy vs. the ground-reality (i.e. actual bridge erected at sites). The
two separate agencies for (a) design of bridge structure and (b) end results of this gap (rather a knowledge gap) and the solu-
for detailing a launching scheme. As a result the coordination tion to ‘bridge’ this gap is discussed in the further sections.
between actual structure and construction is lost, resulting de-
lays and cost overruns. Launching scheme and actual design Bridge Projects in Olden Days
(supers/sub structure) has a strong linkage with each other; in In olden days computing technology / simulation software
complex bridge projects, the scope of design and construction etc. were not available. Engineers had to struggle hard to prove
method can’t be segregated. the adequacy of the concept, before starting the design and
The recent advancements in bridge launching technology construction.
demand changes in the main design itself. In the present paper
the author has described different method of launching (old and
new), along with various Indian and International cases studies,
and their prerequisites. The methods covered in this paper are :-
- In Situ Bridge Construction :- using Formwork-Staging;
Moving scaffolding system
- Precast, Pre Stressed Bridge Launching :- using Cranes,
Floating crafts, Push Launching, Launching Trusses (Un-
der slung / Over slung type), Launching using Ground sup-
ported staging system, Cable cranes.
Paper covers interrelation between permanent, temporary
structures with hints for engineers. (a) Bridge at Conceptual Design Stage

Introduction

Bridges are the backbones of any Transpiration / Infra-


The Masterbuilder | June 2016 | www.masterbuilder.co.in

structure Project like Railway, Metro or a Road. Bridge Engi-


neering has a history of thousands of years, and finds it’s origin
in Indian Mythology and old spiritual scripts like Ramayana /
Mahabharata etc. In those days bridges were made from hip
of stones / soil bunds / timber logs etc. Olden bridges were
expected to merely act as a beam spanning across a gaps
along river or a road; but as the growth of civilisation started (b) Bridge after completion
taking place, the demand on all the branches of engineering in- Fig. 1: Firth of Forth Bridge, Scotland (A Cantilever Bridge)
creased, rapidly. For Civil Engineering, such increased demand Designed by Allen Stewart and Sir Baker
called for more and more research about structural configu-
ration and materials to be used for construction. From study Fig.1 shows, photograph of ‘Firth of Forth Bridge, Scotland’,
of grow of engineering industry in past hundred years, we may which is a steel cantilever type bridge. It was built in the 1880s
observe that the development of Civil / Structural engineering designed by Allan Stewart and Sir Benjamin Baker. But both
is closely associated with the development of other branches of them had to struggle hard to demonstrate by a Conceptual
of science / engineering like – Material Science, Mathematics, Model (as shown in Fig.1 (a) to the sceptical Victorians that a
Communication, Electronics, Computing technology (computer cantilever bridge would be safe. Fig. 1 (b) shows, bridge after
science), IT etc. actual successful construction.
90
BRIDGE ENGINEERING: LAUNCHING TECHNIQUES

Similar to above bridge, Fig.2 shows another interesting - Changing ‘Codes / Standards’ requirements – QAQC, Crack-
configuration of a Suspension cable bridge done out of India. In width, exposure, non-linearity
this structure the main pylons looks like a posture of a standing
person, reclining backward, with both the arms folded, kept on Advances in associated fields like :-
waist. This bridge and many other similar bridges explain how – Material Science (Concrete-steel-etc.)
human is getting inspired by ‘nature’ and ‘natural behaviour’. – Electronic devices (strain gauges and other monitoring de-
But definitely such bridges are the challenges for the Design vices
and Construction. – Surveying Instruments
- Increasing Project demands :- Time, Cost, Safety, Quality,
Aesthetics
- New research towards :– Bridge execution / Testing
- HSE (health safety and environment) Requirements
- Construction Stage Analysis
- Structural Health monitoring systems
- Life expectancy . . . etc.

(a) Bridge Pier - Conceptual Racking human


(a) Alamillo bridge, Seville Spain (b) Ancient musical
Instrument Harp
Fig. 3: Alamillo bridge, Seville Spain

The Architect / Structural Designer / Planner or Execution


engineer cannot overcome all these problems by working in
isolation. A complete ‘Team Work’ is essential to solve these
problems and to converge to effective solution. But, from the
failures of many ambitious bridge projects, it can be observed
that there was a clear absence of the team work (except a few
(b) Bridge during construction cases). Typical failure of bridge may happen in case the de-
Fig. 2: Another innovative bridge which had abutments like a racking signer don’t know how the contractor is going to construct that
human body structure; on the other hand, even when the contractor does
not know how that bridge is designed (boundary conditions, as-
Introduction to New Types of Bridges : A Challenges for De- sumptions, standard design practices, loads etc.). The typical
signers: reasons of failures during construction of a bridge could be :–
(a) Incapable Formwork, (b) Inadequate strength gain for con-
Unlike 50 / 60 years back, the computing technology, mate- crete, (c) Lack of Synchronization between Hydraulic Jacks, (d)
rials sciences have lead to converting even the complex shaped Inadequate bearings / temporary bracings, (e) Unexpected forc-
The Masterbuilder | June 2016 | www.masterbuilder.co.in

bridges in the reality. Fig.3 shows a beautiful String Cable es (wind / Blast) (f) misunderstanding between Designer-plan-
stayed bridge designed by Famous Architect and Structural ner and the site personnel etc.
Engineer Santiago Calatrava with the inspiration behind this Fig.17 (a) shows a typical failure of Bridge staging at Viet-
unique shape of bridge. During conceptual planning and the nam during construction stage itself. In certain cases, wrong
design of such modern bridges, often various challenges are sequence of pre-stressing exerts a huge / concentrated or
faced. A few of these challenges are as listed ahead. even eccentric force for which often the supporting formwork
The various challenges that are faced are as below:- / staging is not designed, leading to collapse. After the col-
lapse of structure occurs, no one can trace out exact reasons,
- Complex Loading :– temperature, wind, erection, blast etc. i.e. whether the structure was designed wrongly or executed
and their combinations. Often the design codes and con- wrongly. Unless thorough investigations are made, one cannot
tract specifications are silent about the construction stage conclude in such cases. Fig. 17 (b) shows a typical collapse of
loadings. segmental bridge, which was getting launched in place using a
- Complex Structural Geometry :– this includes a difficult / Launching Girder. All such failure cases explain that the work
sensitive load transfer mechanism, of a designer, planner and the execution (site) engineer shall be
- Refined understanding about the Structural behavior – fail- complementing to each other and not the contradicting. Thus
ure theories, overall performance based design, reliability each one of them must know the works of others (their count-
analysis as compared to Limit state vs. Working stresses er-parts) to a sufficient extent.
91
BRIDGE ENGINEERING: LAUNCHING TECHNIQUES

Introduction to Various Bridge Erection Techniques : A due congested busy roads. Open drains, cable trenches on the
Challenges for Execution side of road, and other utilities may not always permit access of
cranes to each span. Detailed explanation of these two methods
From the discussion till now it is clear that the complexity (i.e. bridge construction using Formwork and Crane launching)
in Bridge Engineering is increasing, which cannot be handled are kept out of scope of present paper. But just a brief mention
alone by the bridge designer or a site engineer. The Design- is made in present para for completeness of the matter.
er must know the proposed method of construction, which
the contractor wants to use for his construction site; and on
the other hand the execution person and planner must know
briefly, how the designer has designed the structure, with its
Limiting conditions / Boundary Conditions / Assumptions. In
certain cases, the original designs /drawings are found to be
un-executable due to actual site constraints (probably, which
the Structural Engineer missed at design stage). In such cases
the modification in design becomes necessary. If the contactor
knows the design basis, then he can develop a executable pro-
posal indicating desired changes in the design at a particular
spot in the project, on the basis of which Designer can visit the
site, review exact situation and revise the design suitably. On the
other hand even, if the designer knows the constraints at site,
in which the site engineer is supposed to work, he can develop
Fig. 4: Showing A typical floating Bridge erection Crane
better scheme, right from construction stage.
A few of the popular methods adopted for construction of
Bridge Erection using a Floating Crane:
bridge super structure are as listed ahead:-
In case of long span bridges, Launching Girder (LG) is
Erection using Traditional Methods
becoming more popular option by the contractors (ref. Fig.6
– Using Formwork / Staging and Fig.7, which shows a typical Truss type Bridge Erection
Launcher, used at Bang-Na-Trade Highway Project, Bangkok).
– With land based hydraulic crawler mounted cranes (single But if the bridge is passing over a large water bodies like rivers,
/ double cranes – for (i) span-by-span construction or even creeks then it is convenient to use floating cranes kept on the
(ii) random span construction Barges / vessels / jack-up platforms. Fig.4 shows such typical
Erection using Modern Methods floating crane. To use this methodology effective, points to pon-
der are as listed ahead.
– Floating Cranes / Barges / Jack-up platforms
Points to Ponder to use floating cranes for bridge launching:-
– Using Bridge Launching Girders, and push / incremental
launching 1) Duration of Project
2) Capacity of Floating Cart; weights of segments to be lifted
– Cable Cranes
3) Availability and characteristics of water way (depth, width,
– CFT (Cantilever Form Traveler) / MSS (Moving Scaffolding tide levels, waves / currents)
System) 4) Facts of actual Site :
- Location / distance of Casting Yard
– Tower Carnes
- Wind Speed
– Ground Supported Staging (GSS) - Tidal variations
The Masterbuilder | June 2016 | www.masterbuilder.co.in

5) Cost / Budget
Bridge Erection using Traditional Methods 6) Cooperation from Designers / Design capacity
Mostly the traditional methods viz. use of Formwork / Stag- Bridge Erection using a Launching Girder:
ing or use of direct cranes is suitable for simple bridges. Simply
supported spans are mostly constructed using these methods. From Fig.7, which is showing Bridge Erection Launcher,
Use of Formwork / Staging consumes lot of construction time used in Bangkok, it may be seen that the Permanent structure
for erection of formwork, placement of reinforcements, casting. has good Aesthetic look, which is correctly utilized by the De-
curing and strength gain and removal of formwork / scaffolds. signer of LG system to place the LG; it can be also seen that due
Hence in modern bridge construction projects it not a preferred to placement of LG inside the pier notch there is impact on the
option. design and reinforcement detailing of such pier, to cater for LG
Bridge erection using direct cranes is suitable for pre- loads. Also, from Fig.8, one may observe the necessity of sta-
cast-components only, heavy cranes are required to lift precast bility of erection system during girder erection. Faulty system
girders / segments (ref. Fig.5). Even large space is required to may lead to incorrect bridge geometry or even accumulation
position the crane. Access roads right upto the erection loca- of secondary stresses in the girder body /distortion. Apart from
tion is another requirement in this scheme. This option is rarely these, there could be accidents leading to damage to structure
used, for one or two locations in the project. In bridge construct- or human life (as shown in Fig. 11, 17).
ed in busy metro cities often this option is found to be unsuitable Apart from the regular bridge erection techniques like
92
BRIDGE ENGINEERING: LAUNCHING TECHNIQUES

Fig.8: Bridge Segment Launching in Progress

Fig. 5: Bridge erection with single Land based Crane

Formwork / Staging, Launching Girders and advanced tech-


nique of Floating Cranes, A suspended erection crane / ca-
bleway is also used now days as shown in Fig. 10, for a steel
Arch Segmental Bridge in China. In such cases the Permanent
structure has to be designed keeping in mind the construc-
tion / erection and dismantling methodology. The construction
scheme / methodology imposes large loads on the permanent
structure, which are often greater than the Design loads even Fig.9 – Bridge Launching in River / Water
(i.e. critical combination of self wt, Live load, wind / earthquake
etc.). one abutment to another abutment. No external LT is used, ex-
Push / incremental launching is another interesting meth- cept a nosing. In such method the super structure experiencing
od, in which the entire precast bridge structure is pushed from ‘cycles of stress reversal’, this has to be catered for in advance.

Bridge Erection using a Suspended Cable Crane (Cableway):


The Masterbuilder | June 2016 | www.masterbuilder.co.in

This is a unique and challenging technique of bridge con-


struction. Fig.10 shows a photograph of steel segmental arch
bridge construction, in China, using cable crane (or alternatively
Fig. 6: Showing Schematic Diagram of Bridge launcher called as a cable way). In India, for erection of Chenab Railway
bridge over Chenab river, M/s Afcons is planning use similar
technique. Cableway is also- being used on the Concrete Arch
Bridge at world famous Hoover dam. In this case the design and

Fig.7 – Bridge Erection Launcher, used at Bang-Na-Trade Highway


Project, Bangkok (LG placed inside piers) Fig.10: Steel Arch Bridge Erection Using a Cable Crane
94
BRIDGE ENGINEERING: LAUNCHING TECHNIQUES

Fig.11: Collapse of a Construction Worker During Bridge Erection Due


to Sudden Cutting of a Wire Rope

– construction must go hand-in-hand to reach to successful


conclusion. Issues like maintaining tension in the cable, limiting
sag due to dead loads, wind velocity for the stability of ropes un-
der self wt and lifted weight condition (i.e. operating and idling
conditions), safety from falling objects at night, possibility of any
object getting hit to the cable etc. are the critical issues in such
method. All these issues must be addressed prior to the start of
design (at conceptual stage itself). Without coordination with the
contactor, it simply cannot be done !
As mentioned earlier there are many other innovative
methods like CFT / MSS / erection using tower crane. They can
be used only if there is close interaction between the designs
– detailer – contractor is established. The same are briefly ex-
plained ahead. Fig.13 – Use of a Precast Segment Erector for balance cantilever
(Ref- MIC / Earlington Heights Connector project at MIAMI, Florida)
Erection / Construction of Balance Cantilever Bridges using
- CFT (Cantilever Form Traveler) or Segemnt Erector or LG

A Cantilever Form Travel (CFT) is commonly used meth-


od for the construction of Balance cantilever bridges. This is
a method of ‘in-situ’ construction. In recent days to save time,
instead of in-situ construction the balance cantilevers are
even erected using a ‘Precast-Segment erectors’ Fig. 12 and
13 ahead show these two methods respectively. In both these Fig.14 – Schematic Sketch showing use of a Launching Girder for
methods the central fixed-pier and the post-tensioning cable erection of Balance Cantilever Bridge
configuration has to be designed to sustain the forces gener-
The Masterbuilder | June 2016 | www.masterbuilder.co.in

ated during the erection stages. The balance cantilever bridge cantilever rests on the far-end pier, the structure starts acting
gets ‘Tension’ at top during construction due to only self-weight. like a ‘propped cantilever’ and the force pattern get completely
But as soon as at the end of the construction the tip of balance changed i.e. top tension in cantilever changes to bottom tension
in the propped cantilever due to self-weight. Thus the Designer
has to design the PT-cable configuration so as to take care of
tension occurring at top during construction and at bottom (at
mid span) in service stage.
Another innovative technique sometime used for the con-
struction of ‘long-span’ balance cantilever bridges is using a
Launching Girder (ref. Fig.14 below). In such erection method
there is no additional ‘bending moment’ generated in the bridge
due to weight of formwork like in case of CFT (or at least can
be minimized). But the contractor need to invest on additional
cost of LG and even the piers and segments shall be designed
/ detailed support the legs of LG. But the construction time can
be reduced. So while selecting any of the above three methods,
Fig.12: A typical bridge constructed using a CFT thorough comparison may be made.
95
BRIDGE ENGINEERING: LAUNCHING TECHNIQUES

Erection using Tower Crane

Yet one another method of bridge erection is using tower


cranes. Normally tower cranes are used for the construction
of pylons in cable stayed bridges due to the large heights. But
rarely tower cranes mounted on track are used for erection /
servicing of the bridge superstructure as well. But as often load
carrying capacity of tower cranes is very less as compared to
crawler cranes, they can be used for erecting light-weight units
only (like bearings, cables etc) instead of full superstructure.

Fig.15: A typical MSS for Bridge Construction

(a) Bridge Formwork Failure

(b) Launching Girder Failure (in Water)


The Masterbuilder | June 2016 | www.masterbuilder.co.in

Fig.16 – GSS System Designed by author for Barapula, Delhi

MSS (Moving Scaffolding System)

Moving Scaffolding System (MSS) is another upcoming


method of bridge construction (Fig.15). It includes a bridge
formwork mounted on a moving girder at the construction site
itself. Thus the girder moves ahead to each span one by one and
keep casting the same at it’s desired place (in-situ construc-
tion). Basically this is a slow method, also imposes additional
loads on the Piers. The moving girder get’s locked with the piers
for the period, till concrete gains specified strength and the
post-tensioning is done. This is a cumbersome / bulky method
of construction; it is suitable only for fairly straight spans with
nominal gradient. While designing the bridge using MSS the (c) Launching Girder Failure (On Land) in Mumbai
designer must first consult the contractor and client. Fig.17 – Photographs of Bridge Failures during erection stage
96
BRIDGE ENGINEERING: LAUNCHING TECHNIQUES

Ground Supported Staging (GSS) b) Longest Railway Bridge at Cochin for RVNL
(example of a project where Erection Method influenced the
Sometimes the launching girder cannot be used for design of Bridge) :-
launching bridge superstructure in cases like – sharp radi- This bridge was constructed by Afcons Infrastructure Ltd.
us of curvature in plan, large gradient (longitudinal slope) and for Rail Vikas Nigam Ltd. in Yr. 2007-08. In this project, Rail Vi-
super-elevation, continuous spans etc. In such the segments kas Nigam Limited (RVNL) had initially proposed a 600Mt single
can be erected using Ground Supported Staging System (GSS). box girder per span. Launching such a heavy structure was not
GSS system can be used only if the ground below has sufficient possible inside the crek area. Also the SBC of soil at casting
load bearing capacity and availability of separate crane / EOT yard was very less. Considering these limitations the contractor
for placing the segments from trailer to the GSS. If these two proposed Two-Pre-stressed concrete I girders at each span.
re-conditions are satisfied then GSS proves to be most com- This Modification was readily approved by the client considering
fortable and fast system of erection. Weight of GSS system is the practical limitations. NRS Asia ‘Over-head type’
significantly lesser than the LG. Ref Fig.16 for GSS. Launching girder was used for erection. The entire proj-
ect was completed ahead of the schedule, within the budgeted
Construction Failures During Bridge Laucnging / Construc-
cost. This example describes how the enabling works forced to
tion
modify the permanent structure, yet leading to ultimate suc-
All Bridge erection methods explained till now have certain cess of the project.
advantages and limitations; to use any selected method effec- Conclusions
tively one need to fulfill certain prerequisites (already discussed
in respective method above). But as explained at the beginning From the discussion till now, which has covered (a) the
of this papers, the consultant may not know (or wants to know) olden method of construction of bridges, (b) the challenges in
the construction method, and on the other hand the contractor new era (like complex loadings, geometry, codes, new mate-
/ bridge erection agency does not know the basis of the designs. rials etc), (c) upcoming methods of bridge construction / erec-
In such cases there is a likelihood of certain pre-requisites may tion, and from various case studies the interrelation between
not get fulfilled, leading to catastrophes as shown in Fig. 17. the Paramagnet design and the Erection Design of Bridge must
be clear. Many hints are embedded for the Designer as well
A Few Case Studies as contractor at each method of launching, one can use them
while working on live project.
From the discussion till now it may be clear that the per-
At the end, the main fact to be remembered is ‘Bridge De-
manent design and erection method (enabling works) have very
sign and Construction’ is not a single agencies responsibility;
close relation to each other. Following are some of the proj-
only ‘Team-work’ can lead to a overall successful project!
ects where the permanents designs and enabling works have
affected each other. The author of this paper has experienced Acknowledgements
many live case studies; amongst which two cases are present-
ed here as a sample:- The author is thankful to the Afcons Infrastructure Limited
a) Allahabad-Nainy Cable Stayed bridge project (example and entire site team for making all the relevant data available
of a project where Permanent Design of Bridge affecting the for this paper. Author is thankful to authors of various books /
design of Formwork) papers / techniques listed in the References below. Author also
This project was done by Joint venture (JV) of HCC and wishes to express his thanks to the Organizers of Structural
Hyundai in Uttar Pradesh India, in Yr. 2002-03. In this project a Engineering World Conference 2015 for considering present
20m wide bridge deck was supported with 1400mm wide and paper.
3500mm deep two Pre-stressed rectangular girders (which References
The Masterbuilder | June 2016 | www.masterbuilder.co.in

were monolithically cast with the deck slab). Each span was
60m long. There were 4 modules to be cast. The longest mod- - Dhanajay Bhide, “Syzygy between Design and Construction of Bridges
(Part-I of II)” Indian Road Congress Journal, July’2015.
ule had nine continuous pres-stressed spans. Every 60m span
was cast along with the 1/5th (i.e. 12m) of next span i.e. at theo- - Dhanajay Bhide, “Replcament of damaged Suspension Span of Verso-
retical point of contra flexure. va Bridge Across Vasai Creek on NH-8”, Indian Roads Congress, Jan-
March’15.
During the application of pre-stress as the 60m portion of
the girder used to get ‘hogged–up’, the remaining 12m portion - Vivek G. Abhyankar, “Nad-al-Sheba Race Course Development Project
used to get dipped-down, because of the continuity in the con- : Construction of three Bridges” Indian Society of Structural Engineers
(ISSE), Mumbai, Vol-13/2, April-May-June’2011 issue.
struction, This resulted into enormous increase in the load on
the formwork / staging in the 12m portion (which was tempo- - Vivek G. Abhyankar, “Construction Longest Railway Bridge Project at
rarily acting as cantilever, till the remaining 48m was cast in Cochin” Indian Society of Structural Engineers (ISSE), Mumbai, Volume
11-3, Jul-Aug-Sep
next pour). This effect was predetermined and the Formwork
and Staging was designed accordingly. Also the pre-camber - M. K. Hurd, “Formwork for Concrete”, ACI, seventh edition.
was pre-determined and set in the staging during erection - Marco Rosignoli, “Bridge Launching”, Thomas Telford Publishing (Jan-
work. uary 1, 2002) w
98

Potrebbero piacerti anche