Sei sulla pagina 1di 4

Office/Plant:

B21 L27 Malanting St. Amparo Village,


Caloocan City, 1425 Philippines
Phone : +632 9306050
+632 9614589
Telefax : +632 9364583
Email : jmccii@yahoo.com

JMCC Industries Inc. SP-6881-1218

11 December 2018

REYSONS FOOD PROCESSING


Brgy. Hangan, Calauan
Laguna

Attention : Mr. ARTHUR ABUNDO


Plant Manager

Subject : RELOCATION OF EQUIPMENT AND PIPING WORKS


Our ref. : SP - 6881 - 1218

Sir :

With reference to your request for quotation for the above subject, we are pleased to submit the
following for your consideration.

I. One (1) Lot - Supply of materials, labor and supervision, use of tools and equipment required
for the Relocation of Equipment and Piping Works. Details base on
following scope of work, terms and condition.

II. Scope of Work

A. Relocation of Equipment and Re-piping Works


1. Dismantling and re-installation of the following;
 2 units – Steam retort
 3 units – Steam kettle (Nos. 1, 2 and 6)
2. Installation of pipe supports for steam line
3. Installation of additional 2ӯ steam main line for the relocated steam kettles.
4. Re-tapping of existing steam line to relocated equipment.
5. Installation of 1-½ Ø” x 3m steam line to cutting machine with isolation valve.
6. Installation of additional air vent and safety valves outlet line and pipe supports to be
discharged above the roof (to the atmosphere).
7. Replacement of existing 1-½“Ø main condensate line within the food processing area.
8. Painting of new pipes with high heat aluminum paint.
9. Insulation and cladding of new steam and condensate line main header.
10. Replacement of insulation and cladding of main steam line affected by relocation of pipes.
11. Modification of existing legs of two (2) units – steam retort.

B. Construction of Trench
1. Construction of additional trench located at the rear side of kettles (0.19m W x 3.75m L).
2. Construction of additional trench located at the front side of steam retorts (0.3m W x 7.0m L).
3. Fabrication and installation of steel cover for new trench located at the front side of retort.

C. Fabrication of Trolley
JMCC Industries Inc. REYSONS FOOD PROCESSING
ENGINEERS CONTRACTOR FABRICATOR
Relocation of Equipment and Piping Works
SP-6881-1218

D. Insulation and Cladding of Two (2) Units - Retort


1. Dismantling of insulation and cladding of two (2) units – retort.
2. Layout and cutting of cladding.
3. Rolling and grooving of cladding.
4. Replacement of damaged stiffeners of insulation and cladding.
5. Insulation of retort.
6. Cladding of retort.

E. Steam Trap Station for Kettles


1. Supply and installation of steam trap station from kettle to condensate header.

III. Material Specification

A. Relocation of Equipment and Piping Works

Steam Line
Pipe : BI Pipe, 2ӯ Sch40, ASTM A53 Grade B (main steam line)
BI Pipe, 1-1/2ӯ Sch80, ASTM A53 Grade B (cutting line)
Valves : Gate Valve, 1-1/2ӯ X 800 lbs, A105, screwed type
Fittings : Black Iron, welded type
Insulation : Perlite insulation for straight line
Rockwool Insulation, 2” thick x 80kg/m3 for elbows
Cladding : Aluminum sheet Ga#24

Condensate Line
Pipe : BI Pipe, 1-½ “Ø Sch 40, ASTM A53 Grade B
Fittings : Black Iron, welded type
Insulation : Perlite insulation for straight line
Rockwool Insulation, 2” thick x 80kg/m3 for elbows
Cladding : Aluminum sheet Ga#24

Air Vent / Safety Valve Outlet


Pipe : BI Pipe, 1-½ “Ø Sch 40, ASTM A53 Grade B

Painting : High Heat Aluminum Paint

B. Construction of Trench

Trench
Cover Sidings : Angle Bar, 1” x 1” x 6mm thk x 20 ft
Grills / Cover : SS304 Round Bar, 3/8ӯ @ 50mm spacing
Dimension : 0.30m W x 6.4m

C. Fabrication of Trolley

Trolley : SS304 Angle Bar, 2-1/2” x 2-1/2” x 5mm thk


Caster Wheel, swivel type, 4ӯ, engineering plastic
Caster Wheel, fixed type, 4ӯ, engineering plastic

2|P a g e
JMCC Industries Inc. REYSONS FOOD PROCESSING
ENGINEERS CONTRACTOR FABRICATOR
Relocation of Equipment and Piping Works
SP-6881-1218

D. Insulation and Cladding of Two (2) Units - Retort

Insulation : Rockwool, 2” thick x 80 kg/m 3


Cladding : Aluminum Sheet Ga #22
Stiffener : SS304 Flat Bar, 3mmthk x 1-1/4”

E. Steam Trap Station for Kettles

Composed of the ff. items per set:


One (1) unit - “TW” or “317” Brand (Taiwan) Steam Trap
Model ST-T3A, ¾”Ø, Cast Iron, Screwed type
Two (2) pcs - “Kitz” brand Gate Valve, Model AKFH, ¾”Ø x 125 psi
Brass, threaded
One (1) pc - “Kitz” brand Check Valve, Model AKR, ¾”Ø x 125 psi
swing type, bronze, threaded
Two (2) pcs - Equal Tee, ¾”Ø x 3000 lbs, Forged steel, screwed type
Three (3) pcs - Elbow 90o, ¾”Ø x 3000 lbs, Forged steel, screwed type
Two (2) pcs - Union Patente, ¾”Ø x 3000 lbs, Forged steel, screwed type
One (1) lot - BI Pipe, ¾”Ø Sch 40

III. Price Breakdown

Description Unit Qty Unit Cost Total Cost


A Relocation of Equipment and Piping Works 1 lot 471,393.00 471,393.00
B Construction of Trench 1 lot 71,845.00 71,845.00
C Fabrication of Trolley 1 unit 52,954.00 52,954.00
D Insulation and Cladding of Two (2) Units - Retort 1 lot 130,730.00 130,730.00
E Steam Trap Station for Kettles 6 units 22,463.00 134,778.00
TOTAL 861,700.00

IV. Terms of Payment


50% Down payment
50% after completion

V. Completion
We shall exert our best effort within our control to finish the above scope of work within fifteen
(15) working days after receipt of firm order, required down payment and settlement of all
technical and contractual details.

VI. Conditions

1. Exclusions:
- Replacement of damaged branch steam lines
- Replacement of leaking valves of steam and condensate line
- Replacement of condensate line outside the processing area
- Replacement of kettle drain line
- Steel covers of trench at the rear and left side.

3|P a g e
JMCC Industries Inc. REYSONS FOOD PROCESSING
ENGINEERS CONTRACTOR FABRICATOR
Relocation of Equipment and Piping Works
SP-6881-1218

2. Customer to provide the following at site free of charge:


- Temporary facilities
- Water supply
- Space for site fabrication
- Electric power (220VAC, 60 Hz) and water supply for our domestic use
3. Any work aside from those mentioned earlier in our scope shall be considered extra work and
subject to additional charges, price of which to be determined later.
4. Delay in the completion of our work due to causes beyond our control and / or not of
our makings shall be excused.

VIII. Validity
Price quoted above is subject for confirmation before the order is placed and the corresponding
down payment is received.

We thank you for giving us the opportunity to quote on your requirements and is looking forward to
receive your valued order soon.

Very truly yours,


JMCC INDUSTRIES INC. Noted by:

NORBERTO VALLE JR. RODRIGO D. VALLE


Sales/ Marketing General Manager

4|P a g e

Potrebbero piacerti anche